You are on page 1of 48

Inside This Issue Editorial Board

Advisor:
From MD’s Desk………………………………………………………………………………………………………..………………… 2
Dr. R. Nagaraja
Steady State Analysis of Power Systems…………………………………………………………………………………….. 3
………..….………………………………….…………………………..….…………………………..………….Dr. K. Balaraman
Editor:
Consultancy Services Rendered……………………………………..….…………………………………………………..…… 9
M. M. Babu Narayanan
Power System Stability Studies…………………………………………………………………………………..….…………… 12
………………………………………………………….………….……………………………..……..…..….…….Dr. R. Nagaraja
Members:
Small Signal Stability in Power Systems…………………………………………………….…….…………………..……… 19
Venkatesh H. R.
………………………………………….…………………………………………………………………………..Prof. K. R. Padiyar
Sandhya R. J.
Voltage Stability - Fundamentals and State-of-the-art……………………………………………………………..… 22
Ch. Vijay Krishna Rao
…...……………………………………………………………………………………………………………….Dr. G. Govinda Rao
Rakesha H. S.
Harmonic Studies............................................................................................................................ 24
Pranati Mohanty
...............................................................................................................................Dr. R. Nagaraja
Thimmappa. N
Ferroresonance Phenomenon in Power Transformers-Simulation Study using MiPower…….…..... 30
………………………………………………...….………..…..……..Dr. K. Parthasarathy &VeerabrahmamBathini
Shunt Reactor Switching in Extra High Voltage System - Criterion for Verification of Proposed
Circuit Breaker Parameters………………………………………………………………..……….…………………………..…. 34
………………..…………………………………………………..……Dr. K. Parthasarathy &Veerabrahmam Bathini
Power System Simulation Tools…………………..…………………………………………………………………………..…. 40
………………………….…………….…………………………………….……..……….….………..…M.M. Babu Narayanan
Page 2 Power Research and Development Consultants
Newsletter

From MD’s Desk


Fortunately for T&D utilities and relevant expertiseand experience has
GENCOs, most of the National and been showcased by the consultant for
State grid codes clearly indicate the similar assignments in the past. The
timing of the system studies and the best practice is to introduce the
type of studies to be conducted in “Conflict of Interest” clause in the
depth including the data to be tender specifications. This clause
furnished for such studies. These avoids the conflict between consulting
guidelines are to be followed activities and the supply of goods or
meticulously. For power evacuation works by the same consultant
study, system studies should be organization. The spirit behind this
conducted at the detailed project clause is to ensure that while providing
report (DPR) preparation stage itself the consulting services, the consultant
and results of such a system study will not be biased in his
Dear Friends, should inter alia be a part of the DPR. recommendations in an attempt to
Power system study is one of the If the system studies pertain to supply equipment of his interest. It
important tasks in the planning and industrial system development or may be mentioned here that all
operation of a power system at all capacity expansion, these should be consulting assignments from World
three levels of the electricity supply conducted as part of the initial Bank and ADB have included this
chain, i.e. generation, transmission feasibility study. Power system study specific clause on ‘Conflict of interest’
and distribution. This special issue of report becomes a major reference for and the same can be practiced by other
PRDC newsletter on “Power System the detailed engineering exercise. organizations that intend to avail of the
Studies” is in your hands and I thank all Furthermore, system study report is services of consultants in the
the authors and other colleagues, who an important document for availing specialized area of power system
have worked directly or indirectly to grid connectivity by industrial power studies.
successfully bring out this special systems. This is also true for seeking
issue. Even though the subject matter approval of synchronizing and power The special issue on system studies is
of power system studies has been evacuation by GENCOs from equally more relevant due to the fact
covered in depth by the experts in transmission utilities. For that recently we had two major grid
their respective articles in this issue, I investigations of grid disturbances and collapses in succession in the Indian
thought of dwelling upon the failure analysis, power system studies Grid. Proper planning of the system,
importance of power system studies should be conducted immediately timely implementation of the plans,
and also on the subject of selection of following the eventuality, so that the best operational practices and more
consultants for carrying out such collection of relevant data for the emphasis on the protection system
studies at the behest of utilities, study becomes easy. audit and relay co-ordination would
industries and similar entities. have avoided the black out. We need
The second issue pertaining to the to conduct the dynamic studies, find
Utilities and industries are often faced power system studies is the selection out the system behavior for various
with the dilemma as to when the criterion for the consultants. system disturbances and based on that
power system study should be Worldwide, most of the utilities design the controlled system
conducted and at what stage of the generally follow the 70:30 criteria, i.e. separation, load shedding and
project the system study consultants 70% weight to the technical score and generator tripping schemes. Let us all
are to be involved. Timing of the study 30% weight to the price score in the put our sincere efforts to strengthen
depends on the nature of the study qualifying criteria.This practice will our power grid, the back bone of Indian
like a routine planning exercise, enable the client to get best economy, there by building an
system expansion study, failure consultants to perform the given economically strong nation.
analysis or even to mitigate some assignment. For specific jobs, it is also
existing problems being faced in the advisable to go in for the selection of Dr. R. Nagaraja
system operation. the consultant on nomination basis,if Managing Director
Power Research and Development Consultants
Page 3
Newsletter

Steady State Analysis of Power Systems


Dr. K. Balaraman
1. Introduction
through the system is determined. • Optimize component or circuit
The planning, design and operation a Another very popular steady state analysis loading
commercial and industrial power system tool is the short circuit analysis for • Develop practical bus voltage
requires continual and comprehensive determining the fault current through profiles
analysis to evaluate current system system. In this paper, the load flow • Identify real and reactive power
performance and to establish the analysis and short circuit analysis is dealt flow
effectiveness of the alternative plans for in detail. • Minimize kW and kVAr losses
operating the system. The computational • Develop equipment specification
work to determine power flows and 2. Load Flow Studies guidelines
voltage levels resulting from single • Identify proper transformer tap
operating condition for even a small Load flow studies or the power flow settings
network is all but insurmountable if studies are used to validate that the
performed by manual methods. The need electrical power transfer from generators Load flow studies are performed using
for computational aids led to the design of to consumers through the grid system is computer software that simulates actual
a special purpose analog computer (ac stable, reliable and economical. The steady-state power system operating
network analyzer) as early as 1929. It principal information obtained from the conditions. Power-flow studies are usually
provided the ability to determine flows power flow study is the magnitude and started by analyzing the power system in
and voltages during normal and phase angle of the voltage at each bus and its normal operating conditions, called the
emergency conditions and to study the the real and reactive power flowing in base case. Then, various load and
transient behavior of the system resulting each line. generation changes (increased/decreased)
from fault conditions and switching may be projected to localize possible
operations. The earliest application of Load flow analysis has a great importance problem spots. By adding system elements
digital computers to power system in future expansion planning, in stability like transmission lines to the system or by
problems dates back to the late 1940s. studies and in determining the best modifying the system configuration, a new
Most of the early applications were limited economical operation for existing systems. configuration may be found for resolving
in scope because of the small capacity of Further, load flow results are also very the problem. These estimated models can
the punched card calculators in use during valuable for setting the proper protection be used for planning.
that period. Large-scale digital computers devices to ensure the security of the
became available in the mid-1950s, and system. In order to perform a load flow Further through power-flow studies,
the initial success of load flow programs study, detailed power system data should possible failures of particular lines and
led to the development of programs for be available about the studied system, generators can be analyzed to see whether
short-circuit and stability calculations. such as connection diagram, parameters the remaining components can handle the
Today, the digital computer is an of transformers and transmission lines, demand. Conducting a load flow study
indispensable tool in power system any reactive power compensation devices, using multiple scenarios (contingencies)
planning, in which it is necessary to predict rated values of each equipment, details of helps to ensure that the power system is
future growth and simulate day-to-day generators, and the values of real and adequately designed to satisfy the
operations over periods of twenty years or reactive power for each load etc. performance criteria.The most important
more [1]. information obtained from the load flow
The analysis of load flow results would analysis is the voltage profile of the system.
In general, the power system analysis is ensure that cables, transformers, If voltage varies greatly over the system,
grouped into two categories, viz., Steady transmission lines are sized appropriately large reactive flows will result. This, in turn,
state analysis and Dynamic analysis. In to carry required load and alsothrough the will lead to increased real power losses
steady state analysis, it is assumed that studies, thetransformer taps are set and, in extreme cases, an increased
any transients from the disturbances are appropriately to obtain satisfactory likelihood of voltage collapse. When a
settled down and the system state is voltage profile within the area of study. particular bus has an unacceptably low
unchanged i.e., the system load including
voltage/high voltage, the usual practice is
transmission system losses are matched A load flow study determines how the
to install capacitor banks/ shunt reactors in
with power generation. The primary tools electrical system will perform during
order to provide reactive compensation to
for analysis for steady state operation is so normal and emergency operating
the load.Load flow studies are used to
called power flow analysis or Load flow conditions, providing the information
determine how much reactive
studies where the voltage and powerflow needed to:
Page 4 Power Research and Development Consultants
Newsletter

compensation is needed at a bus, to bring 2.1 The Power Flow Problem Bus currents and voltages can be calculated
its voltage up to an appropriate level. If using the above equations and since in
new lines (or additional transformers) are The overall power flow problem can be practical systems power is known quantity,
to be installed, to reinforce the system, a divided into following sub-problems [2,3], equations 1and 2 can be written as,
power flow study will show how it will
∗ ∗ ∗
relieve overloads on adjacent lines. An 1. Formulation of a suitable --(5)
inefficient or unbalanced load can also mathematical network model to
cause unpredictable behavior in your adequately describe the And
localized power grid, increasing the risk of relationship between voltages
∗ ∗ ∗
equipment damage and unplanned powers in the interconnected --(6)
outages. system.
2. Initialization of power and are the desired power flow equations in
The load flow study is a pre- requisite to voltages in various buses/nodes nonlinear form for two bus system and
short circuit study, stability study and of the network. these equations can be generalized and
electromagnetic transient study. The load 3. Numerical computation of
Further each bus voltage V will be having
written as shown below in equation (7),
flow study is also used as a part of the power flow equations with the
motor starting study. above initialization to compute both magnitude |V | and angle δ .
the voltages at all the
Load flow studies are the basis for buses/nodes of the network ∗
# # # #

∑%& | #% | | % | Where
ensuring that a power system design will with sufficient accuracy. for ' =1, 2, 3…------------------------------- (7)
satisfy its performance criteria within the 4. Computing the power flows in
boundaries of the most beneficial all the branches of The main solution methods for power flow
investment and operating costs. Some interconnected network. studies are as follows [4,5]
examples of how load flow studies are
used are listed below. In order to form the suitable mathematical
• Newton-Raphson method
model, we can construct the following
• Gauss-Seidel method
• Equipment sizing and loading equations from the basic principles for a • Fast Decoupled method
(Transformers, Lines, Cables, two bus system,

Reactors, etc.) Among the various solution methods, the
• Generator exciter / regulator ∗ ---------------- (1) N-R method is superior to the G-S method
voltage set points because it exhibits a faster convergence
• System loss analysis ∗
characteristic. However, N-R method
And ∗ --------- (2)
• Maintain reliability suffers from the disadvantage that a “flat
• Coordinate protective relays start” is not always possible since the
• Capacitor placement and sizing Equation 1 and 2 can be written in the solution at the beginning can oscillate
• Steady state bus voltages simple forms using vectors and matrix as without converging toward the solution.
• Transformer tap settings shown below using admittance matrix and Hence, the load-flow solution is often
• Load tap changer evaluation are complex, linear, simultaneous carried out with G-S algorithm for
• System reactor load flows equations. distribution system analysis.
• Utility intertie studies
---------------------------- (3)
• To know about component or The fast-decoupled method is a variation of
≅ ≅
circuit loading, real and reactive the N-R method wherein the solution is
Where, and and
power flow decoupled with P and delta on one side


• System performance under and V and Q on the other to obtain faster
emergency and unexpected convergence. This is generally used in the
conditions transmission system which contain many
• To find significant plant buses and where there is a need for faster
expansion. Also using impedance matrix, load-flow solution.
• As a part of motor starting studies ---------------------------- (4)
• Pre-requisite to conduct short During the operation of the power system,
circuit, stability and EMTP studies. Where, each bus has known variables and
unknowns variables.
Power Research and Development Consultants
Page 5
Newsletter

Generally, the bus must be classified as


one of the following bus types: Table 1: Known and unknown variables to be calculated from power flowequations
Known and unknown variables to be calculated from solving equations

| | *
2.1.1 Slack or Swing Bus Bus type
( ( ) )
This bus is considered as the reference Slack or
bus. During the execution, the voltage of √ √ × × √ √
swing bus
this bus is always specified and remains Voltage
constant in magnitude and specified angle √ √ √ √ × ×
control bus
which normally set to zero. In addition to Load bus √ √ √ × √ ×
the generation assigned to it according to
economic operation, this bus is
responsible for supplying the losses of the
system and also any mismatch between Figure 1 shows the load flow results without necessitating the load shedding or
the load and generation. The main criteria obtained through MiPower software for generation rescheduling during steady
for selecting the slack or swing bus is that the sample system taken from text book steate operation.Normally
it should be the largest generation bus. In ‘Computer Methods in Power System regulatorycommissions will set the criteria
addition such slack bus would preferably Analysis - Chapter 8, Figure 8.8 -Sample for analyzing the contingency analysis by
located remote from the location under system for load flow solution’. defining the set of credible continncyes for
study. which system needs to be tested during
2.2 Contingency Analysis planning and operation stages. With the
2.1.2 Generator or Voltage Controlled Bus available software and digital computation
– PV Bus Contingency studies are the essential part tools, contingency analysis has become
of steady state analysis of very simple exercise.
During the execution the voltage largeinterconnected power systems. These
magnitude at this the bus is kept constant studies are used to analyze the Steady state analysis and software tools
subject to reactive power limit. Also, the reliability,loading of elements, voltage are matured with technology development
active power supplied is kept constant at profile and overall behaviorof and recent developmentsare
the value that satisfies the economic interconnected system with the outage of focusingtowards analysis of system with
operation of the system. Most probably, elements viz transmission unbalanced load and distributedgenerators
this bus is connected to a generator where lines,transformer etc.. like wind and solar.
the voltage is controlled using the
excitation and the power is controlled
using the prime mover control.
Sometimes, this bus is connected to a VAr
device where the voltage can be
controlled by varying the value of the
injected VAr to the bus.

2.1.3 Load Bus – PQ Bus

In this bus P & Q are specified. Generally


the loads are connected to this bus. The
generator bus (or PV bus) would also
become PQ bus when reactive power limit
is reached.

Details of known and unknown variables


to be calculated from solving power flow
equations are given in Table 1.
Figure 1: Load flow results for sample system
Page 6 Power Research and Development Consultants
Newsletter

More tools are being developed to Relation between phase values and and hence fault current is,

3
understand the effect of distributed sequence components are shown below in

3
generations in large power systems with equation (8) and (9), +
utmost accuracy. + .
< .= 3 /
. 1 1 1 +
7 7 71 9 9 7 7 7------------------ (8)
4
3. Short Circuit Studies
1 9 9
Typically, only 5% of the initial faults in a
- power system, are three phase faults with
Faults usually occur in a power system due
1 1 1 +
or without earth. Of the unbalanced faults,
to insulation failure, flashover, physical .
damage or human error. These faults may 7 7 71 9 9 7 7 7------------------- (9)
80% are line-earth and 15% are double line
4
1 9 9 -
faults with or without earth and which can
either be three phase in nature involving
often deteriorate to 3 phase fault. Broken
all three phases in a symmetrical manner,
conductor faults account for the rest.
or may be asymmetrical where usually With the above relation between phase
only one or two phases may be involved. values and sequence components, sample The purpose of a short circuit study is to
Faults may also be caused by either short- calculations for three phase fault, double identify the maximum available fault
circuits to earth or between live line to ground fault and line to ground current at all locations, called busses, in the
conductors, or may be caused by broken fault are shown below, power system. It is then compared with the
conductors in one or more phases. ratings of the individual power system
Sometimes simultaneous faults may occur In case of three phase fault, it is assumed components, such as circuit breakers relays
involving both short-circuit and broken that all the three phases are short circuit and fuses, to determine if the equipment is
conductor faults (also known as open- through equal fault impedances / , adequately rated to safely withstand or
circuit faults). vectorial sum of fault current is zero since interrupt the calculated fault current. It is
symmetrical fault is considered without also used to evaluate the withstanding
Balanced three phase faults may be ground. design capability of all the electrical
analyzed using an equivalent single phase equipment (panels, switchboards,
circuit. With asymmetrical three phase Hence,
. 0, + - 0 and fault switchgears, Motor starters, and other
;
9
faults, the uses of symmetrical electrical equipment not mentioned) used
currents, + 0 305
, and
of the calculations as transmission lines - 9
components help to reduce the complexity in the system, against the available fault
currents.
and components are by and large
symmetrical, although the fault may be In case of double line to ground fault, fault For new facilities, a short circuit study
asymmetrical. Sample fault analysis with is considered in phase’s b and c with should be performed before the electrical
symmetrical components are given below, ground through fault impedance / , the equipment is selected. For existing
current in the ungrounded phase is zero, facilities, a short circuit study should be
In the analysis following notations are performed if significant changes have
0, and hence 0
occurred either within the facility or in the
+ .
considered [6,7],
< - = / and the fault
I.e.
utility system.
-
+,
and
• And - are phase to ground current is, The short circuit study provides the

fault does not exists and ,


voltages at the fault point if the following information.
+
and . are sequence components 0 102 34056 • Calculates the fault current at
of voltages, 0 302 3405

+,
various locations in the plant.
• And - are lines currents and
,
• Identifies whether the system and
and . are sequence In case of line to ground fault, fault is the equipment can withstand the
components of currents, considered in phase a with ground
,
available fault current.
• And . are positive, through faultimpedance / , currents in • Evaluates the application of breakers
negative and zero sequence phase b and c are zero andthe voltage at and fuses.
impedances and / is fault the fault point is + + / and • Identifies problem areas in the
impedance and ‘a’ is vector .
4 +
system.
operator.
Power Research and Development Consultants
Page 7
Newsletter

• Specifies the types, ampere ratings While selecting circuit breakers it is 3.2 Determining the Short Circuit Duties of
and device settings of the important to make sure that none of the Breakers
equipment to ensure minimum capabilities areexceeded in their
service interruption. application.These capabilities are basically Considering an industrial scenario
• Helps improve the reliability of your obtained from theshort circuit wherethere is no in-plant power
system. current calculations available at the generation,
• Provides recommended solutions. equipment location. Therefore, the the total three phase fault current at the
• Coordinate protective relays. starting point is the careful fault analysis faulted point includes both currents from
of the power system. the power source (electric utility) and the
A power system is not static but changes fault contribution from electric motors
during operation (switching on or off of 3.1 Fault Analysis of Power System (both synchronous and induction) present
generators and transmission lines) and in the system. If in-plant generation is
during planning (addition of generators If the power system (typically an industrial involved, then the total fault current would
and transmission lines). Major changes system) is connected to the Utility, the be the sum of fault contributions from in-
would be considered a change in feed by supply authority shall supply the necessary plant generator(s), electric utility and from
the electric utility, in the primary or available fault levels at the point of in-plant electrical motors irrespective of
secondary system configuration within the network connection - both three-phase whether they are on the same faulted bus
facility, in transformer size or impedance, and single-phase, or the source impedance or on the downstream buses.
in conductor lengths or sizes, in type of and the corresponding X/R ratios. This will
circuit breaker, or a change in the motors help in analyzing the fault contributions 3.3 Factors Affecting Cable Selection and
that are energized by the system. Thus to/from the Utility. Any approved Ratings
fault studies need to be routinely software packages such as MiPower may
performed by utility engineers. be used or manual computations if the The above discussion briefly recognized the
system is simple. short circuit fault current influence on
The strength of a bus bar (or the ability to cable sizing and selection based on their
maintain its voltage) is directly As the power system constantly ampere ratings. Proper selection and
proportional to its short circuit capacity undergoes changes due to additions of ratings ensures their suitability in the
(SCC). An infinitely strong bus (or Infinite generators and/or distribution networks, power system. Therefore, it may be
bus bar) has an infinite SCC, with zero fault studies need to be performed concluded that the selection of power
equivalent impedance and will maintain its routinely. It would be prudent to consider cables generally depends on the following
voltage under all conditions. the short term expansion programs of the factors.
network while selecting switchgear
Magnitude of short circuit current is time capabilities so that the expected increase • Operating voltage
dependent due to synchronous in short circuit level could well be • Load current
generators. It is initially at its largest value accommodated. • Emergency loading requirements
and decreasing to steady value. These and duration
higher fault levels taxCircuit Breakers Single line to ground fault can be a • Fault current
adversely so that current limiting reactors concern when a delta-wye connected • Fault clearing time (Protection
are sometimes used. three-phase four-wire system or wye- relays & Fuses)
grounded generators are employed • Allowable voltage drop
The short circuit MVA is a better indicator especially when the substation • Ambient temperature for the
of the stress on CB’s than the short circuit transformers or generators are very close particular installation
current as CB has to withstand recovery or are close coupled to the distribution configuration
voltage across breaker following arc switchgear. When the distance is small the • (Environmental conditions)
interruption. The currents flowing during a zero sequence impedance is significantly • Cable route length
fault is determined by the internal emf’s of smaller than the positive and negative • Method of cable installation
machines in the network, by the sequence impedance. This difference can (derated factors)
impedances of the machines, and by the cause the single line to ground fault
impedances between the machines and magnitude to be up to theoretical
the fault. maximum of 150% of the magnitude of a
three phase fault.
Page 8 Power Research and Development Consultants
Newsletter

3.4 X/R Ratio the device will be higher (theoretical


maximum is 31% higher for a molded-case 4. References
The X/R ratio is a measure of the ratio of circuit breaker with interrupting rating
the inductive reactance (X), consisting of greater than 20 kA) than the actual [1] IEEE Std. 399 - IEEE Recommended
the inductive components of cable, calculated fault current if the X/R ratio Practice for Industrial and Commercial
transformer, generator, etc., impedances, calculated at the point of the fault is Power Systems Analysis., IEEE, Year
to the resistive components (R) of those greater than the X/R ratio for which the 1990.
impedances.Every practical electrical device has been tested.
power system has some inductive [2] ‘Computer Methods in Power System
reactance, making the X/R ratio always This can become an issue if the device has Analysis’ (Book) Stagg and EL-Abaid.,
larger than zero.An inductor stores energy an interrupting rating only marginally MaGraw Hill Publication, Year 1968.
in a magnetic field, which requires current higher than the available fault current.
flow. Because this energy cannot be Such a scenario unfortunately, occurs
[3] ‘Electrical Energy Systems Theory an
dissipated instantaneously an inductor often in data center applications,
Introduction’ (Book) Olle l. Elgerd., Tata
opposes changes to current flow. For fault especially where relatively large low-
MaGraw Hill Edition, Year 1983.
conditions, this means that after a fault is voltage generators are operated in
initiated there will be a DC offset to the parallel.
[4] Tinney, W. F. and Hart, C. E. “Power
fault current; the higher the X/R ratio, the
Flow Solution by Newton’s Method,”
higher the DC offset. This DC offset must With today's high fault currents, it's more
IEEE Transactions on Power Apparatus
be taken into account when calculating the important than ever to protect electrical
interrupting duty of fault interrupting equipment from extremely high current and Systems, vol. PAS-86, pp. 1444 -
devices such as circuit breakers. The result, levels. Otherwise, the equipment may 1460, Nov. 1967.
for low-voltage interrupting devices, is explode as it attempts to interrupt the
that the fault duty that is used in fault.Figure 2 shows the short circuit study [5] B Stott, O Alsac. Fast Decoupled Load
comparison to the interrupting rating of results for three phase to ground fault in Flow. Trans IEEE PAS 93: 859–869, 1974.
MVA obtained through MiPower software
for the sample system. [6] ‘Analysis of Faulted Power Systems’
(Book) Paul M Anderson., IEEE Press
Power Engineering Series, Year 1995.

[7] ‘Power System Analysis – Short


Circuit Load Flow And Harmonics’ (Book)
J. C. Das., Marcel Dekker Publication,
Year 2002.

Figure 2: Short circuit results for sample system


Power Research and Development Consultants
Page 9
Newsletter

Consultancy Services Rendered

grid connectivity. This would be Daily Work Schedules:Daily allocation


Fiji Grid Code applicable to all grid users, the ofwork as allotted by the supervisor to
system operator, transmission each individual or to the team as the case
The Government of Fiji plans to encourage licensee, IPPs and consumers. may be and designating thesafety auditors.
private sector participation in power • The Grid Code contains General
through Independent Power Producers Code, Planning Code, Connection Daily Safety Schedules:Details of the
(IPPs) and to form an independent entity Code, Operational Code and briefing by the supervisor before start of
to facilitate the regulation and Schedule & Dispatch Code.These the work and the precautionary measures
enforcement of the Electricity Act for the sections elaborate the role of all grid to be taken by the linemen during working.
electricity industry in Fiji. connected users, governing
rules,responsibilities, authorities, Inspection Schedules:Standard schedules
In view of the proposed modifications in obligations, planning criteria, of inspection prepared & tabulated
the structure and operation of the Fiji connection procedure , operation detailing points to be observed during
power system with private participants, procedureand scheduling and routine inspection of overhead lines, DTCs
revision of the existing Grid Code and its drawing procedure in the Grid for and RMUs in one’s Jurisdiction.
standardization was required to safeguard Grid Connectivity.
the electrical power system by specifying A set of informative booklet is also
the technical and operational Safety Work Book for included in the form of Annexure
characteristics of plants owned by comprising Tools and Plants to be
different entities involved in the BESCOM
maintained in an O & M Section , general
generation, transmission, distribution and BESCOM is one of the best managed safety precautions, work permit system,
consumption of electric power. In this DISCOMS in the country and has fixed its creating safety zone & procedure for
regard, Fiji Electricity Authority (FEA) own bench mark for efficient functioning earthing, Do’s and Don’ts , duties &
assigned responsibility of preparing the and is implementing ‘Best Practices’ responsibilitiesetc.,
new Grid Code to PRDC against a stiff formulated by it. The Utility has published
international competition. a number of manuals namely, ‘Standards Usage of Safety Work Book: The Safety
for Erection’, ‘Maintenance Schedules’, Work Book prepared separately for
The new Grid Codeof Fiji being the ‘Safety Manual’,’ ‘O & M Manual’, etc., for linemen and supervisory staff consists of
technical document containing rules implementation by its staff in daily two parts namely,
governing the planning, operation, routines.
maintenance and development of the 1. Every Day Entry Part: This has
power system has many salient features. BESCOM has now taken the initiative to different sections with checklists for
This document was prepared by PRDC prepare ‘Safety Work Books’ for daily execution of work, precautionary
considering the following: prevention of electrical accidents to the measures and general inspection
• Existing Grid Code structure, departmental staff and distribute the schedules. Every day entries have to
governing rules, responsibilities of same to all staff including linemen and be compulsorily made by the
grid connected entities and supervisory staff. PRDC was entrusted concerned section officer and the
operational philosophy were with the responsibility of preparing these lineman in his Safety Work Book in the
analyzed. In view of proposed safety workbooks.Based on the standard corresponding sections before, during
modifications in the Fiji electricity safety practices in various utilities and also and after execution of work as the
system, references from standard based on the expertise available with the case may be, depending on the type of
international grid codes of other consultants, the Safety Work Book was work and nature of inspections.
countries were taken. prepared for the linemen and supervisory 2. Reference Part: A set of informative
• The proposed Grid Code prepared by staff of BESCOM separately. This booklet.
PRDC clearly specifies roles of various document comprises different sections viz.
organizations/entities in Fiji andtheir The book has been submitted to BESCOM
responsibilities, General Particulars: Details of distribution and is being published by them for
participation,limitations and network in one’s Jurisdiction. distribution among its staff.
obligations for the
Page 10 Power Research and Development Consultants
Newsletter

levels of nearby substations, operation (including generation reserve


Power Evacuation Studies for checkthestability of the machines as per planning) of such renewable power plants.
the Proposed Concentrated security standards, assess the vulnerability Hence statistical analysis was carried out to
Solar Power Plants in / adaptability of 220kV, 400kV substations quantify variability of wind and solar
Rajasthan near the solar power plants and also to generation over multiple time frames
analyze the systemfor switching over (seasonal, daily, hourly and 10-minute).The
The solar energy potential in India is voltages. average daily profiles of wind, solar and
immense due to its location near the system demand were plotted for
Equator. India can generate over 1,900 Methodology and Technical Approach: seasonally representative months and for a
billion units of solar power annually, which The transmission network of Rajasthan period of one year (as shown in fig 1, 2, 3
is estimated to be enough to service the was modeled from 400kV voltage level and 4). Solar irradiation data were derived
entire annual power demand even in 2030. upto 132kV voltage level. As the system from the available direct normal Irradiance
From the solar irradiation map of India, it under consideration consists of wind data.
is evident that Rajasthan and Gujarat are generations, conventional generations and
the regions with maximum solar energy other solar generations, the power From detailed statistical analysis, it was
potential. Considering India’s solar evacuation schemes were analyzed observed that, when the solar generation is
potential, the government has rolled out comprehensively by considering the more than 70%, the wind generation is also
various policies and subsidy schemes to variability of wind, solar and system more than 70% during 3.8 - 10.6% of the
encourage growth of the solar industry. demand. Solar and wind generator period. During remaining time period, the
One such initiative is the Jawaharlal Nehru outputs vary as the intensity of their wind generation is only around 10%,which
National Solar Mission, formulated with a energy sources vary. Solar and wind is the most probable case. However, the
target of 20,000MW solar power by 2022. generation are similar to “load” which also adequacy of the system has been analyzed
With considerable amount of solar power varies over the day. The variability (over for wind and solar generation coinciding
generation getting interconnected to the 24 hours) and uncertainty (due to sudden peak (that is occurring for 3.8 - 10.6% of
grid, it becomes important to analyze the cloud cover for solar and wind speed the period as stated above). Based on
various consequences arising due to change in windpower plants) of these observations, different scenarios
interconnection with respect to voltage generation in solar and wind power plants considered for analysis are summarized in
profile at the grid network, short circuit needs to be considered in any network Table 1 and various power evacuation
level at the grid network etc. Hence, integration planning and options were analyzed.
detailed power system studies for the Table 1: Load Flow Scenarios
proposed solar power generations are Scenario Solar Generation % % Probability of
essential. A brief description of one such Month
No. Scenario Solar Wind Occurrence
study for a solar power evacuation project 1 Peak solar Jan-April 80 10 >60 %
executed by PRDC is presented. 2 generation period Sept - Dec 100 80 3.8%
Minimum solar
3 July - Aug 70 80 10.6 %
Study system has the total capacity of generation period
600MW comprising 500MW of
concentrated solar power (CSP) and
100MW of solar photo voltaic (SPV) which
is planned in Jaisalmer district of
Rajasthan in four phases viz. Phase I –
40MW (SPV), Phase II – 125MW(CSP) +
100MW (SPV), Phase III – 2x125MW(CSP) +
100MW (SPV), Phase IV – 4x125MW(CSP)
+ 100MW (SPV).The power evacuation
studies were carried outfor the proposed
solar generations. The objective of the
study was to identify: various evacuation
options, recommendation of the techno-
economically feasible evacuation
optionconsidering the most optimum
evacuation voltage, determination of short
circuit Fig 1: April
Power Research and Development Consultants
Page 11
Newsletter

For the recommended evacuation option


with 80% solar generation and 10% wind
generation (mentioned earlier as the most
occurring scenario), short circuit studies
were carried out. The transient stability
studies were also carried out for various
disturbances in the system. Further, over
voltage studies were carried out for the
various conditions.

Outcome of the Project:

• A techno-economically feasible
evacuation option suitable for all
Fig 2: June
the phases of generation was
recommended.

• Suitable breaker ratings were


recommended based on the
results of short circuit analysis.

• The critical clearing times and the


stability of the machine under
consideration for various
disturbances were determined
from transient stability analysis.

• Suitable surge arrestor was


recommended based on the
results of over voltage studies.

Fig 3: July

Fig 4: Annual Data


Page 12 Power Research and Development Consultants
Newsletter

Power System Stability Studies


Dr. R. Nagaraja

1. Introduction

Electrical power system is one of the most the utilities are well conversant with the Critical clearing time is that time, within
dynamic and complex human made steadystate analysis consisting ofload flow which the fault should be isolated so that
system on earth. Complexity is due to and faultstudies. However, as stability the machines in the system will not go out-
different voltage levels, amount of power studies involve the solution of both of-step. When the machine goes outof step,
being handled and the varieties of algebraic and differential equations, its power output oscillates from the
equipment being used. Dynamic, because representation of various controls in the generating mode to motoring mode and
of the time frame and response to system system, detailed modeling of the viceversa.
disturbances, this is of the order of several machines, that much importance is not
days for energy resource dynamics and empathized on the stability studies by the Most of the grid codes emphasize that
micro seconds to nano seconds during fast utilities. As the power systems increase in credible outages/contingencies in the
and very fast transients in the power size and complexity, more and more system shall not cause loss of supply,
system. Further, power system can be devices are added to control the power prolonged operation of the system
visualized as a spring mass problem, the system quantities, stability studies are frequency below andabove specified limits,
machines acting as masses and the gaining importance nowadays. This paper un-acceptable high or low voltage, system
interconnecting transmission lines as is written to help the practicing system instability, un-acceptable overloading of
springs. Whenever a spring is plucked and study engineers to understand the lines. Even though the references to voltage
released, oscillations are seen everywhere. concept of stability studies, data levels and the timing varies from grid code
Similarly in an interconnected system requirement for achieving different to grid code, typically for a specific grid
when a fault occurs, machines closer to objectives of stability studies and code, it states that stability of the system
fault swing more and the machines away emerging trends and technologies. should be ensured for the following cases –
from the fault swing less. Machines with Emphasis is given to understand the
higher inertia constant swing less and physical concept and interpretation of • 400 kV line: A permanent single
those with lower inertia constant swing results rather than detailed mathematical line to ground fault with a duration
more. This type of oscillations in the analysis, which can always be obtained of 5 cycles(100 milliseconds) with
power system falls under the classification from the reference books listed. unsuccessful re-closure 1.0 sec
of electro-mechanical oscillations, as it dead time followed by 3 pole
involves the interaction between the 2. Grid code references to stability opening of the faulted line.
electrical system transients and studies Unsuccessful re-closure (Figure 1)
mechanical transients of rotating masses. should be simulated and tested
Power system stability studies fall under Need for the stability studies are very before suggesting the au-re-closure
electro-mechanical oscillation studies. much emphasized in the national and facility for the 400 kV lines.
These studies are further classified into international grid codes. In this section,
transient stability studies for large references to some of the grid codes on • 220 kV and 132 kV lines: A
disturbances and small signal stability stability studies are drawn to emphasize permanent three phase fault with a
study or dynamic stability studies for small the importance of stability studies by fault clearing time of 8 cycles (160
disturbances in the system. In the planning and operational engineers. milliseconds)assuming 3 pole
transient stability studies one is generally opening.
interested in the rotor angle swing and in 2.1 Critical clearing time:
the dynamic stability study, the Further, grid codes emphasize that planning
performance of the various control Stability characteristics of the generators of the additional lines or elements in the
and the automatic voltage regulator are
functions to bring down the oscillations of system may become mandatory not
two important features that operate
different state variables in the system is because of the static contingency analysis
studied. throughout the period from the inception (load flow) but because of system stability
of the fault, until after its removal to considerations.
Most of the system studyengineers in the maintain voltage and stability ofthe
planning and operational departmentsof protective relaying.
Power Research and Development Consultants
Page 13
Newsletter

(amortissure winding) effect is seen along


with the field winding effect and armature
reaction. This impedance is termed as sub
transient reactance xd” along the direct
axis. When the damper winding effect has
decayed with sub transient open circuit
time constant Tdo”, we have the field
winding effect along with armature
reaction. This impedance is termed as
transient reactance xd’, which decays with
a time constant Tdo’, the transient open
circuit time constant. Finally one sees the
steady state reactance xd consisting of
leakage reactance and the reactance
arising out of armature reaction. Figure 2
gives the machine current when a dead
short circuit occurs at the terminal of a 210
Figure 1: Simulation of Unsuccessful re-closure
MW machine delivering initially the rated
power. Modeling of the machine in the
2.2 Model validation 3.1 General power system elements stability studies depends on what
model impedance value is considered and what
Accuracy of the stability studies depends voltage is represented behind that
on how best the computer models of the Modeling of the transmissionlines, reactance [1,2,3]. The simplest model is the
machine, control function tally with the transformers, series and shunt reactors classical representation of the machine,
real system. In most of the European and and capacitors in the stability studies is wherein constant voltage is represented
Australian Grid codes, it is mandatory to same as that in the load flow model. Pi behind the transient reactance xd’. Once
validate the machine model and the circuit model is used to represent the the data is formulated for the large system
control function performance before the transmission lines. The transformers are stability studies, it is advisable to go in for
commercial operation of the new power modeled using the leakage reactance classical representation of the machine to
plants. Computer simulation models are between the primary and the secondary get the first cut information on the
validated with reference to commissioning along with off nominal turn’s ratio. Series successful running of the model and
test reports and models are fine tuned. reactors and capacitors are modeled using validation for first swing stability studies. In
the reactance value at system frequency. the transient model of the machine,
3. Modeling and data requirement Shunt reactors and capacitors are differential equations governing the
modeled by computing the shunt variation of the transient direct and
System model for the stability studies admittance value at the rated voltage and quadratrue axis voltages (Ed’ and Eq’) with
depends on the type of study and the rated MVAr rating and applying the respect to time are represented. In the sub
duration for which the simulation is correction at bus base voltage. Stability transient model of the machine, in addition
carried out. In the load flow study, studies require the converged load flow to above two differential equations, the
internals of the machine is not study results as input to establish the differential equations governing the
represented. Also, in the load flow study it initial conditions in the solution of variation of the sub transient direct and
is assumed that terminal voltage of the differential equations. At each time step of quadrature axis voltages (Ed” and Eq”) with
machine is maintained within its reactive the stability study, the power flow solution respect to time are represented. In all the
power limits by the AVR and the scheduled is obtained. cases, the machine swing equation is also
power output of the machine is also represented. The inertia constant of the
maintained constant. However, in the 3.2 Machine model machine is the combined inertia constant
stability study, detailed modeling of the of all the rotating masses, i.e. turbine,
machine, associated control system When one sitting at the terminal of the generator rotor and the excitation system.
representation is very much essential. In machine, looks into the machine, at When the generator and the turbine
this section, equipment modeling for the different intervals oftime following a vendors are different, inertia
stability studies is explained in brief. disturbance, different impedance values constantfurnished by the respective
are seen. Initially the damper winding vendors should be converted onto
common base and
Page 14 Power Research and Development Consultants
Newsletter

added to arrive at asingle inertia constant For one Hz change in the frequency, the done by single machine
value to be used in the swing equation change in real power is defined as the performanceconnected to infinite bus or
solution.During the planning exercise, the power number of the system.Power radial load. Voltage and frequency plots
typical values of the machine for the number of the system depends on the forload throw off and pickup are cross
proposed machines can be considered. base load and the load mix i.e.industrial, checked with the design calculations and
However, for the existing machines and for commercial, domestic, agricultural etc. As commissioning reports to fine tune the
operation studies, the data supplied by the the load mix changes with season, power model.
manufacturer should be considered and number of the system also exhibits
further validated by the commissioning seasonal variations. 3.5 High Voltage Direct Current (HVDC)
test reports. system model

The modeling of the HVDC system becomes


important as HVDC Transmission link is
fully controllable, during transient
disturbance, the dc power can be ramped
down rapidly to reduce the
generation/load un-balance in ac system
on both sides, the dc power can be ramped
to assist in system stability by taking
advantage of the short term over load
capability of the HVDC system and from the
viewpoint of the ac system performance,
the rapid control of dc power hasthe same
beneficial effect as generator/load tripping.
HVDC system with proper control can also
damp out the low frequency oscillations in
Figure 2: Current during dead short circuit at machine terminal
the ac system (Figures 3 and 4).
3.3 Load model 3.4 Automatic Voltage Regulator (AVR) When the load flow analysis is performed
and turbine & governor model on the AC-DC interconnected system,
Both voltage and frequency dependency constant voltage, current or power control
modeling of the loads in stability studies For the first swing stability study, of the convertor station is modeled
give realistic results. Generally in stability modeling of the AVR, turbine & governor representing the DC system as a pure
studies involving fault, loads are control system is not required. However, if resistive network [1, 4]. The firing angle at
represented as impedance model, the stability study simulation is beyond the the rectifier station and extinction angle at
computed at the end of initial load flow first swing response, representation of the the inverter station or the converter
solution taking the power and the bus AVR is a must. Further, if the simulation transformer tap setting at converter
voltage. However, this model will not hold study is beyond three seconds, turbine & stations arethe un-known quantities. In the
good for the realistic governor control systemrepresentation is stability studies, the converter transformer
systemrepresentation, that too for studies necessitated. In the stability studies, AVR, tap setting is generally fixed at the value
pertaining to controlled system separation turbine & governor control systems are obtained from the initial load flow study
and load shedding. For such studies, loads modeled using transfer function blocks. and the objective is to find the AC-DC
are represented as a function of both Transfer function block gives the system interaction for ac system fault, dc
voltage and frequency [1]. Voltage relationship between the input and output system fault, change in converter power
dependency of the load is represented variables in frequency domain. Most of reference etc. Detailed firing angle control
using the polynomial model. Constant the software tools for the stability studies system is modeled using the transfer
power, constant current and constant support the standard control blocks as function block [1] along with the
impedance coefficients are obtained from defined by IEEE [1]. However, for specific VoltageDependent Current Order Limiter
measurementstudies or computed from control system model, it is advisable to (VDCOL) and other control functions. DC
composite model of the load. Frequency use the free programmable capability of link is represented as a T-model comprising
dependency coefficient is obtained from the software, withoutapproximating or dc line series resistance, inductance and
the power number of the system. reducing it to standard blocks. Once the shunt capacitance. At each time step of the
model is represented, model validation is stability study, algebraic and differential
equations of the AC-DC systems are solved.
Power Research and Development Consultants
Page 15
Newsletter

Right of way being the major hurdle for


building new lines in the system, judicious
deployment of FACTS devices has become
compulsion rather than luxury in the
present day AC system. Steady state
performance of the FACTS devices can be
modeled and studied in the load flow
analysis.However, their interac
interaction with
the other AC systems,control to enhance
the system stability anddamp
anddampingof the low
frequency oscillationsare better
understood byproper modeling of these
devices in the stability studies.
SVC, a shunt FAC FACTS device model [1]
consists of:
• The voltageage and current measuring
Figure 3: AC system voltage oscillations without HVDC system control (and filtering) circuits.
• A regulator including possible
additional signals fed to the
reference point.
• Additional control signals which are
used for damping improvement
• A distribution unit
• A model of the thyristor susceptance
control
trol module
• A model of the interface with the
power system (a controlled
susceptance)
It is recommended to obtain the exact
control circuit and the associated gains,
time constants and the limiter values from
the supplier to model the FACTS devices in
the stability studies in a realistic manner,
rather than using standard blocks and
Figure 4: AC system voltages with HVDC system damping control typical values.

3.6 Flexible AC Transmission System


(FACTS) model
AC system performance and loading can
be greatly enhanced by suitable
deployment of series and shunt FACTS
devices in the system[5]. Shunt FACTS
devices help in the reactive power
management in the AC system and there
by control the system voltage. Figure 5
showsthe improvement in the voltage
performance with individual phase
compensation static var compensator
(SVC) following a disturbance.

Series FACTS devices enhance the Figure 5: Voltage Balancing with Individual Phase Compensation SVC
powertransfer capability of the AC lines.
Page 16 Power Research and Development Consultants
Newsletter

3.7 Protection system model

For the operational studies to simulate the


grid disturbances and to fine tune the
distance and frequency relay settings, it
becomes essential to model the protection
relays. Re-shaping of thedistance relay
characteristics to avoid the load
encroachment is better performed by
modeling the distance relays (Figure 6). If
the fault iscleared beyond the critical
clearing time, themachines go out of step
and the same can be better visualized by
plotting impedance loci in R-X plane Figure 6: Distance relay simulation to ascertain the load encroachment
(Figure 7). The relay settings to achieve the
controlled system separation to avoid the
total black out is simulated by modeling
the out of step protection (Figure 8) and
under frequency and over frequency
relays.

Thequantum of load shedding to be done


to avoid the black out after the system
separation, the frequency at which the
load shedding to be done and the time
delay involved should be selected such
that the generators in the system do not
trip on under frequency (Figure 9).
Referring to figure 9, without the under
frequency load shedding, as the frequency
falls to as low as 42.7 Hz, many of the
generators would have tripped, since the Figure 7: Impedance loci when fault is cleared beyond the critical clearing time
under frequency setting for the generator
protection is generally at 47.5 Hz with 2-3
seconds time delay.

Frequency based system separation should


happen first, followed by the load
shedding and as a final resort the
generator tripping. This implies that all the
three frequency relay settings should be
properly coordinated in terms of
frequency set point and the time delay. If
the system sees higher frequency after the
islanding, it is worthwhile to trip few
generators in the system to avoid the
generator tripping on over frequency or
the turbine tripping on over speed.

Figure 8: Out of step protection operation after three slip counts


Power Research and Development Consultants
Page 17
Newsletter

Figure 10 shows the reactive power


typically drawn by two healthy feeders in a
distribution system following a fault and
removal of the faulty feeder. High reactive
current drawn by the dynamic loads in the
healthy feeders at times may trip the
feeders, if the protection settings are not
fine-tuned to overcome this issue,
specifically with delayed clearing of the
healthy feeder fault.

5.Stability studies for industrial system

Figure 9: Frequency response with and without under frequency load shedding Many of the stability case studies typically
carried out for the utility system are
4. Stability studies for utility system dynamic voltage instability assessment, alsoapplicable to the industrial system,
selection, sizing and optimal location of especially when the industrial system
Stability case studies typically performed FACTS devices, interaction between isembedded with own generation
for the utility systems are explained with different devices and their controls, (captivepower plant - CPP).
its importance in the modeling section. system performance with renewable
The case studies to be performed depend energy integration like solar and wind, Stability studies are to be conducted to
on the conclusions to be drawn from the which are infirm in nature. In those arrive at the proper grid islanding schemes
studies and the necessary corrective systems having predominantly air and required relay settings, under
actions to be taken to control and protect conditioning loads, it is necessary to frequency based load shedding within the
the interconnected system. Studies ascertain the system performance during plant after the load shedding so that the
typically conducted are for determining the phenomenon called sympathetic CPP generator under frequency protection
the critical clearing time for different types tripping. will not operate during that condition.
of faults, system performance during un- Starting of large motor and analysis of the
successful re-closure, equipment tripping Operation of the protection system in the voltage dip during starting is another
(n-1 and n-2 outage) following a fault, healthy feeders due to the huge current typical study generally carried out in the
generator parameter evaluation, fine being drawn by its dynamic loads when industrial systems.
tuning the AVR, turbine-governor, PSS, the faulty feeder protection system
HVDC, FACTS device control block settings, operates is termed as sympathetic
study of power swing phenomenon and tripping.
performance of distance relay blocking
settings, study of load encroachment
problems and re-shaping the distance
relay settings, arriving at under frequency
and df/dt relay based load shedding
schemes, over frequency based system
separation and generator tripping. Special
case studies to be performed are identified
based on the problems envisaged in the
operation and control of interconnected
systems. Some of the stability studies
performed are design and implementation
of special protection schemes when major
chunk of load or generation is lost (e.g.
loss of HVDC system, loss of major AC tie
lines between two interconnected
Figure 10: Reactive power drawn by healthy feeders
systems), transformer tap control and
Page 18 Power Research and Development Consultants
Newsletter

Worst system conditions for the motor Good amount of research work is going on
starting like minimum grid fault level, to validate and improve the transient
minimum CPP generation etc. are to be stability model with the PMU data
identified and studies are conducted. In recording included.
case of arc furnace loads, the transient
voltage dip at the grid bus (PCC) and the 7. Conclusions
requirement, sizing and performance
tuning of the SVC are done using stability In this paper, an attempt is made to
studies. For the industrial plants having explain the importance of the stability
the rolling mill loads, loads are studies to practicing engineers. References
represented as cyclic loads and system to grid codes are drawn to insist that the
voltage and frequency variations are stability studies should be conducted to
ascertained. This study will help to take ascertain the transient and dynamic
appropriate decision to run the plant behavior of the power system, following
rolling mills or varying loads with the CPP the disturbance. Modeling of equipment
without any grid support. for stability studies is discussed. Analysis
and interpretation of results are illustrated
6.Wide area measurement and its through case studies under each section.
application
8. References
To facilitate the wide area monitoring,
control and disturbance analysis, to [1] Prabha Kundur , “Power System Stability
minimize the future black outs caused due and Control”, (Book), McGraw-Hill Professional
to the cascade tripping, there is a growing Publishing, 1994.
interest in Phasor Measurement Unit
[2] J.Arrillaga, “Computer Modeling of Electrical
(PMU). The introduction of PMU
Power Systems”, (Book), Wiley-Blackwell, 2nd
technology can significantly improve Edition, 2001.
theobservability of the power system
dynamics. It can warn system operators of [3] Edward Wilson Kimbark , “Power System
potential problems more quickly during Stability”, (Book), Volumes I, II, III , Wiley-IEEE
critical situations. PMUs would be very Press, 1995
useful in determining where and how to
perform system separation to limit the [4] K.R.Padiyar, “HVDC Power Transmission
Systems”, (Book), New Age International, 1990
effect of the system disturbance.
[5] K.R.Padiyar, “FACTS Controllers in Power
The major areas of applications of PMU Transmission and Distribution”, (Book), New
are Age International P Ltd, 2007

• Wide area systems dynamic


recording
• Real time system state
determination
• Phase angle monitoring
applications
• System oscillations monitoring
• Wide area protection and control
• Model validation
Power Research and Development Consultants
Page 19
Newsletter

Small Signal Stability in Power Systems


Prof. K. R. Padiyar

I. Introduction A cost efficient and satisfactory solution to Real solutions for ?D and D define
Historically, transient (angle or the problem of oscillatory instability is to equilibrium values. In general, equilibrium
synchronous) stability has been a major provide damping for the generator rotor values are functions of the parameters ‘B’.
concern in the system operation. It was oscillations. This is conveniently done by
anticipated that the introduction of high providing Power System Stabilizers (PSS) Considering small perturbations around

? ?D F,
gain AVR and fast acting exciter will help in which are supplementary controllers in the equilibrium point, we can define
the improvement of transient stability in the excitation systems. The control signal D
addition to the increase in steady state VS in Fig.1 (which shows the block diagram
stability limit. It is to be noted that the for a static exciter)is the output of a PSS and obtain the linearized state equation
AVR acts to overcome the armature
reaction and thus reduce the effective
reactance of the generators (from Xd to
around X'd ). As a matter of fact, modern
turbo-generators cannot operate at full
rated power, as the synchronous
reactance, Xd, is around 2.0 pu.

Although transient stability can be


improved by fast acting excitation system Fig 1: Block diagram of static exciter
with high gain AVR, this introduces a new

F@ GH F
problem of oscillatory instability of the
which has input signal derived from speed (3)
equilibrium (operating) point. Even small
(rotor velocity) or frequency or electrical
perturbations in the system caused by
power (or a combination of these
IA IA IC IC
random load changes can lead to loss of where,
GH GJ ,G
variables). The objective of PSS design is to
I? I I? J I
synchronous stability (loss of synchronism)
increase the damping torque on the
due to undamped (growing) oscillations
generator rotor without affecting the
Note that G H is termed as the system
which appear as spontaneous and cannot
synchronizing torque at the critical
Jacobian and GJ is the load flow Jacobian.
be predicted as the result of an observable
frequencies.
major disturbance.
It is assumed that the load flow Jacobian is
The system operators observed that II. Basic Concepts of Stability of non-singular.
tripping (or disabling) of the AVR resulted Equilibrium Point
in damping of the oscillations. However, The stability of the equilibrium point is
this is not a viable strategy. DeMello and We can describe the mathematical model judged by the location of the eigenvalues
Concordia (1969) presented a simplified of a power system by the following set of of the system Jacobian matrix. If the real
analysis of the problem, using Heffron- differential and algebraic equations (DAE). parts of all eigenvalues of the system

?@ A <?, , B=
Phillips constants defined for a SMIB Jacobian are negative, the system is
system (Padiyar, 2002). It was explained (1) asymptotically stable. If one or more

0 C <?, , B=
that the problem of oscillatory instability is eigenvalues have positive real part, then
aggravated at peak loading conditions and (2) the system is unstable.

Where ? is the state (variable) vector


high system impedances(viewed from the
generator terminals). In general, the major Although the criterion is valid for very
factors that contribute to the instability defining the dynamic (differential) small perturbations(caused by small,
are: equations. is the vector of voltage random load changes), several analytical
magnitudes and angles at buses other studies (Busby,1979, Van Ness,1980) show
a) Loading of the generator or tie line than the generator internal buses. ‘B’ is a excellent correlation between theory and
b) Power transfer capability of the vector of transmission and load field tests.
transmission lines and parameters (which are assumed to be

then obtain equilibrium values (?@D and D@ )


c) Power factor of the generator. The constant at an operating point). We can For classical models of generators

of ? and by equating ?@D 0 and thus


leading power factor operation is more (represented by constant voltage sources
behind transient reactance), neglecting
solving for A 0, C 0.
problematic than the lagging power factor
operation. damping, we can derive a second order
Page 20 Power Research and Development Consultants
Newsletter

vector differential equation given by systems which can be divided into distinct synthesized from the electric power and
KB Δ* MΔ*(4)
areas and which are separated by long speed signals.
distances. For systems in which the The gain of PSS is to be chosen to provide
generating stations are distributed adequate damping of all the critical modes
where M is a diagonal matrix with
OP
KNN
uniformly over a geographical area, it under various operating conditions. The
QR
(SN is the inertia constant of would be difficult to distinguish between critical modes include not only local and
machine ‘ ’). Neglecting losses, M#N
TUVW local and interarea modes from physical interarea modes, but other modes (termed
TXP considerations. However, a common as control or exciter modes) introduced by
where D# is the power output of machine
‘'’. The matrix M is singular and has the
observation is that the interarea modes the excitation system and/or torsional

rank Y <Z 1= where ‘Z’ is the number


have lowest frequency and highest filter.
participation from generators in the It is to be noted that PSS is to be tuned at a

<Z 1= relative angles that can be


of machines. This indicates that there are system spread over a wide geographical particular operating condition which is
area. most critical. This leads to optimum
defined . There is no loss of generality in damping at the critical operating condition

Thus, the <Z 1= vector of relative angles rotor are adequate to damp intra-plant
assuming the machine 1 as the reference. The amortisseur circuits on a generator and satisfactory damping at other
operating conditions. The output of PSS
can be expressed as: modes. PSS is designed mainly to stabilize must be limited to prevent PSS acting

Δ* [ ∑e N 1\N cos `N a bN sin `N a6 (5) must be taken to avoid unfavourable


local and interarea modes. However, care counter to the AVR action. For example,
N& when load rejection takes place, the AVR

Where Δ* [ fΔ* Δ*4 … . Δ*e hi is the


interaction with intra-plant modes. acts to reduce the terminal voltage
whereas the PSS action calls for a higher
(Δ*#
Δ*# Δ* , j , … . je , b , b , … . be
vector of relative angles III. Design of PSS value of the terminal voltage due to
are The block diagram of a PSS used in increase in the speed or frequency. It may
scalars depending on the initial industry is shown in Fig.2. The washout even be necessary to trip the PSS in case of
conditions). circuit ensures that the output of PSS is load rejection. The negative limit of PSS
zero in steady state. The PSS is expected output is of importance during the
The structure of the vector N depicts the to respond only to transient variations in backswing of the rotor. While AVR action is

oscillatory mode whose frequency is `N . be required with speed input signal as it is


participation of various machines in the the input signal. The torsional filter may required to maintain the voltage and
prevent loss of synchronism (after the
Typically, the frequency varies from 0.2 to inherently sensitive to the presence of angularseparation has increased). PSS
3.5 Hz. The radian frequencies are torsional oscillations at frequencies in the action in the negative direction must be
obtained as the square roots of the non- range of 8-20 Hz. This can lead to negative curtailed more than in the positive

fK Mh.
zero and real eigenvalues of the matrix damping of the torsional mode. direction.

In a practical system, the various modes of


oscillation can be grouped into 3 broad
categories. (Larsen and Swann,1981)
1) Intra-plant modes in which only the
generators in a plant participate.
The frequencies of these modes are Fig 2: Block diagram of PSS
higher up to 3.5 Hz.
2) Local modes in which several The transfer function of the dynamic
generators in an area participate. compensator, T(s) is typically given by IV. Stabilization through HVDC Converter
the frequencies are in the range of and FACTS Controllers
mn < 3 o =< 3 op =
0.8-1.8 Hz. k <l= < 3 o =< 3 oq=
(6) It is now a well-established practice to
k r k , k r k
3) Interarea modes in which
generators over an extensive area where, 4 s In general, the apply fast acting high power electronic
participate. The oscillation compensator provides a phase lead in the controllersused in the transmission
frequencies are low and in the range of frequencies of swing modes.The network for the modulationof power flow
range of 0.2-0.5 Hz. required phase lead depends on the in a line fordamping oscillations.The first
It is to be noted that the distinction exciterresponse and the control signal such application was in HVDC links using
between the local modes and interarea used. The acceleration signaltends tobethe converter controls.The control signals used
modes applies mainly to those best input signal to use and can be are bus frequency deviations or power flow
Power Research and Development Consultants
Page 21
Newsletter

in a parallel AC tie. The power modulation of troublesome swing modes is normally [6] Byerly et al.(1982).Eigenvalue analysis
(normally applied at the rectifier station) is done by experiments and transient of synchronizing power flow
the primary damping control. However, records of relevant system variables. Also, oscillations in large electric power
with weak AC systems (low SCRs), both design of damping controllers requires systems. IEEE Trans.PAS-100(1),
active and reactive power modulation are more detailed system models that capture pp.235-243
implemented using rectifier and inverter the dynamics of interest. In this context,
stations. Also, the modulation of extinction Selective Modal Analysis (SMA) techniques [7] Wong D.Y. et al.(1988).Eigenvalue
angle at the inverter, in response to the AC developed at MIT (Perez-Arriaga,1982) are analysis of very large power systems.
voltage magnitude signal can avoid voltage of interest. IEEE Trans. Power Systems,103(2),
instability. pp.472-480
Generally, we consider reduced system
Small signal power modulation models with adequate detail for analysis [8] Perez-Arriaga et al.(1982).Selective
implemented at Pacific DC intertie has and control design. Padiyar(2002) modal analysis with applications to
helped to prevent interarea mode of 1/3 describes modeling techniques based on electric power systems ,Part I: Heuristic
Hz from reducing power transfer capability identifying individual dynamic devices and introduction; Part II: The dynamic
of a parallel AC tie. The power or current their connections to the network. The AC stability problem. IEEE Trans.PAS-
modulation has now become a standard network is modeled by linearized algebraic 101(9), pp.3117-3134
practice.HVDC technology of using equations using rectangular or polar
thyristor valves for control was extended coordinates. For tuning multiple damping
to develop Static Var Compensators (SVC) controllers, one can use nonlinear
for voltage regulation and Thyristor programming techniques that consider
Controlled Series Capacitors (TCSC) for constraints on the locations of eigenvalues
power flow control. These controllers in a sector in the LHP of s-domain.
belong to the first generation of FACTS
controllers. Supplementary Modulation VI. References
Controllers (SMC) has been applied for
reactive power modulation in SVC and [1] Padiyar K.R. (2002). Power System
help to damp swing modes. Similarly, Dynamics-Stability and Control
power swing damping control is an (Second Edition), Hyderabad: BS
auxiliary control in TCSC that supplement Publications
PSS action. New and emerging FACTS
controllers such as STATCOM, SSSC, UPFC [2] DeMello F.P and C.Concordia
and IPFC are based on Voltage Source (1969).Concepts of synchronous
Converters that use self-commutated machine stability as affected by
devices such as GTO or IGBT. STATCOM is excitation control IEEE Trans. PAS-
a shunt controller that may replace SVC 88(4),pp.316-329
and the reactive power modulation is
[3] Busby et al. (1979).Dynamic stability
expected to improve small signal stability.
improvement at Monticello station-
V. System Models and Modal Analysis in analytical study and field tests IEEE
Large Power Systems Trans.PAS-98(3), pp.889-901

In the eighties, computer programs for the [4] Van Ness J.E. et al.(1980).Analytical
eigenvalue analysis of large power systems investigations of dynamic instability
have been developed. Examples are, occurring at Powerton station. IEEE
AESOPS (Analysis of Essentially Trans.PAS-99(4), pp.1386-1395
Spontaneous Oscillations in Power
Systems)(Byerly,1982) and PEALS [5] Larsen E.V. and D.A. Swann
(Program for Eigenvalues of Large (1981).Applying Power System
Systems)(Wong,1988). These programs Stabilizers-Parts I,II and III .IEEE Trans.
generally consider classical models of PAS-100(6), pp.3017-3046
generators and can handle up to 1000
generators. However, identification
Page 22 Power Research and Development Consultants
Newsletter

Voltage Stability - Fundamentals and State-of-the-art


Dr. G.Govinda Rao

I. Introduction (2) A power system ata givenoperating flow equations


Power System Stability dates back to early state and subjected to a given disturbance aresimultaneously/sequentially solved to
20th century while the voltage stability is undergoes voltage collapse if post test for instability and to arrive at control
of more recent times and approximately disturbance equilibrium values are below strategies. Along with rotor angles and
dates back to last decades of 20th century. acceptable limits. Voltage collapse may be speeds, the bus voltage magnitudes are
Why should there be such a time gap? total or partial black out. also computed following a large or small
Are both the phenomena different? This (3) Voltage instability stems from an disturbance. Following a disturbance if the
question is addressed in reviewing the attempt of load dynamics to restore bus voltage falls below the acceptable
fundamentals of the voltage stability. Over power consumption beyond the capability limits, the phenomenon can be referred to
the span of one century, power networks of the combined transmission and as voltage instability, in the dynamic sense.
have grown in size, sophistication and generation systems. But this phenomenon is known long back
technological advancement. The problem III. Transmission Capabilities of Real and as associated with angle-stability.
of voltage instability therefore is more a Reactive Powers The important concept of voltage
problem of large networks and hence it is The steady state load flow equations put a instability viewed wholly as a static viability
categorically said that it’s a problem of power limit transferable to loads. The problem will be discussed now. In this
developed countries. The problem is due active power can be transmitted over problem the power grid with respect to
to either insufficient or inefficient longer distances compared to reactive load buses is viewed as multiport static
management of creating a balance power, because the transmission lines are transmission (distribution) network. The
between active and reactive power less resistive and more reactive causing loads are usually largely inductive. If the
sources and loads together with their more losses in the case of reactive power. generation-transmission network is
controllers. incapable of supplying the load reactive
II. Fundamental Aspects Fig. 1 shows the block schematic of the power for set active powers, the bus
In 2004, CIGRE-IEEE Joint committees classification of voltage stability. voltages drastically fall to very low and
revised the existing definitions in the unacceptable values creating voltage
literature from a fundamental view point. collapse conditions. Similar conditions also
Broadly the committees categorized the prevail if the network is unable to supply
power system stability into a) angle active loads. For analysis purpose, a P-Q
stability, (b) frequency stability and (c) load at a bus is considered, treating rest of
voltage stability. These three terms are the grid as Thevenin’s voltage source. The
sometimes mutually inclusive and equation relating the source voltage, load
sometimes mutually exclusive. The voltage, impedance parameters and P&Q
phenomenon of stability is essentially of a Fig 1: Voltage Stability Categories of the load play a central role in
dynamic system and is governed by the determining voltage stability of the load,
well established mathematical and system The long-term voltage stability problem stability margins and the remedial
theories. Thus the definitions evolved are can further be classified into two strategies to be adopted using Q-V and P-V
well within the framework of these categories. In the first one, the problem is curves [1, 2, 5].
mathematical theories. The rotor angle that of long term dynamic system and in V. The Role of Q-V Characteristic
stability and frequency stability are the second one the ‘long–term’ Because the transmission network is largely
governed by differential equations accommodates the generators to settle to an inductive network, reactive power
concerning rotor dynamics. But their quasi- steady state. However, the cannot be transmitted over long distances,
thevoltagestability is being viewed both as voltage of buses fall out drastically to very as much as the real power can be
a dynamic problem and also as a static low values, often referred as voltage transmitted.
problem. The following are some collapse creating black-out or brown-out The reference [5] presents a complete Q-V
definitions of voltage stability as given by conditions, commonly seen in several characteristic analysis giving exact
the said committee and text book western countries. expressions for voltage collapse point i.e.
literature. IV. Voltage Instability Considered as a the nose of the Q-V characteristic. The
Definitions [1, 2, 3]: Dynamic Problem distance of any operating point from the
(1) A power system at any given operating Power system stability problem nose point gives the reactive power
state and subjected to a given isessentially keeping two or more margin. A family of Q-Vcharacteristics
disturbanceis voltage stable, if voltages generators in synchronism.The set fordifferent real powers help in scheduling
near loadsapproach post disturbance ofdifferential equations governing generator powers.The Q-V and P-
equilibriumvalues. rotordynamicstogether withthe Vcharacteristics are usually based on a
Power Research and Development Consultants
Page 23
Newsletter

model containing a generator(as aslack generator load dynamics are analyzed by deviations in voltage across motor
bus) feeding P-Q load via a lossless line. using nonlinear simulation. For small and terminals resulted in the stability of
With respect to a power grid delivering a short-term disturbances, linearized synchronous motor with a constancy of
P-Q load, the grid is considered as a models (around operating region) are used voltage across motor terminals. Further,
Thevenin’s equivalent. The best way of for making an Eigen value/Eigen vector the fluctuating reactive load also was
getting this Thevenin’s equivalent together analysis. (In this it is very involving if tap causing fluctuations in the voltage at the
with its limitations is discussed elaborately changers are used in the model.)For long- load bus as well as fluctuations in tie-line
in [6]. This model can be used only for a term small or large disturbances, P-V & Q- power oscillations. A Static VAR
rough assessment of voltage stability V analysis is performed for obtaining compensator designed suitably resulted in
margin. The regular load flow methods are stability margin. Sensitivity analysis using a minimal fluctuation and a flat voltage
to be used for accurate assessment. L-indices is also largely being performed. profile.
The Voltage-instability can also be viewed For large networks, ANN based algorithm, X. Conclusion
as a dynamic problem wholly caused by Fuzzy Controlling Techniques, neuro- The phenomenon of voltage-instability is
loads. When the loads (induction motors) computing using genetic algorithms for very subtle and here is a quote by one of
change governed by differential equations, optimization of active and reactive powers pioneering authors, Carsow W. Taylor:
an Eigen value analysis for small are being attempted. “May be I can’t define voltage stability, but
perturbations or a nonlinear dynamics The EPRI and Energy Corporation have I know it, when I see it”.
analysis for large disturbances, will usually validated a method developed by EPRI for
XI. References:
be conducted. This kind of voltage- continuously calculating the voltage
[1] ‘Power System Voltage Stability’, Carson W.
instability could be totally different from stability margin on transmission networks Taylor, McGraw-Hill International Edition,
the angle-instability. using measurements from the CT and PTs 1994.
VI. Voltage Stability Indices at the substation level. The method [2] ‘Voltage Stability of Electric Power
Voltage Collapse Proximity Indicator (VCPI) promises to overcome thelimitationsof Systems’, Thierry van custemcostas
is the total change in generator reactive traditionalmethods that rely primarily on vicunas, Springer, 1998, ISBN 0792381394
power for a change in demand. Two such simulation-based methods developed [3] ‘Definitions - Classification of Power System
from the data used at planning level. Stability’, IEEE-CIGRE, IEEE Transactions on

VCPIPi =∑ ∆ g/∆ i
indicators are proposed in literature [1]:
Power Systems, Vol. 19, No.2, May 2004.
VIII. Prevention of Voltage Collapse [4] ‘EPRI and Entergy Validate Measurement-
VCPIqi=∑ ∆ g/∆C i
To prevent voltage collapse, the Based Voltage Stability Monitoring to
assessment of voltage stability along with Improve Grid Reliability and capacitive
(The buses with large values of VCPI are the available margin is very essential. effectiveness’, EPRI News Release Feb
the most effective locations for load Once that is possible, the conventional 2009.
shedding. The indices change from unity at remedial measures of activating reactive [5] ‘Voltage Stability: Some Refection on Q-V
light load to almost infinity at voltage Characteristics of Loads’, G. Govinda Rao,
compensating devices like thyristor
H. P. Khincha, D. Thukaram, proceedings
∑ ∆ g is computed considering SVCs also
collapse) controlled VAR compensators, generator
1998, Int. conf. on EMPD, Singapore, IEEE
excitation controllers, on-load tap Catalog No. 98EX137.
as reactive generators. changers etc. can be carried out. Under [6] “Model Validation Studies in Obtaining Q-V
The voltage stability for the static case is voltage load shedding is also in practice to characteristics of PQ Loads in Respect of
analyzed by performing load flow studies move the operating point far from the Reactive Power Management and Voltage
to determine ‘L-indices’. If there are g- nose point. Adequate spinningreservealso Stability”, G. Govinda Rao, K. V. S. R.
generators, and g+1 to n load buses, the L- helps in increasing the stability margin. Murthy, IEEE International Conference on
index for the voltage stability for the jth Power Electronics, Drives and Energy
load bus is given by Systems for Industrial Growth PEDES, New
{
IX. Author’s Experience
xy
Lj =1-u Fw x
Delhi, Dec, 2006.
; j = g+1…n Case studies were conducted on a power
#&
[7] “An Expert Fuzzy Control Approach to
z grid supplying a steel plant actuated by
Voltage Stability Enhancement”, A.
All quantities in this equation are complex cyclic P-Q loads of about 80 seconds NarendranathUdupa, D.Thukaram,
in nature and Fji are elements of FLGmatrix. periodicity. A synchronous motor was K.Parthasarathy, ELSEVIER, Electric Power
If the L-index is close to zero, the load bus found to be experiencing long-term and Energy Systems 21 (1999) pp. 279-287.
is voltage stable. If it is close tounity, the voltage instability, on simulation of the [8] “Voltage Dependent Reactive Power Limits
load is nearing instability [7]. non-linear model of the grid. Interestingly, for Voltage Stability Studies”, P. A. Lof, G.
VII. State-of-the-art in Simulation an automatic voltage regulator actuated Anderson and D. J. Hill, IEEE Transactions
Methodologies on Power Systems, Vol.10, No.1, Feb.1995.
For large and short-term disturbances,
Page 24 Power Research and Development Consultants
Newsletter

Harmonic Studies
Dr. R. Nagaraja

of harmonic currents, where harmonic Switch-mode power supplies (SMPS),


1. Introduction frequencies are generally considered to be variable speed motors and drives,
There are basically four attributes to integer multiples of the system frequency. photocopiers, personal computers, laser
define the power quality of a given power However, certain nonlinear loads, such as printers, fax machines, battery chargers
system viz., voltage, frequency, unbalance an arc furnace or a cyclo-convertor, may and UPSs are examples of nonlinear loads.
in the system and harmonics. Voltage also have non-integer harmonic Single-phase non-linear loads are prevalent
should be within the acceptable limit as frequencies in addition to the expected in modern office buildings, while three-
per the specific grid codes both during integer harmonics. References [1] to [6] phase, non-linear loads are widespread in
steady state and transient conditions. Due cover in depth the harmonic issues, power factories and industrial plants.
to various measures taken by the CTU and system equipment modelling techniques
STUs in India, the voltage at the 220 kV for harmonic analysis and harmonic These non-linear loads create significant
and 400 kV levels have considerably problem mitigation techniques. Reference distortion in the electrical current and
improved in the recent past. At places, it is [7] discusses the computer modelling for voltage wave shape. The distortion travels
the over voltage problem compared to the harmonic power flow program, input back into the power source and can affect
under voltage during steady state and output expected out of the program other equipment connected to the same
condition. Again referring to Indian grid, and interpretation of results. source. It should be noted that the
after the introduction of the ABT and UI fundamental component of the current
mechanism, the discipline has been 2. Purpose of harmonic study flows from the generating station to the
brought in the grid and the frequency is With the growing installation of nonlinear load point, while the harmonic current
more are less steady around 49.7 Hz to loads in commercial buildings and flows from the nonlinear load point which
50.1 Hz. Unbalance in the distribution industrial plants, which may be in the are sources of harmonic to the generating
network causes the shift in the neutral range of 30% to 50% of the total load, the station, linear loads and filters. In view of
voltage and also the neutral current flow, effects of harmonics within the system this, the harmonic voltages are maximum
resulting in voltage drop and increased and their impact on the utility and at the load points and minimum at the
losses. Unbalance in the high voltage neighboring loads needs to be examined generating stations.
system, especially due to traction load before any complaints are made,
causes the negative sequence current to Most power systems can accommodate a
equipment is damaged, or production is certain level of harmonic currents but will
flow in the generators, resulting in lost. Harmonic analysis plays an important
additional heating. Harmonic content in experience problems when harmonics
role in characterizing and understanding become a significant component of the
the voltage and the current in the system the extent of harmonic problems.
should be within the acceptable limits and overall load. As these higher frequency
Harmonic studies are often performed harmonic currents flow through the power
this paper discusses power quality issue when,
related to harmonics. system, they can cause communication
• Finding a solution to an existing errors, overheating and hardware damage,
harmonic problem such as:
Any load or device that does not draw a • Installing large capacitor banks on
sinusoidal current when excited by a utility distribution systems or industrial • Overheating of electrical distribution
sinusoidal voltage of the same power systems equipment, cables, transformers,
frequency is termed a nonlinear load. • Installing large nonlinear devices or standby generators, etc.
The most common are switching loads • High voltages and circulating currents
devices, such as solid-state converters, • Designing a harmonic filter caused by harmonic resonance
which force the conduction of currents • Converting a power factor capacitor • Equipment malfunctions due to
for only certain periods and, to a lesser bank to a harmonic filter excessive voltage distortion
extent, saturable impedance devices • Increased internal energy losses
such as transformers with nonlinear 3. Harmonic causes and its effects: inconnected equipment, causing
voltage vs. impedance characteristics. A component failure and shortened life
nonlinear load is considered a source Harmonics are a distortion of the normal
span
electrical current waveform, generally
transmitted by nonlinear loads.
Power Research and Development Consultants
Page 25
Newsletter

• False tripping of branch circuit as summarized below:- consumed by all of the loads on the
breakers system when the system is at peak
Total Voltage Harmonic Distortion
• Metering errors demand. The denominator used in this
(VTHD) defined as -
• Fires in wiring and distribution ratio does not change with load.
n
systems
∑ V h
2

• Generator failures V THD (%) = h=2 Since IEEE standard 519 harmonic current
X 100

V1 limits are written in terms of percentage
Crest factors and related problems
• Lower system power factor, resulting of full load current, IL (TDD), and not as a
in penalties on monthly utility bills Where, percentage of fundamental current, I1
(ITHD), studies at partial load are usually not
4. Harmonic Standards “V 1 ” is fundamental component of line worth the effort. In general, full load
voltage. operation is the worst case condition
The harmonic studies are generally carried “h” is harmonic order from 2 to n toanalyze in harmonic studies. Further the
out based on the guidelines given by the TDD will always be less than or equal to
utility grid code or the IEEE or IEC Total Current Harmonic Distortion
(I ) defined as - ITHD. At the full load TDD equals ITHD.
standards. The guidelines outlined in the THD
standards are designed to limit harmonic 4.2 IEC Standards
currents from individual customers and n
Unlike the IEEE standards on harmonics
equipment so that harmonic voltage levels ∑
h = 2
I 2h
where there is only a single publication
on the overall power system will be I THD (%) = X 100
I1 covering all issues related to harmonics, IEC
acceptable. Where, standards on harmonics [9] are separated
into several publications.
Harmonic limits are typically evaluated at “I1” is fundamental current magnitude
the point of common coupling (PCC) “Ih“ is current magnitude of each There are standards dealing with
between the power supply utility and the harmonic order h environments and limits which are further
plant load. The responsibility of the plant broken down based on the voltage and
The ITHD represents the total harmonic
substation consumer is to ensure that the current levels. These key standards are as
current distortion of the wave form at the
limits are not exceeded by the harmonic follows:
particular moment when the
distortion generated within their facility. measurement is taken. It is the ratio of • IEC 61000-2-2 (1993): Electromagnetic
These limits can also be applied to the rms value harmonic current to the Compatibility (EMC). Part 2:
individual buses throughout an electrical fundamental (non-harmonic) current Environment. Section 2: Compatibility
distribution system to reduce the harmful measured for that load point and usually Levels for Low-Frequency Conducted
effects of the harmonic currents. expressed as percentage. Note that the Disturbances and Signaling in Public
denominator used in this ratio changes Low-Voltage Power Supply Systems.
4.1 IEEE Standards with load.
• IEC 61000-3-2 (2000): Electromagnetic
IEEE STD 519-1992 guideline [8], Compatibility (EMC). Part 3: Limits.
Total Demand Distortion (TDD) defined
elaborates harmonic current and voltage Section 2: Limits for Harmonic Current
as -
distortion limits. The IEEE 519 standard Emissions (Equipment Input Current Up
provides two limits one for voltage and to and Including 16 A per Phase).
one for current. Voltage limits are based n

on the bus voltage level at the PCC ∑ I 2h • IEC 61000-3-4 (1998): Electromagnetic
h = 2
TDD (%) = X 100 Compatibility (EMC). Part 3: Limits.
whereas the current limits vary by the IL
ratio of short circuit current at the PCC Section 4: Limitation of Emission of
divided by the load current. It should be Harmonic Currents in Low-Voltage
noted that as the short circuit ratio Where, Power Supply Systems for Equipment
increases, that is load current decreases, with Rated Current Greater Than 16 A.
“IL” is maximum demand load current
higher limits are allowed. This is due to the (fundamental frequency current) at PCC. • IEC 61000-3-6 (1996): Electromagnetic
fact that although more distortion is Compatibility (EMC). Part 3: Limits.
allowable the overall magnitude of the Total Demand Distortion (TDD) is the ratio
of the rms value of the harmonic current Section 6: Assessment of Emission
distorted current is smaller. This will tend Limits for Distorting Loads in MV and
to the maximum demand load current
to have a less significant effect on the HV Power Systems. Basic EMC
power system. (full load fundamental frequency current).
The full load fundamental current is the publication.
The definition of key harmonic
indicesanalyzed to assess system total amount of non-harmonic current
performance is
Page 26 Power Research and Development Consultants
Newsletter

Depending on the utility practice and the flow study or the measurements Step 4: Develop solutions (filter, etc.) and
standard being applied, which is generally conducted. Table 2 gives the typical investigate possible adverse system
county or utility specific, relevant calculation for the Total Demand interactions. Also, check the sensitivity of
standards are to be referred for the Distortion (TDD) for different voltage the results to important variables. If the
harmonic distortion limits for both voltage levels based on IEEE Std. solution is based on the filter design, the
and current. filter is selected such that at fundamental
5. Harmonic Analysis Procedure frequency, the filter compensates the
4.3 Utility Grid Code
reactive power requirement at the plant
Most of the utility grid codes specify the Procedure for the harmonic analysis to improve the power factor.
maximum total levels of harmonic depends on the basic question as whether
distortion at different voltage levels in the the analysis is for the existing system or Step 5: After the installation of proposed
system. Table 1 gives the distortion limits for the proposed system. If the analysis is solutions, perform monitoring to verify
specified in a typical grid code. Unless for the existing system, harmonic the correct operation of the system.
otherwise specified, generally these measurements are done at the plant using
distortion limits are for the voltage the power/harmonic analyzers. However, if the analysis is for the
harmonics. Further, specifications do not Measurement values are cross checked proposed system, studies are done based
refer to the fault level at the bus. It is very with the appropriate applicable standard. entirely on the simulation. The proposed
important to understand that consumer If the values are not within the acceptable plant is modelled in the harmonic study
cannot be responsible to limit the grid limit, filter or remedial measures are software tool [7]. The nonlinear loads are
voltage harmonic distortion limits to these suggested and harmonic simulation modelled as current injecting sources. The
values. For the consumer perspective, it is studies are done to ascertain the effect of magnitude of the current at each
the current harmonic distortion limits as filters. Following are the steps involved in harmonic frequency is arrived from the
specified by IEEE or IEC standard, which the harmonic analysis for an existing plant data furnished by the equipment supplier
only can be controlled. It is the - or empirical formula or the measurement
responsibility of the utility to find out the Step 1: Determine the objectives of the conducted at similar installations at other
voltage distortion arising out of these study. The objective might be to identify sites or as per standards. Harmonic
consumers and limit the additional/new what is causing an existing problem. analysis software tool gives the current
connections on to weak buses in the Another might be to determine if a new distortion at the series elements and
system and ensure that the voltage plant expansion containing equipment voltage distortion at different buses.
harmonic distortions are within the limit. such as adjustable-speed drives and These values are compared with the
Table 1: Typical grid code for harmonic capacitors is likely to have problems. applicable standards and if not within the
distortion level Step 2: Make measurements of the limit, remedial measures are suggested and
Voltage Total
Individual existing harmonic conditions. simulated. Once the plant is commissioned,
distortion in % it is worthwhile to conduct the
Level in distortion Step 3: Study the new circuit condition
kV in % Odd Even measurements at site to ascertain the
or existing problem.
simulation values.
69 3.0 2.0 1.0

132 1.5 1.0 0.5 Table 2: Typical calculation for the selection of allowable current Harmonics limit
Load current
Bus Fault
220 1.5 1.0 0.5 in A Ratio =
Voltage current TDD Basis from reference [8]
(Series Isc/IL
level in A
branch)
Current Distortion Limits for
4.4 Selection of current harmonic limit as General Transmission Systems
per IEEE Std. 220 kV 9800 450 21.78 2.5
(>161 kV)
Isc/IL <50
The basis of selecting the individual
Current Distortion Limits for
current harmonic limit depends on the
General Sub transmission
ratio of Isc (maximum short circuit current 132 kV 8200 245 33.47 4 Systems (69001 V through
at PCC) and IL (maximum demand load 161000 V)
current (fundamental frequency 20<Isc/IL<50
component at PCC). The fault level Isc is Current Distortion Limits for
computed at the PCC from the short circuit General Distribution Systems
33 kV 12400 225 55.11 12
study of the given network and maximum (120 V through 69000 V)
load current IL is considered from the load 50<Isc/IL<100
Power Research and Development Consultants
Page 27
Newsletter

6. Harmonic Analysis Data Collection This also minimizes the 2nd and 3rd conducted with the minimum fault level at
harmonic current injection by the the grid bus.
Entire system data required for load flow filter bank to the system, as the
and fault study are required for the presence of 2nd and 3rd harmonic Some of the harmonic study requirements
harmonic study also. In addition to above voltages in the system are less. In specify that the background harmonics in
data, specific attention should be given to certain designs, the current limiting the grid be considered for the simulation
following data - reactor is selected as 0.2%, if the bus study. If the background harmonic is
fault level is less and the inrush considered as voltage source, voltage
current is controlled to acceptable harmonic distortion will not change at the
Transformer winding connections –
limits. With 0.2% reactor, the source bus (generally considered as PCC)
As winding connection provides the
resonant frequency lies between 22 with the plant under study being
path for certain harmonic currents
and 23 harmonic order, resonating represented. Author is of the opinion that
and blocks specific harmonic current,
frequency being 1118 Hz on 50 cycle it is better to represent the background
exact representation of the winding
fundamental frequency basis. harmonics in the grid as current source.
connection and the phase shift angle
Capacitor bank with this arraignment The magnitude of the current source is
arising out of the vector connection
acts as capacitive circuit up to 22nd adjusted in proportion to IEEE current
should be collected.
harmonic. If in the plant, 5th, 7th and limits so that required total voltage
Capacitor values and locations
11th harmonic voltages are present, distortion at the PCC is obtained. In this
(critical) – In the power flow study,
the capacitor bank starts injecting the model, if the plant load has more linear
generally the current limiting reactor
corresponding harmonic currents, loads, the overall distortion at the PCC
or filter reactor associated with the
there by amplifying the harmonic may come down. If the plant load has
capacitor banks are not represented.
currents in the plant or system. It is more nonlinear loads and no harmonic
The effective MVAR at fundamental
better to ascertain the harmonic filters are present in the plant, then the
frequency is sufficient to be modelled
levels in the plant and then decide the voltage harmonic distortion at the PCC will
for the load flow study. In the
reactor value. Cost cutting done in the increase. Representation of the
harmonic analysis study, exact
selection of the reactor at 0.2% will background harmonic is also required to
representation of reactor value is very
create the problems in the plant at arrive at the voltage and current ratings of
much essential. If there is no reactor
the later date, if the lower order the filter element within the plant.
in the capacitor circuit, for all
harmonic frequencies, as long as there harmonic voltages are present in the
system. Peak load demand – Load flow
exists specific frequency harmonic
studies will reveal the peak load
voltage, capacitor injects the
Harmonic spectra for nonlinear loads demand. For the existing plants, the
corresponding frequency harmonic
– Harmonic sources or nonlinear loads peak load demand can be obtained
current into the system. If the current
can be represented as current through measurements at site or
limiting reactor value is say 6%, then
readings obtained from the panel
around 4thharmonic frequency, the injection sources or voltage sources.
Values of the injected currents should meters.
inductor-capacitor circuit resonates,
resonate frequency being 204.12 Hz be determined by measurement. In
on 50 cycle fundamental frequency the absence of measurements, 7. Harmonic Measurement
th
basis. Till 4 harmonic frequency, the standard manufacturer data can be Objectives of the harmonic measurements
capacitor bank acts as capacitive assumed for the study. are to identify power quality problems, to
circuit and injects the harmonic minimize the losses in the production
current to bus. Above 4th harmonic Grid fault level and background process and to increase the plant
frequency, the capacitor bank acts as harmonics in the grid – In the fault productivity. Benefits of power quality
inductive circuit and absorbs the study, the grid fault level is measurement are preventive and
harmonic current, depending on the considered to be the maximum to predictive maintenance, determining the
th
impedance path. As such, 4 determine the maximum interrupting need of mitigation equipment, ensuring
harmonic current presence in the capabilities of the breaker within the equipment performance and sensitivity
system is very minimum, 6% current plant. For harmonic study, prevailing assessment of the equipment to
limiting reactor is referred to as de- fault level at the grid bus should be disturbance. The issues related to
tuned reactor. considered and studies are also to be measuring are sampling rate, accuracy,
Page 28 Power Research and Development Consultants
Newsletter

precision, resolution, bandwidth Table 3: Harmonic Injection for the Sample


amplitude/frequency, differential mode System
argument and frequency, anti-aliasing discussed. The reference to relevant
filter, sampling window width, flag when standards on harmonic analysis is covered.
hardware & software error occurs, flag The importance of harmonic study for the
when some frequency components proposed plant and the various
present in the signal is not recorded and measurement aspects for the existing
instrument immunity to disturbance in the plants are discussed.
supply voltage.
It is concluded that harmonic study should
Typical power quality monitoring (PQM) be taken up in the beginning of the plant
parameters measured are voltage and design stage itself, rather than facing
current harmonics up to 49th harmonics, 9. Conclusions surprises and equipment failures once the
waveforms of voltage and current, In this paper, power system harmonic, one plant is commissioned.
trending of these values, sag and swell of the major power quality issues is
events of voltage waveforms, THD and
individual harmonic distortions,
fundamental and total power
measurements. Types of PQM instruments
commercially available are wiring and
grounding test device, oscilloscope,
disturbance analyzer, power analyzer or
network analyzer, flicker meter and energy
monitor device.
Figures 1 and 2 give the typical
measurement results. The format and the
presentation may change as the
instruments used to measure differ. But
the inferences to be drawn are the same, Figure 1: Typical individual current harmonic distribution obtained from the
whatever the meters we use. measurement

8. Case Study
Figure 3 shows the typical system
considered for the harmonic study. The
encircled region in the system is the area
of concern in the harmonic study. Table 3
gives the 5th , 7th and 11th harmonic
current injection because of the non linear
load at the plant. From the harmonic
power flow, it is found that the harmonic
voltage distortions are not acceptable.
Figure 4 gives the bar graph showing the
harmonic distortion at few buses in the
system. As the harmonic voltage
distortions are not within the limit, filters
are proposed in the plant as shown in
figure 5. Figure 6 gives the bar graph
showing the voltage harmonic distortion
after the incorporation of the filter.It is
found that the voltage harmonic
distortions are within the limits in the Figure 2: Voltage and current harmonic distribution for entire spectrum at a specific time
entire system.
Power Research and Development Consultants
Page 29
Newsletter

Figure 3: Typical Problem Considered for Harmonic Analysis

Figure 4: Harmonic Distortion at Typical Buses


Page 30 Power Research and Development Consultants
Newsletter

Figure 5: 5th , 7th and 11th Harmonic Filter Values

Figure 6: Harmonic Distortion with Filter

10. References

[1] J. Arrillaga, D. A. Bradley, P. S. Bodger, [5] G. T. Heydt, “Electric Power Quality”, [8] IEEE Guide for harmonic control and
“Power system harmonics”, Wiley, Stars in a Circle Publications, second reactive compensation of Static Power
1985. edition, 1994, Avarua, Rarotonga, Converters, IEEE Std. 519-1992.
Cook Islands.
[2] R. C. Duagan, M. F. Mcgranaghan and [9] IEC Sub-Committee 77A report,
H. W. Beaty, “Electric Power System [6] Arindam Ghosh, and Gerard Ledwich ΄΄Disturbances Caused by Equipment
Quality”, McGraw-Hill, 1221 Avenue “Power QualityEnhancement using Connected to the Public Low-Voltage
of the Americas, New York, NY 10020 custom power devices”, Kluwer’s Supply System Part 2 : Harmonics ΄΄,
Power Electronics and Power System 1990 (Revised Draft of IEC 555-2).
[3] C. Sankaran, “Power Quality” CRC series, U.S.A, 2002.
Press, New York, 2002,
[7] IEEE colour book series 399, 1997,
[4] Alexander Kusko, P.E. Marc IEEE Recommended Practice for
T.Thompson, “Power Quality in Power Systems Analysis, IEEE Brown
Electrical System” McGraw-Hill, New Book.
York Chicago.
Power Research and Development Consultants
Page 31
Newsletter

Ferroresonance Phenomenon in Power Transformers -


Simulation Study using MiPower
3. Dr. K.Parthasarathy, Veerabrahmam Bathini
5. Energization of lightly loaded or
1. Introduction
M/s PRDC has carried out a number of unloaded transformers.
Ferroresonance or nonlinear resonance 6. Transformer connected to a series
projects (both Indian and Overseas)
can occur on circuits with power relating to overvoltage studies and compensated transmission line.
transformers connected to overhead lines insulation co-ordination wherein study of 7. Transformers operating with voltages
or cables and also where wound type ferroresonance phenomenon of power very close to the knee point.
electromagnetic voltage transformers are and voltage transformers was a part of 8. Switching of CVT/CCVT in the system,
connected to isolated sections of busbar. technical task. Based on the experience 9. Ungrounded transformer primary
Energy is coupled via the inter-circuit gained M/s PRDC has developed a connections.
capacitance of the parallel lines or open comprehensive skill set for analyzing 10. Cable damage and manual switching
circuit breaker grading capacitance to possible occurrence of ferroresonance in during construction of underground
sustain the resonance. power transformers connected in either cable systems.
In linear resonance the current and transmission or distribution systems. Typical network configurations causing
voltage are linearly related in a manner, Ferroresonance in power transformers is ferroresonance in power transformers are
which is frequency dependant. In the case briefly described in this technical article shown in figure 1 [3].
of ferroresonance the relationship through a case study.
between voltage and current is dependent
not only on frequency but also on a 2. Ferroresonance Phenomenon
number of other factors such as excitation A. Network configurations cause
voltage magnitude and initial conditions Ferroresonance
such as the transformer magnetic flux and
Ferroresonance phenomena occurs in a
point on wave of the initiating switching (a)
low loss electric circuit containing a non-
incident. The ferroresonance is
linear inductance, capacitor and voltage
characterized by a sudden jump of voltage
sources. Power network is example of
or current from one stable state to
such an electrical circuit, where non-linear
another [1].
inductances are due to magnetizing
On transformer feeder circuits ferro
impedances of power transformers,
resonant condition can be established
measurement inductive voltage
between the circuit (overhead line /
cables) capacitance and the transformer transformers and capacitances are due to (b)
magnetizing inductance. Immediately cables, series capacitors etc. Hence,
following the transformer feeder de- certain switching actions, operating
energisation the transformer can be driven conditions and a few system
into saturation due to the discharge of the configurations may cause occurrence of
capacitance-to-earth on the isolated ferroresonance. Some examples of
network, and a non-linear oscillation switching actions are transformer-
occurs between the reactive components. switching, capacitor switching etc. (c)
On a transformer feeder associated with a Some of the configurations/conditions
double-circuit overhead line route, the that may cause ferroresonance are;
ensuing resonance is maintained by energy 1. Transformer supplied through a long
transferred to the resonating circuit via transmission line or cable with low
capacitive mutual coupling from the short circuit power.
adjacent circuit(s) on the towers, 2. Opening of one or two phases of a
producing the nonlinear current and cable feeding the primary side of a
(d)
voltage waveforms characteristic of lightly loaded transformer.
ferroresonance. Since the power 3. Transformer energized through the
transformer is driven into saturation, grading capacitance of one or more
leakage flux can cause overheating and open circuit breakers.
consequent damage to the transformer 4. Transformer connected to a de-
core and windings. Therefore, an energized transmission line running in
aggregate maximum time limit is normally parallel with one or more energized
lines (e)
assigned to this condition [2].
Page 32 Power Research and Development Consultants
Newsletter

open
Causescondition
over voltages,
arises while
over currents
performing and load flow and short circuit study results.
single pole reclosing.
distortions resultingSimilarly,
in thermaltwo phases and Equivalent network considered for the
could be leftstresses
dielectric open with which
the other mayphase be simulation is shown in Figure 2.
energized during
dangerous for electrical
line de-energization.
de equipment
Shunt reactors
(failure, reduction increase
in performance
the open-phase
open and
voltage of
lifetime considerably
insulators etc.,).
because of unequal
(f) compensation
Various methods of the used positive
are based andonzero-
zero
the
Figure 1. Examples of unbalanced sequence principles:
following line capacitances. As reactors
systems at risk from ferroresonance. • Avoid,
are in parallel by withproper the design
line conductor
and/or
capacitance
switchingtooperations,
ground, the equivalent
configurations
B. Ferroresonance Prediction [3] phase-to-ground
phase reactance at power
susceptible to ferroresonance. Figure 2. Equivalent network considered
Ferroresonance is frequently accompanied frequency is inductive and may reach high
• Ensure that the energy supplied by for simulation
by some of the symptoms described value when the shunt compensation is
below: largethe source65%).
(above is notIn sufficient
such cases, to parallel
sustain
System data considered for simulation as
• High permanent over voltages of the phenomenon.
combination
combina of the shunt This reactor technique
and the
follows.
differential mode (phase-to-phase) line normally consists ofin
shunt capacitance introducing
series with losses
the 1) Equivalent network data:The equivalent
and/or common mode (phase-to- inter-phase
interwhich damp capacitance forms a series
out ferroresonance when source impedance data considered for
earth). resonant circuit. These conditions could
it occurs. study are presented in Table I.
• High permanent over currents, high result in series resonance on shunt
Table 1. Equivalent Source Impedance
permanent distortions of voltage and compensated lines with attendant
3. Ferroresonance Simulation Study Data
current waveforms. overvoltages and their detrimental detrimen effects
A. the
System Modelling [5] SS-A SS-B
• Displacement of the neutral point on connected equipments.
R1 (Ω) 2.0 3.34
voltage, transformer heating (in no- Steady
Equivalent state
Source: analysis
Equivalent of sources
equivalent at X1 (Ω) 32.0 53.34
load operation). network model have to be
different busses are represented using performed for R0 (Ω) 4.5 5.34
• Continuous, excessively loud noise in various
positive and simulated
zero sequence stuck impedance
breaker X0 (Ω) 73.14 85.34
transformers and reactors. conditions.
values corresponding to the expected fault 2) Transmission line data:
data:The 210 km,
• Damage of electrical equipment Details
levels atofthose
one busses.
stuck breaker condition to 400kV double circuit transmission line
(capacitor banks, VT, CVT etc.) due to be simulated are&as follows.
Transformers Shunt reactors: At configuration considered for the study is
thermal effect or insulation • Energizefrequencies,
ferroresonnace transmission line from
transformers presented in Figure 3. Two transposition
breakdown. A characteristic SS-AA
behave to SS
SS-Bas with one
induc
inductive pole of SS-A end
elements. points are considered for simulation and a
symptom of VT destruction by breaker
Capacitances do not have keeping
with one pole stuck and to be shunt compensation of 400 kV, 80 MVAr
ferroresonance is a destroyed open all the Saturation
considered. three polesofofthe breaker at SS-B
magnetizingSS has been considered at one end of each
primary winding and an intact end.
inductance, residual flux and losses circuit for the studies.
secondary winding. •
(copper Vary
andNGRmagnetizing)
value from 0%play to 100% an
• Spurious tripping of protection of phase reactor
important rolevalue.in ferroresonance
devices. •
generation Record
and damping.steady state open
Some of these symptoms are not conductor
Transmission line to or
(s) phase ground vol
voltage.
cable: When
necessary specific to the ferroresonance •
representing
represen Record overhead lines it neutral
steady state is of
phenomenon. For example permanent voltage
importance and tocurrenttake for into allaccount
line shuntthe
displacement of the neutral point of an reactors.
frequency
unearthed neutral system may be the •
dependence Observe of whether
the zero there is any
zero-sequence
consequence of a single phase-to-earth possibility
parameters. Asymmetry hasat specific
of getting resonance to be
fault. Due to the multitude of various value of NGR.
considered as well. Shielding wires may be
sources of capacitances and non linear Perform
eliminatedother assumingstuckzero breaker
voltagesimulated
on these
case studies. Figure 3. Transmission line data
inductances in a real power network and wires. Travelling wave model of
the wide range of operating conditions, Induced
transmission voltages
line isonusedde
de-energized
in the study. circuit: 3) Power transformer data:500
data: MVA,
configurations under which this study is applicable
Loads: Loads represented as constant for only double 400/132 kV, Ynyn trans
transformer with short
ferroresonance can occur are endless. circuit
impedance lines.type A with
shunt compensated
parallel –RL load. de de- circuit impedance of 12.5% and non
non- linear
energized circuit running on the same magnetization branch represented as
C. Preventing or Damping
right
B. of way
System data with an energized circuit can piece-wise
wise linear representation using
Ferroresonance[4]
be subjected to high high-induced voltages due open circuit characteristics of transformer
A number of practical measures can be Equivalent network model considered for
taken to prevent ferroresonance, that to parallel resonance between the line [4].
simulation studies is derived based on
shunt
hunt reactor and the line capacitance.
Power Research and Development Consultants
Page 33
Newsletter

B. Case Study Results Three pole opening: 3-pole opening of


circuit breaker A as shown in Figure 3.
Single pole opening: 1-pole opening of Voltage waveforms at bus 4 and
circuit breaker A as shown in Figure 2. transformer magnetizing current waveform
Voltage waveforms at bus 4 and are shown in figures 8 and 9 for no load
transformer magnetizing current and 10% load on transformer respectively.
waveform are shown in figures 4 and 5 for
no load and 10% load on transformer (a)
respectively.

(a)
(b)
Figure 6. Voltage and current waveform at
(a) transformer terminal with no load on
transformer

(b)
Figure 9.Voltage and current waveform at
transformer terminal with 10% load on
transformer
(b)
4. Observations &Conclusions
Figure 4. Voltage and current waveform at
transformer terminal with no load on
(a) Based on system considered for simulation
transformer study, it is observed that when a
transmission line terminated with
unloaded power transformer and uneven
breaker pole opening operations at source
end can cause ferroresonance in power
transformers. It is also observed that, 10%
(b) load on secondary terminal of transformer
Figure 7. Voltage and current waveform at helps in damping the ferroresonance
transformer terminal with 10% load on oscillation for all the cases. It is necessary
(a) transformer to ensure a minimum 10% loading on
secondary side of power transformer to
minimize the possible occurrence of
ferroresonance.
5. References
[1] Bernard C.Lesieutr, Jama A.mohamed “Analysis
of Ferroresonance in Three-Phase
(b) Transformers, IEEE POWERCON 2000. pp.
1013-1018.
Figure 5. Voltage and current waveform at [2] S.Mozaffari, S.Henschel, A.C.Soudack “Chaotic
transformer terminal with 10% load on (a) ferroresonance in power t transformers”, IEE
transformer Proc. Gener.Transm.Distrib.,Vol.142,No.3,May
1995. pp. 247-250.
[3] Ph. Ferracci, Collection Technique Schneider
Ferroresonance - n° 190.ECT190, first issued
Two pole opening: 2-pole opening of March 1998.
circuit breaker A as shown in Figure 2. [4] Yunge Li, Wei Shi and Furong Li “Novel
analytical solution to Fundamental
Voltage waveforms at bus 4 and ferroresonance –part II: Criterion and
transformer magnetizing current elimination”, IEEE Transactions on Power
(b) Delivery, Vol.21.No.2, April 2006. pp.794-800.
waveform are shown in figures 6 and 7 for Figure 8. Voltage and current waveform at [5] IEC Std-60071-4, 2004-06, Insulation co-
no load and 10% load on transformer ordination–Part 4: Computational guide to
transformer terminal with no load on insulation co-ordination and modeling of
respectively. transformer electrical networks.
Page 34 Power Research and Development Consultants
Newsletter

Shunt Reactor Switching in Extra High Voltage System - Criterion for Verification of
Proposed Circuit Breaker Parameters
Dr. K. Parthasarathy, VeerabrahmamBathini
strength between the CB contacts
I. Introduction II. Switching Device Characteristics increases faster than the build-up of TRV.
Shunt reactors are mainly used in
transmission networks to regulate the Switchgear is the general term covering III. Shunt Reactor Switching
reactive power balance of the power switching and interrupting devices. A. Opening Operations (Chopping
system by compensating the surplus Switchgear performs two important but Overvoltages and Re-ignitions)
reactive power generation of transmission different tasks. The first task is to perform In addition to the inductance of the shunt
lines and thereby stabilize the system routine switching operations such as reactor winding, the windings, the
voltage. Reactors are normally disconnecting or isolating apparatus for a bushings, and the connecting leads of the
disconnected at heavy load conditions and variety of system requirements. The reactor have stray capacitances. When a
are connected to the bus bars/lines at second task is to interrupt current flow reactor is de-energized, the voltage across
periods of low load conditions. Shunt under abnormal or fault conditions to it will oscillate with a natural frequency
reactors are quite often switched in and prevent excessive damages. Switching determined by the inductance and stray
out on daily basis. Shunt reactors absorb devices should be capable of not only capacitances. The oscillation frequency is
the reactive power and reduce the over interrupting normal load and fault typically in the order of few kHz. Due to
voltages during light load conditions, and currents but also capable of re- chopping (premature interruption) of the
also assist in reducing transient establishing the connection within the current slightly before the natural current
overvoltages caused by switching and system very quickly. Therefore, the zero, the oscillating voltage across reactor
lightning. Consequently, frequent function of a switching device is both of will have higher amplitude than the
switching is a significant characteristic of opening and closing of a circuit. supply voltage.
reactors.
When a switching device interrupts the For modern SF6 circuit breakers, typical
M/s PRDC has carried out a number of flow of current several basic activities are magnitudes of this “chopping
projects (Overseas and India) relating to involved. The first is the mechanical overvoltage” are in the order of 1.2 to 2.0
overvoltage studies and insulation co- separation of the contacts. This p.u. with the highest values occurring for
ordination wherein selection of circuit mechanical separation of the conducting low MVAr reactors. The chopping
breaker for shunt reactor switching was a contacts establishes an arc since this overvoltage, with its limited amplitude
part of the technical task. Based on the mechanical separation would not normally and frequency, is normally quite harmless
experience gained, Power System Studies take place at precisely current zero. This both for the reactor itself and for the
group of M/s PRDC has evolved a set of arc will remain until the load or fault surrounding system. However, during de-
guidelines for selection of circuit breaker current passes through a normally energization, transient recovery voltage
for shunt reactor switching. These are occurring current zero. All alternating with considerable magnitude occurs
briefly described in this technical article. current switching devices take advantage across the breaker contacts. Due to
Technical functions of a circuit breaker are of this naturally occurring current zero to oscillatory nature of the reactor voltage,
briefly described in section II. interrupt the normal flow of current. there will be a high voltage stress across
When the current is interrupted at the circuit breaker contacts if the contact
Overvoltages occur during shunt reactor instants other than normal zero crossing, gap is small.
de-energization and inrush current appear transient recovery voltage (TRV) appears
during energization of shunt reactor. across the switching device terminals. The If the arcing time is short, the circuit
These phenomena are described in section shape and magnitude of TRV are breaker probably will reignite. A re-
III.Methodologies to be followed for determined by the parameters of the ignition will generate high-frequency
analyzing the transient effects caused system within which the switching device transients (typically in the order of
during opening and closing operations and is located. To minimize re-ignition or hundreds of kHz) in both reactor voltage
for selecting suitable circuit breaker possible re-strikes due to TRV, it is and current. Following a re-ignition, the
ratings accordingly are described in necessary to ensure that the dielectric reactor current will be interrupted again,
section IV and V. EMTP-type program has either at a high-frequency zero of the
to be used for this analysis.
Power Research and Development Consultants
Page 35
Newsletter

current, or most probably at the IV. De-Energization of Shunt Reactor the rate of change of the arc conductance
subsequent power frequency zero. The A. Circuit Breaker Model (i.e., dg/dt), parameters (e.g. time constant
very steep voltage transients caused byre- There are several methods for and power loss) used to describe the arc,
ignitions will be unevenly distributed across interrupting current and the most and the rate of rise of dielectric recovery
the reactor winding, with the highest stress effective method will depend upon the voltage.
across the initial turns. This voltage stress system voltage and current application.
may lead to puncture of the winding Air, oil, SF6,andvacuum are all dielectrics When interrupting a small inductive
insulation in the reactor, which in the long interrupting media commonly used in current associated with switching off the
run may lead to complete breakdown. commercial switchgear. Vacuum and SF6 shunt reactor, small inductive current
Insulation of nearby equipment may also switching devices are presently used dominates the arc conductance variation
be affected. During these stresses surge routinely, at medium voltages. For high during the interruption process. This
arresters protect the equipments to a voltage applications, SF6 circuit breaker is phenomena may cause multi-oscillations
limited extent, since the severity of the the most predominant technology offered and resonances with the circuits connected
voltage stress is related both to the rate-of- today. All these technologies have to CB. Hence, the arc model parameters
change and the amplitude. (depending upon the interaction with have to be determined by considering
system parameters) the potential for complex interactions between CB, source
The main insulation of reactors can be premature current interruption (current line/feeder and reactor circuits. Therefore,
overstressed if the breaker has high current chopping) and/ or re-ignition which can it is more appropriate to adopt Mayr’s
chopping character. The switching produce an additional oscillatory voltage model given by equation (1), for modeling
overvoltage can be dangerous for on the reactor terminals. such arc behavior, where the CB
equipment if their peak value exceeds the surrounding circuit plays an important role.
rated switching impulse withstand voltage When a circuit breaker (CB) interrupts During the CB contacts parting, the arc
of the equipment. It is very important to while carrying a small inductive current, behaves as a nonlinear conductance. The
know the level of dielectric stress that high frequency and high-amplitude equation (1) can be used to control the arc
occurs during operation of the system in transient voltage appears between the CB conductance, g, and to accomplish the
order to avoid the insulation failures. contacts. The generated high transient energy balance. It is observed that, in
Successful synchronous (controlled) recovery voltage (TRV) may cause addition to the initial value of g, other
switching can reduce the mechanical and undesired effects on the reactor and/or parameters, τ, P, i, α and β are required as
electromagnetic stresses which occur the switching equipments. SF6 is widely inputs to solve Mayr’s arc model equation
during switching operations. used in the HV and EHV insulation systems (1).

b| 1 ' 1 '
because of its stable chemical
B. Closing Operations (Inrush Current):
~ |• ~ |• <1=
characteristics. However, for CB
ba } }. | € . | •
During energization of a shunt reactor,
applications on extinguishing the arc
inrush currents with high asymmetry and
plasma, there are many complicated
long time constants may occur. The actual
gaseous behaviors occurring due to the
magnitude of the inrush current is quite Where,
dissociated and recombined subspecies.
dependent on the range of linearity of the g is conductance of arc, in Siemens.
For interrupting small inductive current
reactor core. The unsymmetrical phase P is Power dissipated from the arc to
namely switching off shunt reactors, SF6
inrush currents during a shunt reactor
Circuit Breakers exhibit less stable and surrounding gas in Watts.
energisation may cause saturation of the
unpredictable arc extinguishing i is current through the arc , in Amperes.
reactor, resulting in overheating. Due to
performance and may lead to several re- τis the time constant of arc, in seconds.
the air gaps utilized in shunt reactor cores
ignitions.
there are no severe saturation effects. In
For analyzing the transient effects caused αis the parameter that influences the
spite of their limited amplitude, reactor conductance dependency of τ
during interruption of small inductive
inrush currents may still have adverse
current accurate modeling of circuit βis the parameter that influences the
effects. They may lead to zero sequence
breaker arc is essential. The model should conductance dependency of P
current, cause saturation of CT cores, with
take into consideration the physical τ and P are judiciously selected from data
resulting nuisance tripping of relays, or
phenomena of arc process with cold gas sheets of CB under consideration.
cause other network disturbances. Excess
characteristic and associated system Using arc model and equivalent system
inrush currents can be avoided by
parameters. An accurate CB model for considered for the system study transient
employing controlled switching of circuit
switching studies should take into account recovery voltage VTRV is computed
breaker.
Page 36 Power Research and Development Consultants
Newsletter

stray inductance
by EMTP-type and Capacitance between
program. on the capacitance
B. Theoretical AnalysisCt seen from the equation peak and (10)
‡‹„ 1 2M ‡+ <B. Œ= <10=
is computed by equation (7)
the
FigureCB 1contactsLb
representsis the
the equivalent
connecting circuit
series circuit breaker
Refer figure terminals,
1. During the N the number
switching of
off the
‡ 2M ‡+ <B. Œ= <7=
inductance CL is the
to be considered for load side capacitance
the transient analysis. interrupters
shunt reactor in series
(CB per opening)pole and the
energy
(3) Where -
1
L is shunt reactor inductance chopping
conservationnumber λ for a bysingle
can be approximated
1 The1chopping1current ich level
is given \by \J (4). ‰'-Š <3= The per unit M
interrupter.
J
2 2 2 2 is computed by
Dielectric recovery characteristics for SF6 J + equation ˆ crest overvoltage-to-ground
' • – —\ “ <4= J
due to a re-ignition

0.01b 20.7b
-Š i
cold gas is given by the equation (2)
In equation (3) Vo is the voltage across the equation (8)
‚ƒ „ of the Q is three phase reactor rating (VA)
7.1 ‡ <2=
According to equation
at the (3), the ratio
the λ is the chopping number Ž • ’ for single
shunt reactor instant of current
‡ž 1 Ÿ<1 2M ‡+√‘ =<B. Œ=<8=
suppression
interruption. Va peak overvoltage
is the suppression to peak
Figure.1. Single-phase equivalent circuit of
reactor
overvoltage voltageto the can ground
be expressedacross the by interrupter
shunt reactor
equation
inductor, which(5), where is thekafirst is the
peakper-unit
of the ω is the angular rated power frequency
with d =Cvs are
Ls and × t, the
where Vdwsv
source sideis inductance
the circuit Theis per
breaker contact gap withstand voltage, d is
and capacitance
value of thewith
oscillation suppression
the samepeak overvoltage
polarity as the N the unit crest overvoltage
interrupting excursion
units in series per
and can be used to estimate
system voltage at the time of interruption. pole. the peak-to peak due to a re-ignition is
the
Lp contact
andCp gap
are atthea time
strayinstant t (ms) and
inductance and parameters required for describing the CB computed by equation (9)
ich is the inductor chopping current. For L is main reactor inductance (H)
vCapacitance
(m/s) is the between
contact velocity at opening.
the CB contacts arc
SF6 model.
currents are typically in the range of 2- ‡ <1 Ÿ=<1 2M ‡+ =<B. Œ= <9=
circuit breaker the values of chopping LN is neutral reactance inductance (H)
‰'-Š
Lb is the connecting series inductance
14A. ‡The +
™1 <5=
Based on computed values VTRV and
+
\J ˆ Ct seen from
C value of the chopped current Case 2: Shunt reactor neutral solidly
L is thethe
loadre-ignition/re-strike
side capacitance checks are
depends onˆ the capacitance
Vdwsv
grounded.
Damping factor β can be considered to be
r
carried
L is shuntoutreactor
by theinductance
following condition.
the circuit breaker terminals, N the For
o[ ‚ƒ „
0.5. the case substitute K=0 in all equations
Generally
number ofininterrupters
EHV systems in Cs>>
seriesCLperandpole
Cp (6) to (10) and compute corresponding
Dielectric recovery
Magnitudes characteristics
of different for SF6
crest voltages is
andnegligible,
the choppingso thatnumber
Ct equalsλ to forCL.a single crest
The pervalues.
unit crest recovery voltage across
cold gas is given by the equation
namely ka (suppression peak overvoltage (2)
Case 1: Shunt
interrupter. Thereactor
chopping neutral
current grounded
ich level Case study results
the circuit breakerareis presented
computedfor bya
to the ground across the inductor in p.u),
0.01b 20.7b
through
is given by reactor
equation (4). typical
equation system
(10) described in section IV-C.
'-Š ka•–—\ i“ <4=
kc (maximum ‚ƒ „ chopping overvoltage-to- For this case is computed by equation
7.1 ‡ <2= C. ‡ Case 1 Study ‡+ <B. Œ=
2M results <10=
ground at the instant of recovery voltage (6)
‹„
1 3—•
peak in p.u), kp (per unit crest overvoltage- According to equation (3), the ratio of the

Where data considered: N=2, λ=4x10 “/


Refer figure 1:
‡+ <1 M=™1 › œ~ • by System
to-ground due to a re-ignition), ks (per unit suppression peak overvoltage to the
can 1 be M 2`
4

equation (5), where ka is the per-unit √A,ω=377 rad/sec,1


crest
with dovervoltage
= v × t, where excursion
Vdwsv peak-to peak
is the circuit reactor voltage expressed
M <6= M
6
Q=80x10 VAr,
2
due to reignition)
contact gapand krv (per unit crest
J
breaker withstand voltage, d is
L=4.787H, L =1.9148H, System voltage 380
J•
recovery voltage N
the contact gap atacross
a timethe circuitt (ms)
instant breaker)
and value of the suppression peak overvoltage
can be iscomputed
v (m/s) the contacttheoretically based on
velocity at opening. and can be used to estimate the kV.
the equivalent circuit shown in figure 1. The maximum
parameters chopping
required the CB Based
overvoltage-to-
for describing on the theoretical analysis the
Q is three phase
valuesreactor ratingcrest
(VA)voltages
arethe chopping number Ž ’ for single

This theoretical analysis is brieflyVTRV
presented ground
arc model. occurs at the recovery voltage computed of various
Based on computed values and
√‘
peak and is computed by equation (7) λ is
C.
‡- +2M ™ ‡+ <B. ‰' -ŠŒ= <7=
in section IV-B.
Vdwsv the re-ignition/re-strike checks are
‡+ 1 <5=
interrupter
\J ˆ
B. Theoretical Analysiscondition.
r
carried out by the following
ˆ
kωa=1.08
is the p.u,
o[ ‚ƒ „
Refer figure 1. During the switching off the angular rated power frequency
shunt reactor (CB opening) energy kNc=1.52
is thep.u,
interrupting units in series per
The per unit
Generally in EHV crest overvoltage-to-ground
systems Cs>> CL and Cp is kp=2.22 p.u,
conservation
Magnitudes can of be approximated
crest by (3) pole.
namely1 ka (suppression
1 1
different voltages due to asoreignition
negligible, that Ct equals is to computed
CL. by
kLsis
=3.78
mainp.u,
\J + across \ ‰'-Š <3=in p.u),
peak overvoltage equation (8) reactor inductance (H)
to the2ground 2 J ˆ the 2inductor 1 Ÿ<1 2M ‡+ =<B. Œ=<8=
‡ž reactor
Case 1: Shunt reactor neutral grounded krv=2.52 p.u
LN is neutral reactance inductance (H)
through The current and voltage waveforms
In equation (3) Vo is the voltage
kc (maximum chopping overvoltage-to across the
computed by EMTP simulation of the
shunt
ground at the instant of recovery current
reactor at the instant of voltage For this Case 2: Shunt reactor neutral solidly
The per case
unit ka is computed
crest overvoltage by excursion
equation equivalent system are presented in Figures
interruption.
peak in p.u), kp Va(per
is the
unit suppression peak
crest overvoltage- (6) grounded.
peak-to peak due to a re-ignition is 1 to 3.
1 3—•
overvoltage
to-ground duetoto the ground across
a re-ignition), the
ks (per unit
‡‡+ <1 <1 Ÿ=<1 M=™1 2M›
computed by equation (9) From simulation krv is computed as 2.42
œ~ • p.u this figure closely matches with the
inductor, which isexcursion
crest overvoltage the first peak-to
peak ofpeak the For the case substitute K=0 in all equations
oscillation with theand
due to reignition) same
krv polarity
(per unitascrest
the 1
‡+ =<B. Œ=M 2` <9= theoretically
(6) to (10) and compute corresponding
M <6=
computed value of 2.52 p.u.
system
recoveryvoltage
voltageatacross
the timethe of interruption.
circuit breaker) crest values.
ich
can isbethe inductor theoretically
computed chopping current.based Foron Damping factor β can be considered to be
SF6
the circuit
equivalent breaker the shown
circuit values of in chopping
figure 1. 0.5.
currents are typically
This theoretical analysisinis briefly
the range of 2-
presented The maximum chopping overvoltage-to-
The per unit crest recovery voltage across
14A. The IV-B.
in section value of the chopped current ground occurs at the recovery voltage
the circuit breaker is computed by
depends
Power Research and Development Consultants
Page 37
Newsletter

Case study results are presented for a Figure 3: Current through circuit breaker Figure 5: Zero sequenc ecurrent during energization of shunt reactor
CBC In
typical system described in section IV-C. 0.200
-0.172
0.140
-0.000
0.150 -0.000 0.120 0.064
0.172 0.064
C. Case Study Results 0.100 0.100
Min -0.172 Min -0.000
0.050 0.080

C u rre n t (k A )
Max 0.172 Max 0.129

C u rre n t (k A )
0.000 0.060

System data considered: N=2,λ=4x10 “/


Refer figure 1:
4 -0.050 0.040

√A,ω=377
-0.100 0.020
rad/sec,Q=80x106VAr, -0.150 0.000
L=4.787H, LN=1.9148H, System voltage 380 -0.200 -0.020
kV. t (sec) 0.380 0.400 0.420 0.440 0.391 t (sec) 0.200 0.250 0.300 0.350 0.400 0.193
0.420 0.323
Based on the theoretical analysis the 0.028 0.130
computed values of various crest voltages Fig.2: Current & voltage Waveforms Fig.3: Inrush current waveforms
are:
Check simulated TRV and RRRV (rate of The inrush current magnitudes as shown in
ka=1.08 p.u, rise of recovery voltage) values with figure 3 compared with breaker current
kc=1.52 p.u, corresponding ratings of the proposed ratings well within limit.
kp=2.22 p.u, circuit breaker and decide on the
ks=3.78 p.u, adequacy of the proposed circuit breaker VI. References
krv=2.52 p.u for shunt reactor switching.
[1] Gary W. Chang, M. Huang, and Jiang-
The current and voltage waveforms V. Energization of Shunt Reactor Hong Lai ‘Modeling SF6 Circuit Breaker
computed by EMTP simulation of the for Characterizing Shunt Reactor
equivalent system are presented in Plots 1 For system shown in figure 1,typical Switching Transients’, IEEE
to 3 of figure 2. inrush currents waveforms obtained Transactions on Power Deliver, Vol 22,
during energization of 380 kV, 80 MVAr No.3, July 2007.
From simulation, krv is computed as 2.42 shunt reactor are presented in Plots 4&5
p.u this figure closely matches with the of figure 3. Normally these inrush current [2] G. St Jean, M. Landry, Y. Leclerc, and A.
theoretically computed value of 2.52p.u. magnitudes are well within breaker Chenier, ‘A new concept in post-arc
current rating. However, controlled analysis applied to power circuit-
Figure 1: Tranisent Recovery Voltage across the circuit breaker
TRV switching of circuit breaker is breakers’, IEEE Trans. Power Delivery,
800
600
0.011
297.570
recommended to minimize the magnitude vol. 3, no. 3, pp. 1036–1044, Jul. 1988.
400 297.558 and duration of zero sequence current
Min -749.621
200 which may otherwise result in nuisance [3] A.T. Johns, R.K. Aggarwal, and Y.H.
V o lta g e (kV)

Max 411.337
0
tripping relays or other network Song, ‘Improved techniques for
-200

-400
disturbances. modeling fault arcs on faulted EHV
-600 transmission systems’, IEEE Proc.
-800 Generation, Transmission, and
t (sec) 0.380 0.400 0.420 0.440 0.460 0.400
0.450 Figure 4: Inrush current drwan by shunt reactor during energization Distribution, Volume 141, Issue 2,
0.049 Ir
0.30
-0.000 March 1994, pp: 148-154.
Figure 2: Voltage at reactor terminal
0.20 -0.070
Vr -0.069
500
134.690 0.10 Min -0.116
400 1.777
C u rre n t (k A )

Max 0.294
300 -132.913 0.00
200 Min -312.058
V o lt a g e (k V )

100 Max 438.736 -0.10


0
-0.20
-100
-200
-0.30
-300 t (sec) 0.190
0.200 0.250 0.300 0.350 0.400
-400 0.360
t (sec) 0.396 0.170
0.400 0.420 0.440
0.435
0.039
Page 38 Power Research and Development Consultants
Newsletter

Events and Achievements


Five-Day National Workshop
on Power System Stability and Control

PRDC- VTU Research Centre and the EEE


Department of CMR Institute of
Technology jointly organized five day
national workshop on “Power System
Stability and Control” at Bangalore during
27th February - 02nd March 2012. The
event was conducted with technical
sponsorship of IEEE PES Bangalore Chapter.
The chief guest and the keynote speaker
was Prof. D.P. Sengupta,Honorary
professor of National Institute of Advanced
Studies (NIAS), Bangalore. The invited
speakers for the workshop were Dr. R.
Nagaraja, MD, PRDC, Dr. K. R. Padiyar,
Emeritus professor, IISc, Mr. M.M. Babu
Narayanan, ChiefTechnical Advisor, PRDC,
Prof. D. Thukaram, Professor, IISc and Mr.
Faraz Khan, Sr Engineer, PRDC. About 33
participants from various Industries and
academic institutions participated in the
workshop. Dr. R. Nagaraja, MD, PRDC addressing the five-day national workshop on ‘Power
system stability and control’ at CMRIT, Bangalore

Two-Day National Workshop on Automated Fault Analysis (AFAS)

PRDC organized a workshop on


“Automated Fault Analysis”during 24th and
25th of February, 2012 at Hotel Atria in
Bangalore. The main purpose of this
workshop was to familiarize the practicing
engineers of utilities and industries about
the benefits of AFAS, the challenges
involvedin setting it up as well as the
variousanalyses possible using this
package. Participants
includedrepresentatives from various
utilities and industries like POSOCO, KPTCL,
TNEB, MSEB, Alstom, PRDC etc. The
speakers for this workshop were Dr. R.
Nagaraja, Faraz Zafar Khan, Raghavendra G,
Francis C Joseph and Mayank Nagendran.
Power Research and Development Consultants
Page 39
Newsletter

Our Expertise in Training


Upcoming Events Training Calendar - 2012
At PRDC, we conduct various training
programmes throughout the year. The
duration of the training programme varies
from one to four weeks.

One Week Training


We conduct one week training programme
on MiPower. It’s a Standard Course.

MiPower Training Level 1

Level 1 is a training programme on basic


theory & simple problems (hands-on).

Level 1 Batch:
th th
1. 5 Nov 2012 to 9 Nov 2012

MiPower Training Level 2

Level 2 is a training programme which


consists of only hands-on and solving own
system problems, sorting out issues and
clarifications.

Level 2 Batch:
rd th
1. 3 Dec 2012 to 7 Dec 2012

Short Term Training


/Workshop
In addition to the above said programme
PRDC is also conducting short term training PRDC organized a two day workshop on The faculty for this workshop included
program and workshops to impart “Power System Grounding Practices “on Dr. R. Nagaraja, MD, PRDC, Dr. G.R
knowledge and practical approach on 2nd and 3rd of August, 2012at Hotel Atria, Nagabhushana,Ex IISC professor , Mr.
specific topics, which are of relevance to Bangalore. The main purpose of the M.M. Babu Narayanan,Chief Technical
power engineers in day-to-day works. Such workshop wasto provide comprehensive Advisor, PRDC, Mr.N.Raman, Senior
training not only enhances their knowledge coverage of boththeoretical background and Consultant, PRDC, Mr.Jayakumar, Ex
but also helps to implement in their regular practicalunderstanding of concepts related Joint Director, CPRI, and Mr. Vamsi
routine works. to designand field testing of earthingsystems Krishna Dadi,Engineer , PRDC.About 40
besides addressing the adequacyof the participants from variousutilities and
For short term and special trainings contact existing grounding systems.Ground Grid industries like , Druk Green Corporation –
our marketing team: design using PRDC’sMiPower packagewas Bhutan, KPTCL, BESCOM, MESCOM,
marketingteam@prdcinfotech.com demonstrated during the workshop. The CESC- Kolkata, GE, ABB,TCE, JSPL, M N
workshop was inaugurated by Mr. S. Dastur Co etc. participated in the
Sumanth, Director (Transmission),KPTCL workshop.
Page 40 Power Research and Development Consultants
Newsletter

Power System Simulation Tools


M.M. Babu Narayanan

Abstract: power electronics based controllers and 5) Small signal stability (for small
Successful operation of today’s complex systems in the modern day power system disturbances)
power systems requires a balanced has created the need for real time digital 6) Electromagnetic transients (EMT)
understanding of technical and economic simulators (RTDS) for the purpose of simulation
issues relating to the generation, Hardware-in-loop (HIL) testing of these 7) Relay coordination studies
transmission and distribution of electrical controllers for optimizing their 8) Load forecasting
energy. A thorough understanding of the performance before being installed in the 9) Unit commitment
operating characteristics and the field. 10) Economic dispatch
limitations of each device within the 11) Steady state contingency analysis
network is needed in order to ensure The evolution of simulation tools has (security assessment) and
reliable and secure source of power. A progressed in step with the evolution of 12) Dynamic security assessment.
wide variety of study tools are available to computing technologies. In recent years,
help engineers gain knowledge and computing technologies have improved Indeed the power system is very complex
confidence required to design and operate dramatically in performance and become both in terms of dimension (physically and
networks in a manner consistent with end- widely available at a steadily decreasing mathematically) and the kind of non-
user expectations. Advances in power cost. Consequently, simulation tools have linearities present. There are no explicit
system simulation have made it possible also seen dramatic performance gains and analytical solutions for the problems
to study in detail, the dynamic behavior of steady cost decreases. Researchers and associated with the faults and
even very large power systems with engineers now have access to affordable, contingencies in such a complex system.
varying degree of complexity. This paper
high performance simulation tools that Simulation is the only method to predict
summarizes the various simulation tools
were previously too cost prohibitive, the performance of the power system
that are employed in such studies both off
except for the largest manufacturers and that is subjected to the above mentioned
line and in real time applications.
utilities. eventualities.
This paper gives an overview of the
I. Introduction
various simulation tools that are widely Further, the sizes of power systems have
Design and stable operation of an electric
used by the manufacturers, developers, grown steadily over the years and the
power system requires careful study of the
researchers and utilities in the planning, need for interconnected power systems
interaction of the different equipment
that constitutes the power system. design and operation of modern day for economic operation resulted in a host
Stretching of electric system performance power system. Application of these tools of other problems such as economic
to its operational limits and deployment of for various types of studies is also dispatch, transient stability, low frequency
special fast-acting controls has not only highlighted. A brief history of power oscillations etc. More recently, the de-
made dynamic simulation more common system simulation is presented at the regulation posed further challenges such
and essential to utility planning and beginning. as congestion management, interaction
operation, but has made the study process with market dynamics etc. The solutions
more complex. In this context, simulation II. Need for Power System Simulators for many of these problems, which have
tools are critical to the effective There are a number of decisions to be generally been on an approximate and
investigation of system response to a taken both at the operational level and at sometimes been on heuristic basis,
variety of disturbances in a fast and the planning level. Any such decision needed an integrated approach. The big
accurate manner. These tools have been process must be based on analysis with a blackouts in North America in 1965 and
widely used for the design and great emphasis on modeling and 2003 as well as grid failures in many
improvement of electrical systems since simulation techniques. The kind of studies countries including India placed fresh
the mid twentieth century. A wide variety done by utilities is numerous of which emphasis on the aspect of modeling and
of both analog and digital simulation tools some are given below: simulation of power systems for taking
are available. However, advances in corrective measures to avoid such
computer hardware and software 1) Short circuit studies blackouts.
complemented by the sophisticated power 2) Load flow studies, also called as power
system component modeling techniques flow studies III. Power System Simulation
have more or less replaced the analogue 3) Optimal power flow The tool for simulation was first in the
simulators with digital simulation. 4) Transient stability (for large form of a DC network analyzer for short
Furthermore, the large scale induction of disturbances)
Power Research and Development Consultants
Page 41
Newsletter

circuit and load flow studies and then an significant challenges to the design and type electromechanical dynamic
AC network analyzer to accommodate stable operation of today’s power simulation tools.
transient stability studies. The traditional systems. Examples include the integration
method of performing transient studies of wind farms, photovoltaic cells or other C. Small Time Step Simulation
utilized simulators made up of scaled power-electronic-based distributed energy It is a common practice with
down power system components. Each generation systems, domestic loads and electromagnetic transient simulators to
component is physically connected to the future plug-in electric vehicles into the use a simulation time step of 30 to 50 μs
next in a manner similar to that of the real existing power grid. The above to provide acceptable results for
system. This analog simulation technique applications take full advantage of several transients up to 2 kHz. Better precision
formed the basis of both the well known very fast and distributed power electronic can be achieved with smaller time steps.
Transient Network Analyzer (TNA) and the systems which in many cases, are of Simulation of transient phenomena with
HVDC simulator [1]. innovative design and consequently have frequency content up to 10 kHz typically
never been integrated together or with a requires a simulation time step of
The impact of the digital computer on power grid. Validated models suitable for approximately 10 μs. Power electronic
simulation was first felt in the late1950s electromagnetic transients, as well as converters with higher Pulse Width
and the early sixties saw a steadyandrapid dynamic stability analysis under normal Modulation (PWM) carrier frequency in
rise in the use of computers ascomparedto and abnormal conditions, are usually not the range of 10 kHz, such as those used in
that of the network analyzers. For the last available. This poses a new and low-power converters, require smaller
three decades, theevolution of simulation significantchallenge to utility and system time steps of less than 250 nanoseconds.
tools has been driven by the rapid engineers who must guarantee total AC circuits with higher resonance
evolution of computingtechnologies. As system performance and security. frequency and very short lines, as
computer technologies have decreased in expected in a low-voltage distribution
cost and increased in performance, the B. Simultaneous Simulation of Short and circuit and railway power feeding system
capability of simulation tools to solve Long Term Phenomena may require time steps below 20 μs. In
increasingly complex problems in less time Simultaneous simulation of fast and long such cases, it is prudent to carry out tests
has improved. In addition, the cost of phenomena pushes simulation tools that with practical system configurations and
digital simulators has also steadily are required in the planning and operation parameters to determine minimum time
decreased, making them available to a of power systems to their limits. One such step for accurate simulation.
larger number of users for awider variety example is checking the transient stability.
of applications. This resulted in the The transient response of an IV. Simulation Tools
evolution of the most commonly interconnected power system ranges from Simulator technology has evolved from
employed study of electromagnetic fast (microseconds) electromagnetic physical/analogue simulators (HVDC
phenomenon which is based on transients, through electro-mechanical simulators, TNA’s) for electromagnetic
mathematical representation of thesystem power swings (milliseconds), to slower transients and protection & control
and its dynamics rather than on scaled modes influenced by the prime mover, studies, to hybrid TNA/Analogue/Digital
down physical components. The boiler and fuel feed systems (seconds to simulators with the capability of studying
algorithms necessary for software minutes). For the modeling of electro-mechanical transient behavior and
basedelectromagnetic transient simulation electromechanical transients caused by to fully digital real-time simulators.
were first described by H. Dommel in 1969 large disturbances such as network faults Physical simulators served their purpose
[2] and have been utilized in several well and/or plant outages, system states must well. However, they were very large,
known programs like EMTP [3] and EMTDC be evaluated at intervals in the order of expensive and required highly skilled
[4]. milliseconds over time scales of seconds. technical teams for the tedious job of
For small-signal and voltage stability setting up networks and maintaining the
A. Issues and Challenges in Simulation assessment, the time scale needs to be extensive inventory of complex
The secure operation of power systems extended to minutes and for voltage equipment. With the development of
has become more and more dependent on security, tens of minutes to hours. During microprocessors and floating-point
complex control systems and power this period, accurate representation of DSPs,physical simulators have been
electronic devices. Furthermore, the power electronic devices require relatively replaced with fully digital real-time
proliferation of distributed generation small time steps, typical of simulators. Nevertheless, the scaled-down
plants, often based on the use of electromagnetic transients (EMT) model approach used in physical
renewable energy resources, presents simulators, but impractical for phasor- simulators findsits virtue, in the relative
ease with which
Page 42 Power Research and Development Consultants
Newsletter

the model components could duplicate • Statistical distribution of representation of the power system to
their actual counterparts with their non- switching surges study its steady state and dynamic
linear behavior. • Energizing and reclosing behavior by employing various solution
transients on lines, cables, open techniques. The equations governing the
A. Transient Network Analyzer (TNA) ended transformer lines elements of the power system are
TNA is a special purpose analog simulator, Switching surge reduction by algebraic and/or differential equations
which has scaled down models of all the means of controlled closing and depending upon the appropriate modeling
power system components. On a TNA, the pre- insertion resistor strategies adopted.
system elements can have either equal • Single pole reclosing
ohmic values or scaled down values, but • Load rejection & Ferro resonance Currently, popular electromagnetic
the voltages are always scaled down. Thus studies transient simulation software is actively
the scaled down system is represented on • Transient Recovery over voltages expanding, such as EMTP [3],
the simulator and switching actions are • Fault initiation surges and PSCAD/EMTDC [4], etc. Besides, checking
performed. The resulting voltages and • Requirement on surge arrester transient stability of a power system is
currents are recorded for analysis. These location and rating one of the important objectives of running
are quickly acquired and processed by the a simulation program which among other
data acquisition system and presented in a B. Digital Simulators: things, can give a lot more information
form required by system designers. One Digital simulators of electric power such as predicting the dynamic
specific advantage of such analog systems have found wide application in performance of the system involving low
simulators are that they operate on real power industry and allow to solve a wide frequency transients (typically below 5 Hz)
time as in an actual system and thus prove range of important tasks such as: [5]. A variety of programs are available in
to be useful for testing of plant size the public domain like SIMPOW®, PSS/E®,
controllers. 1) Producing computational MiPower® to name a few.
experiments when doing research
Modeling Features of TNA: work in developing new technical C. Real Time Digital Simulators (RTDS)
TNA generally has models of 3-phase measures that provide the desired It has now been more than 10 years since
transmission line PI sections, Single phase reliability and security of power the introduction of first fully digital real
and 3 phase transformer banks with system; time power system simulator. Real time
saturation, Linear or non-linear Shunt 2) Implementing projects concerned operation implies that an event in the
Reactors, Static Var Compensators (6 pulse with the choice of the main system which lasts for one second can be
or 12 pulse TSC or TCR) with generic electrical equipment and its simulated on the simulator in exactly one
controls, Load models, Circuit Breakers parameters, the choice of over second. The usual digital simulation
(manually programmable or computer current and overvoltage protection programs typically require many seconds
controlled to close at any instant of sine devices; or even minutes to perform the necessary
wave and with possibility to simulate 3) Analyzing power system accidents computations and produce a solution for
current chopping, current zero opening or and developing measures aimed at such an event. Although specific
pre-strike phenomenon), Synchronous preventing similar accidents in applications vary, real time digital
machines, Lightning Arresters (gap type power system’s operation. simulators are particularly useful when
and gap less type), Voltage & Current 4) Performing simulations in hard actual power system devices and
sources etc. real time for (a) testing of existing controllers such as FACTS and HVDC are to
or new electrical devices (digital be included in the test program or study.
Studies that can be performed on TNA [1] devices of relay protection and This so called closed loop testing method
TNA had been acquired by many automation, monitoring devices, [6] represents an accurate way to
equipment manufacturers, Research etc.) and (b) designing, testing and evaluate the performance of such physical
centers and utilities to find solutions for implementation of new software devices/controllers prior to their
their design, research and operational products (simulators, SCADA, etc.). installation in the actual power system.
problems. Traditionally, the following
types of studies were performed using the As mentioned in Section III above, digital As is the case in most electromagnetic
TNA prior to the introduction of modern simulation is based on the mathematical transient simulations, the RTDS utilizes
day EMTP and real time digital simulators: the so called Dommel algorithm. In this
algorithm, the trapezoidal rule of
Power Research and Development Consultants
Page 43
Newsletter

integration is used to convert integral capability of existing systems, hence CIM based power system simulation has
equations, which result from nodal pushing their operating points closer to been implemented in few of the software
analysis of the power system, into stability limits. The performance and development projects. Future simulation
algebraic equations. Application of effect of any new device must be well programs will have an open architecture
trapezoidal rule requires that the solution understood in order to ensure safe and with loosely coupled pluggable
be computed only at discrete instants of secure operation of power system in components. This kind of architecture will
time, rather than a continuous solution. which these devices are embedded. A enable components and models
The time between the successive solutions RTDS simulator is an excellent tool for the developed by others to be easily plugged
is known as the time step denoted by Δt.
All of the system of equations
representing the power system model
must be computed in each time step. For
large complex power system models, it
may take a modern computer many
seconds to compute even a single time
step. These types of simulators are said to
be non-real time digital simulators as
already explained in section IV above. The
RTDS simulators on the other hand, are Fig 1: Conceptual Overview of RTDS
able to continuously perform the
necessary calculations for a single time investigation,development and integration into to augment their functionality.
step in a measured time that is exactly of new and complex power system
equal to the time step. The RTDS components. Figure 1 gives a conceptual VI. References
simulators combine specialized processing [1] ‘TNA & HVDC Simulator’,
overview of the RTDS that is being
hardware and software to achieve http://www.cpri.in
increasingly used in closed loop with
continuous real time operation [7]. /testing/psd/psd_home.html
various control and protection devices in a [2] H.W. Dommel, ‘Digital computer solution of
power system for development and electromagnetic transients in single and
In order to achieve and sustain real time testing activities.
multiphase networks’, IEEE Transactions on
operation, many RTDS simulators take Power apparatus and systems, Vol PAS 88,
advantage of the two levels of inherent V. Future Trends in Power System no.4, April 1969, pp 388-399.
parallelism in the Dommel algorithm. First, Simulation [3] ‘Electromagnetic transients program
equations for closely coupledcomponents Common Information Model (CIM) is an (EMTP) Rule Book’, Bonneville Power
within the network are solved using effort to develop a common power system Administration
closely coupled processors. These network operation model that can be [4] ‘Electromagnetic Transients including DC’,
components could be part of a sub system shared and exchanged among different Manitoba HVDC Research Centre,
in a power system. The second level of applications. Power system simulation is Winnipeg, Canada,
https://pscad.com/products/pscad/
parallelism results when the overall power one of many intended CIM usage
[5] K.R. Padiyar, “Power System Dynamics,
system model is split into two or more sub scenarios. Being a canonical power system stability and control’, (Book), BS
systems. Each sub system is then solved in data model, CIM is the foundation to Publications, 2006.
parallel using processors. integration of modern information [6] D. Brandt et al, ‘Closed loop testing of a
systems in the power industry. IEC CIM joint Var controller using digital real time
A. RTDS applications model is a general purpose power system simulator’, IEEE Transactions on Power
Since its introduction, the application systems, August 1991, Vol.6, No.3, pp
data model, which is designed to
scope of RTDS has continued to expand. 1140-1146.
model/describe physical power networks [7] M.M. Babu Narayanan et al ‘Real Time
Real time simulators are most suited for and serve multiple purposes. Information, Digital Simulator at CPRI and case studies’,
closed loop testing of physical control and such as connections among physical Proceedings of the Workshop on Real Time
protection devices. Recent trends in the equipments, equipment physical sizes, simulation of power systems, Bangalore,
power industry have led to the equipment geographical locations 24th January 2005, pp 1-8.
introduction of many new and complex (attitude and longitude), and equipment
devices. The purpose of many of these electrical parameters (R, X, Rating), are
devices is to increase power transfer commonly included in the model.
Page 44 Power Research and Development Consultants
Newsletter

Events and Achievements

Achievements Achievements Upcoming Events


• Hindustan Electro Graphite • PRDC has been appointed as a • Launch of new release of
(HEG) situated in Mandideep, technical consultant by MiPower™ 2012
Near Bhopal in Madhya Pradesh, Karnataka Electricity Regulatory onOctober 31, 2012 in
world’s largest integrated Commission (KERC) for New Delhi.
graphite manufacturing plant has preparation of guidelines and
appointed PRDC as technical roadmap for implementation of • Workshop on Power
consultant for design and HVDS system in Karnataka. System Protection in Qatar
development of Electric Arc along with IEI, Qatar
Furnace (EAF) Reorder hardware • PRDC has been appointed as a Chapter on October 18,
for measurement & recording of technical consultant by World 2012 at Asiana Restaurant,
EAF operation along with design Institute of Sustainable Energy Doha.
& development of EAF (WISE) for providing
simulation software for study consultancy services for large • PRDC is participating in
and Optimization of EAF scale renewable energy “Wind Power India 2012”
Operation. This is a unique integration and power – 2nd International
developmental project, as similar evacuation facilities in Tamil Conference and Exhibition
solutions are not ready available Nadu. to held on 28 -30
in the market. November 2012 in
• PRDC has been awarded the Chennai. The conference
• Raj West Power Ltd. (RWPL), a contract for Long Term Demand is being held at Chennai
wholly owned subsidiary of JSW Forecasting and Perspective Trade Center, Chennai.
situated in Barmer district of Planning by Karnataka Power
Rajasthan has appointed PRDC as Transmission Corporation • Workshop on Computer
a expert consultant for power Limited. Applications to Power
system study for tuning of power Systems using MiPower™
system stabilizers (PSS) for their • PRDC has successfully bagged at Ambala, Punjab.
Raj West lignite based pit-head the contracts for supplying
(8x135MW) generating station. Transmission Line Simulators • Platinum Sponsors for
with Automation to O.P. Jindal NPSC 2012 at BHU,
• PRDC has bagged the order from Institute of Technology, Raigarh Varanasi.
Surana Power, for rendering the and Vellore Institute of
engineering services for Technology, Vellore.
development of transmission
system for their on-going • PRDC is been selected as
2x210MW generating station at Technical Advisory to Platina
Raichur, Karnataka. The Partners LLP, a UK based
consultancy services include company investing in Wind
selection of survey agency, Power Sector in India.
preparation of tender
documents for 400kV line by • PRDC has bagged the contract
vendors, coordination with for undertaking Insulation
various authorities for approvals Coordination Studies for ABB
and monitoring progress of Switzerland.
400kV double circuit line
construction.
Power Research and Development Consultants
Page 45
Newsletter

About the Authors

Dr. K. Balaraman Prof K. R. Padiyar


Ltd., Bangalore- one of the reputed Power
System Consultants in the country.
R. Nagaraja has done his B.E. in Electrical
and Electronics Engineering from Mysore
University (India) in the year 1986. He
obtained his M.E in the year 1988,
specialized in Computer Applications to
Power System and Drives and Ph.D. Degree
Prof. K.R. Padiyar is associatedin the field of Energy Management System
Dr. K.Balaraman, M.Tech, (Ph.D)
from Indian Institute of Science (IISc).His
with Indian Institute of Science, Bangalore
worked for BEML at their R&D division.
since 1987, where he is currently an specializations are Power System Analysis,
After a brief stint, he joined Karnataka
Honorary Professor in the Department of Simulation, Power Engineering Education
Electricity Board (now Karnataka Power
and Power System Protection. Dr. Nagaraja
Electrical Engineering. Prior to joining IISc,
Transmission Company Limited – KPTCL) in
he was with Indian Institute of has authored several technical papers and
1992 as Assistant Engineer. He has served
Technology, Kanpur. He obtained M.E conducted a number of
as Shift engineer in 220kV substation also
degree in 1964 from IISc and Ph.D degree workshops/conferences/seminars
worked in Load Dispatch Centre as Shift
from University of Waterloo, Canada in throughout the country.
Engineer till early 1997. In 1997 he was
awarded BRITISH OVERSEAS SCHOLARSHIP 1972. He has taught and lectured at
various Universities in Canada and USA. Dr. Nagaraja is the brain behind the
by CONFEDERATION OF BRITISH INDUSTRY
architecture, design and development of
to undergo practical training in NATIONAL
GRID COMPANY PLC. England. In 2007, he He has authored over 200 papers and 4 the MiPower – Power system analysis
was awarded Doctorate by Visvesvaraya Books including ‘Power system dynamics, software package widely used by Electric
Technological University in the subject of stability and control’. His research interest utilities, Industries, Consultants and
“Developing New Methodologies in Energy are in the areas of HVDC and FACTS, Engineering colleges. Dr. Nagaraja has been
Management System”. In 2006, he joined power system stability and control. He involved in the planning studies of State
Power Research Development Consultants was a member of the Review committee Utilities and Industries in India and abroad.
Pvt.Ltd as General Manager (Power System on the National HVDC project. He is the
studies). recipient of 1999 Prof. RustomChoksi Dr. G. Govinda Rao
award for excellence in research. He was
His areas of interest are power ABB chair professor (2001-03). He is
system studies, power system operation, fellow of Indian national academy of
regulatory issues, project appraisal and Engineering.
Electricity market. He has published over
15 research papers in National Conference Dr. R. Nagaraja
and international conferences. He has
guided over 25 projects of Master degree
and Bachelor degree students. He has
delivered over 200 lectures across the Dr. G. Govinda Rao obtained
Country in the areas of Power system B.E.(EE)and M.E.(Power Systems)from
studies, Power System Planning, Energy Andhra University, Visakhapatnam, India
Management System, Power system and Ph.D. in the area of Long Term
operation, ABT. Dr. R. Nagaraja is the founder Dynamics in Power Systems from IISc,
and Managing Director of M/s. Power Bangalore, India. After working for a short
Research & Development Consultants Pvt. while as an Electrical Engineer, he joined
Page 46 Power Research and Development Consultants
Newsletter

About the Authors

the Teaching Faculty of Andhra University He was Visiting Fellow at the University Research papers in national conferences.
College of Engg., Visakhapatnam, India and of Manchester Institute of Science and Presently, he holds the position of Sr.
served for more than 40 years in different Technology, UK (1970-71). He was ABB Engineer-PSS at PRDC.
positions. After relinquishing his service chair professor (1996-1997). He is fellow
there, he worked as Professor at of Indian national academy of M. M. Babu Narayanan
ANITS,Visakhapatnamfor four years. After Engineering.
working for a semester at Southern He has Over 200 publications in
Polytechnic State University, South National & International journals He was
Marietta, USA as a Visiting Professor, he is Member, R&D Committee, CPRI and
presently working as a Senior Professor in served as Vice Chairman, Protection
the GVP College of Engg., Visakhapatnam. Committee, CBIP, New Delhi. Presently, he
To his credit he presented and published holds the position of Chief Technical
more than 55 Papers in Conferences and Advisor at PRDC.
Journals of National and International
Repute. He was awarded the Best Teacher Veerabrahmam Bathini
Award by the A.P. State Government. His
research interests are in fundamentals of M.M. Babu Narayanan has 35
Circuit Analysis, Power System Dynamics, years’ experience in Power Industry. He
Voltage Stability and Reactive Power works in the areaof Design,planning, R&D,
Management. simulation & Reforms in Transmission and
Distribution. He obtained B.Sc (Engg. ) from
NIT, Calicut and M.Sc (Engg.) from IISc,
Prof K. Parthasarathy Bangalore in 1991.. He has undergone
training at ABB, Sweden in HVDC
Transmission systems and real time
simulation.
VeerabrahmamBathini obtained
B.Tech (Electrical & Electronics) in 2004 He was responsible for setting up
and M.Tech (Integrated Power Systems) in state-of-the-art Real Time Digital
2007 from J.N.T.U College of Engineering, simulation facility in Central Power
Anantapur and V.N.I.T Nagpur Research Institute. At CPRI, he has been
respectively. His areas of interest are involved in dynamic performance studies
Power Systems Dynamics and control and for a number of HVDC and FACTS projects
Dr. K. Parthasarthy obtained Power Electronics Applications to Power in India. He is a recipient of Central Board
M.E.(Power Systems) in 1961 and Ph.D. systems. of Irrigation & Power award for excellence
degree (Protective Relays) in 1967 from in power transmission systems.
Indian Institute of Science Bangalore. His He joined in PRDC in 2007 as
areas of interest are Switchgear and Engineer-PSS, from 2007 majorly he His research interests are HVDC
Protection, Power System Dynamics and executed various projects in the field of transmission, & Grounding. He has lectured
Control, Computer Aided Protection and EMTP Studies (detailed Insulation co- at many Universities in India and abroad.
Power System Analysis. He held various ordination of GIS and AIS substations, He has also been a member of several
positions at IISc, Bangalore during the 1961 Ferroresonance, circuit breaker Switching Govt. of India committees in Transmission
– 1997. He served as Chairman, etc.,).He is also involved in the & Distribution related areas including the
Department of Electrical Engineering IISc development of EMTP-Type module in Power System Development Fund of
(1987-88). MiPower software. He has published CERC.Currently he is Chief Technical
Adviser at PRDC, Bangalore
Power Research and Development Consultants
Page 47
Newsletter

• Load Flow Analysis


• Short Circuit Analysis
• Transient Stability Studies
• Relay Coordination
• Voltage Instability Studies
• Harmonic Analysis
• • Load Analysis
Dynamic Stability Flow Analysis
• • Short Circuit Analysis
Network Reduction
• • Transient
Sub-Synchronous Stability Studies
Resonance
• Relay Coordination
• Electromagnetic transients
• Voltage Instability Studies
• Line and Cable Parameter
• Harmonic Analysis
Calculation
• Dynamic Stability Analysis
• Long Term Load Forecast
• Network Reduction
• D C Network Solutions
• Sub-Synchronous
Synchronous Resonance
• Unit Protection Schemes
• Electromagnetic transients
• Reliability•Analysis
Line and Cable Parameter Calculation
• Open Access• Long
Feasibility
Term Load Forecast
• • D C Network Solutions
ATC Computation
• Unit Protection Schemes
• Reliability Analysis
• Open Access Feasibility
• ATC Computation
For Details Contact:
Power Research & Development Consultants Pvt. Ltd
Page 48 Power Research and Development Consultants
Newsletter

You might also like