Professional Documents
Culture Documents
Advisor:
From MD’s Desk………………………………………………………………………………………………………..………………… 2
Dr. R. Nagaraja
Steady State Analysis of Power Systems…………………………………………………………………………………….. 3
………..….………………………………….…………………………..….…………………………..………….Dr. K. Balaraman
Editor:
Consultancy Services Rendered……………………………………..….…………………………………………………..…… 9
M. M. Babu Narayanan
Power System Stability Studies…………………………………………………………………………………..….…………… 12
………………………………………………………….………….……………………………..……..…..….…….Dr. R. Nagaraja
Members:
Small Signal Stability in Power Systems…………………………………………………….…….…………………..……… 19
Venkatesh H. R.
………………………………………….…………………………………………………………………………..Prof. K. R. Padiyar
Sandhya R. J.
Voltage Stability - Fundamentals and State-of-the-art……………………………………………………………..… 22
Ch. Vijay Krishna Rao
…...……………………………………………………………………………………………………………….Dr. G. Govinda Rao
Rakesha H. S.
Harmonic Studies............................................................................................................................ 24
Pranati Mohanty
...............................................................................................................................Dr. R. Nagaraja
Thimmappa. N
Ferroresonance Phenomenon in Power Transformers-Simulation Study using MiPower…….…..... 30
………………………………………………...….………..…..……..Dr. K. Parthasarathy &VeerabrahmamBathini
Shunt Reactor Switching in Extra High Voltage System - Criterion for Verification of Proposed
Circuit Breaker Parameters………………………………………………………………..……….…………………………..…. 34
………………..…………………………………………………..……Dr. K. Parthasarathy &Veerabrahmam Bathini
Power System Simulation Tools…………………..…………………………………………………………………………..…. 40
………………………….…………….…………………………………….……..……….….………..…M.M. Babu Narayanan
Page 2 Power Research and Development Consultants
Newsletter
compensation is needed at a bus, to bring 2.1 The Power Flow Problem Bus currents and voltages can be calculated
its voltage up to an appropriate level. If using the above equations and since in
new lines (or additional transformers) are The overall power flow problem can be practical systems power is known quantity,
to be installed, to reinforce the system, a divided into following sub-problems [2,3], equations 1and 2 can be written as,
power flow study will show how it will
∗ ∗ ∗
relieve overloads on adjacent lines. An 1. Formulation of a suitable --(5)
inefficient or unbalanced load can also mathematical network model to
cause unpredictable behavior in your adequately describe the And
localized power grid, increasing the risk of relationship between voltages
∗ ∗ ∗
equipment damage and unplanned powers in the interconnected --(6)
outages. system.
2. Initialization of power and are the desired power flow equations in
The load flow study is a pre- requisite to voltages in various buses/nodes nonlinear form for two bus system and
short circuit study, stability study and of the network. these equations can be generalized and
electromagnetic transient study. The load 3. Numerical computation of
Further each bus voltage V will be having
written as shown below in equation (7),
flow study is also used as a part of the power flow equations with the
motor starting study. above initialization to compute both magnitude |V | and angle δ .
the voltages at all the
Load flow studies are the basis for buses/nodes of the network ∗
# # # #
∗
∑%& | #% | | % | Where
ensuring that a power system design will with sufficient accuracy. for ' =1, 2, 3…------------------------------- (7)
satisfy its performance criteria within the 4. Computing the power flows in
boundaries of the most beneficial all the branches of The main solution methods for power flow
investment and operating costs. Some interconnected network. studies are as follows [4,5]
examples of how load flow studies are
used are listed below. In order to form the suitable mathematical
• Newton-Raphson method
model, we can construct the following
• Gauss-Seidel method
• Equipment sizing and loading equations from the basic principles for a • Fast Decoupled method
(Transformers, Lines, Cables, two bus system,
∗
Reactors, etc.) Among the various solution methods, the
• Generator exciter / regulator ∗ ---------------- (1) N-R method is superior to the G-S method
voltage set points because it exhibits a faster convergence
• System loss analysis ∗
characteristic. However, N-R method
And ∗ --------- (2)
• Maintain reliability suffers from the disadvantage that a “flat
• Coordinate protective relays start” is not always possible since the
• Capacitor placement and sizing Equation 1 and 2 can be written in the solution at the beginning can oscillate
• Steady state bus voltages simple forms using vectors and matrix as without converging toward the solution.
• Transformer tap settings shown below using admittance matrix and Hence, the load-flow solution is often
• Load tap changer evaluation are complex, linear, simultaneous carried out with G-S algorithm for
• System reactor load flows equations. distribution system analysis.
• Utility intertie studies
---------------------------- (3)
• To know about component or The fast-decoupled method is a variation of
≅ ≅
circuit loading, real and reactive the N-R method wherein the solution is
Where, and and
power flow decoupled with P and delta on one side
≅
• System performance under and V and Q on the other to obtain faster
emergency and unexpected convergence. This is generally used in the
conditions transmission system which contain many
• To find significant plant buses and where there is a need for faster
expansion. Also using impedance matrix, load-flow solution.
• As a part of motor starting studies ---------------------------- (4)
• Pre-requisite to conduct short During the operation of the power system,
circuit, stability and EMTP studies. Where, each bus has known variables and
unknowns variables.
Power Research and Development Consultants
Page 5
Newsletter
| | *
2.1.1 Slack or Swing Bus Bus type
( ( ) )
This bus is considered as the reference Slack or
bus. During the execution, the voltage of √ √ × × √ √
swing bus
this bus is always specified and remains Voltage
constant in magnitude and specified angle √ √ √ √ × ×
control bus
which normally set to zero. In addition to Load bus √ √ √ × √ ×
the generation assigned to it according to
economic operation, this bus is
responsible for supplying the losses of the
system and also any mismatch between Figure 1 shows the load flow results without necessitating the load shedding or
the load and generation. The main criteria obtained through MiPower software for generation rescheduling during steady
for selecting the slack or swing bus is that the sample system taken from text book steate operation.Normally
it should be the largest generation bus. In ‘Computer Methods in Power System regulatorycommissions will set the criteria
addition such slack bus would preferably Analysis - Chapter 8, Figure 8.8 -Sample for analyzing the contingency analysis by
located remote from the location under system for load flow solution’. defining the set of credible continncyes for
study. which system needs to be tested during
2.2 Contingency Analysis planning and operation stages. With the
2.1.2 Generator or Voltage Controlled Bus available software and digital computation
– PV Bus Contingency studies are the essential part tools, contingency analysis has become
of steady state analysis of very simple exercise.
During the execution the voltage largeinterconnected power systems. These
magnitude at this the bus is kept constant studies are used to analyze the Steady state analysis and software tools
subject to reactive power limit. Also, the reliability,loading of elements, voltage are matured with technology development
active power supplied is kept constant at profile and overall behaviorof and recent developmentsare
the value that satisfies the economic interconnected system with the outage of focusingtowards analysis of system with
operation of the system. Most probably, elements viz transmission unbalanced load and distributedgenerators
this bus is connected to a generator where lines,transformer etc.. like wind and solar.
the voltage is controlled using the
excitation and the power is controlled
using the prime mover control.
Sometimes, this bus is connected to a VAr
device where the voltage can be
controlled by varying the value of the
injected VAr to the bus.
More tools are being developed to Relation between phase values and and hence fault current is,
3
understand the effect of distributed sequence components are shown below in
3
generations in large power systems with equation (8) and (9), +
utmost accuracy. + .
< .= 3 /
. 1 1 1 +
7 7 71 9 9 7 7 7------------------ (8)
4
3. Short Circuit Studies
1 9 9
Typically, only 5% of the initial faults in a
- power system, are three phase faults with
Faults usually occur in a power system due
1 1 1 +
or without earth. Of the unbalanced faults,
to insulation failure, flashover, physical .
damage or human error. These faults may 7 7 71 9 9 7 7 7------------------- (9)
80% are line-earth and 15% are double line
4
1 9 9 -
faults with or without earth and which can
either be three phase in nature involving
often deteriorate to 3 phase fault. Broken
all three phases in a symmetrical manner,
conductor faults account for the rest.
or may be asymmetrical where usually With the above relation between phase
only one or two phases may be involved. values and sequence components, sample The purpose of a short circuit study is to
Faults may also be caused by either short- calculations for three phase fault, double identify the maximum available fault
circuits to earth or between live line to ground fault and line to ground current at all locations, called busses, in the
conductors, or may be caused by broken fault are shown below, power system. It is then compared with the
conductors in one or more phases. ratings of the individual power system
Sometimes simultaneous faults may occur In case of three phase fault, it is assumed components, such as circuit breakers relays
involving both short-circuit and broken that all the three phases are short circuit and fuses, to determine if the equipment is
conductor faults (also known as open- through equal fault impedances / , adequately rated to safely withstand or
circuit faults). vectorial sum of fault current is zero since interrupt the calculated fault current. It is
symmetrical fault is considered without also used to evaluate the withstanding
Balanced three phase faults may be ground. design capability of all the electrical
analyzed using an equivalent single phase equipment (panels, switchboards,
circuit. With asymmetrical three phase Hence,
. 0, + - 0 and fault switchgears, Motor starters, and other
;
9
faults, the uses of symmetrical electrical equipment not mentioned) used
currents, + 0 305
, and
of the calculations as transmission lines - 9
components help to reduce the complexity in the system, against the available fault
currents.
and components are by and large
symmetrical, although the fault may be In case of double line to ground fault, fault For new facilities, a short circuit study
asymmetrical. Sample fault analysis with is considered in phase’s b and c with should be performed before the electrical
symmetrical components are given below, ground through fault impedance / , the equipment is selected. For existing
current in the ungrounded phase is zero, facilities, a short circuit study should be
In the analysis following notations are performed if significant changes have
0, and hence 0
occurred either within the facility or in the
+ .
considered [6,7],
< - = / and the fault
I.e.
utility system.
-
+,
and
• And - are phase to ground current is, The short circuit study provides the
+,
various locations in the plant.
• And - are lines currents and
,
• Identifies whether the system and
and . are sequence In case of line to ground fault, fault is the equipment can withstand the
components of currents, considered in phase a with ground
,
available fault current.
• And . are positive, through faultimpedance / , currents in • Evaluates the application of breakers
negative and zero sequence phase b and c are zero andthe voltage at and fuses.
impedances and / is fault the fault point is + + / and • Identifies problem areas in the
impedance and ‘a’ is vector .
4 +
system.
operator.
Power Research and Development Consultants
Page 7
Newsletter
• Specifies the types, ampere ratings While selecting circuit breakers it is 3.2 Determining the Short Circuit Duties of
and device settings of the important to make sure that none of the Breakers
equipment to ensure minimum capabilities areexceeded in their
service interruption. application.These capabilities are basically Considering an industrial scenario
• Helps improve the reliability of your obtained from theshort circuit wherethere is no in-plant power
system. current calculations available at the generation,
• Provides recommended solutions. equipment location. Therefore, the the total three phase fault current at the
• Coordinate protective relays. starting point is the careful fault analysis faulted point includes both currents from
of the power system. the power source (electric utility) and the
A power system is not static but changes fault contribution from electric motors
during operation (switching on or off of 3.1 Fault Analysis of Power System (both synchronous and induction) present
generators and transmission lines) and in the system. If in-plant generation is
during planning (addition of generators If the power system (typically an industrial involved, then the total fault current would
and transmission lines). Major changes system) is connected to the Utility, the be the sum of fault contributions from in-
would be considered a change in feed by supply authority shall supply the necessary plant generator(s), electric utility and from
the electric utility, in the primary or available fault levels at the point of in-plant electrical motors irrespective of
secondary system configuration within the network connection - both three-phase whether they are on the same faulted bus
facility, in transformer size or impedance, and single-phase, or the source impedance or on the downstream buses.
in conductor lengths or sizes, in type of and the corresponding X/R ratios. This will
circuit breaker, or a change in the motors help in analyzing the fault contributions 3.3 Factors Affecting Cable Selection and
that are energized by the system. Thus to/from the Utility. Any approved Ratings
fault studies need to be routinely software packages such as MiPower may
performed by utility engineers. be used or manual computations if the The above discussion briefly recognized the
system is simple. short circuit fault current influence on
The strength of a bus bar (or the ability to cable sizing and selection based on their
maintain its voltage) is directly As the power system constantly ampere ratings. Proper selection and
proportional to its short circuit capacity undergoes changes due to additions of ratings ensures their suitability in the
(SCC). An infinitely strong bus (or Infinite generators and/or distribution networks, power system. Therefore, it may be
bus bar) has an infinite SCC, with zero fault studies need to be performed concluded that the selection of power
equivalent impedance and will maintain its routinely. It would be prudent to consider cables generally depends on the following
voltage under all conditions. the short term expansion programs of the factors.
network while selecting switchgear
Magnitude of short circuit current is time capabilities so that the expected increase • Operating voltage
dependent due to synchronous in short circuit level could well be • Load current
generators. It is initially at its largest value accommodated. • Emergency loading requirements
and decreasing to steady value. These and duration
higher fault levels taxCircuit Breakers Single line to ground fault can be a • Fault current
adversely so that current limiting reactors concern when a delta-wye connected • Fault clearing time (Protection
are sometimes used. three-phase four-wire system or wye- relays & Fuses)
grounded generators are employed • Allowable voltage drop
The short circuit MVA is a better indicator especially when the substation • Ambient temperature for the
of the stress on CB’s than the short circuit transformers or generators are very close particular installation
current as CB has to withstand recovery or are close coupled to the distribution configuration
voltage across breaker following arc switchgear. When the distance is small the • (Environmental conditions)
interruption. The currents flowing during a zero sequence impedance is significantly • Cable route length
fault is determined by the internal emf’s of smaller than the positive and negative • Method of cable installation
machines in the network, by the sequence impedance. This difference can (derated factors)
impedances of the machines, and by the cause the single line to ground fault
impedances between the machines and magnitude to be up to theoretical
the fault. maximum of 150% of the magnitude of a
three phase fault.
Page 8 Power Research and Development Consultants
Newsletter
• A techno-economically feasible
evacuation option suitable for all
Fig 2: June
the phases of generation was
recommended.
Fig 3: July
1. Introduction
Electrical power system is one of the most the utilities are well conversant with the Critical clearing time is that time, within
dynamic and complex human made steadystate analysis consisting ofload flow which the fault should be isolated so that
system on earth. Complexity is due to and faultstudies. However, as stability the machines in the system will not go out-
different voltage levels, amount of power studies involve the solution of both of-step. When the machine goes outof step,
being handled and the varieties of algebraic and differential equations, its power output oscillates from the
equipment being used. Dynamic, because representation of various controls in the generating mode to motoring mode and
of the time frame and response to system system, detailed modeling of the viceversa.
disturbances, this is of the order of several machines, that much importance is not
days for energy resource dynamics and empathized on the stability studies by the Most of the grid codes emphasize that
micro seconds to nano seconds during fast utilities. As the power systems increase in credible outages/contingencies in the
and very fast transients in the power size and complexity, more and more system shall not cause loss of supply,
system. Further, power system can be devices are added to control the power prolonged operation of the system
visualized as a spring mass problem, the system quantities, stability studies are frequency below andabove specified limits,
machines acting as masses and the gaining importance nowadays. This paper un-acceptable high or low voltage, system
interconnecting transmission lines as is written to help the practicing system instability, un-acceptable overloading of
springs. Whenever a spring is plucked and study engineers to understand the lines. Even though the references to voltage
released, oscillations are seen everywhere. concept of stability studies, data levels and the timing varies from grid code
Similarly in an interconnected system requirement for achieving different to grid code, typically for a specific grid
when a fault occurs, machines closer to objectives of stability studies and code, it states that stability of the system
fault swing more and the machines away emerging trends and technologies. should be ensured for the following cases –
from the fault swing less. Machines with Emphasis is given to understand the
higher inertia constant swing less and physical concept and interpretation of • 400 kV line: A permanent single
those with lower inertia constant swing results rather than detailed mathematical line to ground fault with a duration
more. This type of oscillations in the analysis, which can always be obtained of 5 cycles(100 milliseconds) with
power system falls under the classification from the reference books listed. unsuccessful re-closure 1.0 sec
of electro-mechanical oscillations, as it dead time followed by 3 pole
involves the interaction between the 2. Grid code references to stability opening of the faulted line.
electrical system transients and studies Unsuccessful re-closure (Figure 1)
mechanical transients of rotating masses. should be simulated and tested
Power system stability studies fall under Need for the stability studies are very before suggesting the au-re-closure
electro-mechanical oscillation studies. much emphasized in the national and facility for the 400 kV lines.
These studies are further classified into international grid codes. In this section,
transient stability studies for large references to some of the grid codes on • 220 kV and 132 kV lines: A
disturbances and small signal stability stability studies are drawn to emphasize permanent three phase fault with a
study or dynamic stability studies for small the importance of stability studies by fault clearing time of 8 cycles (160
disturbances in the system. In the planning and operational engineers. milliseconds)assuming 3 pole
transient stability studies one is generally opening.
interested in the rotor angle swing and in 2.1 Critical clearing time:
the dynamic stability study, the Further, grid codes emphasize that planning
performance of the various control Stability characteristics of the generators of the additional lines or elements in the
and the automatic voltage regulator are
functions to bring down the oscillations of system may become mandatory not
two important features that operate
different state variables in the system is because of the static contingency analysis
studied. throughout the period from the inception (load flow) but because of system stability
of the fault, until after its removal to considerations.
Most of the system studyengineers in the maintain voltage and stability ofthe
planning and operational departmentsof protective relaying.
Power Research and Development Consultants
Page 13
Newsletter
added to arrive at asingle inertia constant For one Hz change in the frequency, the done by single machine
value to be used in the swing equation change in real power is defined as the performanceconnected to infinite bus or
solution.During the planning exercise, the power number of the system.Power radial load. Voltage and frequency plots
typical values of the machine for the number of the system depends on the forload throw off and pickup are cross
proposed machines can be considered. base load and the load mix i.e.industrial, checked with the design calculations and
However, for the existing machines and for commercial, domestic, agricultural etc. As commissioning reports to fine tune the
operation studies, the data supplied by the the load mix changes with season, power model.
manufacturer should be considered and number of the system also exhibits
further validated by the commissioning seasonal variations. 3.5 High Voltage Direct Current (HVDC)
test reports. system model
Series FACTS devices enhance the Figure 5: Voltage Balancing with Individual Phase Compensation SVC
powertransfer capability of the AC lines.
Page 16 Power Research and Development Consultants
Newsletter
Figure 9: Frequency response with and without under frequency load shedding Many of the stability case studies typically
carried out for the utility system are
4. Stability studies for utility system dynamic voltage instability assessment, alsoapplicable to the industrial system,
selection, sizing and optimal location of especially when the industrial system
Stability case studies typically performed FACTS devices, interaction between isembedded with own generation
for the utility systems are explained with different devices and their controls, (captivepower plant - CPP).
its importance in the modeling section. system performance with renewable
The case studies to be performed depend energy integration like solar and wind, Stability studies are to be conducted to
on the conclusions to be drawn from the which are infirm in nature. In those arrive at the proper grid islanding schemes
studies and the necessary corrective systems having predominantly air and required relay settings, under
actions to be taken to control and protect conditioning loads, it is necessary to frequency based load shedding within the
the interconnected system. Studies ascertain the system performance during plant after the load shedding so that the
typically conducted are for determining the phenomenon called sympathetic CPP generator under frequency protection
the critical clearing time for different types tripping. will not operate during that condition.
of faults, system performance during un- Starting of large motor and analysis of the
successful re-closure, equipment tripping Operation of the protection system in the voltage dip during starting is another
(n-1 and n-2 outage) following a fault, healthy feeders due to the huge current typical study generally carried out in the
generator parameter evaluation, fine being drawn by its dynamic loads when industrial systems.
tuning the AVR, turbine-governor, PSS, the faulty feeder protection system
HVDC, FACTS device control block settings, operates is termed as sympathetic
study of power swing phenomenon and tripping.
performance of distance relay blocking
settings, study of load encroachment
problems and re-shaping the distance
relay settings, arriving at under frequency
and df/dt relay based load shedding
schemes, over frequency based system
separation and generator tripping. Special
case studies to be performed are identified
based on the problems envisaged in the
operation and control of interconnected
systems. Some of the stability studies
performed are design and implementation
of special protection schemes when major
chunk of load or generation is lost (e.g.
loss of HVDC system, loss of major AC tie
lines between two interconnected
Figure 10: Reactive power drawn by healthy feeders
systems), transformer tap control and
Page 18 Power Research and Development Consultants
Newsletter
Worst system conditions for the motor Good amount of research work is going on
starting like minimum grid fault level, to validate and improve the transient
minimum CPP generation etc. are to be stability model with the PMU data
identified and studies are conducted. In recording included.
case of arc furnace loads, the transient
voltage dip at the grid bus (PCC) and the 7. Conclusions
requirement, sizing and performance
tuning of the SVC are done using stability In this paper, an attempt is made to
studies. For the industrial plants having explain the importance of the stability
the rolling mill loads, loads are studies to practicing engineers. References
represented as cyclic loads and system to grid codes are drawn to insist that the
voltage and frequency variations are stability studies should be conducted to
ascertained. This study will help to take ascertain the transient and dynamic
appropriate decision to run the plant behavior of the power system, following
rolling mills or varying loads with the CPP the disturbance. Modeling of equipment
without any grid support. for stability studies is discussed. Analysis
and interpretation of results are illustrated
6.Wide area measurement and its through case studies under each section.
application
8. References
To facilitate the wide area monitoring,
control and disturbance analysis, to [1] Prabha Kundur , “Power System Stability
minimize the future black outs caused due and Control”, (Book), McGraw-Hill Professional
to the cascade tripping, there is a growing Publishing, 1994.
interest in Phasor Measurement Unit
[2] J.Arrillaga, “Computer Modeling of Electrical
(PMU). The introduction of PMU
Power Systems”, (Book), Wiley-Blackwell, 2nd
technology can significantly improve Edition, 2001.
theobservability of the power system
dynamics. It can warn system operators of [3] Edward Wilson Kimbark , “Power System
potential problems more quickly during Stability”, (Book), Volumes I, II, III , Wiley-IEEE
critical situations. PMUs would be very Press, 1995
useful in determining where and how to
perform system separation to limit the [4] K.R.Padiyar, “HVDC Power Transmission
Systems”, (Book), New Age International, 1990
effect of the system disturbance.
[5] K.R.Padiyar, “FACTS Controllers in Power
The major areas of applications of PMU Transmission and Distribution”, (Book), New
are Age International P Ltd, 2007
I. Introduction A cost efficient and satisfactory solution to Real solutions for ?D and D define
Historically, transient (angle or the problem of oscillatory instability is to equilibrium values. In general, equilibrium
synchronous) stability has been a major provide damping for the generator rotor values are functions of the parameters ‘B’.
concern in the system operation. It was oscillations. This is conveniently done by
anticipated that the introduction of high providing Power System Stabilizers (PSS) Considering small perturbations around
? ?D F,
gain AVR and fast acting exciter will help in which are supplementary controllers in the equilibrium point, we can define
the improvement of transient stability in the excitation systems. The control signal D
addition to the increase in steady state VS in Fig.1 (which shows the block diagram
stability limit. It is to be noted that the for a static exciter)is the output of a PSS and obtain the linearized state equation
AVR acts to overcome the armature
reaction and thus reduce the effective
reactance of the generators (from Xd to
around X'd ). As a matter of fact, modern
turbo-generators cannot operate at full
rated power, as the synchronous
reactance, Xd, is around 2.0 pu.
F@ GH F
problem of oscillatory instability of the
which has input signal derived from speed (3)
equilibrium (operating) point. Even small
(rotor velocity) or frequency or electrical
perturbations in the system caused by
power (or a combination of these
IA IA IC IC
random load changes can lead to loss of where,
GH GJ ,G
variables). The objective of PSS design is to
I? I I? J I
synchronous stability (loss of synchronism)
increase the damping torque on the
due to undamped (growing) oscillations
generator rotor without affecting the
Note that G H is termed as the system
which appear as spontaneous and cannot
synchronizing torque at the critical
Jacobian and GJ is the load flow Jacobian.
be predicted as the result of an observable
frequencies.
major disturbance.
It is assumed that the load flow Jacobian is
The system operators observed that II. Basic Concepts of Stability of non-singular.
tripping (or disabling) of the AVR resulted Equilibrium Point
in damping of the oscillations. However, The stability of the equilibrium point is
this is not a viable strategy. DeMello and We can describe the mathematical model judged by the location of the eigenvalues
Concordia (1969) presented a simplified of a power system by the following set of of the system Jacobian matrix. If the real
analysis of the problem, using Heffron- differential and algebraic equations (DAE). parts of all eigenvalues of the system
?@ A <?, , B=
Phillips constants defined for a SMIB Jacobian are negative, the system is
system (Padiyar, 2002). It was explained (1) asymptotically stable. If one or more
0 C <?, , B=
that the problem of oscillatory instability is eigenvalues have positive real part, then
aggravated at peak loading conditions and (2) the system is unstable.
vector differential equation given by systems which can be divided into distinct synthesized from the electric power and
KB Δ* MΔ*(4)
areas and which are separated by long speed signals.
distances. For systems in which the The gain of PSS is to be chosen to provide
generating stations are distributed adequate damping of all the critical modes
where M is a diagonal matrix with
OP
KNN
uniformly over a geographical area, it under various operating conditions. The
QR
(SN is the inertia constant of would be difficult to distinguish between critical modes include not only local and
machine ‘ ’). Neglecting losses, M#N
TUVW local and interarea modes from physical interarea modes, but other modes (termed
TXP considerations. However, a common as control or exciter modes) introduced by
where D# is the power output of machine
‘'’. The matrix M is singular and has the
observation is that the interarea modes the excitation system and/or torsional
Thus, the <Z 1= vector of relative angles rotor are adequate to damp intra-plant
assuming the machine 1 as the reference. The amortisseur circuits on a generator and satisfactory damping at other
operating conditions. The output of PSS
can be expressed as: modes. PSS is designed mainly to stabilize must be limited to prevent PSS acting
fK Mh.
zero and real eigenvalues of the matrix damping of the torsional mode. direction.
in a parallel AC tie. The power modulation of troublesome swing modes is normally [6] Byerly et al.(1982).Eigenvalue analysis
(normally applied at the rectifier station) is done by experiments and transient of synchronizing power flow
the primary damping control. However, records of relevant system variables. Also, oscillations in large electric power
with weak AC systems (low SCRs), both design of damping controllers requires systems. IEEE Trans.PAS-100(1),
active and reactive power modulation are more detailed system models that capture pp.235-243
implemented using rectifier and inverter the dynamics of interest. In this context,
stations. Also, the modulation of extinction Selective Modal Analysis (SMA) techniques [7] Wong D.Y. et al.(1988).Eigenvalue
angle at the inverter, in response to the AC developed at MIT (Perez-Arriaga,1982) are analysis of very large power systems.
voltage magnitude signal can avoid voltage of interest. IEEE Trans. Power Systems,103(2),
instability. pp.472-480
Generally, we consider reduced system
Small signal power modulation models with adequate detail for analysis [8] Perez-Arriaga et al.(1982).Selective
implemented at Pacific DC intertie has and control design. Padiyar(2002) modal analysis with applications to
helped to prevent interarea mode of 1/3 describes modeling techniques based on electric power systems ,Part I: Heuristic
Hz from reducing power transfer capability identifying individual dynamic devices and introduction; Part II: The dynamic
of a parallel AC tie. The power or current their connections to the network. The AC stability problem. IEEE Trans.PAS-
modulation has now become a standard network is modeled by linearized algebraic 101(9), pp.3117-3134
practice.HVDC technology of using equations using rectangular or polar
thyristor valves for control was extended coordinates. For tuning multiple damping
to develop Static Var Compensators (SVC) controllers, one can use nonlinear
for voltage regulation and Thyristor programming techniques that consider
Controlled Series Capacitors (TCSC) for constraints on the locations of eigenvalues
power flow control. These controllers in a sector in the LHP of s-domain.
belong to the first generation of FACTS
controllers. Supplementary Modulation VI. References
Controllers (SMC) has been applied for
reactive power modulation in SVC and [1] Padiyar K.R. (2002). Power System
help to damp swing modes. Similarly, Dynamics-Stability and Control
power swing damping control is an (Second Edition), Hyderabad: BS
auxiliary control in TCSC that supplement Publications
PSS action. New and emerging FACTS
controllers such as STATCOM, SSSC, UPFC [2] DeMello F.P and C.Concordia
and IPFC are based on Voltage Source (1969).Concepts of synchronous
Converters that use self-commutated machine stability as affected by
devices such as GTO or IGBT. STATCOM is excitation control IEEE Trans. PAS-
a shunt controller that may replace SVC 88(4),pp.316-329
and the reactive power modulation is
[3] Busby et al. (1979).Dynamic stability
expected to improve small signal stability.
improvement at Monticello station-
V. System Models and Modal Analysis in analytical study and field tests IEEE
Large Power Systems Trans.PAS-98(3), pp.889-901
In the eighties, computer programs for the [4] Van Ness J.E. et al.(1980).Analytical
eigenvalue analysis of large power systems investigations of dynamic instability
have been developed. Examples are, occurring at Powerton station. IEEE
AESOPS (Analysis of Essentially Trans.PAS-99(4), pp.1386-1395
Spontaneous Oscillations in Power
Systems)(Byerly,1982) and PEALS [5] Larsen E.V. and D.A. Swann
(Program for Eigenvalues of Large (1981).Applying Power System
Systems)(Wong,1988). These programs Stabilizers-Parts I,II and III .IEEE Trans.
generally consider classical models of PAS-100(6), pp.3017-3046
generators and can handle up to 1000
generators. However, identification
Page 22 Power Research and Development Consultants
Newsletter
model containing a generator(as aslack generator load dynamics are analyzed by deviations in voltage across motor
bus) feeding P-Q load via a lossless line. using nonlinear simulation. For small and terminals resulted in the stability of
With respect to a power grid delivering a short-term disturbances, linearized synchronous motor with a constancy of
P-Q load, the grid is considered as a models (around operating region) are used voltage across motor terminals. Further,
Thevenin’s equivalent. The best way of for making an Eigen value/Eigen vector the fluctuating reactive load also was
getting this Thevenin’s equivalent together analysis. (In this it is very involving if tap causing fluctuations in the voltage at the
with its limitations is discussed elaborately changers are used in the model.)For long- load bus as well as fluctuations in tie-line
in [6]. This model can be used only for a term small or large disturbances, P-V & Q- power oscillations. A Static VAR
rough assessment of voltage stability V analysis is performed for obtaining compensator designed suitably resulted in
margin. The regular load flow methods are stability margin. Sensitivity analysis using a minimal fluctuation and a flat voltage
to be used for accurate assessment. L-indices is also largely being performed. profile.
The Voltage-instability can also be viewed For large networks, ANN based algorithm, X. Conclusion
as a dynamic problem wholly caused by Fuzzy Controlling Techniques, neuro- The phenomenon of voltage-instability is
loads. When the loads (induction motors) computing using genetic algorithms for very subtle and here is a quote by one of
change governed by differential equations, optimization of active and reactive powers pioneering authors, Carsow W. Taylor:
an Eigen value analysis for small are being attempted. “May be I can’t define voltage stability, but
perturbations or a nonlinear dynamics The EPRI and Energy Corporation have I know it, when I see it”.
analysis for large disturbances, will usually validated a method developed by EPRI for
XI. References:
be conducted. This kind of voltage- continuously calculating the voltage
[1] ‘Power System Voltage Stability’, Carson W.
instability could be totally different from stability margin on transmission networks Taylor, McGraw-Hill International Edition,
the angle-instability. using measurements from the CT and PTs 1994.
VI. Voltage Stability Indices at the substation level. The method [2] ‘Voltage Stability of Electric Power
Voltage Collapse Proximity Indicator (VCPI) promises to overcome thelimitationsof Systems’, Thierry van custemcostas
is the total change in generator reactive traditionalmethods that rely primarily on vicunas, Springer, 1998, ISBN 0792381394
power for a change in demand. Two such simulation-based methods developed [3] ‘Definitions - Classification of Power System
from the data used at planning level. Stability’, IEEE-CIGRE, IEEE Transactions on
VCPIPi =∑ ∆ g/∆ i
indicators are proposed in literature [1]:
Power Systems, Vol. 19, No.2, May 2004.
VIII. Prevention of Voltage Collapse [4] ‘EPRI and Entergy Validate Measurement-
VCPIqi=∑ ∆ g/∆C i
To prevent voltage collapse, the Based Voltage Stability Monitoring to
assessment of voltage stability along with Improve Grid Reliability and capacitive
(The buses with large values of VCPI are the available margin is very essential. effectiveness’, EPRI News Release Feb
the most effective locations for load Once that is possible, the conventional 2009.
shedding. The indices change from unity at remedial measures of activating reactive [5] ‘Voltage Stability: Some Refection on Q-V
light load to almost infinity at voltage Characteristics of Loads’, G. Govinda Rao,
compensating devices like thyristor
H. P. Khincha, D. Thukaram, proceedings
∑ ∆ g is computed considering SVCs also
collapse) controlled VAR compensators, generator
1998, Int. conf. on EMPD, Singapore, IEEE
excitation controllers, on-load tap Catalog No. 98EX137.
as reactive generators. changers etc. can be carried out. Under [6] “Model Validation Studies in Obtaining Q-V
The voltage stability for the static case is voltage load shedding is also in practice to characteristics of PQ Loads in Respect of
analyzed by performing load flow studies move the operating point far from the Reactive Power Management and Voltage
to determine ‘L-indices’. If there are g- nose point. Adequate spinningreservealso Stability”, G. Govinda Rao, K. V. S. R.
generators, and g+1 to n load buses, the L- helps in increasing the stability margin. Murthy, IEEE International Conference on
index for the voltage stability for the jth Power Electronics, Drives and Energy
load bus is given by Systems for Industrial Growth PEDES, New
{
IX. Author’s Experience
xy
Lj =1-u Fw x
Delhi, Dec, 2006.
; j = g+1…n Case studies were conducted on a power
#&
[7] “An Expert Fuzzy Control Approach to
z grid supplying a steel plant actuated by
Voltage Stability Enhancement”, A.
All quantities in this equation are complex cyclic P-Q loads of about 80 seconds NarendranathUdupa, D.Thukaram,
in nature and Fji are elements of FLGmatrix. periodicity. A synchronous motor was K.Parthasarathy, ELSEVIER, Electric Power
If the L-index is close to zero, the load bus found to be experiencing long-term and Energy Systems 21 (1999) pp. 279-287.
is voltage stable. If it is close tounity, the voltage instability, on simulation of the [8] “Voltage Dependent Reactive Power Limits
load is nearing instability [7]. non-linear model of the grid. Interestingly, for Voltage Stability Studies”, P. A. Lof, G.
VII. State-of-the-art in Simulation an automatic voltage regulator actuated Anderson and D. J. Hill, IEEE Transactions
Methodologies on Power Systems, Vol.10, No.1, Feb.1995.
For large and short-term disturbances,
Page 24 Power Research and Development Consultants
Newsletter
Harmonic Studies
Dr. R. Nagaraja
• False tripping of branch circuit as summarized below:- consumed by all of the loads on the
breakers system when the system is at peak
Total Voltage Harmonic Distortion
• Metering errors demand. The denominator used in this
(VTHD) defined as -
• Fires in wiring and distribution ratio does not change with load.
n
systems
∑ V h
2
• Generator failures V THD (%) = h=2 Since IEEE standard 519 harmonic current
X 100
•
V1 limits are written in terms of percentage
Crest factors and related problems
• Lower system power factor, resulting of full load current, IL (TDD), and not as a
in penalties on monthly utility bills Where, percentage of fundamental current, I1
(ITHD), studies at partial load are usually not
4. Harmonic Standards “V 1 ” is fundamental component of line worth the effort. In general, full load
voltage. operation is the worst case condition
The harmonic studies are generally carried “h” is harmonic order from 2 to n toanalyze in harmonic studies. Further the
out based on the guidelines given by the TDD will always be less than or equal to
utility grid code or the IEEE or IEC Total Current Harmonic Distortion
(I ) defined as - ITHD. At the full load TDD equals ITHD.
standards. The guidelines outlined in the THD
standards are designed to limit harmonic 4.2 IEC Standards
currents from individual customers and n
Unlike the IEEE standards on harmonics
equipment so that harmonic voltage levels ∑
h = 2
I 2h
where there is only a single publication
on the overall power system will be I THD (%) = X 100
I1 covering all issues related to harmonics, IEC
acceptable. Where, standards on harmonics [9] are separated
into several publications.
Harmonic limits are typically evaluated at “I1” is fundamental current magnitude
the point of common coupling (PCC) “Ih“ is current magnitude of each There are standards dealing with
between the power supply utility and the harmonic order h environments and limits which are further
plant load. The responsibility of the plant broken down based on the voltage and
The ITHD represents the total harmonic
substation consumer is to ensure that the current levels. These key standards are as
current distortion of the wave form at the
limits are not exceeded by the harmonic follows:
particular moment when the
distortion generated within their facility. measurement is taken. It is the ratio of • IEC 61000-2-2 (1993): Electromagnetic
These limits can also be applied to the rms value harmonic current to the Compatibility (EMC). Part 2:
individual buses throughout an electrical fundamental (non-harmonic) current Environment. Section 2: Compatibility
distribution system to reduce the harmful measured for that load point and usually Levels for Low-Frequency Conducted
effects of the harmonic currents. expressed as percentage. Note that the Disturbances and Signaling in Public
denominator used in this ratio changes Low-Voltage Power Supply Systems.
4.1 IEEE Standards with load.
• IEC 61000-3-2 (2000): Electromagnetic
IEEE STD 519-1992 guideline [8], Compatibility (EMC). Part 3: Limits.
Total Demand Distortion (TDD) defined
elaborates harmonic current and voltage Section 2: Limits for Harmonic Current
as -
distortion limits. The IEEE 519 standard Emissions (Equipment Input Current Up
provides two limits one for voltage and to and Including 16 A per Phase).
one for current. Voltage limits are based n
on the bus voltage level at the PCC ∑ I 2h • IEC 61000-3-4 (1998): Electromagnetic
h = 2
TDD (%) = X 100 Compatibility (EMC). Part 3: Limits.
whereas the current limits vary by the IL
ratio of short circuit current at the PCC Section 4: Limitation of Emission of
divided by the load current. It should be Harmonic Currents in Low-Voltage
noted that as the short circuit ratio Where, Power Supply Systems for Equipment
increases, that is load current decreases, with Rated Current Greater Than 16 A.
“IL” is maximum demand load current
higher limits are allowed. This is due to the (fundamental frequency current) at PCC. • IEC 61000-3-6 (1996): Electromagnetic
fact that although more distortion is Compatibility (EMC). Part 3: Limits.
allowable the overall magnitude of the Total Demand Distortion (TDD) is the ratio
of the rms value of the harmonic current Section 6: Assessment of Emission
distorted current is smaller. This will tend Limits for Distorting Loads in MV and
to the maximum demand load current
to have a less significant effect on the HV Power Systems. Basic EMC
power system. (full load fundamental frequency current).
The full load fundamental current is the publication.
The definition of key harmonic
indicesanalyzed to assess system total amount of non-harmonic current
performance is
Page 26 Power Research and Development Consultants
Newsletter
Depending on the utility practice and the flow study or the measurements Step 4: Develop solutions (filter, etc.) and
standard being applied, which is generally conducted. Table 2 gives the typical investigate possible adverse system
county or utility specific, relevant calculation for the Total Demand interactions. Also, check the sensitivity of
standards are to be referred for the Distortion (TDD) for different voltage the results to important variables. If the
harmonic distortion limits for both voltage levels based on IEEE Std. solution is based on the filter design, the
and current. filter is selected such that at fundamental
5. Harmonic Analysis Procedure frequency, the filter compensates the
4.3 Utility Grid Code
reactive power requirement at the plant
Most of the utility grid codes specify the Procedure for the harmonic analysis to improve the power factor.
maximum total levels of harmonic depends on the basic question as whether
distortion at different voltage levels in the the analysis is for the existing system or Step 5: After the installation of proposed
system. Table 1 gives the distortion limits for the proposed system. If the analysis is solutions, perform monitoring to verify
specified in a typical grid code. Unless for the existing system, harmonic the correct operation of the system.
otherwise specified, generally these measurements are done at the plant using
distortion limits are for the voltage the power/harmonic analyzers. However, if the analysis is for the
harmonics. Further, specifications do not Measurement values are cross checked proposed system, studies are done based
refer to the fault level at the bus. It is very with the appropriate applicable standard. entirely on the simulation. The proposed
important to understand that consumer If the values are not within the acceptable plant is modelled in the harmonic study
cannot be responsible to limit the grid limit, filter or remedial measures are software tool [7]. The nonlinear loads are
voltage harmonic distortion limits to these suggested and harmonic simulation modelled as current injecting sources. The
values. For the consumer perspective, it is studies are done to ascertain the effect of magnitude of the current at each
the current harmonic distortion limits as filters. Following are the steps involved in harmonic frequency is arrived from the
specified by IEEE or IEC standard, which the harmonic analysis for an existing plant data furnished by the equipment supplier
only can be controlled. It is the - or empirical formula or the measurement
responsibility of the utility to find out the Step 1: Determine the objectives of the conducted at similar installations at other
voltage distortion arising out of these study. The objective might be to identify sites or as per standards. Harmonic
consumers and limit the additional/new what is causing an existing problem. analysis software tool gives the current
connections on to weak buses in the Another might be to determine if a new distortion at the series elements and
system and ensure that the voltage plant expansion containing equipment voltage distortion at different buses.
harmonic distortions are within the limit. such as adjustable-speed drives and These values are compared with the
Table 1: Typical grid code for harmonic capacitors is likely to have problems. applicable standards and if not within the
distortion level Step 2: Make measurements of the limit, remedial measures are suggested and
Voltage Total
Individual existing harmonic conditions. simulated. Once the plant is commissioned,
distortion in % it is worthwhile to conduct the
Level in distortion Step 3: Study the new circuit condition
kV in % Odd Even measurements at site to ascertain the
or existing problem.
simulation values.
69 3.0 2.0 1.0
132 1.5 1.0 0.5 Table 2: Typical calculation for the selection of allowable current Harmonics limit
Load current
Bus Fault
220 1.5 1.0 0.5 in A Ratio =
Voltage current TDD Basis from reference [8]
(Series Isc/IL
level in A
branch)
Current Distortion Limits for
4.4 Selection of current harmonic limit as General Transmission Systems
per IEEE Std. 220 kV 9800 450 21.78 2.5
(>161 kV)
Isc/IL <50
The basis of selecting the individual
Current Distortion Limits for
current harmonic limit depends on the
General Sub transmission
ratio of Isc (maximum short circuit current 132 kV 8200 245 33.47 4 Systems (69001 V through
at PCC) and IL (maximum demand load 161000 V)
current (fundamental frequency 20<Isc/IL<50
component at PCC). The fault level Isc is Current Distortion Limits for
computed at the PCC from the short circuit General Distribution Systems
33 kV 12400 225 55.11 12
study of the given network and maximum (120 V through 69000 V)
load current IL is considered from the load 50<Isc/IL<100
Power Research and Development Consultants
Page 27
Newsletter
6. Harmonic Analysis Data Collection This also minimizes the 2nd and 3rd conducted with the minimum fault level at
harmonic current injection by the the grid bus.
Entire system data required for load flow filter bank to the system, as the
and fault study are required for the presence of 2nd and 3rd harmonic Some of the harmonic study requirements
harmonic study also. In addition to above voltages in the system are less. In specify that the background harmonics in
data, specific attention should be given to certain designs, the current limiting the grid be considered for the simulation
following data - reactor is selected as 0.2%, if the bus study. If the background harmonic is
fault level is less and the inrush considered as voltage source, voltage
current is controlled to acceptable harmonic distortion will not change at the
Transformer winding connections –
limits. With 0.2% reactor, the source bus (generally considered as PCC)
As winding connection provides the
resonant frequency lies between 22 with the plant under study being
path for certain harmonic currents
and 23 harmonic order, resonating represented. Author is of the opinion that
and blocks specific harmonic current,
frequency being 1118 Hz on 50 cycle it is better to represent the background
exact representation of the winding
fundamental frequency basis. harmonics in the grid as current source.
connection and the phase shift angle
Capacitor bank with this arraignment The magnitude of the current source is
arising out of the vector connection
acts as capacitive circuit up to 22nd adjusted in proportion to IEEE current
should be collected.
harmonic. If in the plant, 5th, 7th and limits so that required total voltage
Capacitor values and locations
11th harmonic voltages are present, distortion at the PCC is obtained. In this
(critical) – In the power flow study,
the capacitor bank starts injecting the model, if the plant load has more linear
generally the current limiting reactor
corresponding harmonic currents, loads, the overall distortion at the PCC
or filter reactor associated with the
there by amplifying the harmonic may come down. If the plant load has
capacitor banks are not represented.
currents in the plant or system. It is more nonlinear loads and no harmonic
The effective MVAR at fundamental
better to ascertain the harmonic filters are present in the plant, then the
frequency is sufficient to be modelled
levels in the plant and then decide the voltage harmonic distortion at the PCC will
for the load flow study. In the
reactor value. Cost cutting done in the increase. Representation of the
harmonic analysis study, exact
selection of the reactor at 0.2% will background harmonic is also required to
representation of reactor value is very
create the problems in the plant at arrive at the voltage and current ratings of
much essential. If there is no reactor
the later date, if the lower order the filter element within the plant.
in the capacitor circuit, for all
harmonic frequencies, as long as there harmonic voltages are present in the
system. Peak load demand – Load flow
exists specific frequency harmonic
studies will reveal the peak load
voltage, capacitor injects the
Harmonic spectra for nonlinear loads demand. For the existing plants, the
corresponding frequency harmonic
– Harmonic sources or nonlinear loads peak load demand can be obtained
current into the system. If the current
can be represented as current through measurements at site or
limiting reactor value is say 6%, then
readings obtained from the panel
around 4thharmonic frequency, the injection sources or voltage sources.
Values of the injected currents should meters.
inductor-capacitor circuit resonates,
resonate frequency being 204.12 Hz be determined by measurement. In
on 50 cycle fundamental frequency the absence of measurements, 7. Harmonic Measurement
th
basis. Till 4 harmonic frequency, the standard manufacturer data can be Objectives of the harmonic measurements
capacitor bank acts as capacitive assumed for the study. are to identify power quality problems, to
circuit and injects the harmonic minimize the losses in the production
current to bus. Above 4th harmonic Grid fault level and background process and to increase the plant
frequency, the capacitor bank acts as harmonics in the grid – In the fault productivity. Benefits of power quality
inductive circuit and absorbs the study, the grid fault level is measurement are preventive and
harmonic current, depending on the considered to be the maximum to predictive maintenance, determining the
th
impedance path. As such, 4 determine the maximum interrupting need of mitigation equipment, ensuring
harmonic current presence in the capabilities of the breaker within the equipment performance and sensitivity
system is very minimum, 6% current plant. For harmonic study, prevailing assessment of the equipment to
limiting reactor is referred to as de- fault level at the grid bus should be disturbance. The issues related to
tuned reactor. considered and studies are also to be measuring are sampling rate, accuracy,
Page 28 Power Research and Development Consultants
Newsletter
8. Case Study
Figure 3 shows the typical system
considered for the harmonic study. The
encircled region in the system is the area
of concern in the harmonic study. Table 3
gives the 5th , 7th and 11th harmonic
current injection because of the non linear
load at the plant. From the harmonic
power flow, it is found that the harmonic
voltage distortions are not acceptable.
Figure 4 gives the bar graph showing the
harmonic distortion at few buses in the
system. As the harmonic voltage
distortions are not within the limit, filters
are proposed in the plant as shown in
figure 5. Figure 6 gives the bar graph
showing the voltage harmonic distortion
after the incorporation of the filter.It is
found that the voltage harmonic
distortions are within the limits in the Figure 2: Voltage and current harmonic distribution for entire spectrum at a specific time
entire system.
Power Research and Development Consultants
Page 29
Newsletter
10. References
[1] J. Arrillaga, D. A. Bradley, P. S. Bodger, [5] G. T. Heydt, “Electric Power Quality”, [8] IEEE Guide for harmonic control and
“Power system harmonics”, Wiley, Stars in a Circle Publications, second reactive compensation of Static Power
1985. edition, 1994, Avarua, Rarotonga, Converters, IEEE Std. 519-1992.
Cook Islands.
[2] R. C. Duagan, M. F. Mcgranaghan and [9] IEC Sub-Committee 77A report,
H. W. Beaty, “Electric Power System [6] Arindam Ghosh, and Gerard Ledwich ΄΄Disturbances Caused by Equipment
Quality”, McGraw-Hill, 1221 Avenue “Power QualityEnhancement using Connected to the Public Low-Voltage
of the Americas, New York, NY 10020 custom power devices”, Kluwer’s Supply System Part 2 : Harmonics ΄΄,
Power Electronics and Power System 1990 (Revised Draft of IEC 555-2).
[3] C. Sankaran, “Power Quality” CRC series, U.S.A, 2002.
Press, New York, 2002,
[7] IEEE colour book series 399, 1997,
[4] Alexander Kusko, P.E. Marc IEEE Recommended Practice for
T.Thompson, “Power Quality in Power Systems Analysis, IEEE Brown
Electrical System” McGraw-Hill, New Book.
York Chicago.
Power Research and Development Consultants
Page 31
Newsletter
open
Causescondition
over voltages,
arises while
over currents
performing and load flow and short circuit study results.
single pole reclosing.
distortions resultingSimilarly,
in thermaltwo phases and Equivalent network considered for the
could be leftstresses
dielectric open with which
the other mayphase be simulation is shown in Figure 2.
energized during
dangerous for electrical
line de-energization.
de equipment
Shunt reactors
(failure, reduction increase
in performance
the open-phase
open and
voltage of
lifetime considerably
insulators etc.,).
because of unequal
(f) compensation
Various methods of the used positive
are based andonzero-
zero
the
Figure 1. Examples of unbalanced sequence principles:
following line capacitances. As reactors
systems at risk from ferroresonance. • Avoid,
are in parallel by withproper the design
line conductor
and/or
capacitance
switchingtooperations,
ground, the equivalent
configurations
B. Ferroresonance Prediction [3] phase-to-ground
phase reactance at power
susceptible to ferroresonance. Figure 2. Equivalent network considered
Ferroresonance is frequently accompanied frequency is inductive and may reach high
• Ensure that the energy supplied by for simulation
by some of the symptoms described value when the shunt compensation is
below: largethe source65%).
(above is notIn sufficient
such cases, to parallel
sustain
System data considered for simulation as
• High permanent over voltages of the phenomenon.
combination
combina of the shunt This reactor technique
and the
follows.
differential mode (phase-to-phase) line normally consists ofin
shunt capacitance introducing
series with losses
the 1) Equivalent network data:The equivalent
and/or common mode (phase-to- inter-phase
interwhich damp capacitance forms a series
out ferroresonance when source impedance data considered for
earth). resonant circuit. These conditions could
it occurs. study are presented in Table I.
• High permanent over currents, high result in series resonance on shunt
Table 1. Equivalent Source Impedance
permanent distortions of voltage and compensated lines with attendant
3. Ferroresonance Simulation Study Data
current waveforms. overvoltages and their detrimental detrimen effects
A. the
System Modelling [5] SS-A SS-B
• Displacement of the neutral point on connected equipments.
R1 (Ω) 2.0 3.34
voltage, transformer heating (in no- Steady
Equivalent state
Source: analysis
Equivalent of sources
equivalent at X1 (Ω) 32.0 53.34
load operation). network model have to be
different busses are represented using performed for R0 (Ω) 4.5 5.34
• Continuous, excessively loud noise in various
positive and simulated
zero sequence stuck impedance
breaker X0 (Ω) 73.14 85.34
transformers and reactors. conditions.
values corresponding to the expected fault 2) Transmission line data:
data:The 210 km,
• Damage of electrical equipment Details
levels atofthose
one busses.
stuck breaker condition to 400kV double circuit transmission line
(capacitor banks, VT, CVT etc.) due to be simulated are&as follows.
Transformers Shunt reactors: At configuration considered for the study is
thermal effect or insulation • Energizefrequencies,
ferroresonnace transmission line from
transformers presented in Figure 3. Two transposition
breakdown. A characteristic SS-AA
behave to SS
SS-Bas with one
induc
inductive pole of SS-A end
elements. points are considered for simulation and a
symptom of VT destruction by breaker
Capacitances do not have keeping
with one pole stuck and to be shunt compensation of 400 kV, 80 MVAr
ferroresonance is a destroyed open all the Saturation
considered. three polesofofthe breaker at SS-B
magnetizingSS has been considered at one end of each
primary winding and an intact end.
inductance, residual flux and losses circuit for the studies.
secondary winding. •
(copper Vary
andNGRmagnetizing)
value from 0%play to 100% an
• Spurious tripping of protection of phase reactor
important rolevalue.in ferroresonance
devices. •
generation Record
and damping.steady state open
Some of these symptoms are not conductor
Transmission line to or
(s) phase ground vol
voltage.
cable: When
necessary specific to the ferroresonance •
representing
represen Record overhead lines it neutral
steady state is of
phenomenon. For example permanent voltage
importance and tocurrenttake for into allaccount
line shuntthe
displacement of the neutral point of an reactors.
frequency
unearthed neutral system may be the •
dependence Observe of whether
the zero there is any
zero-sequence
consequence of a single phase-to-earth possibility
parameters. Asymmetry hasat specific
of getting resonance to be
fault. Due to the multitude of various value of NGR.
considered as well. Shielding wires may be
sources of capacitances and non linear Perform
eliminatedother assumingstuckzero breaker
voltagesimulated
on these
case studies. Figure 3. Transmission line data
inductances in a real power network and wires. Travelling wave model of
the wide range of operating conditions, Induced
transmission voltages
line isonusedde
de-energized
in the study. circuit: 3) Power transformer data:500
data: MVA,
configurations under which this study is applicable
Loads: Loads represented as constant for only double 400/132 kV, Ynyn trans
transformer with short
ferroresonance can occur are endless. circuit
impedance lines.type A with
shunt compensated
parallel –RL load. de de- circuit impedance of 12.5% and non
non- linear
energized circuit running on the same magnetization branch represented as
C. Preventing or Damping
right
B. of way
System data with an energized circuit can piece-wise
wise linear representation using
Ferroresonance[4]
be subjected to high high-induced voltages due open circuit characteristics of transformer
A number of practical measures can be Equivalent network model considered for
taken to prevent ferroresonance, that to parallel resonance between the line [4].
simulation studies is derived based on
shunt
hunt reactor and the line capacitance.
Power Research and Development Consultants
Page 33
Newsletter
(a)
(b)
Figure 6. Voltage and current waveform at
(a) transformer terminal with no load on
transformer
(b)
Figure 9.Voltage and current waveform at
transformer terminal with 10% load on
transformer
(b)
4. Observations &Conclusions
Figure 4. Voltage and current waveform at
transformer terminal with no load on
(a) Based on system considered for simulation
transformer study, it is observed that when a
transmission line terminated with
unloaded power transformer and uneven
breaker pole opening operations at source
end can cause ferroresonance in power
transformers. It is also observed that, 10%
(b) load on secondary terminal of transformer
Figure 7. Voltage and current waveform at helps in damping the ferroresonance
transformer terminal with 10% load on oscillation for all the cases. It is necessary
(a) transformer to ensure a minimum 10% loading on
secondary side of power transformer to
minimize the possible occurrence of
ferroresonance.
5. References
[1] Bernard C.Lesieutr, Jama A.mohamed “Analysis
of Ferroresonance in Three-Phase
(b) Transformers, IEEE POWERCON 2000. pp.
1013-1018.
Figure 5. Voltage and current waveform at [2] S.Mozaffari, S.Henschel, A.C.Soudack “Chaotic
transformer terminal with 10% load on (a) ferroresonance in power t transformers”, IEE
transformer Proc. Gener.Transm.Distrib.,Vol.142,No.3,May
1995. pp. 247-250.
[3] Ph. Ferracci, Collection Technique Schneider
Ferroresonance - n° 190.ECT190, first issued
Two pole opening: 2-pole opening of March 1998.
circuit breaker A as shown in Figure 2. [4] Yunge Li, Wei Shi and Furong Li “Novel
analytical solution to Fundamental
Voltage waveforms at bus 4 and ferroresonance –part II: Criterion and
transformer magnetizing current elimination”, IEEE Transactions on Power
(b) Delivery, Vol.21.No.2, April 2006. pp.794-800.
waveform are shown in figures 6 and 7 for Figure 8. Voltage and current waveform at [5] IEC Std-60071-4, 2004-06, Insulation co-
no load and 10% load on transformer ordination–Part 4: Computational guide to
transformer terminal with no load on insulation co-ordination and modeling of
respectively. transformer electrical networks.
Page 34 Power Research and Development Consultants
Newsletter
Shunt Reactor Switching in Extra High Voltage System - Criterion for Verification of
Proposed Circuit Breaker Parameters
Dr. K. Parthasarathy, VeerabrahmamBathini
strength between the CB contacts
I. Introduction II. Switching Device Characteristics increases faster than the build-up of TRV.
Shunt reactors are mainly used in
transmission networks to regulate the Switchgear is the general term covering III. Shunt Reactor Switching
reactive power balance of the power switching and interrupting devices. A. Opening Operations (Chopping
system by compensating the surplus Switchgear performs two important but Overvoltages and Re-ignitions)
reactive power generation of transmission different tasks. The first task is to perform In addition to the inductance of the shunt
lines and thereby stabilize the system routine switching operations such as reactor winding, the windings, the
voltage. Reactors are normally disconnecting or isolating apparatus for a bushings, and the connecting leads of the
disconnected at heavy load conditions and variety of system requirements. The reactor have stray capacitances. When a
are connected to the bus bars/lines at second task is to interrupt current flow reactor is de-energized, the voltage across
periods of low load conditions. Shunt under abnormal or fault conditions to it will oscillate with a natural frequency
reactors are quite often switched in and prevent excessive damages. Switching determined by the inductance and stray
out on daily basis. Shunt reactors absorb devices should be capable of not only capacitances. The oscillation frequency is
the reactive power and reduce the over interrupting normal load and fault typically in the order of few kHz. Due to
voltages during light load conditions, and currents but also capable of re- chopping (premature interruption) of the
also assist in reducing transient establishing the connection within the current slightly before the natural current
overvoltages caused by switching and system very quickly. Therefore, the zero, the oscillating voltage across reactor
lightning. Consequently, frequent function of a switching device is both of will have higher amplitude than the
switching is a significant characteristic of opening and closing of a circuit. supply voltage.
reactors.
When a switching device interrupts the For modern SF6 circuit breakers, typical
M/s PRDC has carried out a number of flow of current several basic activities are magnitudes of this “chopping
projects (Overseas and India) relating to involved. The first is the mechanical overvoltage” are in the order of 1.2 to 2.0
overvoltage studies and insulation co- separation of the contacts. This p.u. with the highest values occurring for
ordination wherein selection of circuit mechanical separation of the conducting low MVAr reactors. The chopping
breaker for shunt reactor switching was a contacts establishes an arc since this overvoltage, with its limited amplitude
part of the technical task. Based on the mechanical separation would not normally and frequency, is normally quite harmless
experience gained, Power System Studies take place at precisely current zero. This both for the reactor itself and for the
group of M/s PRDC has evolved a set of arc will remain until the load or fault surrounding system. However, during de-
guidelines for selection of circuit breaker current passes through a normally energization, transient recovery voltage
for shunt reactor switching. These are occurring current zero. All alternating with considerable magnitude occurs
briefly described in this technical article. current switching devices take advantage across the breaker contacts. Due to
Technical functions of a circuit breaker are of this naturally occurring current zero to oscillatory nature of the reactor voltage,
briefly described in section II. interrupt the normal flow of current. there will be a high voltage stress across
When the current is interrupted at the circuit breaker contacts if the contact
Overvoltages occur during shunt reactor instants other than normal zero crossing, gap is small.
de-energization and inrush current appear transient recovery voltage (TRV) appears
during energization of shunt reactor. across the switching device terminals. The If the arcing time is short, the circuit
These phenomena are described in section shape and magnitude of TRV are breaker probably will reignite. A re-
III.Methodologies to be followed for determined by the parameters of the ignition will generate high-frequency
analyzing the transient effects caused system within which the switching device transients (typically in the order of
during opening and closing operations and is located. To minimize re-ignition or hundreds of kHz) in both reactor voltage
for selecting suitable circuit breaker possible re-strikes due to TRV, it is and current. Following a re-ignition, the
ratings accordingly are described in necessary to ensure that the dielectric reactor current will be interrupted again,
section IV and V. EMTP-type program has either at a high-frequency zero of the
to be used for this analysis.
Power Research and Development Consultants
Page 35
Newsletter
current, or most probably at the IV. De-Energization of Shunt Reactor the rate of change of the arc conductance
subsequent power frequency zero. The A. Circuit Breaker Model (i.e., dg/dt), parameters (e.g. time constant
very steep voltage transients caused byre- There are several methods for and power loss) used to describe the arc,
ignitions will be unevenly distributed across interrupting current and the most and the rate of rise of dielectric recovery
the reactor winding, with the highest stress effective method will depend upon the voltage.
across the initial turns. This voltage stress system voltage and current application.
may lead to puncture of the winding Air, oil, SF6,andvacuum are all dielectrics When interrupting a small inductive
insulation in the reactor, which in the long interrupting media commonly used in current associated with switching off the
run may lead to complete breakdown. commercial switchgear. Vacuum and SF6 shunt reactor, small inductive current
Insulation of nearby equipment may also switching devices are presently used dominates the arc conductance variation
be affected. During these stresses surge routinely, at medium voltages. For high during the interruption process. This
arresters protect the equipments to a voltage applications, SF6 circuit breaker is phenomena may cause multi-oscillations
limited extent, since the severity of the the most predominant technology offered and resonances with the circuits connected
voltage stress is related both to the rate-of- today. All these technologies have to CB. Hence, the arc model parameters
change and the amplitude. (depending upon the interaction with have to be determined by considering
system parameters) the potential for complex interactions between CB, source
The main insulation of reactors can be premature current interruption (current line/feeder and reactor circuits. Therefore,
overstressed if the breaker has high current chopping) and/ or re-ignition which can it is more appropriate to adopt Mayr’s
chopping character. The switching produce an additional oscillatory voltage model given by equation (1), for modeling
overvoltage can be dangerous for on the reactor terminals. such arc behavior, where the CB
equipment if their peak value exceeds the surrounding circuit plays an important role.
rated switching impulse withstand voltage When a circuit breaker (CB) interrupts During the CB contacts parting, the arc
of the equipment. It is very important to while carrying a small inductive current, behaves as a nonlinear conductance. The
know the level of dielectric stress that high frequency and high-amplitude equation (1) can be used to control the arc
occurs during operation of the system in transient voltage appears between the CB conductance, g, and to accomplish the
order to avoid the insulation failures. contacts. The generated high transient energy balance. It is observed that, in
Successful synchronous (controlled) recovery voltage (TRV) may cause addition to the initial value of g, other
switching can reduce the mechanical and undesired effects on the reactor and/or parameters, τ, P, i, α and β are required as
electromagnetic stresses which occur the switching equipments. SF6 is widely inputs to solve Mayr’s arc model equation
during switching operations. used in the HV and EHV insulation systems (1).
b| 1 ' 1 '
because of its stable chemical
B. Closing Operations (Inrush Current):
~ |• ~ |• <1=
characteristics. However, for CB
ba } }. | € . | •
During energization of a shunt reactor,
applications on extinguishing the arc
inrush currents with high asymmetry and
plasma, there are many complicated
long time constants may occur. The actual
gaseous behaviors occurring due to the
magnitude of the inrush current is quite Where,
dissociated and recombined subspecies.
dependent on the range of linearity of the g is conductance of arc, in Siemens.
For interrupting small inductive current
reactor core. The unsymmetrical phase P is Power dissipated from the arc to
namely switching off shunt reactors, SF6
inrush currents during a shunt reactor
Circuit Breakers exhibit less stable and surrounding gas in Watts.
energisation may cause saturation of the
unpredictable arc extinguishing i is current through the arc , in Amperes.
reactor, resulting in overheating. Due to
performance and may lead to several re- τis the time constant of arc, in seconds.
the air gaps utilized in shunt reactor cores
ignitions.
there are no severe saturation effects. In
For analyzing the transient effects caused αis the parameter that influences the
spite of their limited amplitude, reactor conductance dependency of τ
during interruption of small inductive
inrush currents may still have adverse
current accurate modeling of circuit βis the parameter that influences the
effects. They may lead to zero sequence
breaker arc is essential. The model should conductance dependency of P
current, cause saturation of CT cores, with
take into consideration the physical τ and P are judiciously selected from data
resulting nuisance tripping of relays, or
phenomena of arc process with cold gas sheets of CB under consideration.
cause other network disturbances. Excess
characteristic and associated system Using arc model and equivalent system
inrush currents can be avoided by
parameters. An accurate CB model for considered for the system study transient
employing controlled switching of circuit
switching studies should take into account recovery voltage VTRV is computed
breaker.
Page 36 Power Research and Development Consultants
Newsletter
stray inductance
by EMTP-type and Capacitance between
program. on the capacitance
B. Theoretical AnalysisCt seen from the equation peak and (10)
‡‹„ 1 2M ‡+ <B. Œ= <10=
is computed by equation (7)
the
FigureCB 1contactsLb
representsis the
the equivalent
connecting circuit
series circuit breaker
Refer figure terminals,
1. During the N the number
switching of
off the
‡ 2M ‡+ <B. Œ= <7=
inductance CL is the
to be considered for load side capacitance
the transient analysis. interrupters
shunt reactor in series
(CB per opening)pole and the
energy
(3) Where -
1
L is shunt reactor inductance chopping
conservationnumber λ for a bysingle
can be approximated
1 The1chopping1current ich level
is given \by \J (4). ‰'-Š <3= The per unit M
interrupter.
J
2 2 2 2 is computed by
Dielectric recovery characteristics for SF6 J + equation ˆ crest overvoltage-to-ground
' • – —\ “ <4= J
due to a re-ignition
•
0.01b 20.7b
-Š i
cold gas is given by the equation (2)
In equation (3) Vo is the voltage across the equation (8)
‚ƒ „ of the Q is three phase reactor rating (VA)
7.1 ‡ <2=
According to equation
at the (3), the ratio
the λ is the chopping number Ž • ’ for single
shunt reactor instant of current
‡ž 1 Ÿ<1 2M ‡+√‘ =<B. Œ=<8=
suppression
interruption. Va peak overvoltage
is the suppression to peak
Figure.1. Single-phase equivalent circuit of
reactor
overvoltage voltageto the can ground
be expressedacross the by interrupter
shunt reactor
equation
inductor, which(5), where is thekafirst is the
peakper-unit
of the ω is the angular rated power frequency
with d =Cvs are
Ls and × t, the
where Vdwsv
source sideis inductance
the circuit Theis per
breaker contact gap withstand voltage, d is
and capacitance
value of thewith
oscillation suppression
the samepeak overvoltage
polarity as the N the unit crest overvoltage
interrupting excursion
units in series per
and can be used to estimate
system voltage at the time of interruption. pole. the peak-to peak due to a re-ignition is
the
Lp contact
andCp gap
are atthea time
strayinstant t (ms) and
inductance and parameters required for describing the CB computed by equation (9)
ich is the inductor chopping current. For L is main reactor inductance (H)
vCapacitance
(m/s) is the between
contact velocity at opening.
the CB contacts arc
SF6 model.
currents are typically in the range of 2- ‡ <1 Ÿ=<1 2M ‡+ =<B. Œ= <9=
circuit breaker the values of chopping LN is neutral reactance inductance (H)
‰'-Š
Lb is the connecting series inductance
14A. ‡The +
™1 <5=
Based on computed values VTRV and
+
\J ˆ Ct seen from
C value of the chopped current Case 2: Shunt reactor neutral solidly
L is thethe
loadre-ignition/re-strike
side capacitance checks are
depends onˆ the capacitance
Vdwsv
grounded.
Damping factor β can be considered to be
r
carried
L is shuntoutreactor
by theinductance
following condition.
the circuit breaker terminals, N the For
o[ ‚ƒ „
0.5. the case substitute K=0 in all equations
Generally
number ofininterrupters
EHV systems in Cs>>
seriesCLperandpole
Cp (6) to (10) and compute corresponding
Dielectric recovery
Magnitudes characteristics
of different for SF6
crest voltages is
andnegligible,
the choppingso thatnumber
Ct equalsλ to forCL.a single crest
The pervalues.
unit crest recovery voltage across
cold gas is given by the equation
namely ka (suppression peak overvoltage (2)
Case 1: Shunt
interrupter. Thereactor
chopping neutral
current grounded
ich level Case study results
the circuit breakerareis presented
computedfor bya
to the ground across the inductor in p.u),
0.01b 20.7b
through
is given by reactor
equation (4). typical
equation system
(10) described in section IV-C.
'-Š ka•–—\ i“ <4=
kc (maximum ‚ƒ „ chopping overvoltage-to- For this case is computed by equation
7.1 ‡ <2= C. ‡ Case 1 Study ‡+ <B. Œ=
2M results <10=
ground at the instant of recovery voltage (6)
‹„
1 3—•
peak in p.u), kp (per unit crest overvoltage- According to equation (3), the ratio of the
Case study results are presented for a Figure 3: Current through circuit breaker Figure 5: Zero sequenc ecurrent during energization of shunt reactor
CBC In
typical system described in section IV-C. 0.200
-0.172
0.140
-0.000
0.150 -0.000 0.120 0.064
0.172 0.064
C. Case Study Results 0.100 0.100
Min -0.172 Min -0.000
0.050 0.080
C u rre n t (k A )
Max 0.172 Max 0.129
C u rre n t (k A )
0.000 0.060
√A,ω=377
-0.100 0.020
rad/sec,Q=80x106VAr, -0.150 0.000
L=4.787H, LN=1.9148H, System voltage 380 -0.200 -0.020
kV. t (sec) 0.380 0.400 0.420 0.440 0.391 t (sec) 0.200 0.250 0.300 0.350 0.400 0.193
0.420 0.323
Based on the theoretical analysis the 0.028 0.130
computed values of various crest voltages Fig.2: Current & voltage Waveforms Fig.3: Inrush current waveforms
are:
Check simulated TRV and RRRV (rate of The inrush current magnitudes as shown in
ka=1.08 p.u, rise of recovery voltage) values with figure 3 compared with breaker current
kc=1.52 p.u, corresponding ratings of the proposed ratings well within limit.
kp=2.22 p.u, circuit breaker and decide on the
ks=3.78 p.u, adequacy of the proposed circuit breaker VI. References
krv=2.52 p.u for shunt reactor switching.
[1] Gary W. Chang, M. Huang, and Jiang-
The current and voltage waveforms V. Energization of Shunt Reactor Hong Lai ‘Modeling SF6 Circuit Breaker
computed by EMTP simulation of the for Characterizing Shunt Reactor
equivalent system are presented in Plots 1 For system shown in figure 1,typical Switching Transients’, IEEE
to 3 of figure 2. inrush currents waveforms obtained Transactions on Power Deliver, Vol 22,
during energization of 380 kV, 80 MVAr No.3, July 2007.
From simulation, krv is computed as 2.42 shunt reactor are presented in Plots 4&5
p.u this figure closely matches with the of figure 3. Normally these inrush current [2] G. St Jean, M. Landry, Y. Leclerc, and A.
theoretically computed value of 2.52p.u. magnitudes are well within breaker Chenier, ‘A new concept in post-arc
current rating. However, controlled analysis applied to power circuit-
Figure 1: Tranisent Recovery Voltage across the circuit breaker
TRV switching of circuit breaker is breakers’, IEEE Trans. Power Delivery,
800
600
0.011
297.570
recommended to minimize the magnitude vol. 3, no. 3, pp. 1036–1044, Jul. 1988.
400 297.558 and duration of zero sequence current
Min -749.621
200 which may otherwise result in nuisance [3] A.T. Johns, R.K. Aggarwal, and Y.H.
V o lta g e (kV)
Max 411.337
0
tripping relays or other network Song, ‘Improved techniques for
-200
-400
disturbances. modeling fault arcs on faulted EHV
-600 transmission systems’, IEEE Proc.
-800 Generation, Transmission, and
t (sec) 0.380 0.400 0.420 0.440 0.460 0.400
0.450 Figure 4: Inrush current drwan by shunt reactor during energization Distribution, Volume 141, Issue 2,
0.049 Ir
0.30
-0.000 March 1994, pp: 148-154.
Figure 2: Voltage at reactor terminal
0.20 -0.070
Vr -0.069
500
134.690 0.10 Min -0.116
400 1.777
C u rre n t (k A )
Max 0.294
300 -132.913 0.00
200 Min -312.058
V o lt a g e (k V )
Level 1 Batch:
th th
1. 5 Nov 2012 to 9 Nov 2012
Level 2 Batch:
rd th
1. 3 Dec 2012 to 7 Dec 2012
Abstract: power electronics based controllers and 5) Small signal stability (for small
Successful operation of today’s complex systems in the modern day power system disturbances)
power systems requires a balanced has created the need for real time digital 6) Electromagnetic transients (EMT)
understanding of technical and economic simulators (RTDS) for the purpose of simulation
issues relating to the generation, Hardware-in-loop (HIL) testing of these 7) Relay coordination studies
transmission and distribution of electrical controllers for optimizing their 8) Load forecasting
energy. A thorough understanding of the performance before being installed in the 9) Unit commitment
operating characteristics and the field. 10) Economic dispatch
limitations of each device within the 11) Steady state contingency analysis
network is needed in order to ensure The evolution of simulation tools has (security assessment) and
reliable and secure source of power. A progressed in step with the evolution of 12) Dynamic security assessment.
wide variety of study tools are available to computing technologies. In recent years,
help engineers gain knowledge and computing technologies have improved Indeed the power system is very complex
confidence required to design and operate dramatically in performance and become both in terms of dimension (physically and
networks in a manner consistent with end- widely available at a steadily decreasing mathematically) and the kind of non-
user expectations. Advances in power cost. Consequently, simulation tools have linearities present. There are no explicit
system simulation have made it possible also seen dramatic performance gains and analytical solutions for the problems
to study in detail, the dynamic behavior of steady cost decreases. Researchers and associated with the faults and
even very large power systems with engineers now have access to affordable, contingencies in such a complex system.
varying degree of complexity. This paper
high performance simulation tools that Simulation is the only method to predict
summarizes the various simulation tools
were previously too cost prohibitive, the performance of the power system
that are employed in such studies both off
except for the largest manufacturers and that is subjected to the above mentioned
line and in real time applications.
utilities. eventualities.
This paper gives an overview of the
I. Introduction
various simulation tools that are widely Further, the sizes of power systems have
Design and stable operation of an electric
used by the manufacturers, developers, grown steadily over the years and the
power system requires careful study of the
researchers and utilities in the planning, need for interconnected power systems
interaction of the different equipment
that constitutes the power system. design and operation of modern day for economic operation resulted in a host
Stretching of electric system performance power system. Application of these tools of other problems such as economic
to its operational limits and deployment of for various types of studies is also dispatch, transient stability, low frequency
special fast-acting controls has not only highlighted. A brief history of power oscillations etc. More recently, the de-
made dynamic simulation more common system simulation is presented at the regulation posed further challenges such
and essential to utility planning and beginning. as congestion management, interaction
operation, but has made the study process with market dynamics etc. The solutions
more complex. In this context, simulation II. Need for Power System Simulators for many of these problems, which have
tools are critical to the effective There are a number of decisions to be generally been on an approximate and
investigation of system response to a taken both at the operational level and at sometimes been on heuristic basis,
variety of disturbances in a fast and the planning level. Any such decision needed an integrated approach. The big
accurate manner. These tools have been process must be based on analysis with a blackouts in North America in 1965 and
widely used for the design and great emphasis on modeling and 2003 as well as grid failures in many
improvement of electrical systems since simulation techniques. The kind of studies countries including India placed fresh
the mid twentieth century. A wide variety done by utilities is numerous of which emphasis on the aspect of modeling and
of both analog and digital simulation tools some are given below: simulation of power systems for taking
are available. However, advances in corrective measures to avoid such
computer hardware and software 1) Short circuit studies blackouts.
complemented by the sophisticated power 2) Load flow studies, also called as power
system component modeling techniques flow studies III. Power System Simulation
have more or less replaced the analogue 3) Optimal power flow The tool for simulation was first in the
simulators with digital simulation. 4) Transient stability (for large form of a DC network analyzer for short
Furthermore, the large scale induction of disturbances)
Power Research and Development Consultants
Page 41
Newsletter
circuit and load flow studies and then an significant challenges to the design and type electromechanical dynamic
AC network analyzer to accommodate stable operation of today’s power simulation tools.
transient stability studies. The traditional systems. Examples include the integration
method of performing transient studies of wind farms, photovoltaic cells or other C. Small Time Step Simulation
utilized simulators made up of scaled power-electronic-based distributed energy It is a common practice with
down power system components. Each generation systems, domestic loads and electromagnetic transient simulators to
component is physically connected to the future plug-in electric vehicles into the use a simulation time step of 30 to 50 μs
next in a manner similar to that of the real existing power grid. The above to provide acceptable results for
system. This analog simulation technique applications take full advantage of several transients up to 2 kHz. Better precision
formed the basis of both the well known very fast and distributed power electronic can be achieved with smaller time steps.
Transient Network Analyzer (TNA) and the systems which in many cases, are of Simulation of transient phenomena with
HVDC simulator [1]. innovative design and consequently have frequency content up to 10 kHz typically
never been integrated together or with a requires a simulation time step of
The impact of the digital computer on power grid. Validated models suitable for approximately 10 μs. Power electronic
simulation was first felt in the late1950s electromagnetic transients, as well as converters with higher Pulse Width
and the early sixties saw a steadyandrapid dynamic stability analysis under normal Modulation (PWM) carrier frequency in
rise in the use of computers ascomparedto and abnormal conditions, are usually not the range of 10 kHz, such as those used in
that of the network analyzers. For the last available. This poses a new and low-power converters, require smaller
three decades, theevolution of simulation significantchallenge to utility and system time steps of less than 250 nanoseconds.
tools has been driven by the rapid engineers who must guarantee total AC circuits with higher resonance
evolution of computingtechnologies. As system performance and security. frequency and very short lines, as
computer technologies have decreased in expected in a low-voltage distribution
cost and increased in performance, the B. Simultaneous Simulation of Short and circuit and railway power feeding system
capability of simulation tools to solve Long Term Phenomena may require time steps below 20 μs. In
increasingly complex problems in less time Simultaneous simulation of fast and long such cases, it is prudent to carry out tests
has improved. In addition, the cost of phenomena pushes simulation tools that with practical system configurations and
digital simulators has also steadily are required in the planning and operation parameters to determine minimum time
decreased, making them available to a of power systems to their limits. One such step for accurate simulation.
larger number of users for awider variety example is checking the transient stability.
of applications. This resulted in the The transient response of an IV. Simulation Tools
evolution of the most commonly interconnected power system ranges from Simulator technology has evolved from
employed study of electromagnetic fast (microseconds) electromagnetic physical/analogue simulators (HVDC
phenomenon which is based on transients, through electro-mechanical simulators, TNA’s) for electromagnetic
mathematical representation of thesystem power swings (milliseconds), to slower transients and protection & control
and its dynamics rather than on scaled modes influenced by the prime mover, studies, to hybrid TNA/Analogue/Digital
down physical components. The boiler and fuel feed systems (seconds to simulators with the capability of studying
algorithms necessary for software minutes). For the modeling of electro-mechanical transient behavior and
basedelectromagnetic transient simulation electromechanical transients caused by to fully digital real-time simulators.
were first described by H. Dommel in 1969 large disturbances such as network faults Physical simulators served their purpose
[2] and have been utilized in several well and/or plant outages, system states must well. However, they were very large,
known programs like EMTP [3] and EMTDC be evaluated at intervals in the order of expensive and required highly skilled
[4]. milliseconds over time scales of seconds. technical teams for the tedious job of
For small-signal and voltage stability setting up networks and maintaining the
A. Issues and Challenges in Simulation assessment, the time scale needs to be extensive inventory of complex
The secure operation of power systems extended to minutes and for voltage equipment. With the development of
has become more and more dependent on security, tens of minutes to hours. During microprocessors and floating-point
complex control systems and power this period, accurate representation of DSPs,physical simulators have been
electronic devices. Furthermore, the power electronic devices require relatively replaced with fully digital real-time
proliferation of distributed generation small time steps, typical of simulators. Nevertheless, the scaled-down
plants, often based on the use of electromagnetic transients (EMT) model approach used in physical
renewable energy resources, presents simulators, but impractical for phasor- simulators findsits virtue, in the relative
ease with which
Page 42 Power Research and Development Consultants
Newsletter
the model components could duplicate • Statistical distribution of representation of the power system to
their actual counterparts with their non- switching surges study its steady state and dynamic
linear behavior. • Energizing and reclosing behavior by employing various solution
transients on lines, cables, open techniques. The equations governing the
A. Transient Network Analyzer (TNA) ended transformer lines elements of the power system are
TNA is a special purpose analog simulator, Switching surge reduction by algebraic and/or differential equations
which has scaled down models of all the means of controlled closing and depending upon the appropriate modeling
power system components. On a TNA, the pre- insertion resistor strategies adopted.
system elements can have either equal • Single pole reclosing
ohmic values or scaled down values, but • Load rejection & Ferro resonance Currently, popular electromagnetic
the voltages are always scaled down. Thus studies transient simulation software is actively
the scaled down system is represented on • Transient Recovery over voltages expanding, such as EMTP [3],
the simulator and switching actions are • Fault initiation surges and PSCAD/EMTDC [4], etc. Besides, checking
performed. The resulting voltages and • Requirement on surge arrester transient stability of a power system is
currents are recorded for analysis. These location and rating one of the important objectives of running
are quickly acquired and processed by the a simulation program which among other
data acquisition system and presented in a B. Digital Simulators: things, can give a lot more information
form required by system designers. One Digital simulators of electric power such as predicting the dynamic
specific advantage of such analog systems have found wide application in performance of the system involving low
simulators are that they operate on real power industry and allow to solve a wide frequency transients (typically below 5 Hz)
time as in an actual system and thus prove range of important tasks such as: [5]. A variety of programs are available in
to be useful for testing of plant size the public domain like SIMPOW®, PSS/E®,
controllers. 1) Producing computational MiPower® to name a few.
experiments when doing research
Modeling Features of TNA: work in developing new technical C. Real Time Digital Simulators (RTDS)
TNA generally has models of 3-phase measures that provide the desired It has now been more than 10 years since
transmission line PI sections, Single phase reliability and security of power the introduction of first fully digital real
and 3 phase transformer banks with system; time power system simulator. Real time
saturation, Linear or non-linear Shunt 2) Implementing projects concerned operation implies that an event in the
Reactors, Static Var Compensators (6 pulse with the choice of the main system which lasts for one second can be
or 12 pulse TSC or TCR) with generic electrical equipment and its simulated on the simulator in exactly one
controls, Load models, Circuit Breakers parameters, the choice of over second. The usual digital simulation
(manually programmable or computer current and overvoltage protection programs typically require many seconds
controlled to close at any instant of sine devices; or even minutes to perform the necessary
wave and with possibility to simulate 3) Analyzing power system accidents computations and produce a solution for
current chopping, current zero opening or and developing measures aimed at such an event. Although specific
pre-strike phenomenon), Synchronous preventing similar accidents in applications vary, real time digital
machines, Lightning Arresters (gap type power system’s operation. simulators are particularly useful when
and gap less type), Voltage & Current 4) Performing simulations in hard actual power system devices and
sources etc. real time for (a) testing of existing controllers such as FACTS and HVDC are to
or new electrical devices (digital be included in the test program or study.
Studies that can be performed on TNA [1] devices of relay protection and This so called closed loop testing method
TNA had been acquired by many automation, monitoring devices, [6] represents an accurate way to
equipment manufacturers, Research etc.) and (b) designing, testing and evaluate the performance of such physical
centers and utilities to find solutions for implementation of new software devices/controllers prior to their
their design, research and operational products (simulators, SCADA, etc.). installation in the actual power system.
problems. Traditionally, the following
types of studies were performed using the As mentioned in Section III above, digital As is the case in most electromagnetic
TNA prior to the introduction of modern simulation is based on the mathematical transient simulations, the RTDS utilizes
day EMTP and real time digital simulators: the so called Dommel algorithm. In this
algorithm, the trapezoidal rule of
Power Research and Development Consultants
Page 43
Newsletter
integration is used to convert integral capability of existing systems, hence CIM based power system simulation has
equations, which result from nodal pushing their operating points closer to been implemented in few of the software
analysis of the power system, into stability limits. The performance and development projects. Future simulation
algebraic equations. Application of effect of any new device must be well programs will have an open architecture
trapezoidal rule requires that the solution understood in order to ensure safe and with loosely coupled pluggable
be computed only at discrete instants of secure operation of power system in components. This kind of architecture will
time, rather than a continuous solution. which these devices are embedded. A enable components and models
The time between the successive solutions RTDS simulator is an excellent tool for the developed by others to be easily plugged
is known as the time step denoted by Δt.
All of the system of equations
representing the power system model
must be computed in each time step. For
large complex power system models, it
may take a modern computer many
seconds to compute even a single time
step. These types of simulators are said to
be non-real time digital simulators as
already explained in section IV above. The
RTDS simulators on the other hand, are Fig 1: Conceptual Overview of RTDS
able to continuously perform the
necessary calculations for a single time investigation,development and integration into to augment their functionality.
step in a measured time that is exactly of new and complex power system
equal to the time step. The RTDS components. Figure 1 gives a conceptual VI. References
simulators combine specialized processing [1] ‘TNA & HVDC Simulator’,
overview of the RTDS that is being
hardware and software to achieve http://www.cpri.in
increasingly used in closed loop with
continuous real time operation [7]. /testing/psd/psd_home.html
various control and protection devices in a [2] H.W. Dommel, ‘Digital computer solution of
power system for development and electromagnetic transients in single and
In order to achieve and sustain real time testing activities.
multiphase networks’, IEEE Transactions on
operation, many RTDS simulators take Power apparatus and systems, Vol PAS 88,
advantage of the two levels of inherent V. Future Trends in Power System no.4, April 1969, pp 388-399.
parallelism in the Dommel algorithm. First, Simulation [3] ‘Electromagnetic transients program
equations for closely coupledcomponents Common Information Model (CIM) is an (EMTP) Rule Book’, Bonneville Power
within the network are solved using effort to develop a common power system Administration
closely coupled processors. These network operation model that can be [4] ‘Electromagnetic Transients including DC’,
components could be part of a sub system shared and exchanged among different Manitoba HVDC Research Centre,
in a power system. The second level of applications. Power system simulation is Winnipeg, Canada,
https://pscad.com/products/pscad/
parallelism results when the overall power one of many intended CIM usage
[5] K.R. Padiyar, “Power System Dynamics,
system model is split into two or more sub scenarios. Being a canonical power system stability and control’, (Book), BS
systems. Each sub system is then solved in data model, CIM is the foundation to Publications, 2006.
parallel using processors. integration of modern information [6] D. Brandt et al, ‘Closed loop testing of a
systems in the power industry. IEC CIM joint Var controller using digital real time
A. RTDS applications model is a general purpose power system simulator’, IEEE Transactions on Power
Since its introduction, the application systems, August 1991, Vol.6, No.3, pp
data model, which is designed to
scope of RTDS has continued to expand. 1140-1146.
model/describe physical power networks [7] M.M. Babu Narayanan et al ‘Real Time
Real time simulators are most suited for and serve multiple purposes. Information, Digital Simulator at CPRI and case studies’,
closed loop testing of physical control and such as connections among physical Proceedings of the Workshop on Real Time
protection devices. Recent trends in the equipments, equipment physical sizes, simulation of power systems, Bangalore,
power industry have led to the equipment geographical locations 24th January 2005, pp 1-8.
introduction of many new and complex (attitude and longitude), and equipment
devices. The purpose of many of these electrical parameters (R, X, Rating), are
devices is to increase power transfer commonly included in the model.
Page 44 Power Research and Development Consultants
Newsletter
the Teaching Faculty of Andhra University He was Visiting Fellow at the University Research papers in national conferences.
College of Engg., Visakhapatnam, India and of Manchester Institute of Science and Presently, he holds the position of Sr.
served for more than 40 years in different Technology, UK (1970-71). He was ABB Engineer-PSS at PRDC.
positions. After relinquishing his service chair professor (1996-1997). He is fellow
there, he worked as Professor at of Indian national academy of M. M. Babu Narayanan
ANITS,Visakhapatnamfor four years. After Engineering.
working for a semester at Southern He has Over 200 publications in
Polytechnic State University, South National & International journals He was
Marietta, USA as a Visiting Professor, he is Member, R&D Committee, CPRI and
presently working as a Senior Professor in served as Vice Chairman, Protection
the GVP College of Engg., Visakhapatnam. Committee, CBIP, New Delhi. Presently, he
To his credit he presented and published holds the position of Chief Technical
more than 55 Papers in Conferences and Advisor at PRDC.
Journals of National and International
Repute. He was awarded the Best Teacher Veerabrahmam Bathini
Award by the A.P. State Government. His
research interests are in fundamentals of M.M. Babu Narayanan has 35
Circuit Analysis, Power System Dynamics, years’ experience in Power Industry. He
Voltage Stability and Reactive Power works in the areaof Design,planning, R&D,
Management. simulation & Reforms in Transmission and
Distribution. He obtained B.Sc (Engg. ) from
NIT, Calicut and M.Sc (Engg.) from IISc,
Prof K. Parthasarathy Bangalore in 1991.. He has undergone
training at ABB, Sweden in HVDC
Transmission systems and real time
simulation.
VeerabrahmamBathini obtained
B.Tech (Electrical & Electronics) in 2004 He was responsible for setting up
and M.Tech (Integrated Power Systems) in state-of-the-art Real Time Digital
2007 from J.N.T.U College of Engineering, simulation facility in Central Power
Anantapur and V.N.I.T Nagpur Research Institute. At CPRI, he has been
respectively. His areas of interest are involved in dynamic performance studies
Power Systems Dynamics and control and for a number of HVDC and FACTS projects
Dr. K. Parthasarthy obtained Power Electronics Applications to Power in India. He is a recipient of Central Board
M.E.(Power Systems) in 1961 and Ph.D. systems. of Irrigation & Power award for excellence
degree (Protective Relays) in 1967 from in power transmission systems.
Indian Institute of Science Bangalore. His He joined in PRDC in 2007 as
areas of interest are Switchgear and Engineer-PSS, from 2007 majorly he His research interests are HVDC
Protection, Power System Dynamics and executed various projects in the field of transmission, & Grounding. He has lectured
Control, Computer Aided Protection and EMTP Studies (detailed Insulation co- at many Universities in India and abroad.
Power System Analysis. He held various ordination of GIS and AIS substations, He has also been a member of several
positions at IISc, Bangalore during the 1961 Ferroresonance, circuit breaker Switching Govt. of India committees in Transmission
– 1997. He served as Chairman, etc.,).He is also involved in the & Distribution related areas including the
Department of Electrical Engineering IISc development of EMTP-Type module in Power System Development Fund of
(1987-88). MiPower software. He has published CERC.Currently he is Chief Technical
Adviser at PRDC, Bangalore
Power Research and Development Consultants
Page 47
Newsletter