2.6.1.1 Summary
This section provides the control system design, functional requirements, and integration requirements to
be employed for the operation of the DCP. This is intended to augment the tender standard
specifications.
The Contractor shall be responsible for selection and design of the DCP control system. The control
system design shall meet the following goals:
1. Minimize the number of operating personnel needed for operation of the system by providing
fully automated plant with provisional to integrate distribution network system to control the
supply pressure and plant loading based on current and forecasted weather conditions.
2. Standardized control system hardware, software, and field devices for the plant, to provide for
ease of maintenance.
3. A separate control system shall be provided for life safety and building services, including for
the plant HVAC temperature controls.
4. Online water measurements to optimize chemical dosing.
5. Level controls and alarms on all the tanks, including notification when new chemicals should
be ordered.
6. Control system shall be easily expandable to meet growth requirements of the DCP system.
7. Control system for the chiller plant shall be REDUNDANT in configuration and communicate
to all plant equipment (Chillers, Pumps, chemical treatment, Make up water systems,
Electrical system (S/S, TR, VFD etc) and all auxiliary equipment (Valves, Transmitters,
Switches etc) and for monitoring and controlling ETS.
8. The SCADA software shall be configured with dynamic graphics inline with the plant process
to communicate with existing plant PLC to incorporate controls and instrumentation as
mentioned in Section 16935 under Employer’s Technical Specifications (Part 2) is included in
contractor’s scope.
9. Supply, installation, testing and commissioning of any communication interfaces e.g. Modbus,
Profibus etc. to facilitate communication various plant areas like Chemical treatment, Make
up water systems, Electrical system (S/S, TR, VFD etc) and ETS control systems are
included in scope.
10. The control system shall be designed using commercially off the shelf products/software and
use open protocol communications/software; use of bespoke software shall only be on
agreement with the Employer
11. The Contractor shall consider spare requirement for the interfacing of ETS’s control and
monitoring as part of the overall DCP control system. The SCADA software and PLC shall have
enough space (tags, screens, memory etc.) and should not require any upgrade or licenses .
12. The DCP control system shall be powered from uninterruptible power supply (UPS) system.
PLC’s and SCADA shall include software and all necessary licenses provided by the
manufacturer that has been registered in the Owner’s name. The chillers and other
________________________________________________________________________
- 26 -
ACUD Project
Cairo, Egypt
equipment with integral controls shall be seamlessly integrated to the DCP control system so
that such equipment can be monitored and controlled by the system.
Any TSE polishing plant (RO/UF) or internal water treatment included with this project shall be integrated
into the control system.
The intent of this section is to present the concept of the overall plant control. This will be used as guide
for the final equipment selection, coordination with vendors, and preparation of the technical proposal for
approval.
________________________________________________________________________
- 27 -
ACUD Project
Cairo, Egypt
The control system shall be configured to maximize the ability of the superintendent to remotely manage
and control the plant and distribution systems, thus minimizing the need for personnel at the plant or
customer locations. The Contractor shall consider the implications of safe plant operation from a remote
location within his deign and provide safety interlocks as required.
Database logging occurs on both systems. So, if one system fails, the other system continues to log data.
Both computers shall have the storage and archiving functionality of historical values (long- time history
and trending), the generation of the user defined reports by reports manager, historical data analyzing,
recipes, and calculation functions. The archiving of the process data will be to a DVD as a backup-
storage system installed in both the systems.
Database management software shall be the most recent field proven revision to manage the history,
data archiving, trending, and reporting.
________________________________________________________________________
- 28 -
ACUD Project
Cairo, Egypt
2.6.1.10 Integrator
A control system integrator (Integrator) shall be engaged and shall be responsible for interfacing the plant
controls and ETS controls into the cooling control system. The Integrator shall have appropriate
experience in successful implementation of control systems in electric power generation facilities, heating
plants, cooling plants or industrial refrigeration plants. The Integrator shall be capable of supplying the
Contractor services, functional requirements preparation, functional description preparation, control
system engineering, instrumentation engineering and installation engineering for all components of the
cooling control system. The Integrator shall also provide on-site services during construction check out
and start-up of the district cooling system
________________________________________________________________________