Professional Documents
Culture Documents
ABSTRACT: Rock masses obviously represent the most variable of engineering materials, and the
three categories listed in the title represent most of the range of rock quality. We need to include
stress magnitudes, water pressure and permeability to be more complete, but will ignore swelling
pressures. This keynote paper will address some new findings about tunneling through these three
categories. For instance, the critical tangential stress experienced when fracturing of intact rock
initiates in deep tunnels is caused by the ratio of tensile strength/Poisson’s σt/ν. This explains the
critical ratio σθ/σc ≈ 0.4 The extensional strain-induced fracturing will mostly propagate in shearing
mode at higher stress levels, and this can be the source of rock bursts. The presence of jointing helps
to dissipate the latter. Contrary to the experiences with drill-and-blast tunneling, TBM experience
difficulties at both ends of the spectrum (intact, jointed, faulted). Partly for this reason, deceleration
from day to week to month to one year is a common experience, also shown by the remarkable world
records of TBM performance. A simple formula explains the delays of TBM tunnels in fault zones.
1 THE ROCK THAT BEARS THE LOAD Even the thickest concrete lining can hardly
compete with the hundreds or thousands of tons
When we excavate a tunnel through intact, of load that are arched around each running
jointed or faulted rock masses, with Q-values meter of a tunnel. For instance, a 5MPa vertical
potentially ranging from 1000 to 0.001, how stress at 200m depth, which may be
important is the capacity of the support and concentrated to more than 10MPa in the tunnel
reinforcement of the tunnel periphery, compared walls, arch or invert (depending on the stress
to the capacity of the surrounding ‘cylinder’ of anisotropy) causes variation from 1,000 to 500
rock mass to take load? The redistributed tons/m2 in the nearest meter-thick-meter-wide,
stresses, and the slightly deforming and naturally load-bearing ‘rock-mass-ribs’ which
adjusting rock blocks in the surrounding surround the excavation. In the first 10m of the
‘cylinder’ (with dimensions which may be up to surrounding rock ‘cylinder’ an estimated load-
several tunnel diameters in thickness), account in-the-arch of 5,000 to 10,000 tons per running
for a huge majority of the load-bearing abilities, meter of tunnel, obviously far exceeds the load-
except when very close to the surface. bearing abilities of shotcrete, rock bolts or
The shotcrete, rock bolts, and occasional concrete. At 1,000m depth the load-bearing
concrete of single-shell NMT (Q-system-based) capacity of the natural rock arch is even more
tunnels, are selected merely to retain the load essential.
bearing abilities of the all-important The ‘softest’ support of all, the lattice girders
surrounding rock mass. Naturally we can assist used in NATM tunneling, have little to
this process with sufficiently high-pressure pre- contribute in hard rock with marked over-break,
injection, if using stable (non-shrinking and because good contact with the tunnel perimeter
non-bleeding) microcement suspensions. It is is difficult. Why do we seldom see over-break
believed that most of the six Q-parameters are and its volumetric (and stress-distribution)
effectively improved by correctly carried-out consequences in drawings and numerical
high-pressure pre-injection. We know of models of concrete-lined NATM tunnels?
velocity increases and permeability tensor In both single-shell NMT and double-shell
rotations and magnitude reductions, even as a NATM philosophies, we are attempting to help
result of quite conservative grouting in dam the rock to help itself. Clearly there are
abutments (Barton, 2012a). Hydraulic (e) and potentially big cost differences depending on
physical apertures (E) must be differentiated. how we do this, but these will not be addressed
1
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
Figure 1. Theoretical (2D) stress concentration factors for Figure 2a. UDEC-BB distinct element model of a TBM
tunnels and caverns of various shapes, excavated in spiral access tunnel. Chryssanthakis, 1991. The maximum
unjointed isotropic elastic media. Hoek and Brown, 1980. tangential stress reaches 56 MPa in the sandstone invert.
2
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
Figure 2b. UDEC-BB distinct element model of a TBM The above is the traditional way to assess the
spiral access tunnel. Hansteen, 1991. The maximum likelihood of ‘stress-induced’ fracturing. It is
tangential stress reaches 30MPa in the left wall. The supported (independently) by a later
jointing represents the welded tuff of the BVG ignimbrite. compilation of mining and nuclear waste URL
research, published by Martin et al. (1999),
In the three previous examples of maximum reproduced in Figure 3. This also shows the
tangential stress: 75MPa: ideal unjointed, associated approximate depth of ‘stress-
56MPa: thick sandstone bed, and 30MPa in the induced’ ‘dog-earing’ or break-out, when the
left wall of the tunnel in welded tuff, a logical stress/strength ratio exceeds 0.4 (+/- 0.1).
next design step would be to compare these
values with a distribution of (or minimum) UCS We observe that the common ratios of
value. This would be to check if the stress/strength for spalling are in the range of
stress/strength ratio σθ max /σc > 0.4, signifying 0.3 - 0.5, with a medium value of approximately
the possible onset of ‘stress-induced fracturing’. 0.4. In reality, the critical ‘stress/strength’ ratio
In the Q-system, for single-shell NMT tunnel of 0.4 is related to critical tensile strain, and the
support consisting of permanent B+S(fr) typical ratios of σc/σt (about 10) and Poisson’s
(Barton and Grimstad, 2014), this would mean ratio (about 0.25). Barton and Shen, 2017,
selection of a higher SRF value, and a lower Q- explain the new extension strain theory in more
value, therefore requiring heavier support. detail, and give FRACOD modelling examples.
When using the Q-system assessment of the
SRF factor we would examine the following Table 2. The extensional strain logic of Dr. Baotang Shen
table, which was derived by Grimstad and explains the critical ratio of stress/strength = 0.4 (+/- 0.1).
Barton, 1993 and is based on Grimstad’s
numerous observations in deep Norwegian road ε3 = [ σ3 – ν (σ1 + σ2)] / E ε3 = [ σ3 – ν.σ1] /E
tunnels which exhibited ‘stress-induced’ (3D stress/strain) (2D stress/strain)
fracturing, popping and bursting.
When ν (σ1 + σ2) When ν.σ1 > σ3, negative
Table 1. SRF (stress reduction factor) in the Q-system > σ3, negative extensional strain (-ε3) will
rating tables (Table 6 of Grimstad and Barton, 1993).
extension strain occur. If (-) ε3 > (-) εc (critical)
Note the strong acceleration of SRF when the
stress/strength ratio σθ max /σc exceeds 0.4 to 0.5. (-ε3) will occur. tensile failure occurs -εcrit = σt/E
3
Beaumount Tunnel in Chalk Marl Beaumount Tunnel in Chalk Marl
X Axis (m) X Axis (m)
-3.0 -2.5 -2.0 -1.5 -1.0 -0.5 0 0.5 -3.01.0 -2.5 1.5 -2.0 2.0 -1.5 2.5-1.0 3.0
-0.5 0 0.5 1.0 1.5 2.0 2.5 3.0
3.0 3.0 3.0 3.0
Flow Time (s): 0E+0 Flow Time (s): 0E+0
Flow Time Step (s): 0E+0 Flow Time Step (s): 0E+0
Thermal Time (s): 0E+0 Thermal Time (s): 0E+0
2.5 Cycle: 1 of 10 2.5 Cycle: 10 of 10 2.5 2.5
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
Elastic fracture
Open fracture
Elastic fracture
Open fracture
Slipping fracture Slipping fracture
2.0 2.0 2.0 2.0
Fracture with Water Fracture with Water
10, and typical values of Poisson’s ratio ≈ 0.25, 1.0 1.0 1.0 1.0
Y Axis (m)
Y Axis (m)
Y Axis (m)
Y Axis (m)
Beaumount Tunnel in Chalk Marl Beaumount Tunnel in Chalk Marl
failure (and acoustic emission in a laboratory 0
-3.0 -2.5 -2.0 -1.5 -1.0 -0.5
X Axis (m)
0 0.5
-3.0
1.0
0
-2.5
1.5
-2.0
2.0
-1.5
2.5
-1.0
3.0
0
-0.5
X Axis (m)
0 0.5 1.0 1.5 2.0 2.5 3.0
0
3.0 3.0
triaxial test) is when reaching an axial (i.e. -0.5
Flow Time (s): 0E+0
Flow Time Step (s): 0E+0
Thermal Time (s): 0E+0
3.0
-0.5 Flow Time (s): 0E+0
Flow Time Step (s): 0E+0
-0.5
3.0
-0.5
‘tangential’) stress ≈ 0.4 x UCS. Both in a 2.5 Thermal Time (s): 0E+0 2.5
Cycle: 20 of 1010 2.5 2.5
Cycle: 30 of 44
-1.0 Elastic fracture -1.0 -1.0 -1.0
Elastic fracture
Open fracture
Open fracture
Y Axis (m)
Y Axis (m)
Y Axis (m)
Y Axis (m)
-3.0 -2.5 -2.0 -1.5 -1.0 -0.5 0 0.5 1.0 1.5 2.0 2.5 3.0
X Axis (m)
0 X Axis (m) 0 0 0
the latter which may cause rock bursting. -1.5 -1.5 -1.5 -1.5
3. REAL FRACTURING AND SOME MODELLING Figure 5. A FRACOD fracture-propagation model (Shen
-2.5 -2.5
-2.5 -2.5
et al., 2014) of the Beaumont Tunnel cliff-loading
-3.0 -3.0
One of the very earliest successful TBM -3.0
-3.0 -2.5 -2.0
situation with assumed k0 = 0.33. Two other models
-1.5 -1.0 -0.5 0 0.5
-3.0
1.0
-2.5
1.5
-2.0
2.0
-1.5
2.5
-1.0
3.0
-3.0
-0.5 0
X Axis (m)
0.5 1.0 1.5 2.0 2.5 3.0
tunneling projects is accorded to Beaumont. performed by Dr. Shen with higher k0 did not show such a
X Axis (m)
Elastic fracture
7 Open fracture 7
Slipping fracture
Fracture with Water
6 6
Fracom Ltd
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
5 5
Date: 22/12/2004 11:00:09 Tunnel failure mechanisms
X Axis (m)
-8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
8 8
4 4
7 7
6 6
3 3
5 5
4 4
2 2
3 3
2 2
1 1
1 1
Y Axis (m)
Y Axis (m)
Y Axis (m)
Y Axis (m)
0
X Axis (m) 0
0 0
-8 -6 -4 -2 0 2 4 6 8 -1
10 -1
-1 -1
-2 10 -2
-3 -3
-4 -4
-2 -2
-5 -5
-3 -3
-6 8 -6
-7 -7
-8 -8
-4 -4 -8 -7 -6 -5 -4 -3 -2
Tunnel -1
failure0 mechanisms
1 2 3 4 5 6 7 8
X
X Axis
Axis (m)
(m)
8
-8 -7 -6
6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
8
-5 -5 7 7
6 6
-6 -6 5 5
4 4 4
-7 -7
3 3
2 2
-8 -8
1 1
-8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
2
Y Axis (m)
Y Axis (m)
X Axis (m) 0 0
-1 -1
Y Axis (m)
-2 -2
-3 -3
-4
0 -4
-5 -5
-6 -6
-7
-2 -7
-8 -8
-8 -7 -6 -5 -4 -3 -2
Tunnel -1
failure0mechanisms
1 2 3 4 5 6 7 8
XX Axis
Axis (m)
(m)
-8 -7 -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8
8 8
7 7
6
-4 6
5 5
4 4
3
-6 3
2 2
Figure 10. FRACOD modelling performed by Shen, 2005. 1 1
Y Axis (m)
0 0
-4 -4
-8 brittle
-6 rock.
-4 Secondly
-2 the presence
0 2of even 4moderate6 8 -6 10 -6
shows some of the exploratory modelling simulated TBM tunnels at 1km and 2km depth.
performed at that time. More distinctly jointed Some results of 1km deep simulations are
models using UDEC were also performed to shown in Figure 11. Boundary stresses assumed:
explore further behavioural possibilities. In fact Hmax = 50MPa; v = 25MPa. The rock
such deep TBM tunneling was not advised, but properties assumed for several such models
the advice came contractually too late. In a were the same as for the well-researched Äspö
subsequent keynote lecture, which had the diorite, as listed with Finnish data in Siren
benefit of further FRACOD modelling by Shen, (2012). For the base case, the strength and
Barton and Shen (2016) showed specific fracture toughness of the rock were: UCS =
examples of the ‘positive effect’ of jointing in 165MPa; cohesion c = 31MPa; internal friction
6
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
Figure 20. Pre-injection in the Bærum Tunnel of 5km Figure 21 illustrates two extreme cases of
length. Bottom: A single-point post injection is being over-break in order to emphasise the point that
carried out in an essentially dry 80m length of tunnel.
unintended over-excavation is not filled, nor
needs to be filled with concrete (or more
followed, compared to the strange opinion of expensive shotcrete) when using NMT
the need for 10 to 12 x d95 seen elsewhere, as a principles. The real road and rail tunnel over-
presumed result of the erroneous filter pump test break seen in poor-quality stretches of these
method. tunnels in Figure 22 may have 8 to 10cm of
S(fr) and (already covered) systematic bolting.
7 OVER-BREAK NORMALLY NOT FILLED In the case of the two-lane motorway tunnel, a
An obvious point which needs emphasis for free-standing liner and outer membrane ensure
those not familiar with NMT is that whatever dry-but-drained conditions. Of course for the
over-break occurs, due to structural geological permanent support to be specified using the Q-
reasons (the Jn/Jr ≥ 6 criterion, Figure 12), or system, as was the case in both tunnels, the
due to over-enthusiastic blasting, we do not fill engineering geologists from the owner and
the over-break (with concrete). Nevertheless the contractor have to be satisfied with the quality
volume of S(fr) may be considerably increased. of the work. This includes high-pressure air-
10
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
11
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
12
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
13
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
Fault zone delays in TBM tunneling can be It appears that the TBM industry and
deduced from performance data, because when designers of long (TBM) tunnels have not yet
fault-related delays occur there is often a very taken these trends seriously, and partly for this
strong impact on the overall, and generally very reason we see a fair number of TBM tunnels
fast performance. As shown in Figure 29 the so- which are completed by drill-and-blast. A
called ‘unexpected events’, which are often hybrid solution from the start may make much
experienced when no probe drilling is being more sense, and can result in overall faster and
performed, have a dramatic effect on the
cheaper long-distance tunneling. (Barton,
advance rate. They are often fault-related.
2012b, 2013).
Figure 33. The prediction of delays in fault zones is very uncertain (note dotted lines) due to the variety of options
open to TBM operators when encountering an expected (probe-drilled) or unexpected fault zone. Some of the
potential problems are listed under the inset: ‘UNSTABLE’. The adverse nature of fault zones is clearly reflected in
low Q-values, and the deceleration (a steeper -m gradient) seen in case records is documented in Figure 34. (Note
that the machine-rock interaction parameters are as follows: SIGMA = rock mass strength, F = cutter force, CLI =
cutter life index, q = quartz content, σθ = biaxial stress at tunnel face (approx. 5MPa/100m depth). Barton (2000).
Figure 34. The regular Q-value, as opposed to the QTBM 8.1 Fault-zone delays explained
value shown in Figure 33, is seen to have a dramatic
effect on the deceleration gradient (-m) of TBM, when
We need three basic equations to understand
low values of Q (e.g. < 0.1) are registered. It is assumed
that new generations of TBM like cross-overs and ACT potential delays in fault zones. (The following
can help to ‘push the hill’ to the left, but they will not nomenclature will be used as before: AR=
eliminate the adverse nature of serious faults unless pre- advance rate, PR= penetration rate, U=
injection and drainage are successfully carried out. In all utilization, expressed as a fraction, for any
cases there will be delays, but possibly reduced delays. chosen total time period T in hours). Firstly:
15
Proceedings of the World Tunnel Congress 2017 – Surface challenges – Underground solutions. Bergen, Norway.
AR = PR x U (1)
U = Tm (2)
T = L / AR (3)
T = L / (PR x Tm)
T=(L/PR)1/(1+m) (4)
ratio. Joint shearing due to water, clay-coatings, Barton, N. and E. Grimstad, 2014. Q-system - An
wedges and block size may dominate behaviour. illustrated guide following 40 years in tunneling. Web
site www.nickbarton.com, 43 pages, 79 figures and
NMT, the Norwegian Method of Tunnelling, photos.
is basically a collection of economic single-shell Barton, N. and Shen, B. 2017. Risk of shear failure and
B+S(fr) help-the-rock-to-help-itself solutions. extensional failure around over-stressed excavations in
brittle rock, Journal of Rock Mechanics and
Actual arching loads in the rock around tunnels Geotechnical Engineering http://dx.doi.org/10.1016/
dominate their stability. Over-break increases j.jrmge.2016.11.004.
the amount of shotcrete, but filling with Barton, N. 2016. Cavern and Tunnel Failures due to
shotcrete or concrete is neither needed nor Adverse Structural Geology. Keynote lecture, 2nd Int.
ISRM Specialized. Conf. on Soft Rocks, Cartagena,
practiced. The use of lattice-girders should not Colombia. Keynote lecture. 18p.
be part of NMT as they are too deformable. Barton, N. 2017. Minimizing the Use of Concrete in
Tunnelling through fault zones with TBM Tunnels and Caverns – Comparing NATM and NMT.
causes delays and can draw-down water tables. Keynote lecture, GeoMEast2017 Int. Conf. on
Sustainable Civil Infrastructures (SCI): Innovative
TBM suffer time-dependent utilization. Even Infrastructure Geotechnology. Sharm El-Sheikh,
world records show this. Low Q-values are a Egypt, 36p.
specific cause of the deceleration (-m) gradient. Bray, J.W. 1967. A study of jointed and fractured rock.
Part I. Fracture patterns and their failure
REFERENCES characteristics. Felsmechanik, V/2-3, 117-136.
Grandori, R., Jaeger, M., Antonini, F. & Vigl, L. 1995.
Addis, M.A., Barton, N., Bandis, S.C. & Henry, J.P. Evinos-Mornos Tunnel - Greece. Construction of a 30
1990. Laboratory studies on the stability of vertical km long hydraulic tunnel in less than three years under
and deviated boreholes. 65th Annual Technical the most adverse geological conditions. Proc. RETC.
Conference and Exhibition of the Society of San Francisco, CA. Williamson & Gowring (eds).
Petroleum Engineers, New Orleans, September 23-26, 747-767. Littleton, CO: Soc. for Mining, Metallurgy,
1990. and Exploration, Inc.
Barton, N. & Hansteen, H. 1979. Very large span Grimstad, E. & Barton, N. 1993. Updating of the Q-
openings at shallow depth: Deformation magnitudes System for NMT. Proceedings of the International
from jointed models and F.E. analysis. 4th RETC; Symposium on Sprayed Concrete - Modern Use of
Atlanta Georgia, Vol. 2: 1131-1353. Eds Maevis and Wet Mix Sprayed Concrete for Underground Support,
Hustrulid. Am. Inst. of Min. &, Metall., and Petr. Fagernes, 1993, (Eds Kompen, Opsahl and Berg.
Engrs, Inc. New York. Norwegian Concrete Association, Oslo, pp. 46-66.
Barton, N., Grimstad, E., Aas, G., Opsahl, O.A., Bakken, Hoek, E. and Brown, E. 1980. Underground excavations
A., Pedersen, L. & Johansen, E.D. 1992. Norwegian in rock. Institution of Mining and Metallurgy, 527p.
Method of Tunnelling. WT Focus on Norway, World Martin C D, Kaiser PK, McCreath D R. Hoek–Brown
Tunnelling, June 6p. /August 5p. 1992. parameters for predicting the depth of brittle failure
Barton, N. & Grimstad, E. 1994. The Q-system following around tunnels. Can. Geotech. J., 1999; 36:136-151.
twenty years of application in NMT support selection. Shen, C.P., Tsai, H.C., Hsieh, Y.S. & Chu, B. 1999. The
43rd Geomechanic Colloquy, Salzburg. Felsbau, 6/94, methodology through adverse geology ahead of
428-436. Pinglin large TBM. Proc. RETC. Orlando, FL. Hilton
Barton, N. 2000. TBM Tunnelling in Jointed and Faulted & Samuelson (eds). Ch.8: 117-137.Littleton, CO: Soc.
Rock. 173p. Balkema, Rotterdam. for Mining, Metallurgy, and Exploration, Inc
Barton, N. 2006. Rock Quality, Seismic Velocity, Shen, B. & Barton, N. 1997. The disturbed zone around
Attenuation and Anisotropy. Taylor & Francis, UK & tunnels in jointed rock masses. Technical Note, Int. J.
Netherlands, 729 p. Rock Mech. Min. Sci, Vol. 34: 1: 117-125.
Barton. N. 2007. Rock mass characterization for Shen B, Stephansson O, Rinne M. Modelling Rock
excavations in mining and civil engineering. Proc. of Fracturing Processes: A Fracture Mechanics Approach
Int. Workshop on Rock Mass Classification in Mining, Using FRACOD. Springer (publisher), 2014; 173p.
Vancouver. Siren, T. (2012) Fracture Toughness Properties of Rocks
Barton, N. 2012a. Assessing Pre-Injection in Tunnelling. in Olkiluoto: Laboratory Measurements 2008–2009,
Tunnelling Journal, Dec.2011/Jan. 2012, pp. 44-50. Posiva Report 2012-25.
Barton, N. 2012b. Reducing risk in long deep tunnels by Sundaram, N.M. & Rafek, A.G. 1998. The influence of
using TBM and drill-and-blast methods in the same rock mass properties in the assessment of TBM
project – the hybrid solution. Keynote lecture. Risk in performance. Proc. 8th IAEG congress, Vancouver.
Underground Construction. Chinese Academy of Moore & Hungr (eds). 3553-3559. Balkema.
Engineering. CSRME, Wuhan. J. Rock Mech. and Vandevall, M. (1990). Dramix - Tunnelling the World.
Geotech. Eng., 4(2): 115-126, NV Bækert S.A, 1991 edition.
Barton, N. 2013. TBM prognoses for open-gripper and Ward, W.H., Todd, P. and Berry, N.S.M. 1983. The
double-shield machines: challenges and solutions Kielder Experimental Tunnel: Final Results. Geotech-
for weakness zones and water. Bergmekanikkdag,
nique 33, 3, 275-291.
NFF, Oslo, 21.1-21.17.
17