You are on page 1of 35

Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 1 of 35

CROSSRAIL LEARNING LEGACY

CROSSRAIL’S EXPERIENCE OF GEOTECHNICAL BASELINE


REPORTS
Document type: Technical Paper
Author: John Davis EurGeol CGeol MSc DIC, ICE Publishing
Publication Date: 30/09/2017

(Be the first to rate this document)

ABSTRACT

This document sets out to record Crossrail’s experience of the use of Geotechnical Baseline Reports
(GBRs) in its construction contracts. In reading this report it is important to remember that in all of the
major Crossrail Civil Engineering contracts Contractor design activities were limited to temporary works
only. There were no Contractor design and build aspects to the permanent works. This greatly
simplifies the production of Geotechnical Baseline Reports.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 2 of 35

READ THE FULL DOCUMENT

1 Introduction and background


1.1 Introduction
This document sets out to record Crossrail’s experience of the use of Geotechnical Baseline Reports
(GBRs) in its construction contracts. In reading this report it is important to remember that in all of the
major Crossrail Civil Engineering contracts Contractor design activities were limited to temporary works
only. There were no Contractor design and build aspects to the permanent works. This greatly
simplifies the production of Geotechnical Baseline Reports.

This report briefly sets out what a GBR is; why and where Crossrail used them, how GBRs were
implemented and then provides some analysis and commentary on how successful or otherwise they
were in practice. In this report example extracts from GBRs are presented in italic Times New Roman,
with example Baseline Statements specifically being presented in bold italic Times New Roman.

An appendix containing notes on the drafting of GBRs is also included.

1.2 What is a GBR?


A GBR is a commercial document which formed part of the ITT for each Crossrail contract that included
a significant amount of below-ground works.

The purpose of a GBR is to establish the allocation of risk between the Employer and the Contractor in
relation to the ground. It does this by including contractual statements (Baseline Statements) that define
the relevant geotechnical conditions that the contractor can expect to find during construction. If
conditions are found to be equal to or better than a baseline the target cost is unaltered. If conditions
are found to be worse than a baseline and the contractor can demonstrate a loss, a compensation
event is triggered.

At tender the intention is that the GBR is used as a common basis for pricing geotechnical and
geological risk by the tenderers. Post contract award the GBR is used to judge the validity of
compensation events for those issues covered by the GBR.

The Baseline Statements establish what is ‘foreseen’ & ‘unforeseen’ in relation to the ground conditions
as they affect construction. They should only cover issues which could adversely impact on
construction (and hence be the subject of a compensation event).

Baseline Statements must be concise, measurable and clearly defined. They are not necessarily
geotechnical ‘facts’ and can be used to position risk boundaries wherever the Employer wishes. In
practice Crossrail Baseline Statements are almost all based on what the Employer considered to be a
reasonable and realistic view of what was likely to be encountered during the works.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 3 of 35

The Crossrail GBRs were NOT the basis for the tender design or any contractor design, nor were they
interpretative reports. Post contract award the GBR exists solely to determine whether a compensation
event has arisen.

1.3 Why did Crossrail adopt GBRs?


Guidelines on the use of GBR’s were first published in 1997 by the Technical Committee on
Geotechnical Reports of the Underground Technology Research Council in the USA. These guidelines
were updated in a second edition in 2007. This document sets out the advantages inherent in providing
a contractual interpretation of ground conditions as well as providing purely factual data on the ground
conditions.

In the UK in 2003 the Association of British Insurers and the British Tunnelling Society jointly produced
‘The Joint Code of Practice for Risk Management of Tunnel Works in the UK’ (the ‘JCoP’). This code
states:

7.2.5. Contract Documentation (as well as subcontract documentation for


Tunnel Works as appropriate) shall include Ground Reference Conditions or
Geotechnical Baseline Conditions prepared by the Client (or prepared on his
behalf) or shall require each tenderer to submit with their tender their own
assessment of Ground Reference Conditions or Geotechnical Baseline
Conditions, the requirements of which shall be defined and fully described in the
Contract Documentation.
The terms of Crossrail’s insurance policy require compliance with the JCoP.

The JCoP defines ‘Tunnel Works’ as the following: “Tunnels, caverns, shafts and associated
underground structures howsoever constructed and including the renovation of existing underground
structures.”

In practice all Crossrail civils contracts that have significant ‘in ground’ works incorporate GBRs even
where their scopes do not contain ‘Tunnel Works’ as defined by the JCoP.

The JCoP ‘Tunnel Works’ scope was found in the following contracts:

Stations

• C405 Paddington
• C412 Bond Street
• C422 Tottenham Court Road
• C435 Farringdon
• C502 Liverpool Street
• C512 Whitechapel

Stations advance works

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 4 of 35

• C411 Bond Street


• C421 Tottenham Court Road
• C430 Farringdon
• C501 Liverpool Street
• C503 Liverpool Street
• C511 Whitechapel

Running Tunnels

• C300 Drive X Royal Oak Portal to Farringdon


• C305 Drive Y Limmo to Farringdon,
• C305 Drive Z Pudding Mill Lane to Stepney Green,
• C305 Drive G Limmo to Victoria Dock Portal
• C310 Drive H Thames Tunnel
• C315 Connaught Tunnel

Station SCL tunnels

• C410, Bond Street/Tottenham Court Road


• C510 Liverpool Street/Whitechapel

Portals

• C330 Royal Oak Portal


• C350 Pudding Mill Lane Portal
• C340 Victoria Dock Portal
• C310 North Woolwich Portal
• C310 Plumstead Portal

Shafts

• C300 Fisher Street Shaft


• C305 Stepney Green Shaft
• C360 Mile End Shaft
• C360 Eleanor Street Shaft
• C305 Limmo Peninsular Shaft

In addition the following non-tunnel works contracts also utilised GBRs:

• C298 Plumstead Depot Enabling Works


• C336 Paddington New Yard
• C520 Custom House Station
• C695 Plumstead maintenance depot

2 How did Crossrail adopt GBRs?


Crossrail used the NEC3 form of contract for its Civils works. In its un-amended form NEC3 does not
include provision for GBRs, but in Clause 60.1 it does set out 19 types of compensation event including
an ‘unforeseen ground’ compensation event (60.1.12), this states:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 5 of 35

The following are compensation events

(12) The Contractor encounters physical conditions which

• are within the Site

• are not weather conditions and

• an experienced contractor would have judged at the Contract Date to


have such a small chance of occurring that it would have been
unreasonable for him to have allowed for them.

Only the difference between the physical conditions encountered and


those for which it would have been reasonable to have allowed is taken
into account in assessing a compensation event.

GBRs were incorporated into Crossrail tenders by amending this to state (changes in bold):

(12) The Contractor encounters physical conditions which

• are within the Site,


• are not conditions of a type referred to in the GBR,
• are not weather conditions and
• an experienced contractor would have judged at the Contract Date to
have such a small chance of occurring that it would have been
unreasonable for him to have allowed for them.

Only the difference between the physical conditions encountered and


those for which it would have been reasonable to have allowed is taken
into account in assessing a compensation event.

(12A) The Contractor encounters conditions which:

• are within the Site,


• are of a type referred to in the GBR and
• are more adverse than the conditions set out in the GBR

Only the difference between the conditions encountered and those


set out in the GBR are taken into account in assessing a
compensation event.

This establishes two classes of ‘unforeseen ground condition’ compensation events. One is ‘of a type

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 6 of 35

referred to in the GBR’ and one is where the ‘conditions’ are not ‘of a type referred to in the GBR’.

In the 60.1(12) ‘non GBR’ case another clause sets the following test:

60.2 In judging the physical conditions for the purpose of assessing a


compensation event under 60.1(12), the Contractor is assumed to have
taken into account

• the Site Information,


• publicly available information referred to in the Site Information,
• information obtainable from a visual inspection of the Site and
• other information which an experienced contractor could reasonably
be expected to have or to obtain.

This clause only applies to 60.1(12) and not to the ‘GBR conditions’ in 60.1(12A).

This arrangement means there is no hierarchy associated with the GBR in relation to the Site
Information in the Contract as there are no situations where 60.1(12) and (12A) can both apply. It also
means that there are two completely separate sources of information for assessing an ‘unforeseen
ground condition’ depending on whether (12) or (12A) applies.

In other words the Site Information and the GBR cannot be used together in support of a compensation
event claim. The Site Information clearly contains ‘facts’ about the ground whereas the Baseline
Statements in a Crossrail GBR cannot be presumed to be factually correct.

60.1(12) and (12A) also provide an opportunity for the Client to deliberately choose whether a specific
‘type’ of condition will be addressed using the GBR or addressed by using the Site or other Information.

3 How did Crossrail organise its GBRs?


3.1 GBR Introduction
The Introduction to a Crossrail GBR makes statements on the following:

1. The contractual context and the purpose of the GBR and the Baseline Statements
2. That the Baseline Statements are aligned with the tender design. Alongside this is a very brief
statement of the main forms of in-ground construction for that contract.
3. That the Baseline Statements are not ‘geotechnical fact’ and that they do not constitute a
warranty that those conditions will be found.
4. That nothing in the GBR changes the Contractors responsibility for the safe execution of the
works or for providing the works in accordance with the contract
5. That the GBR isn’t Site Information

In general the Crossrail Civils tender documentation provided a fully engineered permanent works
design and typically did not show any temporary works.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 7 of 35

One of the consequences of 2) is that temporary works are not covered by the GBR unless they are
specifically indicated within the tender documentation. An example of this might be where a tender
drawing indicates the minimum extent of ‘ground improvement’ above a shallow tunnel.

The statements in 3) and 5) are very important as they draw a clear distinction between the non-factual
(in contract terms) GBR and the factual Site Information. They are also important as the purpose of the
GBR was commonly misunderstood once works were underway. A typical misunderstanding would
result in the GBR being used by a Contractor as an interpretative report in temporary works design.

For this reason it is worth repeating the point on the purpose of the GBR made above. “The Crossrail
GBRs were NOT the basis for the tender design or any contractor design, nor were they interpretative
reports. Post contract award the GBR exists solely to determine whether a compensation event has
arisen”.

3.2 Baseline Statement Format


In a Crossrail GBR, Section 2 describes in general terms the geological setting for the contract.

None of this text forms part of a ‘condition’ as described in clause 60.1(12A). The 60.1(12A) ‘conditions’
are set out in Baseline Statements in Section 3 onwards. The Baseline Statements themselves are
differentiated from the rest of the contextual text in the GBR by being formatted in a particular way. The
Baseline Statements are set out in bold italic text.
The only text in the GBR that applies in assessing the merits of a particular 60.1(12A) compensation
event is the text in bold italics, the rest is merely context.

Here is an example:

For the purpose described in the Introduction to this GBR, for the
Works at **** Station, the Baseline Statements relating to existing
boreholes are:

• The boreholes indicated in Table 3.5 will be encountered during


the construction of the Works.
• Boreholes identified in the Site Information that are within the
limits of the Works will be grouted prior to construction.
• Boreholes will have a maximum grout diameter of 300mm.
• No other boreholes or wells will be encountered.

This is a simple Baseline Statement, it tells the contractor which boreholes will be encountered (in his
SCL works), it tells the contractor where these boreholes are (via the Site Information), what form the
boreholes will take (grouted, <300mm diameter) and that only those boreholes listed will be found.

The statements are concise, measurable and clearly defined.

Points to note:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 8 of 35

The contractor has to encounter an exceedance of the baselined condition during the construction of
the works to have a valid compensation event.

The second baseline statement in this example doesn’t add much from a commercial standpoint (there
were more boreholes in the Site Information than in the Table) but it does indicate to the tenderer that
all the Crossrail boreholes, whether or not they are expected to be encountered, have been rendered
relatively safe with respect to any SCL works should the tunnel layout be varied from the Tender
arrangements.

What did Baseline Statements cover?


Before setting out the specific Baseline Statements a Crossrail GBR stated how certain conditions were
to be measured. Typically this would take the form of a statement like this:

The test methods required in order to provide a valid comparison


between conditions encountered during construction and those defined
by the Baseline Statements are provided in Table x.y.

Table x.y – Valid Testing Methods

Baseline Parameter Definition Method of Measurement

Undrained shear Single Stage, Unconsolidated


strength for the Undrained Triaxial Compression
Undrained Shear
intact material not Testing in accordance with
Strength of Fine-
the strength BS1377:1990, on a 100mm diameter
Grained Deposits
measured on a pre- sample recovered using triple tube
existing fissure. rotary coring.

Standard Penetration Testing in


accordance with BS EN ISO
Density of Coarse-
– 22476-3:2005. N values should be
Grained Deposits
reported for uncorrected Energy
Ratio.

Unconfined
Uniaxial Compressive Strength
Compressive
– (UCS) testing in accordance with the
Strength of Hard
ISRM Suggested Methods.
Bands and Claystone.

In-situ permeability
of a block of ground, Variable head permeability testing in
minimum accordance with BS5930:1999 or
Mass Permeability
dimensions 10m Pumping tests in accordance with
x10m plan and 0.5m BS ISO 14686:2003
thick

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 9 of 35

In practice applying these statements did not cause any difficulties, but it is recognised that in many
circumstances it would not have been practicable to rigidly apply these methods of measurement. It
would have been better to add the option of ‘any other method of measurement agreed by the Project
Manager’.

Deciding on the ‘types’ of condition to be addressed by Baseline Statements is an important


consideration when writing a GBR. The types of condition addressed by the Baseline Statements
clearly need to be relevant to the intended or likely form of construction. At the same time the purpose
of the Baseline Statements is to foresee the unforeseen.

4 Types of condition used in Crossrail GBRs


A typical high level list of ‘types of condition’ used in a Crossrail GBR is given below. Exactly what was
baselined within these categories was determined by the nature of the construction techniques within
each contract. Each of these high level conditions is discussed in detail below.

Man-made features

• Existing foundations
• Existing Tunnels
• Underground Utilities
• Excavations or filled ground
• The presence of boreholes
• The presence of wells or other shafts

Unexploded Ordnance

Contamination and Waste

Geological features

• Strata Occurrence
• Strata Boundaries
• Strata Description
• Faults
• Hard strata
• Other anomalous features (e.g. ‘drift filled hollows’)
• Ground gas
• Ground Behaviour

Groundwater

• Pore water pressure


• Permeability

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 10 of 35

Where individual contracts contained several significantly different forms of structure and forms of
construction, Baseline Statements for each of these would be collected together in different chapters
within the GBR. For example a major tunnelling contract might have different chapters containing
Baseline Statements for running tunnels, shafts, cross passages, SCL works and so on. Similar splits
would also apply to similar types of structures built in different ways, such as SCL and SGI cross
passages. Running tunnel baseline statements would also tend to be grouped by chainage where
changes in geological conditions varied along the alignment.

All this variation might mean similar conditions (eg strength of particular strata) could be baselined in
different ways in different places or for different construction techniques. This is perfectly reasonably in
a GBR as there is no overarching requirement for consistency. Remember that Baseline Statements
are not ‘geotechnical fact’.

4.1 Man-made Features


4.1.1 Man-made features – Existing foundations
For all forms of construction the key points that require baselining for these types of obstruction are the
dimensions in relation to the extent of the likely encounter, strength and the nature of the materials that
will be encountered. Where existing foundations are well understood Baseline Statements are
straightforward to draft. Examples would be:

• A maximum of fifty-six (56) reinforced concrete piles of


maximum diameter 900mm and with a concrete strength of not
more than 60MPa will be encountered during the construction
of the Works.

• A 500mm thick basement reinforced concrete slab will be


encountered during construction of the Works at ****. The slab
covers an area of 30 m2within the footprint of the Works. The
concrete will have a strength of not more than 50N/mm2.

• A maximum of forty two (42 No.) piles, of concrete strength


not more than 60N/mm2, will be encountered during the
construction of the tunnelling Works of which five (5) will be
reinforced. The pile diameters will be:

Ten (10 No.) will be of maximum 500mm diameter.

An additional ten (10 No.) will be of maximum 1000mm


diameter.

An additional twelve (12 No.) will be of maximum


2500mm diameter.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 11 of 35

Where details of existing foundations were not known then Baseline Statements were typically drafted
on the basis of experience and/or best estimates.

In some cases the Crossrail Employer wished to have the tenderers make an allowance for as yet
unknown obstructions. These statements typically took this form:

• The foundations of four (4) structures will be encountered


within the tunnel face at unknown locations along the length of
the running tunnels in Drives Y and Z. These foundations will
consist of up to six (6) per location, unreinforced concrete
piles of maximum diameter 900mm and concrete strength of
not more than 60N/mm2.

Note the exact location of the individual piles is not baselined, even though this may well have been
known and that information included within the site information.

This was to avoid tenderers pricing for X encounters then being able to claim for X+1 encounters purely
because the one of the X number of piles was not in the anticipated location. Of course if the location of
particular obstructions is significant then baselining the specific locations may be desirable.

4.1.2 Man-made features – Existing tunnels


Normally the Crossrail works were not expecting to encounter pre-existing tunnels and the baseline
statement associated with this type of encounter would typically state:

• No existing tunnels will be encountered during the


construction of the Works.

Non-baseline contextual text would typically be used to flag up the presence of nearby tunnels in this
part of the GBR as a backup to the site information. This Baseline Statement merely confirms that these
tunnels are not expected to be encountered.

It is plausible that Works under a contract could knowingly encounter pre-existing tunnels and if so this
could be identified and baselined here, however it is also highly likely that such an expected (foreseen)
encounter would be dealt with elsewhere in the tender documentation.

4.1.3 Man-made features – Underground Utilities


Underground utilities proved to be one of the harder types of condition to baseline on Crossrail. There
are two principle reasons for this:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 12 of 35

• The difficulty of describing/defining the nature of the utilities in measurable ways when the
physical nature of the utilities was often unknown. Different types of utilities are often recorded on
drawings only by varying line styles.
• The inevitable uncertainty as to the actual location of underground utilities.

These points applied to both live utilities and disused or diverted utilities including those diverted by
Crossrail.

The clearest way to Baseline utilities is to refer to specific drawings in the Site Information. However
drawings often only record a location in plan, often don’t describe the physical nature of the utility or
describe whether it is in use or not.

Ideally tender documentation would include details of all pre-existing utilities and any as-built diverted
locations. On Crossrail this information was not always available at the time of tendering (because
enabling works contracts were incomplete). The Crossrail GBRs would certainly have been easier to
write if they had explicitly excluded encounters with some types of underground utilities and moved
these issues to a 60.1(12) approach. However on Crossrail this would probably have led to more
compensation events and less cost/programme certainty.

4.1.4 Man-made features – Excavations or filled ground


Typically geological Baseline Statements relating to Made Ground, as described in 4.4 below, dealt with
the occurrence and nature of made or filled ground that pre-dated Crossrail.

Baseline statements made under ‘Man-made features – Excavations or filled ground’ tended to cover
only filled/excavated ground deliberately created by neighbouring or preceding Crossrail contracts, i.e.
encounters that were probably not recorded in borehole logs in the Site Information.

4.1.5 Man-made features – The presence of boreholes


For some forms of construction (e.g. TBM and SCL tunnelling) encountering unexpected boreholes can
be a significant hazard (e.g. in-rush of water/soil, metallic obstructions, loss of face support pressure,
and mobilisation of contaminants). As a result it is important to identify the location of all known
boreholes and to baseline something about the form they will be found in. See 3.2 for an example.

4.1.6 Man-made features – wells and other shafts


Unexpectedly encountering wells or shafts, particularly when tunnelling, has the potential to cause
significant delay and extra cost. Crossrail’s consultants were commissioned to exhaustively search for
potential encounters. Despite this there were at least 6 encounters with unknown wells during
tunnelling, fortunately none of them serious.

As with other conditions these Baseline Statements need to define the number, nature and perhaps
location of the encounters. A typical example for a tunnelling contract would be:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 13 of 35

• One (1) well will be encountered at the tunnel face at WB


Chainage 4390 ± 25m.

• Two (2) additional wells will be encountered at the tunnel face at


unknown locations along the length of running tunnels covered by
C***.

• Wells encountered will be brick lined and have a maximum


diameter of 2.5m.

4.2 Unexploded Ordnance


Crossrail provided significant quantities of background desk study information on UXO risk within each
Civils tender pack. In addition all the Civils contracts required the contractor to undertake UXO risk
assessments and if required, investigations for UXO.

Crossrail considered the risk of finding UXO to be effectively un-priceable and as a result took on the
risk of UXO discovery for every GBR contract via this baseline statement:

• No unexploded ordnance will be encountered during the


construction of the Works.

4.3 Contamination and Waste


This was an area of weakness in the Crossrail GBRs. This was not because the subject is intrinsically
difficult to baseline, but more because of Crossrail specific timing issues around obtaining Wallasea
Island acceptance criteria for some natural ‘as dug’ materials that exceeded ‘Inert’ criteria for certain
substances. These timing issues meant not all the relevant information on classification of materials
was able to be included in the tender documentation.

Wallasea Island is the site of a land reclamation project that took a large proportion of Crossrail’s
excavated material. Excavated materials (‘Waste’) were accepted at Wallasea under a Waste Recovery
Permit. The processes within the Wallasea Waste Recovery Permit meant that at the point of
placement at Wallasea the excavated material was no longer ‘Waste’.

For Crossrail contracts that were to deliver spoil to Wallasea the ideal scenario would have been to
define proportions of excavated material that would or wouldn’t meet the Wallasea waste recovery
criteria in Baseline Statements.

A non-Crossrail (or non-Wallasea) equivalent approach would be to Baseline proportions of excavated


material on the basis of the usual European waste classification systems (Hazardous, Inert etc) or
Baseline by using criteria for other known specific disposal sites.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 14 of 35

When selecting the best approach for Baselining disposal of spoil much depends on whether the final
destination for the spoil is known at the time of tender. If the site(s) are known then the acceptance
criteria applicable to those sites can be used to develop Baseline Statements. Clearly different
acceptance criteria at several pre-determined sites could cause difficulty.

The status of the spoil in ‘Waste’ terms and whether or not the contractor is incentivised to minimise
disposal of ‘Waste’ is also an important consideration and the nature of any incentives may need to be
reflected in any Baseline Statements.

Any acceptance criteria used in Baseline Statements might need to incorporate the impact of any
additives that might necessarily be contained within the spoil (e.g. conditioners, bentonite or SCL / SCL
fibres). Since this is moving outside the normal experience of a Geotechnical Engineer advice should
be sought on these matters when writing a GBR.

4.4 Geological Features


4.4.1 Geological features – Strata Occurrence and Strata Boundaries.
These two conditions are typically treated separately in the GBR but are discussed together here.

Before going on to Baseline the relevant properties of geological materials it is necessary to Baseline
the geological materials that the works will encounter. This is not always straightforward. Construction
works for a Crossrail Station typically take place in a minimum volume of ground 400m x 70m x 40m so
there are always variations in the strata encountered. In London these variations are significantly
amplified when the works extend below the base of the London Clay into the laterally variable Lambeth
Group.
One way to simplify this process is to sub-divide a GBR for strata boundary Baseline purposes, e.g.
boxes/shafts and tunnels would have separate sets of Baselines. This approach would also neatly
match the differing Baseline requirements for strata properties needed for different forms of
construction (see below).

For contracts with below ground construction in relatively low volumes of ground, like shafts or small
plan area boxes where there is little variation in strata, a simple table like this usually suffices for both
strata occurrence and strata boundary Baselines:

• The elevations of the strata boundaries relevant to the Works are


shown in Table x.y.

Table x.y Baseline Stratigraphy at the Site

Elevation of base of stratum (m ATD)


Stratum
Maximum Minimum

Made Ground 110 108

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 15 of 35

Alluvium 109 107

River Terrace Deposits 106 100

London Clay Formation 78 76

Harwich Formation 1 to 2m below London Clay Formation

Lambeth Group clay and silt


69 60
units

For more the complex geology found at Farringdon a slightly more sophisticated approach was adopted
to account for differences either side a particular fault. Here Strata Boundaries were separated from
Strata Occurrence. The Strata Boundary Statements took this form:

For the purposes described in the Introduction to this GBR, for the
C435 Tunnelling Works at Farringdon Station, the Baseline Statement
relating to strata boundaries is:

• The elevations of the strata boundaries relevant to the Tunnel


Works are shown in Tables x.y and x.z.

Table x.y – Baseline stratigraphy to the west of the Smithfield (or Bh F10) Fault

Elevation of base of stratum (m ATD)


Stratum
Maximum Minimum

Made Ground 108 98

Alluvium 104 98

River Terrace Deposits 107 98

London Clay Formation 100 94

Harwich Formation Maximum 1m thickness below base of LC

Lambeth Group clay and silt units 87 80

Lambeth Group coarse-grained units 84 78

Thanet Sand 74 69

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 16 of 35

Table x.z – Baseline stratigraphy to the east of the Smithfield (or Bh F10) Fault

Elevation of base of stratum (m ATD)


Stratum
Maximum Minimum

Made Ground 114 107

River Terrace Deposits 113 108

London Clay Formation 93 83

Harwich Formation Maximum 1m thickness below base of LC

Lambeth Group clay and silt units 82 75

Lambeth Group coarse-grained units 78 72

Thanet Sand 70 62

The location of the “Smithfield (or Bh F10) Fault” was defined by references to particular drawings in the
Site Information in the contextual text preceding this Baseline Statement.

The Strata Occurrence statements set out to Baseline additional points about each geological unit and
their relationships to the 3D network of tunnels at Farringdon. In particular they Baselined the possibility
of not encountering certain Strata within the limits set out above. Such a possibility might arise because
of natural variability, the effects of faulting or historic removal or addition by Man.

For the purposes described in the Introduction to this GBR, for the C435 Tunnelling Works at
Farringdon Station, the Baseline Statements relating to strata occurrence are:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 17 of 35

• The London Clay Formation, the Lambeth Group and Thanet


Sand will be present across the site.

• The Made Ground, Alluvium and River Terrace Deposits will be


discontinuous across the site.

• The Harwich Formation and the Lambeth Group Sand Channels


will occur in discontinuous channels and pockets across the site.

• The London Clay, Harwich Formation, Lambeth Group and


Thanet Sand will be dislocated by faulting across the site.

• The SCL Works at Farringdon Station will encounter the London


Clay Formation, Harwich Formation, Lambeth Group and Thanet
Sand Formation with the exception of the SCL components in
Table x.y.

• The SCL Works for ES1/CH1 will encounter the strata listed in
Table x.y.

Table x.y – SCL components expected to encounter additional strata

Reference Structure Ground Conditions

Escalator Incline 1 – Made Ground / Alluvium / River Terrace


ES1 / CH1 Permeation Grouting and Deposits / London Clay / Lambeth
Pipe arches Group / Thanet Sand

An alternative approach to these issues that also deals with a complex network of tunnels and less
complex ground was adopted at Liverpool Street Station. Here a strata boundary table was baselined

• The elevations of the strata boundaries relevant to the Works are


shown in Table 3.7.

Table 3.7- Baseline Stratigraphy at the Site

Elevation of base of stratum (m ATD)


Stratum
Maximum Minimum

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 18 of 35

Made Ground 111 104

Alluvium 110 106

River Terrace Deposits 109 98

London Clay Formation 80 75

Harwich Formation Maximum 2m thickness below base of LC

Lambeth Group (clay and silt units) 69 60

Lambeth Group (coarse- grained units) 61 56

ATD is Above Tunnel Datum.

After this the Strata encountered by individual elements of the tunnel network were tabulated in another
Baseline Statement (only an extract from this particular table is shown below).

The names and codes for each tunnel element matched those defined in the Works Information.

• The Works at Liverpool Street Station will encounter the London


Clay Formation, with the exception of the components shown in
Table 3.8.

Table 3.8 – Components Expected to Encounter Additional Strata

Reference Structure Ground Conditions

Made Ground / Alluvium / RTD /


London Clay Formation / Harwich
Finsbury Circus Shaft Formation / Lambeth Group clay and
silt units / Lambeth Group Sand
Channels

PTE Platform Tunnel East London Clay Formation / Harwich


Formation / Lambeth Group clay and
PTW Platform Tunnel West silt units/ Lambeth Group Sand
Channels
CH1 Lower Concourse Chamber 1

CH2 Lower Concourse Chamber 2

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 19 of 35

Reference Structure Ground Conditions

CP1 Cross Passage 1

CP2 Cross Passage 2

CP3 Cross Passage 3

VD4 Ventilation Duct 4

• The Made Ground, River Terrace Deposits, London Clay


Formation and Lambeth Group will be continuous across the site.
• The Alluvium, Harwich Formation and the Lambeth Group Sand
Channels will occur in discontinuous channels and pockets
across the site.

A different approach to these conditions was adopted for running tunnels. For the EPB TBMs, which
mined mainly in clay, sand or mixed clay sand strata, contextual text was used to list areas of common
geology using tunnel chainage. A Baseline Statement was then used to set out three different classes
of face condition is this way:

• Clay/silt conditions are defined as greater than 35% (by weight)


passing the 0.063mm sieve.

• Coarse material is defined as less than 35% (by weight) passing


the 0.063mm sieve.

• Mixed face conditions are defined as where greater than 10% of


the material at the face is of different material (e.g. greater than
10% sand (by weight) in a predominantly clay face).

Baselined tables were then used to set out face conditions on a chainage basis in this way:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 20 of 35

• Face conditions as detailed in Table x.y will be encountered


within the tunnel face along the length of the eastbound running
tunnel in Drive *.

Table x.y – Drive * eastbound face conditions

Chainage from Chainage to Face conditions

Limmo Peninsula Shaft EB 15350 clay / silt

EB 15350 EB 13240 mixed

EB 13240 EB 12800 coarse

EB 12800 EB 11750 mixed

EB 11750 EB 9670 clay / silt

EB 9670 Farringdon Station mixed

Additional Baseline Statements were also used to add further detail as required. Examples include:

• The mixed face conditions that will be encountered between EB


Chainage 15760 and 16180 will consist of clays, sands (as
Baselined in Section 3.2) and gravels.

• For 70% of the route between chainage EB 15760 and chainage


EB 16180, the sands encountered at the face will be up to 3m
thick.

• The sands are defined as less than 35% (by weight) passing the
0.063mm sieve and more than 65% (by weight) passing the 2mm
sieve.

Portal approaches

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 21 of 35

• Within the 150m prior to entering Victoria Dock Portal, River


Terrace Deposits will be encountered within the crown increasing
in thickness towards the portal.

• Within the 15m prior to entering Pudding Mill Lane Portal, River
Terrace Deposits will be encountered within the crown

Strata expected at individual running tunnel cross passages was separately Baselined.

The contract for Crossrail’s Thames Tunnel used slurry TBMs to mine a weak Limestone (Chalk) with
some overlying sands and gravels for short distances at the portals. The GBR also used contextual text
to list areas of common geology along the tunnel chainage but did not include Baseline Statements on
strata boundaries as the encounters with these were very limited in extent, and they were very well
defined in the Site Information. As a result the risks associated with TBM operation and unexpected
variations were low.

An alternative approach for strata boundaries and strata occurrence Baselines would have been to
reference strata boundaries drawn on Geological sections + or – a value. This approach was not
adopted in any Crossrail GBR because:

• It is awkward to apply in practice (i.e. potentially constantly varying baseline conditions).

• Boundaries on geological sections are almost always broad approximations based on off-set
boreholes (especially so in the case of tunnels where boreholes deliberately avoid the tunnel
alignments). This uncertainty and the fact that a single line has to represent the full width of the
works means any reasonable + or – element is likely to end up being relatively large. This means it
is hard to fine tune any element of risk transfer.

4.4.2 Geological features – Strata Description


In this section geotechnical properties for each stratum are baselined. The properties or parameters
that are baselined are determined by their relevance to the construction techniques involved in that part
of a contract (i.e. what exceedance could cause a problem to that construction technique). As an
example, there is little point baselining London Clay discontinuity spacing for piling, but it could be
important for SCL tunnelling.

The table below summarises the typical properties baselined for different classes of ground and
construction methods used on Crossrail. Sections on baselining more anomalous geological conditions
(in a London context) follow this section, e.g. hard strata, faulting.

Typical Baselined Properties for strata encountered by Crossrail

TBM tunnelling
Piling / Deep Bulk SCL (including
Strata / Parameter
Foundations excavation tunnelling Cross
Passages)

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 22 of 35

TBM tunnelling
Piling / Deep Bulk SCL (including
Strata / Parameter
Foundations excavation tunnelling Cross
Passages)

Made Ground
Yes Yes N/A N/A
Heterogeneity

Made ground
Yes Yes N/A N/A
Max particle size

Made Ground
Yes or No Yes or No N/A N/A
Water Bearing*

Alluvium
Yes Yes N/A N/A
Organic content

Alluvium Max & Min Su. Max & Min


Range of N if Su. Range of N/A N/A
Strength** applicable N if applicable

Alluvium

Plasticity
Yes Yes N/A N/A

Opportunity to Opportunity to
baseline baseline
Alluvium significant significant
high K (e.g. high K (e.g. N/A N/A
Lithology variation sand) or low sand) or low
strength strength
(e.g.peat) (e.g.peat)

River Terrace
Deposits – N Max Max Yes Yes
value**

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 23 of 35

TBM tunnelling
Piling / Deep Bulk SCL (including
Strata / Parameter
Foundations excavation tunnelling Cross
Passages)

Fines content
Fines content Fines content and max Fines content
River Terrace
and max and max particle size and max
Deposits – grading
particle size particle size (prior to particle size
grouting)

River Terrace
Deposits – Water Yes or No Yes or No Yes or No Yes or No
Bearing*

London Clay &


fine grained
Harwich Fm / N/A N/A Yes Max PI
Lambeth Gp –
Plasticity

London Clay & fine Max & Min Max & Min Max & Min
grained Harwich
Max & Min Max, excludes Max, excludes Max, excludes
Fm / Lambeth Gp –
Su** Claystones Claystones Claystones

London Clay & fine Yes Yes


grained Harwich
N/A N/A Vary near Vary near
Fm / Lambeth Gp
-fissure spacing known faults ? known faults ?

London Clay
–seepages * Yes. Vary near
Yes or No Yes or No Yes or No
especially near known faults ?
Claystones

Coarse grained
Harwich Fm,
Yes
Lambeth Group Max & Min N
and Thanet Sand Max & Min N Max & Min N Vary near
Min Ø’
Fm – strength** known faults ?

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 24 of 35

TBM tunnelling
Piling / Deep Bulk SCL (including
Strata / Parameter
Foundations excavation tunnelling Cross
Passages)

Coarse grained
Harwich Fm,
Lambeth Group Yes or No Yes or No Yes or No Yes or No
and Thanet Sand
Fm – water bearing

Yes
Harwich Fm –
Yes or No Yes or No Yes or No Vary near
water bearing
known faults ?

Yes, from Yes, from


fissures, fissures,
laminations laminations Yes
Lambeth Group – and near and near
N/A Vary near
seepages* nodules and nodules and
hard and/or hard and/or known faults ?
cemented cemented
layers layers

Lambeth Gp sand
See below
channels

Thanet Sand –
Fines content Fines content Fines content Fines content
grading

Chalk – Strength** Max UCS Max UCS Max UCS Max UCS

Chalk – Water
Yes or No Yes or No Yes or No Yes or No
bearing

*Ground water levels, pore pressures and permeabilities are baselined elsewhere – see below.
** Max/Min strengths were typically given reasonable and realistic values rather than values that
repeated the maximum and minimum strengths indicated by the Site Information. Specific instances of
hard strata (e.g. Claystones) were baselined separately (see below).

4.4.3 Lambeth Group Sand Channels


Baselining the extent of encounters with sinuous and/or discontinuous Lambeth Group Sand Channels
within a 3D network of SCL tunnels is particularly challenging, especially in faulted ground. Various
methods were adopted with no obvious ‘best way’ being identified.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 25 of 35

The following is a typical set of Sand Channel Baseline Statements, in this case from Farringdon, where
there were many faults, many sand channels and very few boreholes within the station footprint
because of the layout of buildings above:

• Sand Channels will be present within the clay and silt units of the
Lambeth Group.

• 25% of the length of the tunnels listed in Table 3.1 that are
excavated in the Lambeth Group clay and silt units will encounter
Sand Channels up to 3m deep and up to the full width of the
tunnel during construction of the Tunnel Works. The length of
tunnel that encounters any single Sand Channel will vary
according to the geometries of the Sand Channel and the tunnel.
For the purposes of this document the length of tunnel that
encounters a Sand Channel will be taken to be the average length
of tunnel where that Sand Channel is encountered.

• During Temporary Access Shaft construction, Sand Channels


totalling up to 3m thickness, and extending over up to the full area
of the shaft will be encountered. These Sand Channels will extend
horizontally beyond the zone of influence of the SCL Works.

• Sand channels within the Lambeth Group encountered within the


Tunnel Works will exhibit a minimum relative density
corresponding to an SPT N value of 40 and a maximum relative
density corresponding to an SPT N value of 110.

• 90% of the Lambeth Group Channel Sands will have a fines


content (particle size <63µm) of less than 30%. The maximum
particle size encountered will be 60mm in diameter.

• The minimum drained friction angles of the Lambeth Group


Channel Sands encountered by the Tunnel Works will be 32°.

• The Lambeth Group Sand Channels will be water bearing.

The second bullet point refers to 25% of the total length of SCL tunnels “within the clay and silt units
of the Lambeth Group”. If there had been more confidence in the location of sand channels within the
Station this statement could have said 25% of the length of each of the tunnels listed in Table 3…

Note “will encounter Sand Channels up to 3m deep”, this means 3m deep in the encounter, (i.e. in
the tunnel), it doesn’t mean the total channel depth will be no more than 3m.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 26 of 35

4.4.4 Ground Behaviour for TBM interventions


Ground Behaviour for TBM interventions was baselined on a chainage basis for TBM contracts. During
normal TBM operation with a closed face these statements have little relevance as it isn’t possible to
encounter these conditions. However any interventions that involve access to the face (planned or
otherwise) would encounter one of these conditions. Ground behaviours in this circumstance were
baselined using the ‘Tunnelling Ground Classification System’ (Modified After Terzaghi, 1950):

• Firm Ground – A heading may be advanced up to a metre or more without immediate support.
Hard clays and cemented sand or gravel generally fall into this category.

• Ravelling Ground – After excavation, material above the tunnel or in the upper part of the working
face tends to flake off and fall into the heading. Slightly cohesive sands, silts, and fine sands
gaining their strength from apparent cohesion typically exhibit this type of behaviour. Stiff fissured
clays may be ravelling also. In fast ravelling ground the process starts within a few minutes,
otherwise the ground is slow ravelling.

• Squeezing Ground – Ground squeezes or extrudes plastically into tunnel without visible fracturing
or loss of continuity and without perceptible increase in water content.

• Running Ground – Granular materials without cohesion or unstable at a slope greater than their
angle of repose. When exposed at steeper slopes they run like sugar or dune sand until the slope
flattens to the angle of repose. Clean, dry granular materials generally fall into this category.
Apparent cohesion in moist sand or weak cementation in any granular soil may allow the material
to stand for a brief period of ravelling before it breaks down and runs. Such behaviour is cohesive-
running.

• Flowing Ground – A mixture of soil and water flows into the tunnel like a viscous fluid.

4.4.5 Hard Strata


Specific instances likely of Hard Strata were baselined for all types of contract involving excavation,
mining and piling or diaphragm wall construction where they were likely to be encountered. These
instances were:

• Claystone layers within the London Clay

• Cemented bands within the Harwich Formation and Lambeth Group

• Gravel layers within the Lambeth Group

• Flint bands (including the Bullhead Beds)

For TBM contracts the locations of these encounters were defined by chainage. For station contracts
(including boxes and shafts) the locations were baselined according to geological and layout complexity
and this could include both elevation limits, and plan limits, either by chainage or tunnel reference
names. Baseline statements would typically include thicknesses, maximum strengths (usually defined
as a UCS) and in the case of Claystones the number of layers present.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 27 of 35

Where Lambeth Group hard strata were thought to be in the form of discrete nodules maximum size
and maximum strength were baselined together (as only large and strong nodules were considered to
be problematic).

4.4.6 ‘Drift Filled Hollows’


The presence or absence of ‘Drift Filled Hollows’ (or ‘Scour Hollows’) were baselined for all types of
contract involving excavation, mining and piling or diaphragm wall construction. Where the locations of
these features were known the extent and nature of the feature would be baselined in the ways
described above. Some TBM contracts contained speculative baselined encounters with Drift Filled
Hollows phrased in this way:

• One (1) scour hollow/infilled pingo scar feature will be


encountered within the tunnel face at an unknown location along
the length of running tunnels in Drives * and *. The scour hollow
feature shall comprise highly unstable mixed full face conditions
over a distance of 50m with high ground water inflows.

4.4.7 Fault Zones


Where appropriate conditions relating to Fault Zones were baselined, either when faulting could lead to
changes in the type of the strata encountered or where this did not occur changes in the nature of the
strata encountered, for instance reduced strength or increased discontinuity frequency.

4.4.8 Ground Gas


Differences to normal atmospheric gas composition that might be found during construction were
baselined as “Ground Gas”. These statements did not state the specific proportions of gases that might
be encountered but merely that they would be different to normal atmospheric proportions.

4.5 Groundwater
Groundwater levels, permeability and pore pressures were baselined for every contract with a GBR.
These baseline statements were in addition to those in the strata description statements which
addressed the presence or absence of water in each strata unit. Typical examples of baseline
statements are: (Note these are not a ‘set’ of Baseline Statements and they are not necessarily
internally consistent with each other):

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 28 of 35

• The Upper Aquifer groundwater level will be 4m below ground


level ± 1.0m.

• Pore water pressures in the London Clay Formation follow a


hydrostatic profile from 105mATD ± 1.0m to ***mATd. Below
***mATd pore water pressures will be between hydrostatic and
hydrostatic minus 80kPa.

• The maximum porewater pressure that will be encountered by


the Works will be ***kPa

• Pore water pressures in the Lambeth Group will be less than


130kPa.

• The Lower Aquifer water level will be a maximum of 69mATD.

• The range of permeability for the ground conditions encountered


by the running tunnels in Drive * is provided in Table x.y.

Table x.y – Baseline permeability values

Minimum permeability Maximum permeability


Strata
(m/s) (m/s)

London Clay Formation 1×10-11 1×10-7

Harwich Formation 1×10-8 1×10-5

Lambeth Group 1×10-11 1×10-4

Ranges for permeability values would normally be baselined for all strata expected to be encountered,
including superficial deposits such as Made Ground, Alluvium and River Terrace Deposits.

4.6 GBR Appendix


All the Crossrail GBRs also contained an Appendix which listed the relevant geotechnical information
found in the Site Information (Volume 3 of the contract). This is not a necessary component of the GBR
but fulfilled two other useful functions. Firstly the procurement teams compiling the ITT document could
use it to check they had incorporated only the relevant factual geotechnical information and secondly it
provided a useful shortcut to the relevant data for the tenderers and the eventual successful contractor.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 29 of 35

5 How successful were Crossrail’s GBRs?


5.1 Value of GBR compensation events
The total value of the below ground works in Crossrail civils contracts that utilise GBR’s (i.e. those that
contain clause 60.1.12A) is not simple to assess, as some ‘GBR’ contracts with large values had
modest below ground scopes. Nevertheless an estimate has been made and it is approximately £4.25
billion.

An analysis of most of the clause 60.1.12A compensation events (CEs) arising from these contracts
has been undertaken. The dataset analysed covered the period from the start of construction to the end
of January 2016. Almost all civils contracts were either complete or substantially complete at this point,
although some excavation works continued until spring 2017. Despite this the dataset is considered to
be representative of the overall Crossrail experience of GBRs.

In all 321 60.1.12A CE notifications were received.

Of these 182 were rejected* and 7 had no outcome recorded at the time the data was captured. This
leaves 132 valid CE notifications.

However a number of these were repeat occurrences of a single issue within a contract. If these are
taken together as single incidents the total reduces to 102 valid CE notifications.

The total value of these 132 CEs was £15.25M** (or 0.36% of the approximate value of the ‘GBR’
scope). Six of the CEs had values >£1M, the highest being £1.6M. The mean and median values of a
CE were £159K and £25K respectively.

*There are dispute resolution arrangements by which a contractor can continue to pursue a rejected CE
if he wishes.
**Some significant GBR type issues were resolved as part of wider supplemental agreements between
Crossrail and Contractors and the value of these is not included here, if they were it is considered to be
unlikely the proportional value of GBR NCE’s would be significantly greater than 0.5% of the total ‘GBR
contract value’.

5.2 Nature of compensation events


The causes of the valid CE’s were also analysed and of the 132 CEs:

• 72 related to obstructions, with almost all of these being man-made obstructions. This figure
includes unforeseen obstructions and known obstructions with greater than baselined dimensions
or strengths. The 72 included 1 CE with a value of >£1M

• 23 related to bentonite loss during Dwall construction. All these CEs occurred on one contract
with each CE relating to a single wall panel.

• 16 related to the discovery of contaminated material, mostly relating to the discovery and
subsequent disposal of buried asbestos.

• Only 9 related to encounters that could be described as geological or geotechnical. These

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 30 of 35

included 5 of the 6 CEs with values >£1M

5.3 Discussion
Internally within in Crossrail the subjective view is that the GBRs have been a success in three ways:

1. They were relatively straight forward to write.

2. They were relatively straight forward to apply.

3. The cost outcomes struck a reasonable balance between cost certainty & risk transfer.

Comments made by senior figures from a number of Crossrail major civils contractors suggest the form
of the GBRs provided a clear guide to the assumptions that the Client presumed would be taken in
during the pricing of the tenders.

Objective views of the success or otherwise of the Crossrail GBRs are difficult to make in the absence
of other published data for similar schemes in broadly similar ground.

Whilst this report focusses on the content and format of the Crossrail GBRs a significant contributor to
any success the GBRs achieved is the quantity and quality of the information gleaned from the ground
investigations carried out for the project.

In practice the ground presented very few surprises, despite much of the work being in the variable
strata below the traditional tunnelling medium of London Clay. The few ‘surprises’ that were uncovered
were in small volumes of ground in locations where the drilling of ground investigation boreholes etc.
was impracticable.

This is reflected in the statistics on the nature of the successful CEs presented above. Very few of
these were geological or geotechnical. However those that were geological or geotechnical in nature
tended to be the higher value CEs.

Appendix A
Notes on writing GBRs and baseline statements

These notes are based on the Crossrail experience of GBR’s, i.e. no contractor permanent works
design and no contractor involvement in the writing of the GBRs. They are however expected to be
generally valid.

General points

When writing baseline statements you are attempting to foresee the unforeseen and in doing so you are
setting boundaries for what the contractor can claim additional time or money for.

In order to be able to do this you need to understand the client’s views on risk taking versus price
certainty. These views will depend on many things including the quality and quantity of the geological
and geotechnical data available to the project and the level of the client’s technical knowledge.

The author of the GBR needs to:

1. Have in depth knowledge of the design, the ground conditions and the required construction

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 31 of 35

methods.

2. Understand broad geological setting for the project and any possible variation that might arise
over and above that indicated by the ground investigation data.

3. Understand the limitations of the factual information provided by the ground investigation data.

4. Understand the GBR applicable construction scope and the circumstances in which the GBR
would be applied.

5. Understand the GBR related compensation event mechanisms set out in the contract.

6. Have knowledge of the defined terms used in the contract.

7. Understand the client’s appetite for risk versus price certainty.

It is unlikely that any individual or group of individuals from a single organisation (client, designer etc.)
will be able to meet all these criteria. In addition on a large project like Crossrail there are likely to be
many separate contracts that require GBRs (thirty four on Crossrail). So consistency of approach
across several contracts could become a problem for a client if consistency was required.

Crossrail’s approach to this conundrum was to provide the designers with a skeleton GBR format and
ask them to complete the GBR in draft. This dealt with items 1 to 3 (or 4) above.

This draft GBR would then be reviewed, revised (often substantially) and issued by a very small group
of Crossrail technical staff such that items 2 to 7 above were covered.

In finalising the GBR the Crossrail technical staff would be liaising closely with both the designers and
Crossrail’s specialist contract formulation teams.

Notes on drafting Baseline Statements

These are presented as a series of bullets points

• Where contracts include several significant construction techniques Baseline Statements should
be divided up into chapters specific to each construction technique. This is to avoid confusion
arising from irrelevant or misleading conditions being inadvertently baselined for some techniques.
For example problematic strengths may be vary across different construction techniques. This
division also allows greater flexibility in setting risk boundaries as Baseline Statements do not
necessarily have to be factually correct.

• In deciding which conditions to baseline start from a consideration of how each construction
technique could be compromised or constrained by an encounter with an ‘unforeseen’ condition.
Then baseline these conditions. This is attempting to forsee the unforeseen. E.g. piling – high
strengths, hard bands etc; bulk excavation – excessively high and excessively low strengths (plant
support).

• Encounters #1. Remember when drafting Baseline Statements to consider the works the GBR is
intended to cover (e.g. permanent or temporary and permanent) together with the content of
Clause 60.1.12, which says:

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 32 of 35

The Contractor encounters conditions which:

• are within the Site,

• are of a type referred to in the GBR and

• are more adverse than the conditions set out in the GBR

The introduction to a Crossrail GBR says the Baseline Statements are aligned with the tender
design, which in Crossrail’s case was a fully engineered design which typically did not include any
specified temporary works.

This meant for Crossrail that the GBR only applied to encounters with conditions within the space
occupied by the permanent works (if no specific temporary works were prescribed in the tender
design). So it was not possible for a 60.1.12A CE to be raised against an exceeded baselined
condition where the location of the exceedance cannot be encountered within the permanent
works, e.g. in a temporary shaft, not shown in the tender design that was outside the envelope of
the permanent works.

• Encounters #2. Consider the pros and cons of being very specific about the locations of
encounters when drafting Baseline Statements. In some cases being specific can be very cost
effective as the tenderer can price for just the specified location. In other cases it can be
counterproductive. For instance if the GBR baselines X number piles as man-made obstructions at
specific positions A , B and C and X number are encountered, but at locations A, B and D, an
opportunity for a CE is provided even though the number of piles is as defined in the GBR. An
alternative approach could be to be less specific by saying ‘in this particular part of the site X
number of piles will be encountered’.

Good practice would be to include any relevant location information on obstructions in the Site
Information to give the tenderers the opportunity to provide the best price. Much will depend on the
quality of the information available.

• Encounters #3 Baselining continuously variable locations, such as strata boundaries. The advice
here is to never baseline strata boundary lines drawn on geological sections, as this effectively
says the location is exactly this single value at this specific location. In almost all cases this single
value will be not be the actual value in practice. The recommended approach is to tabulate ranges
of locations, if necessary appropriately sub-dividing the site into sub-units based on the structures
being built or variations in the ground conditions or both.

• If the contract has a similar arrangement to Crossrail re. Clauses 60.1.12 and 12A then
remember GBR does not have to baseline every ‘type’ of condition. It is possible for the GBR to
remain deliberately silent on a ‘type’ of condition so as to only use Clause 60.12 for any CEs that
arise. Take care if this approach is adopted because any mention of a ‘type’ of condition anywhere
in a Baseline Statement could allow a 60.1.12A CE to be presented.

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 33 of 35

• Take care to check that any terms defined elsewhere in the contract have the exactly the same
meanings in the GBR. An example might be the terms ‘works’ or ‘site’. This should be reinforced
by adopting the formatting set out in the contract for any defined terms (e.g. Capitalisation or
italics)

• Take care with the use of contractual, technical or geological ‘shorthand’ in Baseline Statements.
If this is unavoidable then define the terms fully within the GBR in a contextual section.

• Geological terminology #1. Always use proper strata names rather than shorthand versions. For
example use ‘London Clay Formation’ rather than ‘London Clay’. This helps to avoid assumptions
being made about the nature of the strata based on the shorthand name, e.g. River Terrace
Deposits rather than Thames Gravels.

• Geological terminology #2. Ensure the terminology used in the GBR is compatible with that used
in the Site Information borehole logs. This could be challenging as desk study sourced historic logs
may use outdated terminology. This can be dealt with by adding a ‘bridging’ contextual section in
the GBR.

• When drafting Baseline Statements on geotechnical parameters it is common to quote ranges of


values or separately quote maximum or minimum values. Best practice would be to only quote the
data limit(s) relevant to the encounter. For example there is little point baselining a minimum
strength for a hard strata or nodule, alternatively it is beneficial to baseline strength ranges or
max/min values for bulk excavation in a shaft where the excavation plant stand on the excavated
material.

• Consider carefully how the term ‘and’ is used (or not used) in Baseline Statements. Some
encounters require two or more conditions to be met to be problematic, for example hard nodules
in SCL excavation need to be both excessively strong and excessively large to be a problem. In a
Baseline Statement these two parameters need to be linked with and for the Baseline Statement to
be effective. Where no linkage is required the use of ‘and’ could inadvertently invalidate the
intention of individual statements. Best practice would be to keep Baseline Statements as short
and simple as possible with the use of formatting to separate them (bullet points for instance).

• Within any group of specific construction technique Baseline Statements avoid inadvertently
baselining the same condition more than once as this can lead to errors. This situation could arise
when tabulating strata boundary elevations for one Baseline Statement and for another, separately
listing strata units to be encountered within specific sub-units of a structure.

• When baselining the groundwater levels or pore pressures that will be encountered consider the
values adopted in the Baseline Statement in relation to abstraction or depressurisation activities of
third parties and their timing.

AUTHORS

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 34 of 35

John Davis EurGeol CGeol MSc DIC - Geotechnical Consulting Group


John was seconded to the Chief Engineers Group within Crossrail from Geotechnical Consulting
Group LLP from 2009 until July 2016.

Within the Chief Engineers Group John was responsible for all Crossrail geotechnical matters
east of Farringdon. Whilst at Crossrail John was also closely involved with the production of
Geotechnical Baseline Reports for all the major Civils contracts. Prior to Crossrail John spent
20+ years as a geotechnical designer working on a diverse range of structures across the world,
these included deep basements, embankments, tunnels, slopes and retaining walls. John was
seconded to London Underground for a couple of years in the mid 90’s where he led a research
programme on the impact of rising groundwater on the tube network.

http://www.gcg.co.uk

ICE Publishing
Free access sponsored by ICE Publishing

http://www.icevirtuallibrary.com

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18
Crossrail's Experience of Geotechnical Baseline Reports - Crossrail Learning Legacy Page 35 of 35

Tags: Geotechnical engineering

MOVING
LONDON
FORWARD

Privacy and Cookies Accessibility


Terms and Conditions

© Crossrail Ltd 2018

https://learninglegacy.crossrail.co.uk/documents/crossrails-experience-of-geotechnical-baselin... 23-Jan-18

You might also like