25/3/2017 TO 25/3/2018 WEATHER TEMPERATIURE REPORT ELCOMETERE RL10413
TIME RELATIVE HUMIDITY SURFACE TEMPERATURE AIR TEMPERATURE DEW POINT TEMPERATURE REMARK
7:00AM 9.4 26.0◦C 26.3◦c 4.0◦C ACCEPTED
9:00AM 15.0◦C 34.9◦C 29.1c◦ 2.2◦C ACCEPTED
11:30AM 19.4◦C 44.6◦C 34.4c◦ 1.7◦C ACCEPTED
4:30PM 11.6◦ 40.5◦C 31.6◦ 3.9◦C ACCEPTED
.
DNGO INSPECTION QUALITY ( THIRD PARTY ) GROUPTypsa
NAME ISMAIL AZIZ MOHAMMED SAMIUDDIN MANOLITO ARANAS LAZARO
Designation QC ENGINEER QC PAINTING & COATING INSPECTOR MATERIAL ENGINEER
Signature/Date
PROJECT Startegic water stprage Tanks -TGSW Reference 180◦ to270◦
CONSULTANT GROUPTypsa DATE 22/07/2017
CONTRACTOR Dngo INSTRUMENT ELCOMETER PF 12576
PAINTING MATERIAL PENGUARD PRIMER INSPECTION PRIMER DFT
TANK NO 1 CALIBRATION DATE : 25/3/217,EXP 25/5/2018
COURSE NO 1
INTERNAL TANK PRIMER DFT
SL NO ORIENTATION ACTIVITY PAINTING Material RESULT (REQ.40-100mic) REMARK
1 PLATE 1 PRIMER DFT PEN GUARD PRIMER 62.2 MIC 50,69,65,72,55