Project Status Report

Project Title: Design, Analysis and Development of Omnidirectional Wind turbine.

Project Guide: Mr. A. Ravinthiran

Batch No: E8

Report Date: 18-01-19

Reporting Period: 27-12-18 to 18-01-19

Current Status:
 The design process is carried out the various designs are
implemented in the solidworks. The Material requirement and
purchase details are analysed with the help of experts.

Areas of Concern:
 For the flow analysis the preparatory errors in the design is to
be resolved as soon as possible.
 The Manufacturing Process Plan or Manufacturing layout is to
be prepared for the ease of fabrication and further references.
 The Detailing drawing sheet of the design is to be prepared for
the fabrication inputs.
 The Documentation work is to be done side by side along with
the fabrication for limiting the work load.

Suggestion:
 The Discussion with our Guide we resolve the issue of analysis.
 We interacted with the well-known fabricators in this field and the
common errors and basic functions for the fabrication to make easy for
the completion of the fabrication.

Plan for next Review:


 The design is finalised and the analysis is to be completed. The
analysis reports are to be generated.
 The Material purchase is done for the initial stage and the other
supplementary accessories are also to be prepared.