You are on page 1of 16

Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 3 3 3 3 3 2 2 3

(coverage / m)
150 0 150 150 0 150 0 85.71

No's UT techs: 1 1 1 1 1 1 1 1.00

(Nos: KP#'s)
36 0 51 27 0 27 0 20.14

Draughtsman 1 1.00

(Iso DRG / m)
0 0.00

Weeky Status MFL (m) UT (KP#) DRG - No's


Progress meters Anomaly KP# GVI DRG meters
Actual (Total)
600 -- 141 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):

Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI02/BARIK - MFL + MUT

Anomalies reported:
No's:

Activities planned next week:


Tag / location: OM.BRK.OQBI02

Issues / Delays:
COMMENTS / Action Party: No work due to the driver shift change.
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 2 2 2 2 2 2 2 2

(coverage / m)
150 0 0 0 0 150 0 42.86

No's UT techs: 1 1 1 1 0 0 0 0.57

(Nos: KP#'s)
13 0 0 0 0 0 0 1.86

Draughtsman

(Iso DRG / m)

Weeky Status MFL (m) UT (KP#) DRG - No's


Progress meters Anomaly KP# GVI DRG meters
Actual (Total)
300 -- 13 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):

Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI02/BARIK - MFL + MUT

Anomalies reported:
No's:

Activities planned next week:


Tag / location: OM.BRK.OQBI02

Issues / Delays:
COMMENTS / Action Party: No work due to the Barik station Operator was not avialable.
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 2 2 2 2 2 2 2 2

(coverage / m)
0 0 150 150 150 0 0 64.29

No's UT techs: 0 0 0 0 0 0 0 0.00

(Nos: KP#'s)
0 0 0 0 0 0 0 0.00

Draughtsman

(Iso DRG / m)

Weeky Status MFL (m) UT (KP#) DRG - No's


Progress meters Anomaly KP# GVI DRG meters
Actual (Total)
450 -- 0 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):

Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI02/BARIK - MFL + MUT

Anomalies reported:
No's:

Activities planned next week:


Tag / location: OM.BRK.OQBI02

Issues / Delays:
COMMENTS / Action Party:
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 2 2 2 2 2 2 2 2

(coverage / m)
150 0 0 150 150 150 150 107.14

No's UT techs: 0 0 0 0 0 0 0 0.00

(Nos: KP#'s)
0 0 0 0 0 0 0 0.00

Draughtsman

(Iso DRG / m)

Weeky Status MFL (m) UT (KP#) DRG - No's


Progress meters Anomaly KP# GVI DRG meters
Actual (Total)
750 -- 0 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):

Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI02/BARIK - MFL + MUT

Anomalies reported:
No's:

Activities planned next week:


Tag / location: OM.BRK.OQBI02

Issues / Delays:
COMMENTS / Action Party:
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 2 2 2 2 2 2 2 2

(coverage / m)
150 150 150 150 0 0 150 107.14

No's UT techs: 0 0 1 1 1 1 1 0.71

(Nos: KP#'s)
0 0 11 8 0 0 16 5.00

Draughtsman

(Iso DRG / m)

Weeky Status MFL (m) UT (KP#) DRG - No's


Progress meters Anomaly KP# GVI DRG meters
Actual (Total)
750 -- 35 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):

Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI02/BARIK - MFL + MUT

Anomalies reported:
No's:

Activities planned next week:


Tag / location:

Issues / Delays:
COMMENTS / Action Party:
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 2 2 2 2 NIL NIL 3 2


(coverage / m) 150 85 150 150 NIL NIL 150 137.00

No's UT techs: 1 1 1 1.00


(Nos: KP#'s) 22 33 16 23.67

Draughtsman
(Iso DRG / m)
Weeky Status MFL (m) UT (KP#) DRG - No's
Progress meters Anomaly KP# GVI DRG meters
Actual (Total) #VALUE! -- 71 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):
Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI06/BARIK - MFL + MUT
Anomalies reported:
No's:
Activities planned next week:
Tag / location:
Issues / Delays:
COMMENTS / Action Party:
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI SAT (AVE)

No of MFL Tech's: 2 2 2 2 NIL NIL 2 2


(coverage / m) 150 150 150 150 NIL NIL 150 150.00

No's UT techs: 1 1 1 1 NIL NIL 1 1.00


(Nos: KP#'s) 30 15 15 12 NIL NIL 15 17.40

Draughtsman
(Iso DRG / m)
Weeky Status MFL (m) UT (KP#) DRG - No's
Progress meters Anomaly KP# GVI DRG meters
Actual (Total) #VALUE! -- #VALUE! 0
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):
Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI02,OM.BRK.OQBI06/BARIK - MFL + MUT
Anomalies reported:
No's:
Activities planned next week:
Tag / location:
Issues / Delays:
COMMENTS / Action Party: No Work on Thursday Friday due to unavailability of operator and driver
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI

No of MFL Tech's: 2 2 2 2 2 2
(coverage / m) 150 150 150 150 150 150

No's UT techs: 1 1 1 1 1 1
(Nos: KP#'s) 15 15 15 15 15 15

Draughtsman
(Iso DRG / m)
Weeky Status MFL (m) UT (KP#)
Progress meters Anomaly KP# GVI
Actual (Total) 1050 -- 105
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):
Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI06/BARIK - MFL + MUT
Anomalies reported:
No's:
Activities planned next week:
Tag / location:
Issues / Delays:
COMMENTS / Action Party:
SAT (AVE)

2 2
150 150.00

1 1.00
15 15.00

DRG - No's
DRG meters
0
Acet / Area: Qarn Alam / Bairk

CONTRACTOR: Hi-tech

SUN MON TUE WED THUR FRI

No of MFL Tech's: 2 2
(coverage / m) 150 150

No's UT techs: 1 1
(Nos: KP#'s) 15 15

Draughtsman
(Iso DRG / m)
Weeky Status MFL (m) UT (KP#)
Progress meters Anomaly KP# GVI
Actual (Total) 300 -- 30
Actual Inspection completed:
Tag ID's ( Reporting /CIMS status):
Ongoing Activities:
Tag ID / Location: OM.BRK.OQBI06/BARIK - MFL + MUT
Anomalies reported:
No's:
Activities planned next week:
Tag / location:
Issues / Delays:
COMMENTS / Action Party: MONDAY TUESDAY NO JOB DUE TO RAMADAN.
SAT (AVE)

2
150.00

1.00
15.00

DRG - No's
DRG meters
0