JULY 2016
GAUTENG PROVINCE
Page 2 of 20
Table of Tables
Table 1: Project objectives and desired outcome .............................................................................................. 6
Table 2: Project Management Team Structure .................................................................................................. 9
Table 3: Time Frames Related to the Project ................................................................................................... 10
Table 4: Option 1 Professional Fees ................................................................................................................. 11
Table 5: Option 2 Professional Fees ................................................................................................................. 12
Table 6: Option 3 Professional Fees ................................................................................................................. 13
Table 7: Option 1 Cash Flow Projection ........................................................................................................... 13
Table 8: Option 2 Cash Flow Projection ........................................................................................................... 14
Table 9: Option 3 Cash Flow Projection ........................................................................................................... 14
Table 10: Reporting Deliverables ..................................................................................................................... 16
Page 3 of 20
1. EXECUTIVE SUMMARY
MORAD Consulting Engineers was appointed by Mogale City Local Municipality for the
Upgrade of Ubuntu Arts & Crafts Centre Project. This Project Charter forms part the
Consultants’ appointment and covers the strategy for the planning, designing, tender
documentation and contract administration of the upgrade of Ubuntu Arts & Crafts
Centre as per the subject project requirements.
Morad undertook site investigations at Ubuntu Arts & Crafts Centre with the view of
establishing the extend of deterioration of the facilities as well as the leaking of the
roof. The investigations showed that there is need to upgrade the Ubuntu Arts & Crafts
Centre as follows:
The allocated budget for the project during this financial year is R 2 300 000.00. All of
the above listed scope of works cannot be done with the given budget. There are three
options of executing the project. The estimated construction cost for Option 1 is R
2 690 130.00 and that for option 2 is R 2 320 200.96. The estimated construction cost
for option 3 is R 2 198 863.92. All these figures include contingencies, VAT and
professional fees. The duration of the construction will be 3 months.
Page 4 of 20
2. BACKGROUND AND PROBLEM STATEMENT
Morad undertook site investigations at Ubuntu Arts & Crafts Centre with the view of
establishing the extend of deterioration of the facilities as well as the leaking of the
roof. During the investigations, it was discovered the following;
Page 5 of 20
3. OUTLINE BUSINESS CASE
Mogale City Local Municipality’s sole objective is to provide quality service delivery for
all in Mogale City. Mogale City Local Municipality has the unique opportunity to lead
this service delivery mandate in Magalisburg through the requisite strategies and
policies that they have in place. Their 2014/15 Top Layer Service Delivery and Budget
Implementation Plan (SDBIP) is one of the tools that will assist them to achieve this
mandate. It gives details of the key actions that the administration of Mogale City Local
Municipality intends to take and be accountable for during the financial year (2014/15).
According to the 2014/15 SDBIP, the Social Services Department needs to undertake
the upgrade of the Ubuntu Arts & Crafts Centre and finish it by the end of the current
financial year. See Appendix E for extracts of the Capital Expenditure tables from the
2014/15 SDBIP for the Social Services department.
To meet this target, Mogale City Local Municipality assigned Morad Consulting the
Upgrade of Ubuntu Arts & Crafts Centre project in-order to assist in coming up with an
engineering sound solution to upgrade the deteriorated and damaged facilities.
Quart end Sep Quart end Dec Quart end Quart end Jun 2015
2014 2014 Mar 2015
Stage 1: Prepare a Stage 2: Final Stage 3: Stage 4: Repair of the
report to request Designs and Bid Tender roof and ceilings,
Permission from the Specifications process redesign of the workshop
MM to assign the Completed. completed and related facilities.
Project and draft and
Designs. contractor
appointed
Page 6 of 20
5. PROJECT SCOPE
The project scope according to the three options is as follows;
Option 1
• Replacement of the thatched roof with tiled roof to avoid leaking.
• Repairing the tiled roofs to avoid leaking.
• Replacement of damaged ceiling.
• Replacement of damaged gutters.
• Replacement of damaged fascia board.
• Painting of the whole building exterior and interior walls.
• Refurbishment of the kitchen to make it fully functional.
• Repairing and repainting of the palisade fence.
• Redesign of the workshop and related facilities.
• Creating a shed on the outside for the workshop.
Option 2
• Replacement of the thatched roof with tiled roof to avoid leaking.
• Repairing the tiled roofs to avoid leaking.
• Replacement of damaged ceiling.
• Replacement of damaged gutters.
• Replacement of damaged fascia board.
• Refurbishment of the kitchen to make it fully functional.
• Repairing and repainting of the palisade fence.
• Redesign of the workshop and related facilities.
• Creating a shed on the outside for the workshop.
Option 3
• Replacement of the thatched roof with tiled roof to avoid leaking.
• Repairing the tiled roofs to avoid leaking.
• Replacement of damaged ceiling.
• Replacement of damaged gutters.
• Replacement of damaged fascia board.
Page 7 of 20
• Painting of the whole building exterior and interior walls.
• Repairing and repainting of the palisade fence.
• Redesign of the workshop and related facilities.
• Creating a shed on the outside for the workshop.
6. REGULATORY REQUIREMENTS
This project is not listed under the Environmental Impact Assessment Regulations
Listing Notice 1 of 2010, hence there is no need to conduct an EIA.
Page 8 of 20
estimated construction cost for option 2 is R 2 320 200.96. Option 2 only
excludes the painting of the building interior and exterior. The estimated
construction cost for option 3 is R 2 198 863.92. Option 3 only excludes the
refurbishment of the kitchen. All these figures include contingencies, VAT and
professional fees. See annexure F for a detailed cost estimate of the three
options.
Project Team
Project Team Role Organization Email
Member(s)
Executive Manager: S. Mathebula Mogale City Local shirley.mathebula@mogalecity.gov.za
Social Services Municipality
Manager: Sports, Art , Bertha Mogale City Local bertha.bogopane@mogalecity.gov.za
Culture and Recreation Bongopane Municipality
Page 9 of 20
Additional team members will be introduced as required for the successful completion
of the project. Only skilled and experienced staff, professionally registered where
appropriate, will be assigned to the project.
Inceptio
n
Concept
and
Viabilit
y
Design
develop
ment
Docume
ntation
and
Procure
ment
Workin
g
drawing
s
Constru
ction
Stage
Close
Out
Legend:
Planned Tasks
Completed Tasks
Page 10 of 20
11. PROJECT FINANCES
11.1 Professional Fees
As per Mogale City Local Municipality appointment letter to Morad Consulting
Engineers, the appointment is in line with Morad’s existing Contract
COO(PMU)01/2011 with Mogale City Local Municipality.
Fees will be calculated according to the fee scales agreed in the above contract, for
the following stages as defined in the Engineering Professions Act (Act 46 of 2000)
3.0 DISBURSEMENTS
ITEM DESCRIPTION RATE QTY AMOUNT
3.1 Travelling R 4.00 4000 R 16 000.00
3.2 Health and Safety R 500.00 4 R 2 000.00
3.2 Copies and Printing R 0.35 25000 R 8 750.00
Sub-Total Excl. VAT (Disbursements) R 26 750.00
TOTAL (Excl. 14% VAT) R 359 964.00
Add 14% VAT R 50 394.96
Page 11 of 20
Option 2 Professional Fees
3.0 DISBURSEMENTS
ITEM DESCRIPTION RATE QTY AMOUNT
3.1 Travelling R 4.00 4000 R 16 000.00
3.2 Health and Safety R 500.00 4 R 2 000.00
3.2 Copies and Printing R 0.35 25000 R 8 750.00
Sub-Total Excl. VAT (Disbursements) R 26 750.00
TOTAL (Excl. 14% VAT) R 310 464.00
Add 14% VAT R 43 464.96
Page 12 of 20
2.0 ADDITIONAL FEES
ITEM DESCRIPTION RATE QTY AMOUNT
2.1 Survey R - 1 R -
2.2 Geotechnical Investigation R - 1 R -
Sub-Total Excl. VAT (Additional Fees) R -
3.0 DISBURSEMENTS
ITEM DESCRIPTION RATE QTY AMOUNT
3.1 Travelling R 4.00 4000 R 16 000.00
3.2 Health and Safety R 500.00 4 R 2 000.00
3.2 Copies and Printing R 0.35 25000 R 8 750.00
Sub-Total Excl. VAT (Disbursements) R 26 750.00
TOTAL (Excl. 14% VAT) R 294 228.00
Add 14% VAT R 41 191.92
Page 13 of 20
OPTION 2 Cash Flow Projection
Page 14 of 20
12. PLACES OF WORK
The planning, designing, tender document and preparation for the new business
plan will be primarily carried out at the Morad Consulting Offices, at 274
Voortrekker Road, Noordheuwel. Site visits will be done to the Ubuntu Arts &
Crafts Centre in Magalisburg as necessary. Attendance of scheduled meetings
will be done at the offices of MCLM.
14. DELIVERABLES
The project deliverables for this upgrade of Ubuntu Arts & Crafts Centre project are as
follows;
Option 1
• Replacement of the thatched roof with tiled roof to avoid leaking.
• Repairing the tiled roofs to avoid leaking.
• Replacement of damaged ceiling.
• Replacement of damaged gutters.
• Replacement of damaged fascia board.
• Painting of the whole building exterior and interior walls.
• Refurbishment of the kitchen to make it fully functional.
• Repairing and repainting of the palisade fence.
• Redesign of the workshop and related facilities.
• Creating a shed on the outside for the workshop.
Option 2
• Replacement of the thatched roof with tiled roof to avoid leaking.
Page 15 of 20
• Repairing the tiled roofs to avoid leaking.
• Replacement of damaged ceiling.
• Replacement of damaged gutters.
• Replacement of damaged fascia board.
• Refurbishment of the kitchen to make it fully functional.
• Repairing and repainting of the palisade fence.
• Redesign of the workshop and related facilities.
• Creating a shed on the outside for the workshop.
Option 3
• Replacement of the thatched roof with tiled roof to avoid leaking.
• Repairing the tiled roofs to avoid leaking.
• Replacement of damaged ceiling.
• Replacement of damaged gutters.
• Replacement of damaged fascia board.
• Painting of the whole building exterior and interior walls.
• Repairing and repainting of the palisade fence.
• Redesign of the workshop and related facilities.
• Creating a shed on the outside for the workshop.
Page 16 of 20
15. MILESTONE
The main project milestone is to complete the upgrade of Ubuntu Arts & Crafts
Centre by the end of the 2014/15 financial year within the allocated budget.
Other staff shall attend the meeting when required by the Manager: Sport, Art, Culture
and Recreation.
During the execution of the project, the following reports will be prepared and
submitted
• Concept Design Report
• Preliminary Design Report
• Detail Design Report
• Monthly Technical Project Report
Page 17 of 20
• Close-out Report
Additional guidelines and standards will be consulted where required. In such cases
Morad will ensure that only recognized local and international documents are used as
the basis for any analysis or design.
Morad project team members will at all times conduct themselves in a professional
manner and act in accordance with the provisions of the Engineering Services Act (Act
46 of 2000).
Page 18 of 20
20. RISK MANAGEMENT
Each stage of the project shall be approved by the Manager: Sport, Art, Culture and
Recreation before the next stage is commenced.
Page 19 of 20
23. ACCEPTANCE
This Project Charter prepared by Morad Consulting is based on the content of the
appointment letter dated 01 October 2014 and the discussion during the Project
Specification Meeting held on 13 October 2014 at 11H00 at the Mogale City Local
Municipality Social Services Board Room in Commissioner Street, Krugersdorp.
The meeting was attended by the persons identified on the Attendance Register
attached to the Minutes of the Project Inception Meeting, included in the Annexure B.
Page 20 of 20