You are on page 1of 20

RIPARIAN CORRIDOR STUDY

FINAL PARLEYS CREEK MANAGEMENT PLAN

APPENDIX B: DETAIL DRAWINGS OF SELECTED


IMPROVEMENT TECHNIQUES

This appendix provides schematic drawings (not to scale) that illustrate the materials, form, and construction of
selected improvement techniques. These drawings are not intended to substitute for site-specific engineering design.
Site-specific calculations should be completed by a qualified hydrologist, engineer, and/or landscape architect to
determine appropriate rock sizing, structure dimensions, etc. for installation in a particular location. In most cases,
installation of these types of projects will require relevant State, County, and City permits. It is recommended that
the publications, tables, and resources provided in chapter 4 of this document be consulted prior to designing or
constructing any of these improvement measures. Particular care should be exercised when construction involves
disturbance of areas within the annual high water level of any stream.

List of Drawings:

Drawing 1. No-mow buffer


Drawing 2. Vegetated soil lifts with rock toe protection
Drawing 3. Vegetated modular block retaining wall
Drawing 4. Vegetated crib retaining wall
Drawing 5. Vegetated gabion basket retaining wall
Drawing 6. Slope flattening
Drawing 7. Storm drain outlet protection using vegetated rock
Drawing 8. Vegetated rock-lined swale
Drawing 9. Replacement of narrow-span stream crossing structures
Drawing 10. Rock-lined tailwater pool (plan view)
Drawing 11. Rock-lined tailwater pool (cross-section view)
Drawing 12. Rock step pool
Drawing 13. Gabion basket retrofit
Drawing 14. Vortex rock weir
Drawing 15. A-jacks toe protection
Drawing 16. Plan view of recommended bank stabilization installation
Drawing 17. Rock vanes with J-hooks
Drawing 18. Access steps
Drawing 19. Stabilized pervious access ramp

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-1 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 1. No-mow buffer.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-2 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 2. Vegetated soil lifts with rock toe protection.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-3 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 3. Vegetated modular block retaining wall.


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-4 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 4. Vegetated crib retaining wall.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-5 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 5. Vegetated gabion basket retaining wall.


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-6 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 6. Slope flattening.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-7 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 7. Storm drain outlet protection using vegetated rock.


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-8 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 8. Vegetated rock-lined swale.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-9 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 9. Replacement of narrow-span stream crossing structures.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-10 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 10. Rock-lined tailwater pool (plan view).


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-11 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN
DRAWING NOT TO SCALE
Drawing 11. Rock-lined tailwater pool (cross-section view).
SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-12 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 12. Rock step pool.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-13 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 13. Gabion basket retrofit.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-14 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 14. Vortex rock weir.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-15 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 15. A-jacks toe protection.


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-16 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 16. Plan view of recommended bank stabilization installation.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-17 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 17. Rock vanes with J-hooks.


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-18 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 18. Access steps.


SALT LAKE CITY OCTOBER 2010
DEPARTMENT OF PUBLIC UTILITIES B-19 BIO-WEST, INC.
RIPARIAN CORRIDOR STUDY
FINAL PARLEYS CREEK MANAGEMENT PLAN

DRAWING NOT TO SCALE

Drawing 19. Stabilized pervious access ramp.

SALT LAKE CITY OCTOBER 2010


DEPARTMENT OF PUBLIC UTILITIES B-20 BIO-WEST, INC.