Project To Do List

To be completed by: Deadline: Highlight Activities


Kim Abercrombie 6/30/2019 This Week [18 Jun - 24 Jun]

Project 1
Activity Due By Budget % Done Progress Notes
TIP: Click the drop
Planning 12/27/2018 $476.00 25% down arrows in the
Preparation 3/25/2019 $301.00 10% table header row to
filter or sort your
Task A 3/20/2019 $429.00 0% project information.
Task B 4/16/2019 $332.00 70%
Task C 5/6/2019 $471.00 10%
Task D 5/11/2019 $418.00 100%
Paperwork 5/21/2019 $150.00 0% Start After Task B is Complete
Hand-off 6/5/2019 $330.00 25%
Follow-up 6/25/2019 $353.00 50%
Highlight Settings
The tables below store settings and calculations for the Highlight Activities drop down list.
Any changes could result in errors or loss of functionality.

No Highlight No Highlight
Interval: Start: End: Due:
This Week Monday, March 25, 2019 Sunday, March 31, 2019 This Week [25 Mar - 31 Mar]
This Month Friday, March 01, 2019 Sunday, March 31, 2019 This Month [1 - 31, Mar]
This Quarter Friday, February 01, 2019 Friday, May 31, 2019 This Quarter [1 Feb - 31 May]
This Year Tuesday, January 01, 2019 Tuesday, December 31, 2019 This Year [2019]
Interval: Interval:
Last Week Monday, March 18, 2019 Sunday, March 24, 2019 Last Week [18 Mar - 24 Mar]
Last Month Friday, February 01, 2019 Thursday, February 28, 2019 Last Month [1 - 28, Feb]
Last Quarter Thursday, November 01, 2018 Thursday, January 31, 2019 Last Quarter [1 Nov - 31 Jan]
Last Year Monday, January 01, 2018 Monday, December 31, 2018 Last Year

Selected Highlight: This Week [18 Jun - 24 Jun] 0


Highlight Start
Highlight End

You might also like