Schedule for park inn hotel Project

WEEK MONTH FABRICTION INSTALLTION

VANITY LEDGE THRESHOLD VANTIY LEDGE THRESHOLD

1st WEEK 11 MAR TO 18 MAR 26 pcs 40 pcs 84 pcs

2nd WEEK 19 MAR TO 26MAR 18pcs 26 pcs 40 pcs 84 pcs

3rd WEEK 27 MAR TO 3 APRIL 22 pcs 40pcs 84 pcs 18 pcs

4th WEEK 4 APRIL TO 11 APRIL 18 pcs 22pcs 40 pcs 84 pcs

5th WEEK 12 APRIL TO 19 APRIL 22 pcs 40 pcs 84 pcs 18 pcs

6th WEEK 20 APRIL TO 27 APRIL 18 pcs 22 pcs 40 pcs 84 pcs

7th WEEK 28 APRIL TO 5 MAY 22 pcs 40 pcs 84 pcs 18 pcs

8th WEEK 6 MAY TO 13 MAY 18 pcs 22 pcs 40 pcs 84 pcs

9th WEEK 14 MAY TO 21 MAY 22 pcs 35pcs 81pcs 18 pcs

10th WEEK 22 MAY TO 29 MAY 2 pcs 24 pcs 35 pcs 81 pcs

SUM 188 pcs 195 pcs 417 pcs