You are on page 1of 46

EMPLOYER : 

MINISTRY OF PUBLIC WORKS

MAIN CONTRACTOR : 
ASIAN GROUP CO. FOR 
GENERAL TRADING & CONTRACTING  W.L.L
• Project  General Information.
• Project Description & Components.
• Location of the Site & General Layout.
• Site Staff Organization Chart.
• General Scope of  Work.
• Site Mobilization & Temporary Facilities.
• Project Planning Methodology.
• Submittals & Approvals
• Material & Procurements 
• Construction Activities.
• Power Connection procedures.
• Crew Movement.
• Construction Schedule.
• Proposed Master Schedule Plan .
• Schedule Work Break Down Structure (WBS)
• Proposed ID & Coding System
Table  of  • Calendrers
Contents  • Authorities Approvals
• General Layouts
Project Name  The Public Authority For Civil Information (PACI) 
Location Al Ahmadi
Employer Ministry Of Public Works
End User  Public Authority For Civil Information 
Contractor Asian Group for General Trading and Contracting
Contract No. 267 HMA
Contract Value  2,669,010.650 KD
Date of Enterprise 9th November 2016
Contract Duration  730 day
Project 
General Project completion  8th November 2018
Date 
Information
The building of Public Authority of Civil 
Information Consists of :

Floor Consist Of Area


2nd Basement  Car Park ‐ Stores – Pump Room – 2000
Floor Diesel Tank
1st Basement  Car Park – Electrical Substation – 2000
Floor Operator Room ‐ Multi Purpose Hall 
– Toilet 
Ground Floor Offices – Waiting Area –Clinic – 1540
Toilets ‐ Kitchen
First Floor Offices ‐ Waiting Area – Toilets ‐ 1600
Kitchen
Second Floor Head Offices – Offices ‐ Computer  1620
Room –Toilets
Project 
Lower Roof  Pump Rooms – Lift Rooms‐ Chillers – 1740
Description Water Tank
& Components Upper Roof 230
Total built up  10730
area
Location of site 
& General Layout
Project 
Manager

Planning  Quantity  Site  Site 


Surveyor
Engineer Surveyor Engineer Engineer

Supervisor Supervisor

Site Staff 
Organization 
Chart
The scope of work under this Contract comprises the construction,
completion, handing over and maintenance of work related to
Drawings, Specifications, BOQ and other Contract Documents.
All of the Contract Documents shall be complementary to each
other in defining the Scope of Work, in particular the following, but
not limited to:

 GENERAL  ELECTRICAL WORKS
 MOBILIZATION  PLUMBING
 SUBMITTALS  FIRE FIGHTING WORKS
 APPROVALS  HVAC WORKS
 PROCUREMENT  CONVEYING SYSTEM WORKS
General   EXCAVATION  INTERNAL FINISHING WORKS
Scope of    EXTERNAL FINISHING WORKS
Work  AUTHORITIES APPROVALS
 TESTING & COMMISSIONING
% of Division
0.80% 2.94%
21.67%

29.64%

10.60%

3.72% 6.65%

2.93%

2.25% 0.39%

0.22% 7.33% 5.28% 0.77%


2.80% 2.00%

2‐Site works, 2.94% 3‐Concrete, 29.64%

4‐Masonry, 6.65% 5‐Metal works, 0.39%

6‐Wood& Plastic, 0.77% 7‐Thermal& Moisture Protection, 2.00%

Scope  8‐Doors & Windows, 5.28% 9‐Finishes, 7.33%

of  Work by  10‐Specialities, 2.80% 12‐Furnishings, 0.22%


Value weight 14‐Conveying sys, 2.25% 15a‐Plumbing, 2.93%

15b‐Fire Fighting, 3.72% 15c‐HVAC, 10.60%

16‐Electrical Works, 21.67% PR, .80%
The period for Mobilization is 30 Calendar days .During the
mobilization period the following activities shall be completed:

1. Temporary access routes to, from, and upon the site.


2. Removal of top soil & other rubbish.
3. Installation of site offices, temporary fencing, gates, project sign boards.
4. Installation of temporary power, water & drainage facilities.

5. The following main documentation works shall also be carried


out during the period.

1. Submission of subcontractors for : Shoring, dewatering system data


for review & approval.
2. Submittal for approval : concrete ready mix supplier, materials for
concreting , water proofing
3. Submittal of drawings for : excavation, foundation works for review
Site  & approval.
Mobilization
& Temporary 
Facilities
‫المبـــــــني‬ ‫مكاتب‬
‫جھاز‬
‫االشراف‬

‫‪Site ‬‬ ‫الحارس‬
‫‪Mobilization‬‬
‫‪plan‬‬
Project Planning Methodology
Submittals & Approvals A B
Submittal FF LAG 10

Approval
SS LAG 10 C D
• A   Submittal date for 1st submittal to Engineer. 
• B   Submittal date for last approved submittal to Engineer .
• C   Action date for 1st submittal by Engineer.
• D   Action date for last submittal by Engineer.
The Contractor will submit Sub‐contractors, Shop drawings, Martials for approval by 
Engineers. The Submittal period will be according to the material or equipment type 

Material & Procurement 
The materials will be procured by the contractor & his subcontractors but all 
procurements will be through the main contractor only, since it is his responsibility as 
per contract conditions.
Some materials will be procured directly after taking approval on them, because they
are needed to proceed work at site, while some others will be procured later because
the priority in storing in the site is to the material needed to proceed work first.
The duration of procurement of materials will differ from materials to other
depending on its availability in Kuwait .
Procurement of material Plan
for example, and not as a limitation 

a) Early Critical Materials
DIV Material
02 Termite Control

03 Steel Reinforcement
03 Formwork Systems

03 Ready Mix concrete

07 Water Stop
07 Water Proofing Material
15a Drainage & Water supply  Pipes
c)  Long Lead Materials
DIV. Material DIV. Material
04 Exterior Stone Cladding 16 Light fittings

08 Aluminum windows & doors 16 Diesel Generator
08 Steel doors 16 Fuel Tank
08 Wooden doors
09 Ceramic & Porcelain tiles

09 Marble & Granite for floors and walls 
12 Kitchen Cabinet
14 Elevators
15 Fire Pumps
15 Plumbing Pumps
15 Fan coil unit 
15 Air handling unit 

15 Fans
15 BAS
Construction Activities
SURVEY WORK :  
The contractor shall install a permanent B.M and establish setting out for concrete work and also
verify all the angles, curves, linear measurements, levels and shall check any contradiction of the
measurements with the contract documents. The contractor representative shall submit all the
particulars to the Engineer for review and approval, upon which setting out of work shall be
based.

SHORING SYSTEM:  
The shoring system is proposed around the site excavation. The contractor shall submit design
calculations & drawings with construction techniques of H piles or soldier its bottom depth,
protection of existing services (if any) before commencing the work.
And its activities will be revised with the approved subcontractor according to his steps in works

DEWATERING :  
After the subsurface investigation the water table height shall be determined in the entire site.
The contractor shall submit the design & the detailed layout of dewatering system for the
Engineer’s approval. The dewatering system shall run 24 hours and would maintained till
downward pressure exerted by the building equals upward thrust from soil. At minimum 0.00
level according to specifications.
Site Works
All excavation will be done using machines and the backfilling will be compacted by roller plate
compactor and inspected by the engineer at different levels. Areas that are deeper than the
water table will be carried out by the use of well‐point dewatering system. Earthwork will be
carried out to complete all site clearing excavation, filling and grading including preparation of
sub‐grade for slabs and pavement. Work will include the following:
1. Excavation to the level of foundations
2. Paved areas and kerbs
3. Filling grading and compaction
4. Testing
5. Clearing away surplus excavated material

Termite Control 
Approved material for termite control will be used on site. 
The concrete will be obtained from an approved ready mix plant as per approved design mix and
will be transported to site by transit mixers by sequencing their movement in order to avoid
under waiting period. Concrete discharge to the required formwork will be arranged by concrete
pumps or by bucket crane depending upon location of casting. All precautions shall be taken
during casting at hot weather in order to guarantee quality of concrete as per specifications. All
concrete will be compacted using vibrators and casted concrete will be protected and cured as
per specifications.

Formwork
Formwork acceptable to engineer will be used taking into consideration safety and quality control
requirements. Adequate formwork will be made available at site in order to ensure speedy
progress and meet the construction milestones as presented in the construction schedule.
Reinforcement
All reinforcement steel will be cut and bent to the required details and stored in proper order of
use. All reinforcement shall be transported taking into consideration safety precautions and will
be lifted manually to fixing position or by crane depending on locations. Beam reinforcement will
be erected before slab in stages as work progresses from one end of slab to another.

Masonry walls 
All concrete blocks and block accessories will be from an approved source as per quality control
requirements. After removing shuttering of floor slab, masonry blocks works will start.

Plastering works
After completion of block work and be cured for 3 days, Plastering works will start. The 1st step 
for rendering and fix plastering accessories. The 2nd one to make the 1st coat plastering. The 3rd
will be the 2nd coat of plastering. Each coat of plaster has to be cured for 3 days.
The electro mechanical work and steel door frames have to be finished before starting the 1st
layer of plastering.

Doors and Windows
All doors and windows will be manufactured as per drawings / specifications and from an
approved source.
This item of work has 3 types: Alum doors& windows / Steel doors / Wooden doors.
‐ The Aluminum doors after painting coats and before the final painting coat.
‐ Steel & wooden doors frames will be painted and fixed to block or concrete during rendering
works and before starting the plaster. The doors will be done after floor tiling and painting
coats but before final coat.
Ceiling works
All material for ceilings like hangers, framing, supports, ceiling tiles and special finishes will be
from an approved source as per quality control requirements. All materials will be properly stored
with adequate markings. All ceiling finishes shall be carried out in accordance / coordination with
HVAC, Plumbing & Fire fighting and Electrical works on the ceiling for the anchors. The electrical
drops for fittings shall be completed along with anchors for ceiling. After all above works are
completed (ducts, pipes, … etc.), framing will start and afterwards ceiling finishes. Site fabrication
and cutting shall be as per specifications. No extra protection is required on ceiling once the area
is closed.

Painting works
After completion of plastering work and be cured for 12 days, painting works will start .
The 1st step is to work for surface preparation, primer and putty coats.
The 2nd step is to make painting coats and this will be done after finishing the electro mechanical
ducting and piping over the false ceiling .
The 3rd step will be the final coat of painting. This step will be done after finalization of finishing,
mechanical and electrical fixtures while testing and commissioning work be under progress.

Flooring works
After finishing the coats of painting the contractor will start the work of flooring tiles.
All material of floors such as mortar, marble, ceramic will be from an approved source as per
specifications. All materials will be packed and handled in such away that the shape and size are
not changed. Material will be stored at factory or at site on wooden platforms or as
recommended. Before starting of any finishing on floors, all concealed items like pipes or other
fixtures will be checked and approved by the engineer. Flooring works shall start after major
heavy works are completed.
Roofing 
Once all heavy works are completed on roof, and drainage and other inserts are fixed in place,
the area will be cleaned and roofing works starts. All roofing layers shall be as per drawings /
specifications / manufacturer recommendations. After each layer is completed, it will be
inspected / approved by the engineer before applying the next layer. After roof work works are
completed, flash up and rain water outlets and other roof fixtures shall be erected.

Mechanical works 
‐ Plumbing works
All high level and inside shafts drainage & water supply pipes will be started before block walls 
Water supply and drainage pipes inside toilets area will be installed after block works.
Installing floor drains, ,traps and cleanouts will start before water proofing.
Water closet concealed flash tanks will be installed before ceramic work. The other sanitary 
fixtures will be installed after finishing ceramic works.
Pumps, filters and GRP tanks & heaters will be installed after all mechanical room will be ready. 

‐ Fire fighting works 
Sprinklers systems, pipes upright sprinkler heads work shall be started before any block work 
Installation of Pipes, fittings, landing valves, fire cabinet fixation  will start after finish block works.  
Other sprinklers types of will be installed after finishing false ceiling. Fire protection sprinklers 
heads shall be finish to finish with ceiling suspension system . Fire cabinet and extinguishers, will 
start during painting coats.
‐ HVAC works 
Install smoke air ducts and supports will start before block work. Installing of AHU & FCU will start 
when mechanical rooms be ready. Install HVAC ducts and chilled water pipes and supports will be 
done before and during block works. Installing & connecting exhaust & fresh air fans will start 
after ceiling suspension systems. Installation of diffusers & grilles will finish with finish of ceiling 
panels.

Electrical works
‐ Cable trays installation will be followed by installing cables and wires. Then by the installation
of data communication systems, CCTV cables. Then low voltage cables and outlets, wiring
accessories and switches, low voltage equipment, fire alarm detectors, and finally light fittings
and accessories as well as earthling copper tapes and connections.
‐ The conduits & fittings for light, power, fire alarm system and public address sys. Shall be laid
in reinforcement steel before concrete casting of slab or walls.
‐ In the same way, the enclosure for distribution boards shall be fixed on the surface of block
wall or semi recessed and connects all conduits. Pull the wires for light points, wiring devices
and fire alarm system devices. Fix the support from the ceiling slab or wall for cable tray from
the LT room up to field location Fix and terminate the wiring devices once the wall is painted.

EXTERNAL CLADDING, CURTAINWALLS & GLAZING :


The external cladding would start after the completion of concrete work:
The cladding work shall be commence of GF & proceed upwards along with completion of 
concrete casting works of roof floor slab .
Installation work of curtain walls & glazing shall succeeded stone cladding and shall start after the 
completion of concrete works.
POWER Connection Procedure
K.F.D submittals & approvals
1. The contractor shall submit shop drawings & equipment of smoke ventilation , Fire
fighting System and Fire Alarm system for Ministry Engineers for Approval
2. After MPW Approval these approved drawings and equipment will be submitted to
the KFD for Approval
3. After KFD approval , subcontractor will start work in site
4. After finishing FF & FA networks above false ceiling the KFD will be asked to the 1st
inspection (Before closing the false ceiling )
5. After the Approval letter from KFD to close the false ceiling
6. After finishing all civil works and finishing of all FF & FA & Ventilation systems the
KFD will be asked for the 2nd inspection of Approval for POWER
7. The approval of KFD will be the 1st step for POWER ON
8. The 3rd appointment for KFD will be after POWER ON for testing all systems
MEW submittals & approvals
1. The contractor will submit for MEW the HVAC calculations and the Elect. load for
approval.
2. After finishing all civil works of substation and its as built drawings the MEW will be
asked for 1st inspection
3. After Approval MEW will lay high tension cable, transformers, high tension switch
gear
4. After finishing all electrical works, AS BUILT drawings will be submitted to MEW for
electrical & power load.
5. After the telephone and data system are finished, as‐built drawings will be
submitted to MOC for approval.
6. After finishing façade works, the AS BUILT drawings will be send to the MINUCIBILITY
for Approval
7. After Approval, cleaning certificate will be issued from MINUCIBILITY
8. The Approval of KFD, MEW and MINUCIBILITY will be taken to request power release
9. Field test for electrical works will be by MEW
10. After inspection & approval MEW will connect to the city main
11. POWER ON
Formwork A = 230 m2

Slab Formwork B  = 1630m2

Slab Formwork A  = 1630m2

Slab Formwork B  = 1630m2

Slab Formwork A = 1570 m2

Slab Formwork A = 2000 m2

‐ Two separate form work to be provided.
Form work ‐ No zoning for each floor.
Movement
Construction Schedule 
Structure 
Master Schedule Plan
The work breakdown structure, WBS, prepared in such a way to help in
planning and organizing the schedule activities.
To achieve the above purpose the WBS will contain FOUR primary levels
consisting of.
These levels are incorporated in the schedule as listed below :‐
Level 1: Phase
Level 2: level
Level 3: Type of work PHASE
Level 4: Area
LEVEL
Level 4: CSI Divisions of BOQ
Level 5: Activity TYPE OF WORK
WBS AREA
STRUCTURE The diagram illustrates
the WBS levels BOQ CSI DIVISION
and hierarchy. ACTIVITY
Schedule Work Break Down Structure
(WBS)
Project ID WBS Code WBS Name Project
Status

PACI-Rev1 PACI-Rev1 The Public Authority For Civil Information in Active


PACI-Rev1 PACI-Rev1.ST Start of Project Active
PACI-Rev1 PACI-Rev1.ST.GE General Active
PACI-Rev1 PACI-Rev1.ST.GE.GE General Active
PACI-Rev PACI-Rev1.ST.GE.GE.GE General Active
PACI-Rev1 PACI-Rev1.MO Mobilization Active
PACI-Rev1 PACI-Rev1.MO.GE General Active
PACI-Rev1 PACI-Rev1.MO.GE.GE General Active
PACI-Rev PACI-Rev1.MO.GE.GE.GE General Active
PACI-Rev1 PACI-Rev1.EN Engineering Active
PACI-Rev1 PACI-Rev1.EN.SB Subcontractors Active
PACI-Rev1 PACI-Rev1.EN.SB.SB Submittals Active
PACI-Rev PACI-Rev1.EN.SB.SB.CV Civil Works Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.EN.SB.SB.CV.D14 Div.14 Conveying System Active
PACI-Rev PACI-Rev1.EN.SB.SB.1 Mechanical & Electrical Works Active
PACI-R PACI-Rev1.EN.SB.SB.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.EN.SB.SB.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.EN.SB.AP Approvals Active
PACI-Rev PACI-Rev1.EN.SB.AP.CV Civil Works Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.EN.SB.AP.CV.D14 Div.14 Conveying System Active
PACI-Rev PACI-Rev1.EN.SB.AP.1 Mechanical & Electrical Works Active
PACI-R PACI-Rev1.EN.SB.AP.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.EN.SB.AP.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.EN.SH Shop Drawings Active
PACI-Rev1 PACI-Rev1.EN.SH.SB Submittals Active

Page 1 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-Rev PACI-Rev1.EN.SH.SB.CV Civil Works Active


PACI-R PACI-Rev1.EN.SH.SB.CV.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D04 DIV.04 Masonry Works Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.EN.SH.SB.CV.D14 Div.14 Conveying System Active
PACI-Rev PACI-Rev1.EN.SH.SB.1 Mechanical & Electrical Works Active
PACI-R PACI-Rev1.EN.SH.SB.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.EN.SH.SB.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.EN.SH.AP Approvals Active
PACI-Rev PACI-Rev1.EN.SH.AP.CV Civil Works Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D04 DIV.04 Masonry Works Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.EN.SH.AP.CV.D14 Div.14 Conveying System Active
PACI-Rev PACI-Rev1.EN.SH.AP.1 Mechanical & Electrical Works Active
PACI-R PACI-Rev1.EN.SH.AP.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.EN.SH.AP.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.EN.MT Materials Active
PACI-Rev1 PACI-Rev1.EN.MT.SB Submittals Active
PACI-Rev PACI-Rev1.EN.MT.SB.CV Civil Works Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D04 DIV.04 Masonry Works Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D06 DIV.06 Wood & Plastic Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.EN.MT.SB.CV.D14 Div.14 Conveying System Active

Page 2 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-Rev PACI-Rev1.EN.MT.SB.1 Mechanical & Electrical Works Active


PACI-R PACI-Rev1.EN.MT.SB.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.EN.MT.SB.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.EN.MT.AP Approvals Active
PACI-Rev PACI-Rev1.EN.MT.AP.CV Civil Works Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D04 DIV.04 Masonry Works Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D06 DIV.06 Wood & Plastic Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.EN.MT.AP.CV.D14 Div.14 Conveying System Active
PACI-Rev PACI-Rev1.EN.MT.AP.1 Mechanical & Electrical Works Active
PACI-R PACI-Rev1.EN.MT.AP.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.EN.MT.AP.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.PR Procurement Active
PACI-Rev1 PACI-Rev1.PR.AM All Materials Active
PACI-Rev1 PACI-Rev1.PR.AM.AL All Levels Active
PACI-Rev PACI-Rev1.PR.AM.AL.CV1 Civil Works Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D04 DIV.04 Masonry Works Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D06 DIV.06 Wood & Plastic Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.PR.AM.AL.CV1.D14 Div.14 Conveying System Active
PACI-Rev PACI-Rev1.PR.AM.AL.1 Mechanical & Electrical Works Active
PACI-R PACI-Rev1.PR.AM.AL.1.D15 DIV.15 Mechanical Works Active
PACI-R PACI-Rev1.PR.AM.AL.1.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO Construction Active
PACI-Rev1 PACI-Rev1.CO.SK Skeleton Active

Page 3 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-Rev1 PACI-Rev1.CO.SK.FD Foundation Active


PACI-Rev PACI-Rev1.CO.SK.FD.AA All Area Active
PACI-R PACI-Rev1.CO.SK.FD.AA.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.SK.FD.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.FD.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.SK.FD.AA.D16 DIV.16 Electrical Works Active
PACI-R PACI-Rev1.CO.SK.FD.AA.PR PROVISIONAL Active
PACI-Rev1 PACI-Rev1.CO.SK.B2 Basement 2 Active
PACI-Rev PACI-Rev1.CO.SK.B2.AA All Area Active
PACI-R PACI-Rev1.CO.SK.B2.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.B2.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.SK.B1 Basement 1 Active
PACI-Rev PACI-Rev1.CO.SK.B1.AA All Area Active
PACI-R PACI-Rev1.CO.SK.B1.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.B1.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.SK.GR Ground Floor Active
PACI-Rev PACI-Rev1.CO.SK.GR.AA All Area Active
PACI-R PACI-Rev1.CO.SK.GR.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.GR.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.SK.1F First Floor Active
PACI-Rev PACI-Rev1.CO.SK.1F.AA All Area Active
PACI-R PACI-Rev1.CO.SK.1F.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.1F.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.SK.2F Second Floor Active
PACI-Rev PACI-Rev1.CO.SK.2F.AA All Area Active
PACI-R PACI-Rev1.CO.SK.2F.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.2F.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.SK.LR Lower Roof Active
PACI-Rev PACI-Rev1.CO.SK.LR.AA All Area Active
PACI-R PACI-Rev1.CO.SK.LR.AA.D03 DIV.03 Concrete Works Active
PACI-R PACI-Rev1.CO.SK.LR.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.SK.UR Upper Roof Active
PACI-Rev PACI-Rev1.CO.SK.UR.AA All Area Active
PACI-R PACI-Rev1.CO.SK.UR.AA.D03 DIV.03 Concrete Works Active
PACI-Rev1 PACI-Rev1.CO.FI Finishes Active
PACI-Rev1 PACI-Rev1.CO.FI.B2 Basement 2 Active
PACI-Rev PACI-Rev1.CO.FI.B2.AA All Area Active
PACI-R PACI-Rev1.CO.FI.B2.AA.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.B2.AA.D04 DIV.04 Masonary Works Active

Page 4 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-R PACI-Rev1.CO.FI.B2.AA.D07 DIV.07 Thermal & Moisture Protection Active


PACI-R PACI-Rev1.CO.FI.B2.AA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.B2.AA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.B2.AA.D15 DIV.15 Mechanicl Works Active
PACI-R PACI-Rev1.CO.FI.B2.AA.D16 DIV.16 Electrical Works Active
PACI-Rev PACI-Rev1.CO.FI.B2.WA Waiting Area Active
PACI-R PACI-Rev1.CO.FI.B2.WA .D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.B2.WA .D05 DIV.05 Metals Active
PACI-R PACI-Rev1.CO.FI.B2.WA .D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.B2.WA .D10 DIV.10 Specialities Active
PACI-Rev PACI-Rev1.CO.FI.B2.OF Offices Active
PACI-R PACI-Rev1.CO.FI.B2.OF.D09 DIV.09 Finishes Active
PACI-Rev1 PACI-Rev1.CO.FI.B1 Basement 1 Active
PACI-Rev PACI-Rev1.CO.FI.B1.AA All Area Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D01 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D05 DIV.05 Metals Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D15 DIV.15 Mechanicl Works Active
PACI-R PACI-Rev1.CO.FI.B1.AA.D16 DIV.16 Electrical Works Active
PACI-Rev PACI-Rev1.CO.FI.B1.WA Waiting Area Active
PACI-R PACI-Rev1.CO.FI.B1.WA .D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.B1.WA .D05 DIV.05 Metals Active
PACI-R PACI-Rev1.CO.FI.B1.WA .D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.B1.WA .D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.B1.WA .D10 DIV.10 Specialities Active
PACI-Rev PACI-Rev1.CO.FI.B1.OF Offices Active
PACI-R PACI-Rev1.CO.FI.B1.OF.D09 DIV.09 Finishes Active
PACI-Rev PACI-Rev1.CO.FI.B1.WT Wet Area Active
PACI-R PACI-Rev1.CO.FI.B1.WT.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.B1.WT.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.B1.WT.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.B1.WT.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.CO.FI.B1.WT.D15 DIV.15 Mechanicl Works Active
PACI-Rev1 PACI-Rev1.CO.FI.GR Ground Floor Active
PACI-Rev PACI-Rev1.CO.FI.GR.AA All Area Active
PACI-R PACI-Rev1.CO.FI.GR.AA.D02 DIV.02 Site Works Active

Page 5 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-R PACI-Rev1.CO.FI.GR.AA.D04 DIV.04 Masonary Works Active


PACI-R PACI-Rev1.CO.FI.GR.AA.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.GR.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.GR.AA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.GR.AA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.GR.AA.D15 DIV.15 Mechanicl Works Active
PACI-R PACI-Rev1.CO.FI.GR.AA.D16 DIV.16 Electrical Works Active
PACI-Rev PACI-Rev1.CO.FI.GR.WA Waiting Area Active
PACI-R PACI-Rev1.CO.FI.GR.WA .D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.GR.WA .D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.GR.WA .D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.GR.WA .D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.GR.WA .D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.CO.FI.GR.WA .D15 DIV.15 Mechanicl Works Active
PACI-Rev PACI-Rev1.CO.FI.GR.OF Offices Active
PACI-R PACI-Rev1.CO.FI.GR.OF.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.GR.OF.D09 DIV.09 Finishes Active
PACI-Rev PACI-Rev1.CO.FI.GR.WT Wet Area Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.CO.FI.GR.WT.D15 DIV.15 Mechanicl Works Active
PACI-Rev1 PACI-Rev1.CO.FI.1F First Floor Active
PACI-Rev PACI-Rev1.CO.FI.1F.AA All Area Active
PACI-R PACI-Rev1.CO.FI.1F.AA.D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.1F.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.1F.AA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.1F.AA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.1F.AA.D15 DIV.15 Mechanicl Works Active
PACI-R PACI-Rev1.CO.FI.1F.AA.D16 DIV.16 Electrical Works Active
PACI-Rev PACI-Rev1.CO.FI.1F.WA Waiting Area Active
PACI-R PACI-Rev1.CO.FI.1F.WA.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.1F.WA.D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.1F.WA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.1F.WA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.1F.WA.D10 DIV.10 Specialities Active

Page 6 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-R PACI-Rev1.CO.FI.1F.WA.D15 DIV.15 Mechanicl Works Active


PACI-Rev PACI-Rev1.CO.FI.1F.OF Offices Active
PACI-R PACI-Rev1.CO.FI.1F.OF.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.1F.OF.D09 DIV.09 Finishes Active
PACI-Rev PACI-Rev1.CO.FI.1F.WT Wet Area Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D12 DIV.12 Furnishing Active
PACI-R PACI-Rev1.CO.FI.1F.WT.D15 DIV.15 Mechanicl Works Active
PACI-Rev1 PACI-Rev1.CO.FI.2F Second Floor Active
PACI-Rev PACI-Rev1.CO.FI.2F.AA All Area Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D15 DIV.15 Mechanicl Works Active
PACI-R PACI-Rev1.CO.FI.2F.AA.D16 DIV.16 Electrical Works Active
PACI-Rev PACI-Rev1.CO.FI.2F.WA Waiting Area Active
PACI-R PACI-Rev1.CO.FI.2F.WA.D02 DIV.02 Site Works Active
PACI-R PACI-Rev1.CO.FI.2F.WA.D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.2F.WA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.2F.WA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.2F.WA.D10 DIV.10 Specialities Active
PACI-R PACI-Rev1.CO.FI.2F.WA.D15 DIV.15 Mechanicl Works Active
PACI-Rev PACI-Rev1.CO.FI.2F.OF Offices Active
PACI-R PACI-Rev1.CO.FI.2F.OF.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.2F.OF.D06 DIV.06 Wood & Plastic Active
PACI-R PACI-Rev1.CO.FI.2F.OF.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.2F.OF.D10 DIV.10 Specialities Active
PACI-Rev PACI-Rev1.CO.FI.2F.WT Wet Area Active
PACI-R PACI-Rev1.CO.FI.2F.WT.D05 DIV.05 Metal Works Active
PACI-R PACI-Rev1.CO.FI.2F.WT.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.2F.WT.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.2F.WT.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.2F.WT.D10 DIV.10 Specialities Active

Page 7 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-R PACI-Rev1.CO.FI.2F.WT.D12 DIV.12 Furnishing Active


PACI-R PACI-Rev1.CO.FI.2F.WT.D15 DIV.15 Mechanicl Works Active
PACI-Rev1 PACI-Rev1.CO.FI.LR Lower Roof Active
PACI-Rev PACI-Rev1.CO.FI.LR.AA All Area Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D04 DIV.04 Masonary Works Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D08 DIV.08 Doors & Windows Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D10 DIV10 Specialities Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D15 DIV.15 Mechanicl Works Active
PACI-R PACI-Rev1.CO.FI.LR.AA.D16 DIV.16 Electrical Works Active
PACI-Rev1 PACI-Rev1.CO.FI.UR Upper Roof Active
PACI-Rev PACI-Rev1.CO.FI.UR.AA All Area Active
PACI-R PACI-Rev1.CO.FI.UR.AA.D07 DIV.07 Thermal & Moisture Protection Active
PACI-R PACI-Rev1.CO.FI.UR.AA.D15 DIV.15 Mechanicl Works Active
PACI-Rev1 PACI-Rev1.CO.FI.ST Stairs Active
PACI-Rev PACI-Rev1.CO.FI.ST.AF ALL FLOORS Active
PACI-R PACI-Rev1.CO.FI.ST.AF.D09 DIV.09 Finishes Active
PACI-R PACI-Rev1.CO.FI.ST.AF.D05 DIV.05 Metal Works Active
PACI-Rev1 PACI-Rev1.CO.FI.CV Conveying System Active
PACI-Rev PACI-Rev1.CO.FI.CV.AF ALL FLOORS Active
PACI-R PACI-Rev1.CO.FI.CV.AF.D14 DIV.14 Conveying Systems Active
PACI-Rev1 PACI-Rev1.CO.FI.Facades Facades Active
PACI-Rev PACI-Rev1.CO.FI.Facades.EL Elevation -01 Active
PACI-R PACI-Rev1.CO.FI.Facades.EL.GE DIV-04 Masonry Works Active
PACI-R PACI-Rev1.CO.FI.Facades.EL.1 DIV-08 Doors & Windows Active
PACI-Rev PACI-Rev1.CO.FI.Facades.EL1 Elevation -02 Active
PACI-R PACI-Rev1.CO.FI.Facades.EL1.GE DIV-04 Masonry Works Active
PACI-R PACI-Rev1.CO.FI.Facades.EL1.1 DIV-08 Doors & Windows Active
PACI-Rev PACI-Rev1.CO.FI.Facades.EL11 Elevation -03 Active
PACI-R PACI-Rev1.CO.FI.Facades.EL11.GE DIV-04 Masonry Works Active
PACI-R PACI-Rev1.CO.FI.Facades.EL11.1 DIV-08 Doors & Windows Active
PACI-Rev PACI-Rev1.CO.FI.Facades.EL111 Elevation -04 Active
PACI-R PACI-Rev1.CO.FI.Facades.EL111.GE DIV-04 Masonry Works Active
PACI-R PACI-Rev1.CO.FI.Facades.EL111.1 DIV-08 Doors & Windows Active
PACI-Rev1 PACI-Rev1.CL Project Close Out Active
PACI-Rev1 PACI-Rev1.CL.AT Authorities Approvals Active
PACI-Rev1 PACI-Rev1.CL.AT.GE GENERAL Active
PACI-Rev PACI-Rev1.CL.AT.GE.GE GENERAL Active

Page 8 of 9 PACI Project @ Ahmad


Project ID WBS Code WBS Name Project
Status

PACI-R PACI-Rev1.CL.AT.GE.GE.GE GENERAL Active


PACI-Rev1 PACI-Rev1.CL.TC Testing & Commissioning Active
PACI-Rev1 PACI-Rev1.CL.TC.GE General Active
PACI-Rev PACI-Rev1.CL.TC.GE.GE General Active
PACI-R PACI-Rev1.CL.TC.GE.GE.GE General Active
PACI-Rev1 PACI-Rev1.CL.SN Snag List Active
PACI-Rev1 PACI-Rev1.CL.SN.GE General Active
PACI-Rev PACI-Rev1.CL.SN.GE.GE General Active
PACI-R PACI-Rev1.CL.SN.GE.GE.GE General Active
PACI-Rev1 PACI-Rev1.HA Project Handing Over Active
PACI-Rev1 PACI-Rev1.HA.GE General Active
PACI-Rev1 PACI-Rev1.HA.GE.GE General Active
PACI-Rev PACI-Rev1.HA.GE.GE.GE General Active

Page 9 of 9 PACI Project @ Ahmad


Activity ID ( Key Definition )
&
Coding System
Activity ID
The activity ID has structured to allow easy understanding and identifying
the activity type, location and division
ID - Key Definition
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
- - - - .

Phase Level Type of Area CSI ACT. Serial


work Division

Example:
CN‐B1‐FI‐AL‐09.010
That means
Phase – Construction

ID  ‐ Key  Level – Basement 1


Definition Type of work – Finishing
Area – All area
CSI Division – 09 : Finishes
No. of Activity ‐ 010
The Public Authority For Civil Information in PACI-(1)PHASES 06-Feb-2017 16:02

Code Value Description


ST START OF PROJECT
MO MOBILIZATION
EN ENGINEERING
PR PROCUREMENT
CN CONSTRUCTION
PC PROJECT CLOSE OUT
HO HANDING OVER

© Oracle Corporation Page 1 of 1


The Public Authority For Civil Information in PACI-(2) LEVELS 06-Feb-2017 16:03

Code Value Description


GE GENERAL
SU SUBCONTRACTOR
MT MATERIAL
SH SHOP DRWAING
AM ALL MATERIAL
FD FOUNDATION
B2 BASEMENT 2
B1 BASEMENT 1
GR GROUND FLOOR
01 1ST FLOOR
02 2ND FLOOR
LR LOWER ROOF FLOOR
UR UPPER ROOF FLOOR

© Oracle Corporation Page 1 of 1


The Public Authority For Civil Information in PACI-(3)-CSI Divitions 06-Feb-2017 15:58

Code Value Description


GE General
02 Site Works
02.EX Excavation
02.SH Shoring Works
02.DW Dewatering Works
02.TC Termite Control
02.BF Backfilling
02.KS Kerb Stone
02.TS Traffic Signs
02.RM Road marking
02.BW Boundary Wall
02.AS Agriculture Soil & Plants
03 Concrete Works
03.PC Plain Concrete
03.RC Reinforced Concrete
03.SC Secreed
04 Masonry Works
04.MB Masonry Blocks
04.ST Exterior Stone Cladding
05 Metals Works
05.SS Stainless Steel Skirting
05.HR Handrail Works
05.GU Gutter & Gratings
05.CL Steel Cat Ladder
05.CH Chequred Plate Cover
06 Wood & Plastic
06.PF Parquet Flooring & Skirting
07 Thermal & Moisture Protection
07.WP Water Proofing
07.RS Roofing System
07.JF Joint filler and Gaskets
08 Doors & Windows
08.AL Aluminum Doors & Windows
08.WD Wodden Doors
08.SD Steel Doors
08.CW Curtain Walls & Glazing
08.SK Sky Light
08.OH Over Head doors
09 Finishes
10 Specialities
12 Furnishing
14 Conveying System
15 Mechanical Works
15.PL Plumbing Works
15.FF Fire Fighting
15.HV HVAC Works
16 Electrical Works
16.HV High Voltage
16.LV Low Voltage
CP Composite
CP.CM Composite
PR Provisional Items

© Oracle Corporation Page 1 of 1


We will add 3 types of calendars .

1. 7 work days ( full work days )


For activities as
concrete curing – dewatering – concrete casting

2. 6 work days ( Friday off days + holidays )


For all construction activities – Submittals for all
items

3. 5 work days ( Saturdays + Fridays + holidays off )


CALENDARS For activities as ( all ministry activities like
approvals – authority approvals – testing – snag list
Authority approvals, testing and commissioning activities are all
linked to the completion of their respective works and are included
in the schedule under a separate section.

1. The authorities’ approvals start by submitting the firefighting and smoke


ventilation systems for approval from Kuwait Fire Department (KFD)

2. The contractor will submit for MEW the HVAC calculations and the Elect.
load for approval.

3. After completing the substation civil works and approval of Elect. as‐built
drawings, the contractor will ask MEW for inspection. Upon approval, MEW
will install the high‐tension cable, transformer, and high‐tension switchgear.

4. After the contractor installs the firefighting network with its as‐built
drawings, they will request a visual inspection from KFD engineers.

Authorities 5. After closing the false ceiling and fixing all the smoke detectors and
Approvals sprinklers, the contractor will submit the as‐built drawings for KFD for the
power approval.

6. After completing the electrical works and installing the accessories, the as‐
built drawings for electrical works and power load will be submitted for MOE
for approval.
7. After the telephone and data system are finished, as‐built
drawings will be submitted to MOC for approval.

8. Upon approval, MOC. will perform a site inspection in preparation


for connecting with main TEL. lines.

9. After sanitary works are completed, as‐built drawings will be


submitted to MPW for approval.

10. Upon approval, MPW will perform a site inspection prior to


connecting the fresh water and drainage city main.

11. Upon completion of the external works, including work on the


structure, as‐built drawings will be submitted to the Municipality
for approval.

Authorities 12. After approval of item 11, a cleaning certificate will be issued from
Approvals Municipality.

13. The contractor will obtain the KFD & Municipality approvals to
apply client request to connect the power
14. MEW will provide the permanent power subject to approval of
Electricity site inspection and upon receiving the letter from
Municipality that they have no objection to connect power.

15. After releasing the power, then Testing & Commissioning will start 
for all systems such as but not limited to:
• Electrical works 
• Drainage services
• Fresh water supply
• Fire protection and fire alarm system will be finally tested for 
commissioning  by KFD .
• HVAC system
• Telephones and other low voltage systems.
• Elevators and conveying system.
Authorities
After successful testing & commissioning ,and completion of snag list 
Approvals items, the project will be ready for handing over.
Productivity Rate
(Unit/day) for Crew
Productivity Rate (Unit/day) for Crew

Productivity
No. ITEM Crew Description Unit Remarks
Rate (Unit/day)

Site Works
1 Excavation Works in Normal Soil Excavator + 3 Dump Trucks M3 300
2 Backfilling in 300mm layers Loader + Roller Compactors + 2 Dump Trucks M3 350
Concrete Works
1 Steel Reinforcement - Raft Steel Fixer + Helper Ton 0.48
2 Steel Reinforcement - Columns Steel Fixer + Helper Ton 0.35
3 Steel Reinforcement - Walls Steel Fixer + Helper Ton 0.25
4 Steel Reinforcement - solid slab Steel Fixer + Helper Ton 0.312
5 Shuttering - Columns Carpenter + Helper No. 2
6 Shuttering - Walls Carpenter + Helper m2 6
7 Shuttering - solid slab Carpenter + Helper m2 10
Masonry Works
1 Masonry Works (blocks 40*20*20cm) Mason + Helper M2 15
Waterproofing Works
1 Waterproofing Membrane Worker + Helper M2 40
2 Roofing Works Worker + Helper M2 5
Finishing works
1 Plaster Works - Internal Plasterer + Helper M2 40
2 Plaster Works - External Plasterer + Helper M2 30
3 Terrazzo / Ceramic / Porcelain tiles Fixer + Helper M2 30
4 Marble & stone tiles Fixer + Helper M2 5
5 Gypsum Ceiling (tiles 60 * 60) Fixer + Helper M2 20
6 Gypsum Ceiling (Board) Fixer + Helper M2 15
7 Painting Works (preperations & putty) Painter + Helper M2 50
8 Painting Works (Painting) Painter + Helper M2 100
Plumbing
1 Water supply pipes Plumber + Helper M 40
2 Drainage pipes Plumber + Helper M 40
3 Floor Drains Plumber + Helper No. 7
4 Sanitay Fixtures Plumber + Helper No. 3
Fire Fighting
1 Fire Fighting pipes Welder + Helper M 30
2 Sprinkler Heads Plumber + Helper No. 30
3 Hose & Landing Valves Plumber + Helper No. 1
4 Pumps & Storage Tanks & Equipments Plumber + Helper No. 1
HVAC Works
1 Duct works Duct Fixer + Helper Kg 90
2 Duct pipes Pipe Fixer + Helper M 30
3 FCU Fixer + Helper Nos. 4
4 Duct diffusers & grills Fixer + Helper Nos. 10
5 Air handing units & other equipments Fixer + Helper Nos. 2
Electrical Works
1 Emmbedded Conduits Electrician + Helper M 100
2 Exposed Conduits Electrician + Helper M 40
3 Cable Trays Electrician + Helper M 25
4 Distribution Board / back Box Electrician + Helper Nos. 3
5 Wiring Works Electrician + Helper M 400
6 Pulling Cables Electrician + Helper M 40
7 Earthing system Electrician + Helper M 30
8 D.B & Termination Electrician + Helper Nos. 1
9 Wiring devices Electrician + Helper Nos. 30
10 Install MSB & SMSB Electrician + Helper Nos. 22

You might also like