Professional Documents
Culture Documents
If one of the
six primary constraints changes, others may (but don’t necessarily have to) also change. The
six constraints are as follows:
• Scope
• Risk
• Resources
• Quality
• Schedule
• Budget
These six constraints are based on the original triple constraint - scope, time, and cost. Think
about your current project. What would happen if a stakeholder wanted to add more scope?
Would you need to increase the budget, extend the schedule, etc.? A big part of project
management is managing change requests as they occur.
Progressive elaboration - allows for improving and adding detail to the plan as more
information becomes available. Adding additional objectives, requirements, or scope is not
considered progressive elaboration. Progressive elaboration is adding detail to what we
already have, not adding new objectives.
PLANNING - Knowledge and Skills
These ideas discussed below are based on information provided by the PMP® Exam Content
Outline (PMI®, June 2015) and may or may not be directly referenced in the PMBOK® Guide.
management plan the project team develops both a change management plan and a
configuration management plan. Both of these plans are subsets of the project management
plan. Change management is a normal part of running a project and we should plan proactively
for change. When change requests occur, mostly as outputs from the executing and the
monitoring and controlling processes, a change management system should already be in place
to handle them.
minimum amount of input (resources and time). Efficiency is being able to produce an output
with in the minimum amount of time and utilizing the minimum amount of resources.
Efficiency is often confused with effectiveness. Effectiveness is doing the right things.
Efficiency is doing things in the right manor. In project management we think about efficiency
in many areas. For instance, in earned value management, we often use two measures of
efficiency: the schedule performance index (SPI) and cost performance index (CPI).
1. Identify customers and specify value - Define value from the point-of-view of
your end customers and then target removal of all non-value activities
2. Identify and map the value stream, the entire process that delivers value to the
customer
3. Create flow by eliminating waste - Eliminate elements of the value stream that do
5. Pursue perfection - Work toward making every asset and every action add value
is the creation of customer value with the least waste of resources in the shortest amount of
time.
1. Eliminate waste – Among the many types of waste are wasted time and effort at
3. Decide later - Make decisions as late as possible. For example, groom the
4. Deliver fast - Break a project into a series of smaller, more easily achievable
5. Amplify learning - Plan for training. Communicate often, get feedback and learn
from it.
6. Optimize the whole - View the whole project as more than the sum of its parts.
7. Build quality in - Ensure quality throughout the life of the project and not just at
the end. For example, through refactoring, - restructure existing code to improve
may affect project objectives and deliverables. The PMBOK® Guide includes regulations
from government regulatory agencies and classifies them as “government standards” among
enterprise environmental factors. These items should be planned for over the life of the
which can take time, money and resources to produce. Therefore, the project plan should
team should assess the impacts the environment may have on the project and the impacts the
project may have on the environment. Projects impacts can be social, economic, or
environmental and cant long outlive the life of the project. Again the project team should
Scope backlog – In the agile SCRUM model there are two types of backlogs.
1. The product backlog - This is a prioritized list of all the work that needs to
happen to deliver the product. The list is a living document and may be
following:
iii.Refining estimates
iv.Etc.
b. The product owner usually has authority to update the product backlog
2. The sprint backlog, which is a subset of the product backlog, that includes all the