You are on page 1of 33

Offshore Wind Power’s

Contribution to 20% Wind


Energy by 2030

December 2, 2008

Outline

Ž 20% Wind Energy by 2030: Offshore Wind Power’s


Contribution
• Jen Banks, American Wind Energy Association

Ž Recent Developments in the Offshore Wind Landscape


• Laura Smith Morton, Fulbright & Jaworski L.L.P.

Ž Government Actions to Promote Offshore Wind Energy


Production
• Jim Lanard, Bluewater Wind

1
20% Wind Energy
by 2030
Offshore Wind Power’s Contribution

Jen Banks
American Wind Energy Association

20% Wind Scenario

Ž Explores one scenario for reaching 20% wind


electricity by 2030 and contrasts it to a scenario in
which no new U.S. wind power capacity is
installed
Ž Is not a prediction, but an analysis based on one
scenario
Ž Analyzes wind’s potential contributions to energy
security, economic prosperity and environmental
sustainability
Ž Would require about 300 GW (300,000 MW) of
wind generation

2
Resource Potential Exceeds Total
Electricity Demand
180
Land-Based Offshore Deep Offshore
Class 7 Class 7
160 Class 6
Class 6
Levelized Cost of Energy, $/MWh

Class 5 Class 5
140 Shallow Offshore
Class 4 Class 4

Class 3 Class 3
120
Land-Based
100

80

60
The United Stateshas
United States hasample
amplewind
windresources,
resources,
40 including more
more than
than8,000
8,000GW GWland-based—
onshore —the
the most
most affordable
affordable type
type to to harness.
harness.
20

0
2,000 4,000 6,000 8,000 10,000
Quantity Available, GW
2010 Costs w/o PTC, w/o Transmission or Integration costs

Resource Economically Available Including


Transmission Costs Can Support 20% Wind
160 10% of existing transmission
Land-Based Offshore capacity available to wind
Class 7 Class 7
140 Class 6 Class 6
Levelized Cost of Energy, $/MWh

Class 5 Class 5

120 Class 4 Class 4

Class 3 Class 3

100

80

60

40

20

0
- 200 400 600 800 1,000
Quantity Available, GW
2010 Costs w/ PTC, $1,600/MW-mile,
2010w/o Integration
Costs costs
without PTC, $1,600/MW-mile, without Integration costs
43

3
U.S. Wind Resource Map

Wind Power Classification

Wind Resource Wind Power Wind Speeda Wind Speeda


Power Potential Density at 50 m at 50 m at 50 m
2
Class W/m m/s mph

3 Fair 300 - 400 6.4 - 7.0 14.3 - 15.7


4 Good 400 - 500 7.0 - 7.5 15.7 - 16.8
5 Excellent 500 - 600 7.5 - 8.0 16.8 - 17.9
6 Outstanding 600 - 800 8.0 - 8.8 17.9 - 19.7
7 Superb 800 - 1600 8.8 - 11.1 19.7 - 24.8
a
Wind speeds are based on a Weibull k value of 2.0

20% Wind Scenario

305 GW

Installed Capacity as of July


2008 = 19,500 MW

4
Annual Installed Capacity vs. Current Installed
Capacity
18

16

Annual Installed Capacity (GW)


Capacity additions in 20% Scenario 14

12

10

Actual installations 4
2007: 5,329 MW Projected installations
2008: 7,500 MW* 2

0
06

08

10

12

14

16

18

20

22
20

20

20

20

20

20

20

20

20
Annual GW Installed
Source*: AWEA, 2008

46 States Would Have Substantial Wind


Development by 2030

Wind Capacity
Total Installed (2030)
(GW)
0.0 - 0.1 Includes offshore wind.
0.1 - 1
1-5 The black open square in the center of a state represents
the land area needed for a single wind farm to produce the
5 - 10
projected installed capacity in that state. The brown square
> 10 represents the actual land area that would be dedicated
to the wind turbines (2% of the black open square).

5
Economic Costs of the 20% Wind Scenario

Incremental investment cost of 20%


$3000
Wind Scenario
$2500
2% investment
difference between
Billions of 2006 Dollars

$2000 20% Wind and


No New Wind
$1500

$1000

$500

$0
No New Wind 20% Wind

Wind O&M Costs Fuel Costs


Wind Capital Costs Conventional O&M Costs
Transmission Costs Conventional Capital Costs

Incremental Cost of Scenario Compared to Natural


Gas Consumer Savings from 2007-2030

160

140 The benefits from reduced


120
pressure on natural gas
prices across all gas users
100
would be $150 billion
Dollars*

80 (NPV), by itself exceeding


the incremental cost of
60
investing in the 20%
40 Scenario.
20

0
Incremental Fuel Gas
Natural
Cost Savings
Price Benefits

*NPV in Billions of 2006 Dollars

Source: Hand et al., 2008

6
Wind Could Lead the Fight Against Climate
Change

Million Metric Share of


2006 CO2 Sources Tons/Year Total
Power Generation 2,328 41.3%
Transportation 1,856 32.9%
Industry 862 15.3%
Residential 327 5.8%
Commercial 210 3.7%
Other 55 1.0%
Total 5,638 100.0%
Source: US EPA Inventory of US GHG Emissions & Sinks 1990-2006

Summary: Costs & Benefits

$43 billion
Incremental direct cost to society
50 cents/month avg. hh
825 million tons of CO2
Reductions in emissions of greenhouse gasses and
annually
other atmospheric pollutants
$50 to $145 billion

8% total electric
Reductions in water consumption
17% in 2030
500,000 total with
150,000 direct jobs
Jobs created and other economic benefits
$2 billion in local
annual revenues

Natural gas use reductions and present value 11%


consumer benefits $86-214 billion

Sources: DOE, 2008 and Hand et al., 2008

7
Offshore Projects

Ž Capital cost reduction of 10%

Ž Turbines only 1/3 of installed project cost

Ž Research Development and Demonstration options


• Develop certification methods and standards
• Minimize work at sea
• Increase offshore turbine reliability
• Assess potential of ultra-large offshore turbines

20% Wind by 2030 – Key Findings

Ž 20% US wind by 2030 is feasible

Ž Even at 20%, wind still part of an overall portfolio

Ž Substantial net benefits would be realized, and would


be spread across all 50 States

Ž Consistent, long term Federal policies are needed to


realize the full potential of wind

Ž Shows that affordable, accessible wind resources are


available across the nation

8
Recent Developments in the
Offshore Wind Landscape
Laura Smith Morton, Senior Counsel
Washington, D.C.

lmorton@fulbright.com

The Political Landscape

9
Presidential Platform:
Investment in Wind Energy

"We should be building windmills all across the country . . . .”


- Barack Obama
March 11, 2008

“That’s one of the reasons I supported the energy bill that was
passed a year ago . . . because it represented a huge expansion
and investment in wind energy . . . . But it’s also a terrific tool
for economic development, especially in rural areas and places
. . . where we could generate as much as half, the equivalent of
half of the electricity needs of the United States . . . .”
- Barack Obama
May 16, 2008

Presidential Platform:
Transmission Lines

™“One of the most important infrastructure projects we


need is a whole new electricity grid. If we are going to
be serious about renewable energy, I want to be able
to get wind power from Minnesota to population
centers like Chicago . . . .”
- Barack Obama
October 30, 2008

10
Presidential Platform:
Renewable Electricity Standards

™ National Renewable Electricity Standard


● Percentage of electricity consumed in U.S. must be derived from clean,
sustainable energy sources
● Goals:
™ 2012: 10%
™ 2025: 25%

™ Federal Renewable Electricity Standard


● 2020: 30% of federal government’s electricity to come from renewable
sources

Presidential Platform:
Production Tax Credit

™Extend production tax credit for 5 years to encourage


production of renewable energy

“If we don’t get those tax incentives, those federal tax


breaks in place, then you’re going to see a whole lot of
wind power generation and industry moving to
Europe. … It’s already starting to happen.”

- Barack Obama
May 16, 2008

11
OFFSHORE WIND:
CONTRIBUTION TO 20% GOAL

™ Federal Government Progress:


● U.S. Department of Interior’s Minerals Management Service (MMS)
to publish final regulations on “Alternative Energy and Alternate
Use on the Outer Continental Shelf” by Year-End 2008

™ States Proceeding with Offshore Wind Development:


● Massachusetts
● Texas
● Delaware
● Rhode Island
● New Jersey
● On the Horizon?

Federal Lands On the OCS


™ In 2006, DOE estimated that more than 900,000 MW of potential wind
energy exists off the coasts of the United States.
● “Development of offshore wind energy technologies has the potential to
provide up to 70,000 MW of domestic generating capacity to the nation’s
electric grid by 2025.”
™ Technology White Paper on Wind Energy Potential on the U.S. Outer
Continental Shelf, Minerals Management Service, Renewable Energy and
Alternate Use Program, U.S. Department of the Interior
™ http://www.ocsenergy.anl.gov/documents/docs/OCS_EIS_WhitePaper_Wind.pdf

™ In May of 2008, DOE estimated offshore wind capacity could be about


one-sixth of total wind power generation by 2030.
● 28 of the 48 contiguous states have coastal boundaries and use 78% of the
nation’s electricity

12
Statutory Authority
™ For the seabed of the continental shelf beyond state submerged lands,
OCSLA is the authority, MMS the agency. 43 U.S.C. § 1331 et seq.

™ Before 2005, OCSLA was a statute for leasing “minerals”: oil and gas,
sulfur, and “other” minerals. 43 U.S.C. § 1337(a), (i) & (k).

™ EPAct 2005 added § 1337(p): DOI acquired the authority to manage


Alternative Energy and Alternate Use (AEAU) projects on the OCS
● DOI may “grant a lease, easement, or right-of-way” on the OCS for
facilities which “produce or support production, transportation, or
transmission of energy from sources other than oil and gas.” 43 U.S.C. §
1337(p)(1)(c).

™ Primary Statute Governing Environmental Review


● National Environmental Policy Act

13
Principal Statutes Governing
Wind Development
™ NEPA (42 U.S.C. § 4331, et seq.) ™ Endangered Species Act (16 U.S.C. §§ 1531 -
1544)
● Requires environmental impact statement ● Consultation with FWS or NFMS on
for federal actions “significantly affecting effects of action on endangered or
the quality of the human environment” threatened species before agency issues
● Triggered by siting on federal land, leases or permits
accessing federal transmission line, federal ● Triggered by acts that result in take or
grants harm to species or habitat such as site
clearing or wind turbine operations
™ Clean Water Act (33 U.S.C. § 1251, et seq.)
● Regulates discharge of dredged or fill ™ National Historic Preservation Act (16
materials into waters of the United States U.S.C. § 461 et seq.; 30 C.F.R. parts 60 & 800).
● Triggered by activities that may impact ● Applies whenever a federal “undertaking”
federal waters, including wetlands ● Agencies responsible are Advisory Council
on Historic Preservation, Tribal Historic
™ Federal Aviation Act of 1958 (49 U.S.C. § Preservation Office, State Historic
44718; 14 C.F.R. part 77) Preservation Office, and NPS
● Form requiring proposed markings and lighting
notifies FAA of proposed structures that might
affect navigable airspace ™ Migratory Bird Treaty Act (16 U.S.C. §§703-
712)
● FAA must review possible impacts to air safety
and navigation, as well as the potential or adverse ● Prohibits harm, possession, or taking of
effects on radar system migratory bird species, nests, and eggs
● Strict liability statute
● FWS is lead agency

Principal Statutes Governing


Wind Development (Cont’d)

™ Rivers and Harbors Act of 1899 (33 U.S.C. ™ Coastal Zone Management Act (16 U.S.C. §
§ 401 et seq.; 33 C.F.R. parts 320-331 & 40 C.F.R. part
230) 1451 et seq.)
● Regulates obstructions to navigable waters of the
● States with federally-approved programs for
United States coastal zone management play major role in siting
wind facilities along the coast and offshore
● U.S. Army Corps of Engineers issues permits.
● Applicant for a federal license or permit to
conduct an activity “affecting any land or water
™ Marine Mammal Protection Act (16 U.S.C. use or natural resource of the coastal zone of that
§ 1361 et seq.) state” must certify that activity will be conducted
“in a manner consistent with the program”
● Imposes “moratorium” on the “taking” of marine
mammals. Lead agency either FWS or NMFS
● Exceptions relevant to wind development ™ Resource Conservation and Recovery
offshore: intentional take authorization, incidental
harassment authorization Act (42 U.S.C. § 6901 et seq.)
● Requires waste generators to determine whether
they generate hazardous waste
™ Clean Air Act (42 U.S.C. § 7401 et seq.) ● If any, determine how much they generate and
● Requires EPA (or authorized State agency) to notify the responsible regulatory agency
issue a permit before construction of any new
major stationary source or major modification of a
stationary source of air pollution ™ Marine Protection, Research, and
Sanctuaries Act of 1972 (33 U.S.C. § 1401, et
seq.)
™ Magnuson-Stevens Fishery ● Prohibits, with certain exceptions, the dumping or
Conservation and Management Act (16 transportation for dumping of materials into ocean
U.S.C. § 1801 et seq.) waters without a permit from the EPA
● Federal agencies must consult with the NMFS on ● Army Corps of Engineers issues permits
proposed Federal actions that may adversely affect
Essential Fish Habitats

14
PROGRESS ON THE
DEPARTMENT OF INTERIOR’S
ALTERNATIVE ENERGY PROGRAM

MMS Alternative Energy Program:


Progress Made

™Final Programmatic EIS (PEIS) (issued Nov. 2007)


™http://www.ocsenergy.anl.gov/
● Record of Decision (Jan. 2008)
™ http://www.ocsenergy.anl.gov/documents/docs/OCS_PEIS_ROD.PDF
● Adoption of 52 Best Management Practices
™Interim Policy for Leasing (issued Nov. 2007)
● Over 40 nominations received
● Lease Form & Information Collection
● Stakeholder meetings with State agencies

15
MMS Alternative Energy Program:
Progress Made

™ Regulations (proposed July 11, 2008) 73 Fed. Reg. 39376


™ http://www.mms.gov/offshore/AlternativeEnergy/Assets/PDFs/NPRfinalF
R07-09-08.pdf
● 283 individual comment letters submitted September 8, 2008
● Currently being reviewed by OMB and other federal agencies
● Expected to be finalized and made effective before January 21, 2009

™ Alternative Energy Study Program (Ongoing)


● Collecting information for pre-lease needs such as basic
characterization of the environment
● Creation of database of historical properties that may be impacted by
offshore wind development
● http://www.mms.gov/offshore/AlternativeEnergy/Assets/PDFs/AE_SD
P_2009_2011_FINAL.pdf

Interim Policy for Leasing


™ Interim policy on Offshore Alternative Energy Resource Assessment and
Technology Testing Activities issued Nov. 6, 2007. 72 Fed. Reg. 62673
● http://www.mms.gov/federalregister/PDFs/DataCollectionTechTesting.pdf
● Received over 40 nominations related to approval of meteorological or
marine data collection facilities

™ Lease Form MMS-0001: for short-term data collection and testing leases
issued Dec. 14, 2007. 72 Fed. Reg. 71152.
● Limited-term leases authorizing data collection and technology testing
subject to compliance with relevant federal statutes;
● Requestors must also obtain necessary approvals for the construction and
placement of associated structures on the OCS lease area;
● No priority rights for commercial sale or distribution

™ On April 18, 2008, MMS designated five areas as priorities for alternative
energy research. Ten proposed wind energy projects could go forward
in the waters offshore New Jersey, Delaware, and Georgia. 73 Fed.
Reg. 21152.

16
Proposed Rule:
Major Elements
™ Leasing Process and Issuance ™ Payments (Subpart E)
(Subpart B)
● Competitive & Noncompetitive ● Bonding & Payments
Leasing
● Commercial & Limited Leases
™ Decommissioning (Subpart I)
™ Plans (Subpart F)
● Site Assessment & Construction
& Operations ™ Alternate Use (Subpart J)
● General Activities

™ Conduct of Approved Plan


Activities (Subpart H)
● Environmental & Safety
Monitoring & Inspections

The Rule: Lease Process

™ Call for Information


™ Area Identification
™ Lease Sale Compliance Documents (e.g., EIS, ESA)
™ Proposed Notice
™ Final Notice
™ Award Lease

17
The Rule: Lease Process

™ Leases issued on a competitive basis unless there is no


competitive interest
● Section 388: Secretary shall issue a lease, easement, or right-of-way on
a competitive basis unless the Secretary determines after public notice
of a proposed lease, easement, or right-of-way that there is no
competitive interest

™ Competitive or Non-Competitive
● Competitive bidding process, possibly including auctions of proposed
sites
● Alternative methodologies for resolving lease requests from different
proponents involving overlapping areas.
● Non-competitive? Similar to negotiated agreements for conveyance of
sand or gravel on the OCS

The Rule: Lease Process

™ At each stage, MMS will conduct required Federal


environmental compliance (e.g., NEPA, ESA, MBTA,
MMPA) and technical reviews
● Applicant pays for NEPA compliance

™ Coastal States potentially impacted by proposed lease and


project retain a consulting role in leasing process
● Coastal Zone Management Act (CZMA) and individual state’s
federally-approved coastal zone management plans
● Access to grid

™ Must obtain all permits otherwise required under state or


federal law (e.g., state energy plans, Army Corps of
Engineers’ permits)

18
The Rule: Lease Types
™ Commercial Lease: Full development and power generation
● Access and operational rights to produce, sell, and deliver energy
● 6-month preliminary term
● 5-year site assessment term
● 25-year operations term; can be relinquished

™ Limited Leases: Resource/site assessment and technology testing


● Access and operational rights to conduct short-term activities
● 6-month preliminary term
● 5-year operating term
● Cannot be converted into commercial leases

™ Both types include a project easement for necessary wires, cables or


pipelines necessary for transmission and/or transportation of energy to
shore (subject to state rights)
● Can be added through an addendum to lease without separate, competitive process

The Rule: General Requirements


for Competitive Leases

™ Developer’s general eligibility (i.e., U.S. citizen or resident


alien over 18 years of age)
™ Posting of security:
● $100,000 initial bond proposed
● Additional bonds possible with site assessment and construction and
operations plans
™ Mandatory payments to U.S.
● Upfront payments of site acquisition fee or deposit on cash bonus
established through solicitation
● Ongoing rental and operating fees for site and rights-of-way and easements
™ Minimize adverse effects on marine and coastal environment
● Comply with site assessment and construction and operations plans
● Make available to MMS all data about project

19
The Rule: Plans

™ Site Assessment Plan (SAP) – describes assessment and


survey activities needed to characterize the site (applies to
commercial leases)

™ Construction & Operations Plan (COP) – describes all


activities and facilities to be installed and used to gather,
transport, transmit, generate, or distribute energy from the
lease (applies to commercial leases)

™ General Activities Plan (GAP) – describes all activities and


operations related to technology testing, siting (applies to
limited leases, ROWs, RUEs)

The Rule: Inspections

™ MMS will conduct scheduled and unscheduled inspections

● Verify that activities are conducted as outlined under the lease and
approved plan
● Determine that proper safety equipment has been installed and is
operating as provided under the approved plan

™ Lessee must develop an annual shelf inspection plan


describing type, extent, and frequency of plan inspections

20
The Rule: Decommissioning

™ Decommissioning plan
approved by MMS

™ MMS discretion to allow


structures to remain in place
for alternate use or “rigs to
reefs”

ENVIRONMENTAL STUDIES

™ AE Environmental Studies Development Plan will guide


MMS’ funding decisions, Leasing, Plan review,
Environmental Assessments and Program decisions.
™ Proposed, Ongoing, and Completed Studies include:
● Avian Workshops
● Visual Impacts on Historic Properties
● Meteorological and Wave Measurements
● Interactions between Bird Species and Wind Facilities
● Noise Impacts
● Energy Market and Infrastructure Evaluation
™ For more information on the program, see
http://www.mms.gov/offshore/AlternativeEnergy/Studies.htm

21
Technological Assessment &
Research Studies
™ Technological Standards and Safety Risk Assessments must
be addressed. Included in program are:
● Comparative Studies to Assess Offshore Wind Turbine Generators
● Inspection Methodologies for Wind Turbine Facilities
● Design Standards to Ensure Structural Safety, Reliability, and
Survivability of Wind Farms and/or Wave or Current Energy
Devices
● Accident studies

™ For more information, see


http://www.mms.gov/tarprojectcategories/AlternativeEnergy.htm

STATE INITIATIVES:
Offshore Wind Project Developments

22
Massachusetts

™ Massachusetts Ocean
Management Act enacted
May 2008
● Mandates development of a
comprehensive plan for
state waters, including
identification of offshore
wind development sites, by
December 2009

Massachusetts
™ Cape Wind
● 130 wind turbines, up to 420 MW, Horseshoe Shoal in Nantucket
Sound
● Permitting process for project components in state waters ongoing
● MMS issued a Draft Environmental Impact Statement (DEIS) and
received public comment
● FEIS anticipated by the end of 2008

™ Hull
● Mass Technology Collaborative
™ $1.7 million in a forgivable pre-development loan provided to Town of
Hull Municipal Light Plant (HMLP) for preliminary studies for a 4
turbine wind farm approximately 1.5 miles offshore
● Hull submitted an Environmental Notification Form (ENF) and
Secretary issued Scope for a DEIR
● Technical analysis ongoing

23
Texas

™ Texas General Land Office (GLO) awarded


competitively bid leases for offshore power
● Five active leases being explored for wind generation.
● First open bidding for leases in 2006
● Four leases awarded in 2007 to Wind Energy Systems
Technology, which already held lease off of Galveston
● Resource Assessment Progressing
● State Waters so not governed by MMS regulations

Delaware Offshore Wind Grant

™ June 23, 2008, Bluewater


Wind and Delmarva Power
executed a negotiated PPA
for construction of a 200
MW facility off the coast
of Rehoboth Beach,
Delaware
● 25 year contract
● 11.5 miles off coast
● Output of up to 600 MW
expected

24
Rhode Island Offshore Wind

™ State law mandates that the State must get 16 % of its energy from
renewables by 2019

™ Wind Farm Siting Study – June 2007


● State and Federal Areas identified
● Entire Rhode Island RPS (15%) to be satisfied

™ “Special Area Management Plan” funded July 2007 (ongoing)


● Leads: R.I. Coastal Resources Management Council (CRMC), Univ. RI, Sea
Grant
● Participants: MMS, ACOE, RI DEP & adjacent States
● To address Federal Consistency & State Ocean Zoning for current uses - such
as commercial fishing; habitat protection for fish, marine animals, and birds;
and marine transportation --and potential new activities, including renewable
energy development

Rhode Island Grant


™ RFP issued for company to
● design, build, finance and
operate a wind generation
facility in the waters off RI
coast
● supply at least 15% of the
energy consumed by RI’s
electricity customers

™ Grant awarded October 2008 to


Deepwater Wind LLC
● 90 day negotiation period
● Cost: $1.5 billion
● Privately funded
™ First Wind Holdings Inc.
™ D.E. Shaw & Co., L.P.
Ospraie Management LLC
of New York

25
New Jersey Grant
™ Executive Order December 2004
● Blue Ribbon Panel on Offshore
Wind
● April 2006 recommendation to seek
pilot program of up to 350 megawatts

™ Department of Environmental
Protection (DEP) commissioned 18
month, $4.5 million Ocean/Wind
Power Ecological Baseline Study of
Ocean Resources
● Covers waters 20 miles off NJ shore,
excluding Delaware Bay and other
specified areas.
● Environmental analysis (EA)
expected to be issued in summer 2009
● Construction can begin at that time

New Jersey Grant

™ Solicitation for Proposals to Develop Offshore Wind


Renewable Energy issued in October 2007
● $19 million, 5-year production credit for construction and operation
of an up to 350 MW facility
● 10% to be made available up front to support studies and permitting

™ September 2008, Board of Public Utilities (BPU) awarded


grant of $4 million to Garden State Offshore Energy
● Joint venture between PSEG Renewable Generation and Deepwater
Wind
● Anticipated to install 96 wind turbines 16-20 miles off the coast of
Atlantic City
● 345.6 MW -- over 1% of State annual electricity consumption
● Construction: 2010 at the earliest

26
New Jersey Offshore Wind
Going Forward
™ New Jersey Master Plan (October 2008)
● Offshore Wind Planning Group to be established to consider
environmental and economic impacts and various financing
models to support development
● Encourages 4 companies that lost the bid to work with the
Governor’s office, the BPU, and the DEP in order to achieve 1000
MW by 2012

™ New Goal:
● 20% of state’s power from renewables by 2020
● Includes 3,000 MW from offshore wind power
™ 800,000 homes
™ 13% of state’s energy needs

On the Horizon?

™ On the Horizon? ™ For a summary of state initiatives


● Federal Waters/OCS as of September 2008, please see
the Report issued by the U.S.
™ Carolinas
Offshore Wind Collaborative
™ Georgia
● Status of US Offshore Wind
™ Maine Development Activity by State
™ Maryland (2008) which can be
™ New York downloaded at:
™ Oregon http://offshorewind.net/Othe
r_Pages/Links%20Library/S
™ Virginia
ept%202008%20Status%20
● State Waters of%20US%20Offshore%20
™ Great Lakes Wind%20Development%20
by%20State.pdf

27
When You Think
ALTERNATIVE ENERGY,
TM
Think Fulbright.

HOUSTON • NEW YORK • WASHINGTON, D.C. • AUSTIN • DALLAS • DENVER • LOS ANGELES • MINNEAPOLIS
SAN ANTONIO • ST. LOUIS • BEIJING • DUBAI • HONG KONG • LONDON • MUNICH • RIYADH

www.fulbright.com • 866-FULBRIGHT [866-385-2744]

Government Actions
to Promote Offshore Wind
Energy Production

28
OSW needed to meet state RPS
450 MW OSW Park = ~1.6 M MWh/Yr
• VA 12% 2022 (voluntary) Elec use:106 M MWh/Yr*
• MD 20% by 2022 Elec use: 63 M MWh/Yr
• DE 20% by 2019 Elec use: 11 M MWh/Yr
• NJ 22.5% by 2021 Elec use: 79 M MWh/Yr
• NY 24% by 2013 Elec use: 142 M MWh/Yr
• RI 16% by 2020 Elec use: 7 M MWh/Yr
• MA 15% by 2020 Elec use: 55 M MWh/Yr
Database of State Incentives for Renewables and Efficiency; US EIA 2006 usage data.
*"Elec use" data reflect all electricity used for each state; RPS may be lower.

Benefits of OSW:
ES³ Plus
• Economic Security – Creates jobs and
manufacturing opportunities
• Environmental Security – Supports efforts
to fight climate change
• Energy Security – Reduces reliance on
foreign energy sources
• Consumer Protection – Guarantees stable
pricing

29
Benefits of OSW:
Emissions avoidance
Pollution avoided annually from a
450 MW offshore wind park
CO2 1.35 billion pounds
SOx 14.4 million pounds
NOx 5.17 million pounds

Source: Analysis based on data provided in “Assessment of Delaware Offshore


Wind Power”, University of Delaware. Dhanju, Whitaker, Burton, Tolman, and
Jarvis. September 2005.

The OSW Industry:


Ready for prime time
• By end of 2009, states/utilities will have:
– Issued RFPs for as many as ten OSW parks
– Selected OSW developers to begin fed/state
permitting process
• By end of 2009, OSW developers will have:
– Committed to projects valued at over $10B
– Begun development on siting, ports, vessel
construction/procurement, and
identification of turbine suppliers

30
States will play critical role in
development of OSW
• Provide incentives for U.S. manufacturing
• Job training for OSW technicians
• Adopt policies to support financeable projects
– PPAs
– Merchant with carve out for OSW-RECs
• Coordinated permitting with neighboring states
and federal government
– Coastal zone consistency
– MMS final rule

Federal government has


critical role: Executive Branch
• Publish final MMS Rule
• Single NEPA review
• Fair lease and operating fees
• Permitting
• Support additional staff positions
• Inter (and intra) agency coordination

31
Federal government has
critical role: Congress
• Enact effective PTC and carbon regulation
• Create informal Congressional OSW caucus
to support
– Regulatory refinements
– Inclusion in stimulus package of OSW
initiatives; e.g., support for manufacturing
and port facilities and technology upgrades

Thank You
For more information contact:
Jim Lanard
201.420.1195
jim@bluewaterwind.com

32
Questions?
Offshore Wind Power’s
Contribution to 20% Wind
Energy by 2030

33

You might also like