Professional Documents
Culture Documents
PM PS PDF
PM PS PDF
Long-Term Planning
Joseph Layani, PMP
Société de Transport de Montréal –
Montreal Transit Commission
Project
Project control Planning
• Report in CO • Based on engineers
(Internal order) estimates
once a month
• In a third party Maintenance
software by projects
coordinators (Eng. Planning
Dept.)
•In SAP-PM
Project execution •Based on
•Maint. Plans simulation,
• External : PO to •breakdown estimate
contractors in MM-SRV
• & projects
Project Closing and Serv. entry
•Use of Maintenance Work Centers
• Internal : PM work orders
by maintenance planners
Slide 5
Long term planning process
PM task
PM work Preventive Preventive lists
orders
maintenance maintenance
backlog ( hours / work
Infrastructure (hours/WC) centers) Infrastructure
Projects planners Maintenance planners
Estimated Corrective
projects work maintenance
hours for (hours /WC)
internal Overall based on
resources needed historic data
working PM work
orders
hours Infrastructure
Maintenance Manager
Trigger points
Engineering
Maintenance vs. Engineering
Lack of integration : Maintenance
• Impossible to compare project estimates, made in the
third party software, with the planning made in PM
o High level work area vs. PM work centers
o Annual Maint. team capacity allotted to projects : imprecise
Support & BI
deployment
Kick-off
Blueprint Realization Conversion &
(PS & BI) and tests user training
May 2012 September 2012 November 2012 December
October 2011
(6 months) (5months) (2 months) 3rd 2012
Important Considerations
Change management
• Planning tool : Department for infra. projects PS
• Cost collectors : Finance department follow Infra. projects with
WBS instead of internal orders
• Work Centers usage: Maintenance planners have to share
“their” PM work centers with Project planners
WBS
Maintenance Order
Network Activity
Link for projects
(Internal labor)
Infrastructure project planners
Project
Functional
Location
WBS
PM
Estimated Estimated
corrective work
projects work
hours /WC
hours for internal based on
work centers Total work historic data
PS hours
(Planned)
BO
Maintenance managers
• Are able to challenge their participation to projects in
regard to their preventive vs. curative objectives
o By using overall projects analysis and regular PM reporting
Maintenance planners
• Are able to react to change of project timeframe
o Overall work hours needed is adjusted once a month
Short term planning process
Slide 17
Configuration point
Slide 18
Our way to EAM consolidation
Use of Functional location in PS
• Complete Cost analysis per FLOC includes PS data
o Investment planning per location Maintenance deficit reduction
Slide 21
Joseph Layani, PMP
Société de Transport de Montréal
jlayani@stm.info