You are on page 1of 1

Topsun Energy Pvt.

Ltd
Project Schedule and Planning
Installation of Solar Home System requires several steps and preliminary surveys in order to
confirm the reliability of the project. Each phase is essential and the project will be completed
as per specified in the bidding documents. The project cycle after signing of contract will
be as per the following activities flow diagram.

Phase Step Duration

Phase 1 Detail Verification of the targeted


group of people receiving 20 Wp Fifteen Days
System

Phase 2 One Month


Procurement of the
Complete System

Phase 3 Fifteen days


Transport of system component to site

Phase 4
Sixty Days
System Installation

Phase 5 Operation and maintenance of the system For Two


Years