You are on page 1of 2

OPERATION & MAINTENANCE SERVICES

MAJOR MAINTENANCE PROGRAM


2018

SUMP PUMPS
INSTRUMENT MAINTENANCE PROGRAM
(2018-2019)

SCHEDULE & SCOPE OF WORKS


SCHEDULE & SCOPE OF WORKS HRSG3 ANNUAL MAINTENANCE PROGRAM 03 JAN 2016 – 06 FEB 2016

Table of Contents

3.0 SCOPE OF WORK FOR SUMP PUMPS INSTRUMENTATION

3.0 SCOPE OF WORK FOR INSTRUMENTATION


* Instrumentation List – refer Attachment

3.1 PRESSURE

3.1.1 Pressure Gauges


1. Check, fittings, tubing if any rusted or leakage.
2. Check for impulse tubing.
3. Checks fill of glycerin if required.
4. Calibrate gauge.
5. Fill up calibration report, spares required/consumed details.

3.2 SWITCHS
3.2.1 Level switches & Float checklist
1. Check power supply voltage.
2. Check micro switch functionality.
3. Check float switch NO/NC acting
4. Checks switch connections tightness.
5. Tight connections in JB.
6. Fill up calibration report, spares required/consumed details.