Professional Documents
Culture Documents
No: HSEC/QSP/ENG/01
PROCEDURES MANUAL Date: 20.05.2009
Table of Contents
1 TENDER PROPOSAL/PREPARATION 3
1.1 Projects 3
1.1.1 Proposal format 3
1.1.1.1 Background 3
1.1.1.2 Objective 3
1.1.1.3 Scope of Work 3
1.1.1.4 Resources 4
1.1.1.5 Timescale 4
1.1.1.6 Price 3
1.1.1.7 Terms and Conditions 3
1.2 Start up 7
1.2.1 Objective 7
1.2.2 Administration 7
1.2.3 Project planning 7
1.2.4 Delegation 8
2 INVESTIGATIONS GENERAL 11
2.1 General 11
2.1.1 Introduction 11
2.1.2 Field records 11
2.1.3 After the field trip 11
3 DESIGN 12
3.2 Calculations 13
3.5 RC detailing 28
3.5.1 General 28
3.5.2 References 28
3.5.3 Design considerations 28
3.5.4 Detailing 29
3.5.5 Drawings 29
3.5.6 Bar schedules 30
3.8 Quantities 41
4 REPORTS 41
4.1 Introduction 41
4.2 Layout 41
4.2.1 Overall structure 41
4.2.2 Headings and numbering system 43
4.3 Writing 41
4.3.1 Preparing to write 41
4.3.2 Good English 41
4.3.3 Spelling and punctuation 42
4.3.3.1 Spelling 42
4.3.3.2 Abbreviations 42
4.3.3.3 Capitals 43
4.3.3.4 Numbers 43
4.3.4 Dates 43
4.4 Illustrations 41
4.5 Format 41
4.5.1 Typing 41
4.5.2 Production 42
1 TENDER PROPOSAL/PREPARATION
The form that a particular tender/proposal takes will depend on the nature of the request and on the
potential nature and value of the proposed project. The following sections provide outlines for
tender/proposals for potential projects of different size. The outlines should be used for the sizes of
project indicated and may be adapted to meet particular project or client requirements. In each case,
the general format should be followed.
1.1 Projects
Project is an undertaking job by Hydro Solution. Projects may be small or of a large scale.
1.1.1.1 Background
This section should clarify the intent of writing a proposal to the client clearly. It should include the
details of all the communication between the client and Hydro Solutions up to the point of writing
the proposal. Client’s requests for the proposal preparation should be particularly referenced along
with the date and the nature of that request.
The Background section should also show the client that his requirements are clearly understood by
Hydro Solutions. Appropriate reference should be made to the context of the proposed project.This
section should reflect the client’s requirement clearly that there is a clear need for the services and
Hydro Solutions can oblige with those requirements. Hydro Solutions shall use any materials
provided by client at the time of the preparation of the proposal request.The proposal documents
should include the same terms and phrases as used by the client.
A complete background section should clearly indicate to the client that his proposal requirements
have been understood by Hydro Solutions with whom he has requested a proposal.
1.1.1.2 Objective
The objective of the project should be clearly stated in terms that reflect the client’s objective for the
study. The objective shall always be to meet the client’s requirement, not to complete the scope of
work. There should only be one objective. The objective should be written as per the “SMART”
acronym (Specific, Measurable, Achievable, Realistic, Time bound). When required, sub-objectives
may be set for specific tasks but they must fit with the main objective and must also be “SMART”.
3
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
PROPOSALS
value for money. Only the nature of each task should be given. The manpower requirements,
duration and price will be given in later sections of the proposal.
Within the “Scope of Work” section, there should be a sub-section which outlines the reporting tasks
for the project. These will tell the client which reports he will receive, when he will receive them and
the nature and timescale of actions expected of him in response to the reports.
1.1.1.4 Resources
This section tells the client, the resources which Hydro Solutions will mobilise to meet his
requirement. The main resources to be detailed in this section are people, equipment and office
facilities. The names of the key people should be included and reference should be made to their
CV’s in an appendix.
Standard lists of equipment and office and site facilities should be used and adapted to be relevant
to each proposal.
The client should be given the impression that Hydro Solutions is well staffed and well equipped and
that he will benefit from such staff and equipment if he places an order. This section should impart
and impression to the client that Hydro Solutions is well equipped and well staffed to comply with
the clients need and that the clients will benefit from hiring Hydro Solutions for their order
1.1.1.5 Timescale
This section should explain the appropriate time scale for the above scope of work to be completed
with above resources to the client.
For numerous tasks, Microsoft Project should be used to produce project planning chart. For a
smaller number of tasks (<10), GANNT charts or any other charts produced in Word or Excel can be
used.
The chart should clearly show individual task start and finish dates as well as those for the overall
project. Key reporting dates and/or project milestones should also be marked.
4
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
PROPOSALS
1.1.1.6 Price
This section should clarify the client on what he will have to pay for the above scope of works.
The total value of the project should be stated clearly, as should the nature of the price; fixed price
or cost plus. For small projects the price should be lump sum with no breakdown given. For cost plus
projects the price should be stated to be an estimate of the total price payable and the standard
Hydro Solutions schedule of rates should be included and referred to as an appendix.
N.B. Always refers to price, not cost. The price is what the client pays. The cost is what Hydro
Solutions pays to complete the project. Price includes cost and the profit margin for Hydro Solutions.
1.1.1.7.1 Price
For fixed price proposals the following clause should be included.
The above price is fixed and relates to the above Scope of Work, based on Hydro Solution’s current
understanding of the Client’s requirement. Should that requirement or the scope of work change the
above price will be void and a new price based on a revised scope of work will be submitted to the
Client for review and approval.
The above price is an estimate of the total price payable and relates to the above Scope of Work,
based on Hydro Solution’s current understanding of the Client’s requirement.The actual amount to
be charged to the client will be determined by the man hours expended and costs incurred by Hydro
Solution, based on the schedule of rates given on Annex *, in completing the above scope of work.
3
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
PROPOSALS
1.1.1.7.2 Payment
For fixed price proposals, following clause should be included.
The above fixed price is payable in two lump sum instalments. Fifty percent of the Project Price shall
be included with the written instruction from the Client to proceed with project. The remaining fifty
percent shall be paid upon receipt by the Client of the project final report.
For cost plus proposals,following clause should be included.
The above price is payable as an advance followed by payment of monthly invoices submitted in
arrears. An advance to the value of fifty percent of the Project Price shall be included with the
written instruction from the Client to proceed with the project. Thereafter Hydro Solutions will
submit monthly invoices based on the man hours and costs incurred by Hydro Solutions in executing
the project during the previous month.
For both, fixed price and cost plus proposals, following clause should be included.
Payment is to be made within thirty days of the date of each invoice submitted. Delay in payment
beyond thirty days may result in an interest charge at the annual rate of four percent above the
prevailing Nepal Rastra Bank Base Lending Rate.
1.1.1.7.3 Contract
The above proposal is not a contract between Hydro Solutions and the Client to undertake the scope
of works detailed herein. Prior to the initiation of the project, a project contract based on the FIDIC
Client/Consultant Agreement shall be entered into by the Client and Hydro Solutions.
1.1.1.7.4 Validity
The price and timescale given in the above proposal shall be valid for a period of forty five days from
the date on the front cover of the proposal. Following expiry of that date and if requested by the
Client a new proposal with new price and timescale will be submitted to the Client by Hydro
Solutions.
1.1.1.7.5 Confidentiality
This proposal and its contents are to remain confidential to the Client and Hydro Solutions. The
contents of this proposal document are in no way whatsoever to be divulged to any third party
outside the Client and Hydro Solutions. Failure to observe the confidentiality of the proposal will be
deemed sufficient for Hydro Solutions to withdraw the proposal and decline to enter into a project
contract with the Client.
4
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
PROPOSALS COVER
Proposal No:
Submitted to:
Prepared
Checked
Approved
Note: The signature table not to be included on the cover page of the proposal. Instead, use the
same cover page with the table right after the cover page for signatory purposes.
Proposal date
Submitted by:
5
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
PROPOSALS CONTENT PAGE
Proposal Format
Background
Objective
Scope of Work
Resources
Timescale
Price
Price
Payment
Contract
Validity
Confidentiality
6
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
START UP
1.2 Start up
1.2.1 Objective
The objective for a job completion should always be within the allocated time frame, allocated
budget and in par with appropriate applicable standards meeting the requirements of the client. It is
therefore essential that the client's requirements be understood and clarified where necessary, so
that there is no doubt about the scope of work or quality of output expected.
It is the responsibility of the Project Engineer/Team Leader to ensure that the client's requirements
are agreed and documented, and that any changes as the work proceeds are likewise agreed and
documented.
1.2.2 Administration
At the start of a new job the Director, Technical will assign a Project Engineer/Team Leader to take
responsibility. The Project Engineer/Team Leader shall select a suitable brief job name, in
consultation with the Director and advise the Hydro Solutions Administration Officer, who will
allocate a job number when required. The Administration Officer shall advise Hydro Solutions
Accounts Dept of new job names and numbers.
The job name is used as a prefix to drawing numbers and correspondence file numbers (a 3 to 5letter
job code).
Proper guidelines for correspondence system and other administrative utilities involved with a
project are still in the pipe line. It is advised that regular system of correspondence should carry on
until new guidelines are established. A written record of every correspondence incoming and
outgoing is expected for now.
7
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
START UP
1.2.4 Delegation
On all but the smallest jobs, the Project Engineer/Team Leader will normally delegate responsibility
for part of the job to someone else. It is the responsibility of the Project Engineer/Team leader to
ensure that work is only delegated to suitably qualified personnel equipped with adequate resources.
The Project Engineer/Team Leader shall provide such persons with written instructions defining the
extent of responsibility delegated, the time when the work is to be completed, a time budget, job
number and procedures for review: for design work this shall be by means of theDesign and
Development Input Output form (Form HSEC/F/DDIO/00).
8
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
ONGOING WORK
1.3.3 Reporting
Written reports from the Project Engineer should be used to inform concerned parties about
progress of the job, and to highlight any problems. The file copy should be circulated to the Manager
before filing.
1.3.4 Billing
Clients should be billed regularly and promptly as set out in the project agreement. Billing will be
undertaken by Hydro Solutions accounts staff at the request of the Project Engineer.
9
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
JOB COMPLETION
Before completion of a job the Project Engineer is responsible for ensuring that:
final reports have been written, checked and submitted (eg design report,
operation and maintenance manual, completion report, as necessary)
all calculations, files, drawings and reports have been finalized, indexed and
stored properly, after discarding superseded and obsolete material.
any material likely to be of use in future jobs has been suitably written up and
lodged in the library
10
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/PMP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
GENERAL
2 Investigations General
2.1 General
2.1.1 Introduction
Field investigations may be required for a variety of reasons, such as:-
Geological investigations
Hydrological gauging
Community and environmental studies
Engineering planning and assessment
Operation studies
11
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DADDP/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
DESIGN PROCESS
3 DESIGN
3.1 Design process
The design process for a structure will generally be as follows:
a) Assemble all relevant data
b) Set out design assumptions and criteria
c) Prepare outline design proposal
d) Independent review
e) Detailed design and drawings prepared for tracing
f) Independent review
g) Drawings traced by draftsman and signed by him/her after checking
h) Drawings checked by designer and signed by him/her after checking
i) Drawings and calculations checked by another engineer and signed by him/her after
checking. N.B calculations must be checked and signed before drawings are signed by
checker
j) Drawings recommended by Project Engineer for approval
k) Drawings approved by Technical Director
l) Drawings issued
The independent reviews at Stages (d) and (f) are helpful in avoiding abortive work, but one
or other may be omitted in some cases. They may be carried out by the Team Leader,
Project Engineer or Technical Director, and sometimes also by the client at Stage (d). The
detailed check of the calculations may be carried out before the drawings have been traced
if that is more convenient.
The design process is controlled by aDesign and Development Input and Output form
HSEC/F/DDIO/00, which should be issued by the Team Leader to the design engineer before
work starts, and should be completed (in ink) at each stage. It should be filed at the front
of the calculations. Any non-conformance with requirements should be noted by the
checker or reviewer on the design control form: if there is insufficient room, notes should
be written on a subsequent page which is referred to on Page 1.
12
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDC/00
PROJECT MANAGEMENT Prepared Approved
Date: April 24, 2019
DESIGN AND DRAWING
CALCULTAIONS
3.2 Calculations
All designs shall be prepared in SI units (see HSEC/QSP/DDU/00). Calculations may either be done on
paper or using excel spread sheet. If done on paper, the left margin should be kept clear for filing.
All calculations must be written up in such a way that they can be followed easily by another
engineer, even after the original designer has left the office. This means that they should be neat
and tidy, in logical order, and complete with explanations, cross-references etc.
The following design calculation procedures are recommended:
(a) All sources of data should be referenced and, where appropriate, attached to the calculations.
(b) Where methods are taken from manuals or text books, these should be referenced (including
the relevant editions and page numbers).
(c) All assumptions should be labelled as assumptions and clearly stated.
(d) Sketches should be incorporated into the design calculations so that the checker has a clear
idea of the designer's intentions.
(e) Do not use more significant figures than justified. The results of the calculations should reflect
the level of data available, the assumptions and the methods used. Where appropriate, an
indication of the level of accuracy should be given.
f) Results of calculations should be summarized and presented in a simple format. Where
possible, graphs should be prepared, since they provide a simple and visual check of results.
Before handing their work over for checking, designers should check their own calculations and
assemble them into logical order, omitting superseded or irrelevant material.
The calculations shall be tied into a folder on which is written the job name; work area and
calculation file number. The calculation file number shall comprise:
a) Job name
b) /CF/ (for calculation file)
c) Number related to drawing numbering system (see HSEC/QSP/DDPOD/00)
For example, the calculation file for Ankhu Khola Hydropower Project penstock is numbered
AKHP/CF/305, and could be sub-divided into AKHP/CF/305 C, M and R if necessary.
13
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDU/00
DESIGN AND DRAWING Prepared Approved
Date: April 24, 2019
PREFERRED SI UNITS
Length mm, m, km
Force N, kN 1 kg f = 9.80 N
1 t f = 9.80 kN
14
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDPOD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
PLANNING OF DRAWINGS
3.3.1 General
Planning of drawing shall be done by design engineers before actual drafting starts. Care should be
taken to reduce ambiguity in reading drawings by any third party. Drawings shall be complete, users
friendly, simple and clear. All the references relevant to design and drawings are stored in
Engineering/Admin/Formats/Drafting.
3.3.2 Drafting
In general, topographical, general layout, general arrangement drawings of major structures shall be
drawn in 1 meter. All other minor structures and details shall be drawn as 1 unit of AUTOCAD
equivalent to 1 mm.
5 letters for 2 letters for 2 letters for 1 letter 2 letters for 1 letter for
project code indicating stage component for type sequential revision code
of the drawing code code number (if any)
a) Project Code:
Start of numbering will always be the project name initials. The code will be five project
name initials. For an example: For Ankhu Khola Hydropower Project, it will be coded as
ANKHP.
15
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDPOD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
PLANNING OF DRAWINGS
b) Stage Code:
2 letter stage codesindicate the stage/phases of the project. It is shown inTable 3-3.
c) Component Code:
Individual components of the proposed project will be numbered by two digit (00-99)
categorisedas in Table 3-2:
16
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDPOD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
PLANNING OF DRAWINGS
d) Type Code:
1 letter is indicated to identify the type of drawing as inTable 3-4 :
CODE DEFINITION
A General
C Civil
E Electrical
G Geological mapping
H Health/Sanitary
L Cadastral (legal) survey
M Mechanical
N Environment
R Reinforcement
T Topographical survey map
e) Drawing No:
Two digits from 00 to 99 is indicated for drawing sequential number.
f) Revision Code:
One letter is coded for any type of revision in the drawing as in Table 3-5:
Table 3-5: Drawing Revision Code
CODE DEFINITION
17
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDPOD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
PLANNING OF DRAWINGS
For example:
ANKHP/03/50E01-2Ankhu/Tender/Powerhouse Electrical 1st drawing – 2ndin house revision
NYSHP/01/20C03-A Nyasim/Feasibility/Headworks Civil 3rd drawing – 1st Client revision
UMCHP/04/20R05 Upper Mai C/Construction/H/W Reinforcement 5th drawing-no revision
With this type of system it is necessary to have clear instructions about the filing of drawings, so that
they can be retrieved without difficulty, and to provide documentation to all users so that the system
can be understood.
ANKHP/03/50E01-3 ANKHP-03-50E01-3.dwg
NYSHP/01/20C03-A NYSHP-01-20C03-A.dwg
UMCHP/04/20R05 UMCHP-04-20R05.dwg
Additional description of drawings after the drawing shall be stored in the drawing description
properties box through save as or properties.
3.3.6 Scales
Recommended scales are 1:1, 1:2, 1:5 and multiples of 10 of these. However, 1:25 etc may be used,
but never on the same drawing as 1:20. The use of too many different scales on the same drawing
should be avoided. Where more than one scale is used, the scale should be written below each title:
all scales used should be noted in the title block and shown as a graphic scale on the drawing, to
avoid confusion when drawings are photo-reduced.
18
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDPOD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
PLANNING OF DRAWINGS
Text
GRAPHICAL
Text SCALE
Water flow
DETAILS/MINOR REVISIONS
SECTIONS
Water flow
TITLE BOX
PLAN
ADD NOTES
3.3.9 Blocks
The use of blocks is recommended for common objects. Some blocks are listed in Sample Drawing.
19
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
20
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
22
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
23
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
NO. OF
COLOR WIDTH WIDTH OCCURRANCE
COLOR
A1 A3
1 Red 0.25 0.20
2 Yellow 0.30 0.25
3 Green 0.35 0.30
4 Cyan 0.20 0.18
5 Blue 0.70 0.50
6 Magenta 1.40 1.40
7 White/ Black 0.50 0.35
8 Dark Grey 0.15 0.10
9 Bright Grey 0.15 0.10
10 Red 0.30 0.25
20 Red 0.30 0.25 “Hydro-solutions Symbol” in title block
160 Blue 0.15 0.13 “Hydro-solutions Symbol” in title block
44 Brown 0.18 0.18 “Hydro-solutions Symbol “ in title block
250 Black 0.25 0.25 “Hydro-solutions Symbol “ in title block
140 Blue 0.25 0.20 For River, Kholsi
32 Brown 0.20 0.18 For Geology hatch
210 Magenta 0.25 0.25 For Geology hatch boundary (not printable)
130 Blue 0.18 0.15
255 White 0.60 0.50 For Reinforcement
24
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
3.5.5 Dimensioning
All dimensions should be in metres or millimetres, depending on the type of drawing: the relevant
unit is defined in the notes. All dimensions in metres should be shown to at least one decimal place:
the number of decimal places on a drawing should be consistent, according to the required accuracy.
All levels should be in metres. The level datum (i.e sea level, local or arbitrary) should be stated in the
notes. Levels should be quoted to a consistent number of decimal places which reflects the expected
accuracy.
As far as possible, dimensions and levels should be written outside the structure. Sufficient
dimensions to define the structure without ambiguity, but avoid showing too many - they clutter the
drawing shall be shown.
25
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
STYLE HEIGHT
DESCRIPTION TEXT STYLE LAYER COLOR
NAME A3 A1
Text in general, e.g. 1.25 1.25 2.50
Notes, elevations, SIMPLEX-8 Text Red
2.5
inscriptions, legend
2.5 5.0
Title, main, inscriptions Sec. Title ROMAND SectionText White
Dimensions (width
SIMPLEX-8 SIMPLEX-8 Dim By Layer 1.25 2.5
factor 1.0)
3.5.7 Hatch
Hatches shall not be exploded.The outlines of hatch,that shall not be printed on paper, shall be stored in
a separate layers and hidden. Typical set of hatches are presented inTable 3-13.
26
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DRAWING STANDARDS
The line type is preferably chosen as By Layer. In AutoCAD, by selecting Linetype in Layer Manager
and clicking in Load, the different types of line type can be found. The typical line types and their
application descriptions are presented in Table 3-14.
WIDTH
LINE TYPE DESCRIPTION
(Approx.)
27
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDRD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
RC DETAILING
3.6 RC detailing
3.6.1 General
This section covers only the most common mistakes made in RC detailing. Reference should be made
to the publications listed below when necessary.
3.6.2 References
Reinforced concrete design is to be carried out to British Standards:
BS 8110 (1985) Structural use of concrete
BS 8007 (1987) Design of reinforced concrete structures for retaining aqueous liquids
Reinforced concrete detailing is to be consistent with:
BS 4466 (1987) Specification for bending dimensions and scheduling of
reinforcement for concrete
There are a number of Indian publications giving typical RC details which should be treated with
suspicion. Many details are for mild steel bars with hook anchorages, not generally used with
torsteel.
Bar type Mild steel bars are not readily available in Nepal, so should not be specified. Designs
should normally be based on Grade 415 high yield steel, but Grade 500 may be used
where that is more economical. Bar types should not be mixed at the same site.
Note that these bar strengths are not as given in BS 8110, therefore some
interpolation is necessary.
28
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDRD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
RC DETAILING
3.6.4 Detailing
Pour sequence Consider how the contractor may cast the structure dividing it into pours
and detail the reinforcement accordingly. There will usually be construction
joints:
Complexity A large number of bar marks may save money in theory but a
complex arrangement may be difficult to assemble and a costly
mistake may be made.
Congestion Allow plenty of space between bars for concrete or it will be difficult
to assemble the mat and pour concrete. Pay attention to corners,
particularly if there is an acute or oblique angle and at junctions of
walls/slabs. There can be congestion of reinforcement if some bars
are not curtailed.
Bend radius Take into account the bending radius of shear links when considering
the position of main steel.
Water bar At movement joints on slab/wall junctions allowance needs to be
made for reinforcement which may intersect a water bar of 250 mm
width.
3.6.5 Drawings
General Unless details are very simple the reinforcement should be shown on a
separate RC detail drawing not on the general arrangement or
outline drawings.
Layout Plan the drawing before drafting starts, making it easy to understand.
Generally:
• put the plan in the bottom left
• put related views together, ideally in projection
• arrange section and elevation letters sequentially
Organize drawings according to concrete pour so that all information needed at one time is
available on one or two drawings. Do not show shear reinforcement on one drawing and
main reinforcement on another for the same beam or column.
29
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDRD/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
RC DETAILING
Sections andelevation
Show viewed from the correct side, eg not from inside the rock
where a wall is cast against rock. Show the full concrete section,
including slab and beam where beams are integral with the slab; but don't show slab
reinforcement on beam sections.
Calling off Follow the standard notation shown onHSEC/F/RCTN/00.Only call
reinforcement off bars once: on plan for slabs; on elevation for walls,
beams and columns.
Bar marks Bar marks should be numbered and scheduled sequentially usually starting from 01
for a given set of RC detail drawings. It may be decided to use 01-100 for base
slab, 101 - 200 for walls etc.
The bar mark must be different for bars varying in type, diameter, length or
shape.
Varying lengths Bars of varying length may be given bar marks: 13a, 13b, 13c etc (but not using i or
o). Avoid this for small increments of say 25 mm by using a varying lap length
with a constant length of bar. Keep it simple.
Numbering There should be one set of sequentially numbered sheets for each of set
of sheets RC detail drawings.
Revisions Note that the bar schedule contains a revision letter which is unrelated to any
revision letter on the drawing: the schedule may be revised but without a revision
to the related drawing. The schedule revision letter should be written in the right
hand margin of the schedule in line with the bar marks affected.
30
HSEC ENGINEERING PROCEDURES Doc. HSEC/F/RCTN/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
RC DETAILING: TYPICAL NOTES
LEGEND
24 T 12 - 17 - 200 T1
T1 top outer layer N1 near outer layer
Bar layer: T2 top second layer N2 near second layer
B2 bottom second layer F2 far second layer
B1 bottom outer layer F1 far outer layer
Bar spacing (mm)
Bar mark
Bar diameter (mm)
Bar type: X= Grade 500 high yield type 2 deformed
T= Grade 415 high yield type 2 deformed
Number of bars
NOTES
A. Reinforced concrete to be Grade C30 (20 mm max. aggregate).
B. Nominal cover to reinforcement:
a. Foundations 75 mm
b. Above ground 40 mm
C. Minimum lap to reinforcement to be:
a. T12 500 mm
b. T16 620 mm
D. Kicker height to be 75 mm.
E. This drawing to be read in conjunction with:
a. Bar Bending Schedule
b. General arrangement drawings
c. RC detail drawings
31
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDAI/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
APPROVAL AND ISSUE
3.7.4 Approval
Drawings may only be approved by the Technical Director; furthermore, the design, check and
approval of a drawing must be by three different people.
A clean print should be made for approval purposes, unless the check print had very few corrections
made on it. This print should be submitted for approval along with the relevant Design Control Form
and calculations. The approval engineer will mark any required changes on the approval print, then
sign and date it. After all required changes have been made, he will sign the tracing.
If no significant changes are required, the approval print may subsequently be used as the office
copy.
32
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDAI/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
APPROVAL AND ISSUE
A drawing register is maintained for each job in which is recorded the drawing number, title, revision
letter, revision date (approval date), to whom issued, when, and number of copies to each
recipient.This information is also recorded on the Document Transmittal Form which is to be sent
with all drawings. (See HSEC/F/DTF/00).
The record copy is to be filed for the duration of the job, as a record of every issue of every drawing
sent out of the office.
The office copy is retained as a working copy of the current issue of each drawing. Any amendments
required shall be marked onto the office copy.
Prints for the contractor should normally be issued via the resident engineer, who will first stamp the
'Issued for construction' near the title block. (Note: The stamping needs to be done right above the
title block of the drawings.)
33
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDAI/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
APPROVAL AND ISSUE
3.7.7 Revisions
No amendment shall be made to an approved drawing or to an approved revised issue without first
changing the revision letter.
Except where a preliminary issue has been made, the first issue of a drawing will be blank in the
revision box. Subsequent issues should be given revision letters 'A', 'B' etc, and the amendment box
must be completed with a brief description of the change. Even if no changes are made to a
preliminary issue, it should still be given revision letter 'A' and 'Approved drawing' should be entered
in the amendment box before approval.
Following approval of a revised drawing, the old office copy should be discarded and replaced with a
current print.
Note:
Mind the hyphen(-) left of the number in the internal drawing file name.
34
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDRS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
REGISTRATION AND STORAGE
Record copy and office copy should be clearly stamped on each drawing booklet and should be used
accordingly. Incoming drawings which are not given a Hydro Solutions drawing number shall be stored in
box files in the drafting store, in numerical order by the incoming drawing register number. The
Drafting-in-Charge shall label the box file with the job name and incoming drawing registernumbers of
the drawings within. Drawings shall not be removed from the incoming drawings box file, except to
make copies to work with.
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/DDRS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
REGISTRATION AND STORAGE
3.8.3 Calculations
Calculations shall be written up and tied into numbered folders, as described in HSEC/QSP/DDC/00 section
3.2.These folders shall be stored in numerical order.
The design Team Leader shall maintain a register of the calculation files, listing:
file number
subject
name of designer
date of design
name of checker
date of approval
42
HSEC ENGINEERING PROCEDURES Doc. HSEC/F/DTF/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
DOCUMENTS TRANSMITTAL
FORM
HSEC/D/DTF/00
Date:
Dear XYZ,
Name: Name:
Designation: Designation:
Date: Date:
Stamp: Stamp:
Signature: Signature:
------------------ -----------------
Prepared by: Approved by:
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/F/IDS/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
INCOMING DRAWING STAMPS
Incoming No…………………………
Received Date……………………….
Signature……………………………...
Approval Stamp
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/Q/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
QUANTITIES
3.9 Quantities
On most jobs it will be necessary to calculate construction quantities from the design drawings. This
should be done using Form HSEC/F/BOM/00 (Bill of quantity measurement). This form will illustrate the
material quantity and the costs at one place. Standard practise should be as follows. Material quantities
must be defined for a project under design phase. Projects under construction should reflect the total
costs for the materials as well in the form HSEC/F/BOM/00.
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QSP/Q/00
DESIGN AND DRAWINGS Prepared Approved
Date: April 24, 2019
QUANTITIES
42
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RI/00
REPORTS Prepared Approved
Date: April 24, 2019
INTRODUCTION
4 REPORTS
4.1 Introduction
The intention of a report shall always be to convey the required information as simply and clearly as
possible. Often, we being engineers having a technical mind frame, fail to excel in the art of report writing.
This chapter of the Hydro Solutions HSEC ENGINEERING PROCEDURES manual closely resembles the style
of a report that needs to be written and it may be used as a model for report writing and presentation.
The chapter is divided into the following sections:
4.1 Introduction
4.2 Layout
4.2.1 Overall structure
4.2.2 Headings and numbering system
4.3 Writing
4.3.1 Preparing to write
4.3.2 Good English
4.3.3 Spelling and punctuation
4.4.3 Dates
4.4 Illustrations
4.5 Format
4.5.1 Typing
4.5.2 Production
4.6 Review and issue
4.6.1 Checklist
4.6.2 Approval
4.6.3 Issue
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RL/00
REPORTS LAYOUT Prepared Approved
Date: April 24, 2019
4.2 Layout
Transmittal letter
A copy of the letter of transmittal may be bound into the front of the report to identify the main recipient
and give information about the following wherever applicable.
report distribution
outline contents of separate volumes, if used
acknowledgement of help received (alternatively this could be a separate section in the report)
Hydro Solutions file reference
Table of contents
This should be included in all longer reports, giving the main headings, section numbering and page
numbers. Lists of appendices, tables, figures and drawings normally follow the table of contents: they
should indicate where each illustration can be found in the report.
Summary
A long report should normally include a summary (sometimes called an executive summary) which outlines
the principal features of the report and highlights the conclusions and recommendations. The summary
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RL/00
REPORTS LAYOUT Prepared Approved
Date: April 24, 2019
should be one to five pages plus a table of salient features. A reader should be able to get a handle on the
overall presentation through this section of the report.
Introduction
The introduction must include explanation of the aim and scope of the report, the back ground to it and
the methodology used in the report. By thus setting the context in which the report was written, the
introduction gives the reader guidance in how to interpret what he/she reads.
One paragraph of the introduction should state the reason and purpose of the report with absolute clarity.
It should refer to any terms of reference, which should normally be included as an appendix to the main
report.
Main text
The main part of the report should be organized logically under a series of chapter and section headings.
These chapters should contain all the information, ideas, factors, arguments and deductions relevant to
the subject. Facts should stand out and conclusions should be drawn on the same basis. Please avoid any
opinions.
42
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RL/00
REPORTS LAYOUT Prepared Approved
Date: April 24, 2019
It is always better to hang the second line of reference by about half an inch from the original indent. (As
shown above) In case of peer reviewed journals and books, starting the reference line with the author
names ( Abbreviated), the date of publication, title of book or the journal and then the reference of
publisher always looks good in a report.
43
HSEC ENGINEERING PROCEDURES Doc. HSEC/F/RTP/00
REPORTS TITLE PAGE Prepared Approved
Date: April 24, 2019
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/F/RSP/00
REPORTS SIGNATURE PAGE Prepared Approved
Date: April 24, 2019
-------------------------- ---------------------------------
Mr. Sanjay K. Sharma, Mr. Pushpa Chitrakar
Project Manager General Manager
Ankhu Khola Hydropower Project Hydro Solutions Engg. Consultant Pvt. Ltd.
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RW/00
REPORT WRITING Prepared Approved
Date: April 24, 2019
4.3 Writing
General
We, being engineers often lack with linguistic skills in the English language for a better writing. That’s why
it is always wise to express clear, concise and short sentences in a report.
Technical report writing obeys the rules of good English. Other basic rules are: be accurate; be brief; be
clear. Cut out any word, sentence or paragraph which is not necessary, or the reader is liable to become
bored and not bother with the report. Avoid generalizations and quote actual examples of figures where
possible.
Paragraphs
A paragraph consists of one or more sentences (usually more) all bearing on the same aspect of the
subject. A common mistake is to write a number of short paragraphs each containing only one or two
sentences. This makes the report jerky. A properly constructed paragraph should deal with only one
topic: each sentence in the paragraph should be relevant to that topic and to the preceding sentence.
Sentences
The rules of sentence construction are:
a) Keep sentences reasonably short.
b) Be prepared to substitute a full stop for 'and'.
c) Arrange sentences so that each leads naturally and logically to the next. It is unnecessary to tie
each sentence to its neighbour by connecting links such as 'since', 'because', 'therefore' or
'consequently'. If the order of sentences is right the reader will himself see the connection of
ideas.
d) Never forget that a sentence must have a verb.
e) Use direct construction without too many dependent or relative clauses.
f) Never start to write a sentence until you can 'hear' the end and it sounds well when read aloud.
Language
a) Write simple English, using short and familiar words in preference to long or obscure ones.
b) Avoid using too many adjectives. Only use words such as 'essential', 'vital' and ‘unique’ in their
true meaning.
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RW/00
REPORT WRITING Prepared Approved
Date: April 24, 2019
c) Do not use technical jargon which may not be understood by readers. Explain technical
expressions if necessary.
d) Do not use slang.
e) Do not use cliches or platitudes.
4.3.3.2 Abbreviations
Abbreviations should be avoided wherever possible. It is always wise to list out the abbreviations used
after the table of contents page in case many abbreviations are used. Care should be taken that by using
abbreviations, the reader may get confused on what is being expressed in that particular report when a lot
of abbreviations are used Except for comm.
-+on abbreviations (such as ie, eg) all abbreviations should be written out in full the first time they are used
in a report. Avoid using etcetera: it is better to be specific.
Abbreviations of a single word are normally written in lower case letters, and may be given a full stop to
make it clear that an abbreviation is being used. Abbreviations formed from the initial letters of a phrase
or names are normally written in capitals without the use of full stops (but there are exceptions, eg cif for
cost, insurance freight: refer to the dictionary). Abbreviations for units are always written in lower case
letters without full stops, except that:
i) tera- (1012, T), giga- (109, G) and mega- (106, M) are written in capitals to distinguish them from
the abbreviations for tonne, gram and milli- or metre;
ii) units named after a person are abbreviated with a capital letter, eg newton (N), volt (V), watt
(W).
Examples are given below:
max maximum
no. number
nos numbers
cif cost, insurance, freight
NPV net present value
kg kilogram
kW kilowatt
MW megawatt
GWh gigawatt-hour
42
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RW/00
REPORT WRITING Prepared Approved
Date: April 24, 2019
4.3.3.3 Capitals
Capital letters should only be used at the start of a sentence and for:
proper nouns, eg Mr Gadtaula, Kathmandu, Ankhu Khola, Monday, April
some abbreviations (see above)
words which have been given a defined meaning in a contract document, eg Works, Contract,
Site
titles, eg the Ministry of Water Resources, the Baramchi Hydropower Project, Chief District
Officer
headings (first letter of first word only)
specific references, eg Figure 2, Table 5.3, Appendix A, Adit 3, Alternative B
4.3.3.4 Numbers
In text, numbers involving more than four figures before the decimal point should be written in blocks of
three, for ease of reading. In columns, all figures should be in blocks of three, so that figures line up. Use
Decimal tabs to ensure figures are aligned. Decimal fractions are indicated by the use of a point, and
thousands are separated by a comma. If a number is less than one, always add a zero before the decimal
point.
Always leave a space between a number and its associated unit, except for degrees. No space is required
between degrees, minutes and seconds when writing angles, latitude and longitude.
Examples of numbers:
In text In text In columns
Do not write 'approximately' or 'about' followed by a number which implies an accurate measurement.
For example, a distance might be 'approximately 25 km' or '25.7 km' (implying that it has been measured
to the nearest 0.1 km) but it cannot be 'approximately 25.7 km'.
4.3.4 Dates
All reports must use the Western calendar. If it is necessary or helpful to use the Bikram Sambat calendar,
this should be in addition to the Western calendar.
43
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RI/00
REPORTS ILLUSTRATION Prepared Approved
Date: April 24, 2019
4.4 Illustrations
Illustrations such as tables, graphs and figures should be used wherever they clarify the text or save on
words. They must be chosen to serve their intended purpose, eg statistics are normally best given in a
table, but a graph would be more appropriate for showing a trend. Every illustration must be titled,
numbered and referred to in the text.
Tables are the most common illustration. They are ideally suited to presenting numerical data, but can
also be used to present other information, as for example Table 6.1 below:
Table 4.1 Use of illustrations
Type of illustration Suitability Typical size Maximum size
Graphs, key plans, maps, diagrams and sketches are all referred to as figures, and given a figure number.
They should be no larger than A3 size, for binding into the report, but A4 size is preferable.
Tables and figures should normally appear in the report at the place where they are referred to, or at the
end of that chapter. In short reports they should be numbered sequentially straight through the report
(Table 1, Table 2, etc) but for longer reports it is helpful to use a two-part numbering system, with the first
part being the chapter number or appendix letter: this means that a change in one chapter does not affect
the numbering in subsequent chapters.
Drawings should be avoided if possible, because they are too large to bind into a report. A limited number
of drawings may be folded into pockets at the back of the report, however. If more than three or four
drawings are required, it is better to photo-reduce them to A3 size so that they can be bound into the
report.
As it is said, pictures speak a thousand words on its own. Good photographs are much more effective than
words for describing a site, and should be used wherever appropriate. They are normally included in the
text at the `appropriate point, but large numbers of photographs should be put into an appendix.
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RF/00
REPORT FORMAT Prepared Approved
Date: April 24, 2019
4.5 Format
4.5.1 Typing
Lettering should be Aerial 11 scalable font, varied as given in Table 6.2 below.
Table 4.2 Lettering
Sub-headings 13 Bold
Top 1.05
Bottom 0.8
Left 1.1
Right 0.9
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RF/00
REPORT FORMAT Prepared Approved
Date: April 24, 2019
Letter spacing
Use a double space after the full stop at the end of each sentence. Use a triple space between a table
number and title. Refer to Section 4.3.3 for instructions on typing numbers. There should be no space
between a punctuation mark and the word it follows.
Text should be fully (left and right) justified.]
4.5.2 Production
Short reports (less than five pages) are normally photocopied within the office onto one side of the paper,
so that they can be read after being inserted into a file.
Longer reports normally include a title page and are sent out for photocopying and binding. Bound reports
should :
a) use single side of the paper
b) include coloured (preferably blue) interleave pages to enable readers to find the start of
each chapter or appendix;
c) Have a plastic cover on both sides of the report.
d) Use a high quality photo print paper for the cover page which includes a picture;
e) Use spiral bindings with a black spiral.
42
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RF/00
REPORT REVIEW AND ISSUE Prepared Approved
Date: April 24, 2019
4.6.1 Checklist
Every report should be reviewed by the author, preferably at least 24 hours after first writing. At this
review stage the writer should put himself into the position of the reader and check the following:
Is the purpose and content of the report clear?
Does the report satisfy the requirements set out in the terms of reference or
elsewhere?
Is there enough background information for the intended readers? Is it clear and easy for
them to understand?
Is everything in the report relevant to its purpose?
Is the report structure logical?
Have illustrations and appendices been used appropriately? Are they referred to in the text?
Are the conclusions and recommendations clearly reasoned from the information given in
the report?
Is spelling and punctuation correct?
Does the table of contents exactly match the headings and sub-headings used? Are all cross-
references correct?
Is the report written in good English? Is it accurate, brief and clear?
4.6.2 Approval
Every report which will be sent out of the Hydro Solutions office must be checked and approved before
issue. For this reason every report except the ones that will be submitted to DOED (Department of
Electricity Development) should be signed as per HSEC/F/RSP/00.
4.6.3 Issue
No report may be issued before approval. After approval the report should be printed in sufficient copies
for the client, internal use and others as appropriate. For internal use there should always be at least one
office copy, for day to day use within the project team, and one record copy which is filed. A library copy
should also be made for final reports or other significant reports.
Reports should be issued with a letter of transmittal, see Section HSEC/F/DTF/00. This will be signed by the
Team Leader and approved by the Technical Director. The Team Leader must ensure that the collation of
all reports has been checked before despatch.
41
HSEC ENGINEERING PROCEDURES Doc. HSEC/QMS/RF/00
REPORT REVIEW AND ISSUE Prepared Approved
Date: April 24, 2019
42
43