Generator:
STEP 1:
We select the Project A6QJ and then we go to Cost & Revenue > Fluor Planning > Forecasting menu.
Phase: Sombra
Location: AMECO-Dominican Republic
Currency: USD
As you can see at the bottom of the screenshot we have a record with Other Expenses : Miscellaneous
Expenses (Misc) with different values for each week that will be our initial test scenario.
STEP 2:
Then we create a new revenue rule with the same parameters as we selected above and also we select
the Contract Term: Pass Through
And then we click the “Forecast Calculation” button.
STEP 3:
STEP 4:
We go again to Cost & Revenue > Fluor Planning > Forecasting menu and we select the Revenue Tab.