You are on page 1of 5

Resourcer:

Defining staffing plan

Releasing staffing plan.


Releasing to generator staffing plan.

Generator:

STEP 1:

We select the Project A6QJ and then we go to Cost & Revenue > Fluor Planning > Forecasting menu.

We select the Cost Tab and then the filters:

 Phase: Sombra
 Location: AMECO-Dominican Republic
 Currency: USD

As you can see at the bottom of the screenshot we have a record with Other Expenses : Miscellaneous
Expenses (Misc) with different values for each week that will be our initial test scenario.
STEP 2:

Then we create a new revenue rule with the same parameters as we selected above and also we select
the Contract Term: Pass Through
And then we click the “Forecast Calculation” button.

STEP 3:

We confirm that the data was created using the query:

STEP 4:

We go again to Cost & Revenue > Fluor Planning > Forecasting menu and we select the Revenue Tab.

Now we are able to see the data created: