1.

When hydro-test will be performed –

a. after coating,
b. before coating
c. during FAT
d. During final inspection

2. FAT full form FACTORY ACCEPTANCE TEST

3. When electrical continuity test performed – during FAT, after FAT,


During final Inspection

1. Ans - during FAT (BEFORE FINAL INSPECTION)

2. Minimum number of Lifting lugs for Skid?


1. 4 lugs

3. When Davit arm is required for Flanges 23, 24, >25 kg, =<25 Kg
etc…..

4. Information in the name plate


Manufacturer name; tag no.& PO no.; service type ; total weight
5. Projection is permitted in Skid beyond base structure
a. True
B. false

6. What type of marking is needed at Interference points of pipings –

A. permanent tag
B. manual marking
c. Maching marking
b. all of the above
d. None of the above

7. Question about turbine working principle.


a. min input max output.
b. max in put min output.

8. Who is to verify the material manufactured as per procedure,


specification, code

a. Project manger
b. Project engineer
c. Inspector
d. Auditor
e.

9. Standard for weld in the skid frame


AWS

10. Per shipping inspection is carried out at what stage

a. While loading in the truck


b. All the lose parts boxed
c. When the skid is loaded in truck
d. During the final inspection

11. When the loading done found that the truck tire bald what
you do

a. Inform the drive and replace it and then allow for


transportation
b. Inform the manufacture
c. –
d. -

12. Horizontal alignment kept under equipments


1. Shims

13. What is skid


Self contained processed units and intended for specific purpose
14. Types of skids will be given and what are these

1. Skid

15. Motor data will available in which document

1. Data Sheet

16. In Alignment one more question about vertical alignment.

1. Jack Screw