PREPARED BY;
Signature’s
TABLE OF CONTENTS
Section Description Page
1.0 Scope
I 5.3
5.4
Customer Focus
Quality Policy
Planning
16
18
19
5.4.1 Quality Objectives 19
5.4.2 Quality Management Planning 20
5.5 Responsibility, Authority, and Communication 20
5.5.1 Responsibility and Authority 20
Appointing a Quality Manager / Management Representative
5.5.2
2
8.2.5 Inspection Test Plan 53-61
8.3 Control of Non-Conforming Product 62
8.4 Analysis of Data 63
8.5 Improvements 64
8.5.1 Continual and Improvement 64
8.5.2 Corrective Action 64
8.5.3 Preventive Potential Nonconformities 66
9.0 Procurement 66
9.1 Material Requisition Content 66
9.2 Supplier and Sub-supplier Selection 66
9.3 Supplier Qualification Procedure 66
9.4 IAP Requirements and Contents 66
9.5 Quality Team Involvement in P.0 Process 67
Quality Team Involvement in Technical Bid Evaluation Stage
9.6 67
3
1.0 Scone:
1.1 The intent in developing this Quality Plan is to construct The KFUPM
BUSINESS PARK PROJECT in accordance with DVTC Engineering Standards,
Procedures and all applicable regulatory requirements. The main context
of this Quality Plan covers the Procurement, Design, Construction and
Commissioning of KFUPM BUSINESS PARK PROJECT This Quality Plan
defines the Quality Management System that complies with the
requirements of ISO 9001:2015 and Client Specifications.
1.3 AI-XYZ is committed of achieving the requirements set out in Client Quality
Assurance Program and Specification of this contract, and all Saudi regulatory
requirements. We continually improve our services, systems, and processes,
this will be accomplished through:
The Quality Management and related terms used in this Project Quality Plan are
defined below. Wherever possible, reliance is placed on ISO 9000:2000 Quality
Management System — Fundamentals and Vocabulary. This standard covers the
basics of Quality Management System and involves the definition of the terms
used within. The nature of this standard is informative and it was last revised in
2015 with following additional:
2. The customer may be, for example, the ultimate consumer, end
user, beneficiary or purchaser.
3.1.10 Hold Point: Inspection or test may not proceed without the QA/QC
organization representative in attendance.
3.1.11 Witness Point: It defines a point that provides QA/QC Organization with
the opportunity to attend the inspection or test, at their option.
3.1.12 Improvement: Action taken by Al-XYZ to increase the effectiveness and
efficiency of activities and processes in order to provide added benefits to
both XYZ and Subcontractors.
3.1.20 Quality Policy: Is directly integrated to our HSE Policy and incorporated as
one QHSE policy, the overall intentions and direction of an organization with
regard to quality and safety are formally expressed by top management.
3.1.23 Quality Assurance: All the planned and systematic activities implemented
within Al-XYZ quality system, and demonstrated as needed, to provide adequate
confidence that an entity will fulfill the requirements of quality.
3.1.24 Quality Control: Al-XYZ employs an operational techniques and activities that
are used so that its operation and services conform to the quality requirements
as laid down in the Company’s documents.
3.1.25 Quality Plan: A document setting out the specific quality practices,
resources and sequence of activities relevant to a particular product, service,
contract or
product.
3.1.26 Quality Audit: A systematic and independent examination to determine
whether quality activities and results comply with planned arrangements and
whether these arrangements are implemented effectively and are suitable to achieve
Objectives.
3.1.31 Rework: Action taken on a non-conforming product so that it will fulfill the
original requirements. Rework is one type of disposition of non-conforming product.
3.1.33 Service: The result generated by activities at the interface between the
supplier and the customer and by supplier internal activities to meet customer
needs.
3.1 34 Service Delivery: Those supplier activities necessary to provide the service.
3.1.35Shall: “Shall” expresses a provision that is binding between two or more
parties.
3.1.43 Type Test: Test or series of tests directed towards approval of a design
conducted to determine that is capable of meeting the requirements of product
specifications.
3.1.44 Witness Point: It defines a point that provides QA/QC Organization with the
opportunity to attend the inspection or test, at their own option. Work may
proceed even if the QC personnel have not witness the test as scheduled.
4.1 General
4.1.2 On this Project the subcontractors, if available shall perform the work
under their own QMS System. ALXYZ shall review the subcontractor QMS Manual
for conformance to the ISO 9001: 2015 standard as it applies to the assigned
scope of work. ALXYZ shall perform an evaluation of the subcontractor’s
implementation of their QMS Manual at the intervals identified by the Project
Specifications. ALXYZ will perform such internal audits at 20% and 70%
completion of each subcontracted work. Reports of such evaluations shall be
maintained for the duration of the Project. Any noncompliance shall be resolved
to the satisfaction of Client and the records shall be maintained.
4.1.3 Before starting the Project execution, Al-XYZ will identify all processes involved
in the Project. AI-XYZ will identify the sequence of interaction of these
processes, resources required; information required to support the execution,
monitor, and measure and analyze these processes. Al-XYZ will submit a
Project Quality Plan to Company Representative for review and approval a
minimum of (60) calendar days prior to the scheduled start date of the
procurement, construction and pre-commissioning phase as required by
Client.
4.1.5 The Quality Manager shall hold meetings on alternate week with Quality
Control Inspectors to review outstanding items, upcoming activities.
4.1. The Quality Manager is responsible for the daily site activities to establish
and maintain the Project Quality Program. His responsibilities include:
The hierarchy of the Quality Management System to be applied for this Project
mainly consists of three levels of documents, which are described below:
The Al-XYZ Quality Manual (QM1) is a Level 1 and is the governing document of
the Company Quality Management System.
4.2.2.1The Project Quality Plan (PQP) defines the means by which the
requirements of ISO 9001:2015 and Client Standards and Specifications
are met by the elements of the AI-XYZ QMS. This is achieved by providing
a brief outline of, and reference to, the Al-XYZ Quality Manual (QM1),
applicable Company
Procedures, Inspection and Test Plans and Work Instructions.
4.2.2.2 Al-XYZ establish and maintain the Quality Plan intended for the
10
AlXYZ Contracting Company (KCCJ EMB
Procurement, Construction and Commissioning of KFUPM BUSINESS PARK PROJECT
10
AlXYZ Contracting Company (KCCJ EMB
«
the Quality Plan will be maintained and updated by the QA/QC Manager in
accordance with the Company Quality Management System. The Quality Plan
identifies the scope of Quality Management System that Al-XYZ needs to
demonstrate its ability to consistently provide products and services that meets
the Project Requirements and applicable statutory and regulatory requirements.
The Quality Plan aims to enhance Client satisfaction through the effective
application of
the system, including process for improvement of the system and the assurance
of conformity to customer and applicable statutory and regulatory requirements.
AI
XYZ will identify all applicable Client Project Standards and Specifications and obtain
Client Approval prior to detail design activities. Al-XYZ plan and organized,
control and execute the work in accordance with the approved Quality Plan,
Inspection Test Plan and documented procedures. AI XYZ ensures that all quality
personnel, processes including the sub- contractors is effective and that the
executed work will be completed in compliance with the Contract Specification,
scope of work and
procedures covering the design, procurement, construction and commissioning.
The Project Quality Plan is subjected for review during the course of the construction
by the Company Representative through scheduled audit to ensure that any
developments or improvements in Al-XYZ Quality Management System are
accurately reflected in this document. It is the responsibility of QA/QC Manager
and all Plan Holder to ensure that every employee under his jurisdiction has been
fully informed and understood the entire context of this document.
4.2.2.3 Distribution:
The original Project Quality Plan will be retained at the QA/QC Department and the
approved copies will be distributed to the following:
Distribution Form (KCC-KFUPM-QC-15)
11
AlXYZ Contracting Company (KCC) EMB
I Al-Klfah Store Yard Store
Manager
07 Al-XYZ Fabrication Fab. Manager
08 AI-XYZ Procurement Proc.
Manager
09 AI-XYZ QC Fab Yard QC Supervisor
The distribution is “Controlled” and recorded. All controlled copies are identified with
RED Stamp “Controlled Copy”. All amendments will be issued to the approved
copyholders and it is the responsibility of the copyholder to replace the old with
amended one. All old documents will be collected by the Document Controller as
explained earlier.
The Project Quality Plan is the property of Al-XYZ and should not be reproduced
or transmitted to any 3’d party without the written approval of KCC Chief
Executive Officer (CEO).
4.2.2.4Amendment Records and Approvals
This indicates all the amendments to the latest issue of the Project Quality Plan.
Any revision, addition or changes shall be highlighted through a vertical line in
the right
hand margin. The amendment record is to be maintained as per section 3.4 using
the Form (KCC- KFUPM-QC-16).
(Sample)
Record Date of Amended Change Rev. Authorizatio
No. Issue Sec/Page Description # n
CM comments
01 25/12/ 3.2,Page 1 are incorporated as 01
16 indicated by a line at
the right margin
12
‹O AlXYZ Contracting Company (KCCJ EMB
4.2.2.8The Project QA/QC Manager or his designate in consultation with the
Project Manager to review and update the PQP, as necessary to ensure
that it matches with the scope of work. Any such modifications are to be
agreed by the Project Manager and approved by CQC prior to submission
for Client approval.
A list of the following is attached at the end of this
PQP: List of Specific Procedure QCP
List of Company Procedures applicable to this Project
Also, a copy of the above is attached with
this QCP
c. Level 3 Work Instructions
Work Instructions (WI) for the execution of the specific activities on the Project
form level “e” of the QMS. It includes Drawings, Welding
Procedures, and
Construction Method Statement.
4.2.3 Control of Documents
4.2.3.1 The Quality Plan, referenced procedures, and Inspection & Test Plans are
controlled documents. The Document Controller, to ensure that initial
issue and subsequent changes are acknowledged by those authorized to
receive the Quality Plan.
4.2.3.3 The Technical Manager is responsible to review all Project documents for the
conformance of the contract prior submitting to Client.
All essential documents affecting quality will be reviewed for adequacy and approved
for release by the QA/QC Manager.
4.3.2 Al-XYZ has made the applicable issues of such documents based on the
contractual freeze date available at all functional areas and inspection and
test points where they applied so that they are readily accessible to the
personnel concerned.
4.3.3 The issue, control and recall of all engineering documents, is under the
jurisdiction of the QA/QC Manager. Inspection and Test Plans and other
related instructions shall be prepared and issued by the QA/QC Manager.
4.3.4 Test Reports, Request for Inspection and Internal NCR shall be prepared
and issued by Discipline Quality Control Personnel.
13
AlXYZ Contracting Company (KCC) EMB
4.3.5 The System of Documentation and Data Control will ensure that essential
drawings, technical requirements, contract change information,
inspection
13
AlXYZ Contracting Company (KCC) EMB
instructions, specifications or any other documents required by Quality
Management, are available at the time and place of the operation.
4.3.6 Approved Quality Control Procedures (Latest version) - ITP, Forms, etc. will
be distributed by the QC Department to all locations, where required, for
the effective functioning of the Quality Program.
4.3.7 All changes of these documents are implemented in writing and processed
in a manner that ensures prompt action at the specified locations.
Changes to documents shall receive the same authorization as the original
documents. Records shall be maintained for changes as they are made.
Provision shall be made to promptly remove obsolete documents from all
points of issue and activity locations.
4.3.8 Al-XYZ will prepare and submit a request for changes to Company’s
documents when required.
4.2.4.1 Requirements
4.2.4.1.1 A document procedure to control the identification, storage, retrieval,
4.2.4.1.2 An index of Project records will be part of the file. The responsibility for
the accuracy and completeness of records will be assigned to the Document
Controller. Access to records will be under the control of QA/QC Manager.
Removal of records to a location other than the immediate area where the file is
located will be restricted to the Project Manager. Measure to identify removed
files and their current location shall be maintained.
14
0 AlXYZ Contracting Company (KCC) EMB
retention time, disposal method, and arranging for their protection and controlled
retrieval.
a. AI-XYZ will conduct a weekly progress meeting with Client to discuss the status of
the Project with regards to procurement, construction and to update all other
programmed activities to avoid delays.
b. Al-XYZ will employ liaison personnel (preferably Saudi National) responsible for
communicating on authorities concerning regulatory and legal requirements.
i
15
AlXYZ Contracting Company /KCCJ EMB
c. Al-XYZ Interface Manager to keep Client fully informed on all matters arising
and will include Client on all communications relating to the execution of the
work.
From time to time AI-XYZ will attend meetings and communicate with other
parties as required to resolve outstanding issues.
5.1.1.2 Al-XYZ will establish quality policy and Objectives as per KFUPM
BUSINESS PARK PROJECT requirements:
a. AI-XYZ will be totally responsible for the Quality of work required by the Contact.
b. Al-XYZ QC Inspectors will inspect, test and verify all parts of the work and
every purchase orders as applicable including subcontractors in conformance
with Project specifications, drawings and standards in accordance with the
Specifications in this contract.
c. Al-XYZ will review and identify all Project standards and specifications.
d. AI-XYZ will provide sufficient resources to implement the Quality Management
5.1.1.4. Al-XYZ ensures the availability of necessary resources to support the quality
management including all departments to maintain the smooth operations in
accordance with Section 6.1 and 6.2 of this Quality Plan.
5.1.1.5 This section of Quality Plan set forth the Organizational arrangement
employed by AlXYZ in providing support service and executing Projects
they undertake. It also defines the organizational relationship,
responsibility, authority and lines of communication of the Quality
Management function.
5.1. 1..6 In providing effective management of Projects and support services, Al-XYZ
assures optimum use of manpower, technological and financial resources
utilizing expertise from a variety of disciplines to meet the requirements
of their customers. Such expertise is developed in engineering and
construction techniques.
It is AI-XYZ’s policy to understand and satisfy the current and future needs of
present and potential customers and to provide products that
meet those needs while enhancing customer’s satisfaction.
16
Additionally, AI-XYZ shall ensure that all Client requirements and other
regulatory requirements (as mentioned in the contract issued to
AlXYZ) are met on receipt and final product delivery to the
satisfaction of Client.
c. Promoting new and flexible ways for delivering services that are
responsive to customer’s needs;
17
0 AlXYZ Contracting Company (KCCJ EMB
processes enable the delivery of excellent customer service.
17
0 AlXYZ Contracting Company (KCCJ EMB
5.3 Project Quality Policy
5.3.4 Conformity with the Project Quality Plan and supporting procedure is
mandatory and shall be adhered to by all personnel employed on the
Project, to achieve a common approach to Quality Assurance and Quality
Control.
5.3.5 This Quality Policy is communicated to grass root level and understood
within the organization. The Project Manager has the overall responsibility
for ensuring that the contents of this Project Quality Plan are
implemented in a satisfactory manner. The Project QA/QC Manager will
monitor the effectiveness. Any problems or disputes arising from such,
shall be brought to the attention of the Chief Operation Officer and where
necessary the General Manager for resolution.
5.3.6 All personnel working in the Project are responsible for the quality of their
work and shall perform their duties in accordance with the requirements
of this Project Quality Plan and in conformity with the reference
procedures. No deviations are permitted without the written approval by
the Company. AI-XYZ is committed for the continual improvement of its
effectiveness of the
QMS.
5.3.7 Every effort will be made by AI-XYZ to cultivate joint working relationship
with Client, to enable an open and free exchange of information, in order
to ensure that the Project is completed safely, on time, within the budget,
to the required quality and conformity with all applicable
Statutory/Legislative requirements.
AlXYZ Contracting Company (KCC) EMB
5.4 Planning
5.4.1.1 The Top Management of AI-XYZ has identified the following quality
Objectives for the Project. The Objectives are measurable, consistent with policy,
relevant to the successful completion of the Project, and attainment of
Objectives is considered as part of our effort for the improvement. Al-XYZ has
identified the
quality Objectives in meeting the contract requirements, resources allocations, cost
control, control of scheduling and all other relevant quality Objectives as
declared in Section 3.1, 4.3 and 5.3 of this Quality Plan.
5.4.1.1.3 be measurable;
5.4.1.1.6be monitored;
5.4.1.1.7 be communicated;
5.4.1.1.8 be updated as appropriate.
5.4.1.3 Al-XYZ Quality Management System for the Project is to ensure that;
5.4.1.3.1Planned and performed in such a manner that it is safe and free from
errors and deficiencies;
19
Oc AlXYZ Contracting Company (KCC) EMB
5.4.1.3.2 Undertaken correctly, to ensure cost effective and efficient completion,
in accordance with contractual and regulatory requirements;
5.4.2.1 The elements that comprise the quality planning process are this Quality Plan,
Inspection and Test Plan, Project Organizational Charts that prescribe personnel
allocations and mobilizations, titles of individuals, subcontractors to complete
the work, and integration of quality improvement initiatives described in
paragraph 5.6 Management Review and in Section 8.2.1, Measurement and
Monitoring.
5.4.2.2 This section of the Quality Plan sets forth the organizational arrangement
employed by Al-XYZ in providing support services and in executing Projects they
undertake. It is also defining the organizational relationship, responsibility, authority
and lines of communication of the Quality Management function
Chief Executive
Officer (CEO): Approval of all Quality Management System (QMS)
documentation prior to issue after revision.
20
Oc AlXYZ Contracting Company (KCC) EMB
QHSE Manager Review/change of Quality Management System
Management documentation in conjunction with the responsible
Representative: department. The preparation, issue, revision and
withdrawal of Quality Management System (QMS)
documentation. Establish, implement and maintain
processes required for the QMS. Inform the top
Project Manager: management of any need for improvement.
21
AlXYZ Contracting Company (KCC) EMB
IFC Drawing, Project Specification,KCC Work Procedure, Welding Procedure, Al-XYZ
Management Instructions and disseminate to his QC Supervisors ensuring the work
has been properly executed to avoid non-conformances and rework. He will give
specific instructions to all his subordinates to stop activities that does not comply
with the approved plan and Project Specification and give solution not to delay the
Project. He will encourage all QC discipline to issue Internal NCR any activities that
does not comply with the Contract Specification and find solution in closing the
non-conformances in a timely manner.
5.5.1.5 Top management ensures that the responsibilities and authorities for
relevant roles are assigned, to communicate and understood within the organization.
The Top
management will assign the responsibility and authority for:
a. Ensuring that the quality management system conforms to the requirements
5.5.1.6 To this end, Al-XYZ has an obligation to ensure that the final product i.e.
result of activities or processes meets its fitness for purpose" and has been
carried out in accordance with the Job Specifications and is consistent with
design
requirements.
Responsibilities:
5.5.2.1 Al-XYZ has the overall responsibility for the development and
implementation of the Quality Plan in accordance with ISO 9001:2015 and
the
Job Specification requirements.
5.5.2.2Test Plan in accordance with Specifications and will monitor and assess
the implementation of the Plan.
5.5.2.3 Top management has demonstrated leadership and commitment with respect
to the quality management system by:
22
0 AlXYZ Contracting Company (KCC) EMB
management system;
b) Ensuring that the quality policy and quality Objectives are
established for the quality management system and are
compatible with the context and strategic direction of the
organization;
23
0 AlXYZ Contracting Company (KCC) EMB
c) Ensuring that the integration of the quality management system
requirements into the organization’s business processes;
QHSE Manager
i “
5.5.2 Appointing a Quality Manager / Management Representative
5.5.3.1 AI-XYZ has appointed QA/QC Manager as the management representative
for the quality on this Project. He ensures the quality system is established,
maintained and implemented and he will report to the top management on a
monthly basis and make recommendations for quality system improvements. Reports
will be issued in writing to the top management and maintain in an open status
until the resolution of outstanding items. The management representative for quality
shall
23
Oc AlXYZ Contracting Company (KCC) EMB
ensure that the Project team is aware of customer requirements regarding the
Project.
2. Establishing the Company Quality Health Safety and Environment policy and
Objectives, and ensuring that they are deployed effectively at all function and
level;
24
AlXYZ Contracting Company (KCCJ EMB
arising during construction activities.
25
AlXYZ Contracting Company (KCCJ EMB
5.5.3.4 Al-XYZ appoints a Construction Managers in different disciplines who will
report directly to the Project Manager. He is responsible for the planning of all
activities in the Project ensuring quality and safety is his first priority. He will
identify discipline personnel that are qualified, properly trained and educated. He
shall report to the Project Manager where activities that requires sufficient
resources in terms of manpower and equipment. He will coordinate with Quality
personnel in conducting inspection and identify works that requires
improvement and rectify any quality comment immediately to avoid committing
violations resulting in the issuance of internal NCR. He will cooperate with all
Quality Inspectors in doing daily inspections and identify all problems, quality
concern during the course of construction. He will guide his people in doing
quality work and help promote the effectiveness of Quality Management System
as a continual improvement of its processes and system operation.
5.5.3.6 The overall organization for the Project shall be in accordance with the
organization chart included in the Project Quality Plan.
4. Construction Manager
6. Project Engineers
7. Field Engineers
25
0 AlXYZ Contracting Company (KCC) EMB
9. Document Controller
5.5.3.8 Key personnel for the Project will be assigned in accordance with the Al-
XYZ Company's Procedure. The mobilization of key personnel shall be as per
approved mobilization plan. As a general principle, only trained, qualified and
experienced personnel are to be assigned to the work.
5.5.3.8.1 The Project QA/QC Manager will report directly and maintain
communicafion with the Project Manager concerning day-today Project quality
matters, with regards to quality related problems that require AI-XYZ Management
resolution. Project QC Supervisors and discipline inspectors are repomng directly
to QA/QC Manager. All QC personnel are made available for interview with
Client, if required, prior to assign them on job. All QC personnel shall meet the
requirements of Client.
Project Manager has the overall authority and responsibility for all aspects of the
Project.
a. Representation of Al-XYZ towards Company for all matters relating to the Contract
b. Overall management of the Project activities and control of the related personnel
g. Maintenance and coordination of contacts with the local authorities for all matters
related to the work execution.
h. The Project Manager the overall responsibility for the quality of work and
safety of workers and equipment. The QA/QC Manager will report directly to
the Project Manager on day to day activities including welding works,
procurement and receiving of materials that require quality.
26
AlXYZ Contracting Company (KCCJ EMB
i. He will coordinate with the Management Representative to evaluate on areas
that require improvement through site demonstrations and training and identify
where improvements are needed. He verifies with the Management
Representative that Quality Audit has been carried out according to the
approved schedule.
The above task will be achieved by coordinating the activities of the Project
Personnel.
The Quality Assurance Manager will report directly to the Quality Management
Representative. His main function will be acting as the interface between AI-XYZ
and Client pertaining to Quality Assurance Documentations. His responsibilities
include but not limited to:
g. Conduct on the job training to workers in line with the approved quality
procedures.
27
AlXYZ Contracting Company (KCCJ EMB
I. Establishing Inspecfion and Test Plan for procurement, construction and
commissioning phases as required by Specifications.
m. Conduct Weekly meeting with all Quality Personnel to discuss quality issues.
The Quality Control Manager directs the activities of the Project Quality Organization,
but maintaining communication with the Project Manager regarding quality status of
the Project.
b. Issue of Project Quality Procedures, Inspection and Test Plans and Forms
j. Following a suitably start and approved procedure for the formal control
of deviation/waivers from the Project specification
28
AlXYZ Contracting Company (KCC) EMB
m. Preparation of Daily Quality Reports.
n. Maintain red line drawing as per site changes and Technical Queries.
in the construcflon site. His responsibilities include but not limited to:
a. The Construction Manager will monitor all employees’ functions and
quality of work to ensure the effectiveness and adequacy of construction
has fulfilled the requirements QMS and that successfully implemented.
29
AlXYZ Contracting Company (KCC) EMB
c. Assuring the traceability of uniquely identified critical materials while
materials are in storage
He shall report to the QA/QC Manager; His responsibilities include but are not
limited to:
g. Assist vendor inspectors in all aspects of their work to ensure that all
Project requirements are fulfilled and that all inspections carried out and
correctly recorded
The Drawings and Document Controller assist the QA/QC Manager for all the
information concerning the Project Documents. His responsibilities include
but are not limited to:
5.5.3.8.9Welding Inspector
The welding Inspector shall report to QA/QC Manager; His responsibilities include the
following:
30
Oc AlXYZ Contracting Company (KCC) EMB
b. Ensure that Al-XYZ maintains accurate, concise records of approved welding,
NDT and heat treatment procedures
d. The inspector shall ensure that Construction Contract complies with the
requirements of the approved contract Quality Plan, including all the
sequential inspections associated with weld preparation. All non-
conformances shall be reported and recorded.
e. The inspector shall be available for formal stage witness inspections defined in
ALXYZ inspection and Test Plan.
Quality Control Inspectors shall report directly to the Project QA/QC Manager.
a. Ensure that all site activities comply with the contract requirements, scope of
• Civil works
• Mechanical works
• Electrical works
• Architectural work
b. Assisting the Procurement/Material coordinator in the task of overseeing the
31
AlXYZ Contracting Company (KCC) EMB
5.5.3 Internal Communication:
5.5.4.1 The QA/QC Manager and Management Representative ensure the processes
of quality management system and their effectiveness are communicated throughout
the organization. Internal Communication consist of flow of information (appropriate
information on Process Performance, Customer Satisfaction, Customer Complaints,
QHSE performance, legal and statutory compliance). From the Project Manager,
Construction Manager with his Departmental Staff down to all employees and
employees from the Project Management to ensure that all levels and functions
are aware of QHSE policy, Objectives and Integrated Management System. It also
ensures that the views and suggestions on QHSE performance, Environmental
aspects, and impacts/hazards are identified by employees reach to the department
managers and the relevant personnel for effective communication among all levels
within Al-XYZ / Client KFUPM BUSINESS PARK PROJECT Management Team. The
Project Management aims and Objectives to promote the QHSE culture through
effective communication by using the following as medium:
5.6.1.1 AI-XYZ Top Management will review the Quality Management System at
least once every six months for its suitability, adequacy and effectiveness. The
QMS, Quality Policy and Quality Objectives will be evaluated for any needed
change. Records for this review will be maintained.
32
AlXYZ Contracting Company (KCCJ EMB
effectiveness of Al-XYZ QMS and provide continual improvement where it is
required.
h. Other changes such as design change notice (DCN), field changes notification
(FCN), scope of change and other changes that could affect the QMS.
c. Resource needed.
5.6.3 Al-XYZ Contracting Company constantly strives to continually improve the IMS
System through the use of QHSE Policy and documented information QHSE
Objectives, audit results, analysis of data, corrective actions and management review
meetings. The QHSE Objectives are upgraded gradually on routine basis for improving
performance of different departments.
a. Internal Audit;
b. Quality Inspection;
5.6.4 The Company QHSE Manager, who will be responsible for the preparation
of the agenda and writing of the minutes, and convene the meeting at
approximately six month’s intervals.
5.6.5 The Management reviews are additional to the findings of internal audits
conducted to ensure continued adherence to the system.
5.6.4 Al-XYZ ensures that Senior Management Reviews are scheduled event
included in the quality audit schedule approved by Client.
5.6.5 XYZ will inform the Company Representative in writing of the results and
recommended actions of Management review within (2) weeks after the
scheduled review date. Changes to the Quality Plan, with the approval of the
Company Representative.
6.1.2 Means and personnel for verification are located within the Al-XYZ
departments and reflected in the Project organization chart.
6.2.1 General - Al-XYZ will assign personnel to KFUPM BUSINESS PARK PROJECT
in accordance with Specifications,that is competent on the basis of education,
training, skills and experience. All personnel assigned to this Project meet the
minimum qualification and experience level as specified in the Specifications. HR
Manager is responsible to review the contract to determine any customer
requirements for competency level of personnel assigned to the Project and
ensure that assignment of personnel including Subcontractors meet the
requirements. Resume of all quality personnel including subcontractor quality
personnel will be submitted to Client for review and approval.
6.2.2 Al-XYZ has planned the staffing level to comply with Client Quality plan.
Reduction from the required level of quality personnel specified in Specifications
will require Client written approval.
6.2.2.1 Al-XYZ has developed position descriptions for those personnel performing
activities affecting quality the identify competency requirements. The HR
Manager maintains the late issue of position descriptions.
6.2.2.2 The Project HR Manager identifies the training needs and assures training
is performed. Personnel lacking required competency will have received training
such as formal, informal or On-Job-Training (OJT). Al-XYZ will provide training as
deemed appropriate to satisfy competency needs or utilize external training
sources.
6.2.2.3 A formal training program is essential to ensure that all staff receives the
necessary training to supplement their existing expertise and experience to
enable them to perform their duties as well as for their acquisition of quality
consciousness.
35
Oc AlXYZ Contracting Company (KCC) EMB
6.2.2.5 Job proficiency obtained by experience is considered adequate for personnel
carrying out quality related activities not requiring special knowledge or skills.
New personnel for such positions shall receive "on-the-job training" under the
provision of experienced personnel. Such training in designed to ensure a
satisfactorily skill progression for employees.
6.2.2.6 The Human Resources Manager (HRM) and Department Manager will arrange
orientation sessions for all new recruited company employees. In addition to
this, all employees shall be given Quality and Safety Orientation before they start
work on the Project.
6.2.2.8 The Project Manager is responsible for assessing the training needs of
personnel assigned to the Project team. Any training needs shall be arranging in
conjunction with the HR Manager. HR Manager shall arrange for updating the
training records in the employee's personnel file.
6.2.2.10 Al-XYZ will provide adequate personnel coverage required due to vacation,
illness, temporary assignments, emergency leave, resignations or other reasons
as necessary to maintain required quality coverage. A minimum of 30 days’
notice shall be provided to the company for all schedule changes and as soon as
possible for other changes.
6.3 Infrastructure
6.3.1 Al-XYZ provides a work environment suitable to achieve its business Objectives
and satisfy Project requirement. Al-XYZ provides Project Support Building and
Contractors Camps. The following requirements apply to Project Support Building
including Project Management Team Offices and Contractor/Subcontractor offices at
the Job Site, and Contractor Camp which include accommodation for Al-XYZ and
Subcontractor.
6.3.2 Operation and maintenance required for the work will be in accordance to
contract and for facilities requirements.
36
AlXYZ Contracting Company (KCC) EMB
In addition, Al-XYZ management will determine and provide a suitable and safe
work environment necessary for the effective implementation of its processes and to
achieve conformity of products and services.
c. Transportation resources;
6.3.2 Al-XYZ management will determine, provide and maintain the environment
necessary for the operation of its processes and to achieve conformity of
products and services.
6.3.3 Al-XYZ will arrange for safe accommodation, transport, etc. for their
employees in accordance with the national standards. Clients have access to
inspect these facilities, as required by the contract.
7.1.1 Al-XYZ planned and documented the Project Execution processes. The
documentation for the Project execution is stated in Section 5.3 of this Quality
Plan.
7.1.2 The quality Objectives for the design, procurement and construction
activities etc. are identified as mentioned in Section 5.4.1 of this Quality Plan the
internal Quality Objectives and signed contract document, between Client and
Al-XYZ as per Contract, standards and specifications.
7.1.3.2 Al-XYZ has designated the Procurement Manager responsible for the
preparation, planning and procurement of all Equipments and Materials required for
the construction ofKFUPM BUSINESS PARK PROJECT . As the initial stage of
preparation, he develops the Project Procurement Plan and this was submitted to the
37
‹D AlXYZ Contracting Company (KCC) EMB
Company for approval. The Procurement Manager was included in the Quality
Organization Chart having the authority over the procurement supervisor,
material receiving supervisor including procurement for subcontractors.
7.1.3.3 Al-XYZ identified and organized the construction personnel with their
specific functions as detailed on the organization chart, it begins from the
corporate officers down to Project site construction team, the Project manager,
construction manager, QA/QC Manager, Technical Manager, Procurement Manager,
HR manager and Safety Manager.
7.1.4 Verification and validation are incorporated into the planning processes as follows:
1. Al-XYZ appoint the Technical Manager to receive drawing from the design
engineering and review the document ensuring that Client specification
requirements have been considered and incorporated prior to submit officially
for approval. All submitted drawings are controlled by entering to the drawing
register for the purpose of tracking and monitoring the stages of review and
approval.
b. Disposition Reports
c. Internal Audit Results and closures
d. Records of management reviews
7.2.2.3 Al-XYZ management has reviewed the product and service to be offered
to Client will meet the requirements. The management has conducted a review
before committing to supply the product and services to Client which include:
b. Requirements not stated by the Client, but necessary for specified or intended use,
when known;
39
AlXYZ Contracting Company (KCC) EMB
c. Statutory and regulatory requirements applicable to the product and services.
Al-XYZ ensures that it has the ability to meet the requirements for products and
services to be offered to customers. The management shall conduct a review
before committing to supply products and services to a customer, to include:
7.2.2.2 Al-XYZ ensures that contract or order requirements differing from those
previously defined are resolved.
a. The Project Manager will conduct a weekly meeting to discuss and update
Project progress, planned activities and status of Project quality and safety.
b. The Project Manager will maintain communication with Client through formal
written communication.
c. By form of daily consultation with Client in line with the Project activities.
40
AlXYZ Contracting Company (KCC) EMB
7.3 Design and Developments:
7.3.1.1 Al-XYZ will conduct review, verification, and validation of all activities,
Limited to requirements of the Contract and specifications of KFUPM BUSINESS
PARK PROJECT.
7.3.1.4 Design documents and the design concepts and requirements expressed
therein, are subject to review and approval by qualified personnel, other than
those who did the original design, with clearly designated responsibility and
authority to do so, prior to release for purchasing, fabrication or construction as
needed and limited only to contract requirements and specifications.
7.3.1.5 Al-XYZ Engineering Department shall Review and identify those items of
the design and specify the quality standards.
7.3.2 The Following Procedures will be Included and become part of this
project Quality Plan but limited to the requirements of this Contract and
Specifications.
7.4 Purchasing
7.4.1.1 Where Subcontractors and suppliers are engaged to work on this Project,
their capability to perform the assigned scope of work is evaluated by the QM
Representative in accordance with Specifications. Physical surveys, when needed will
be performed by a qualified auditor and supported by a technical specialist for
the equipment under consideration.
41
Oc AlXYZ Contracting Company (KCCJ EMB
7.4.1.3 Supply of services, fabrication and welding works will be processed from
Client subcontractors and suppliers.
7.4.1.4 To extent to the practical, Al-XYZ will procure its equipment and material
from company approved sources as per Specifications. Company shall approve
alternative sources for material identified in Company’s Regulated Vendor List (RVL)
prior to placing of purchase orders. Other sources for material selected by the
Purchasing Department shall be evaluated and approved by AI-XYZ’s Quality Control
(QC) Department prior to placing them on the acceptable
suppliers/subcontractors list. Material, for which inspection requirements are
specified.
Procedure:
7.4.3.2 Test and Inspection is associated with the plan systematic actions necessary to
assure that the materials and items procured satisfy the minimum Client
requirements for Quality.
7.4.3.3. The Inspection and Test Plan using the KCC Form is a part of Project
42
Oc AlXYZ Contracting Company (KCC) EMB
Quality Plan (PQP). This described activities to detect flows, and find ways and
means to
43
Oc AlXYZ Contracting Company (KCC) EMB
eliminate them. The Client/Al-XYZ Inspection and Test Plan procedure are quality
control means in detecting un-acceptable condition of the material procurement
activities and further aims to eliminate and prevent them from occurrence.
7.4.3.3 Al-XYZ verification and testing of purchased product/items where any of the
following conditions apply:
a. Suppliers sub-orders will be reviewed for conformance to the original purchase order
requirement and document.
d. Detailed Inspection and Test Plans for all equipment and material with Inspection will
prepared by the supplier and submitted to Client with the Inspection Assignment
Package three weeks prior to start of fabrication.
e. Applicable supplier process control procedure (i.e. welding, heat treatment, NDT,
refractory installation, PMI) will be reviewed by the Technical Manager and
Mechanical Superintendent and submit to Client as required.
7.5.1.2 Al-XYZ will implement production and service provision under controlled
conditions. Controlled conditions shall include, as applicable:
44
AlXYZ Contracting Company (KCC) EMB
7.5.2 Validation of Processes for Production & Services
7.5.2.2 Al-XYZ will adopt monitoring and measuring activities which will ensure
the control of processes and outputs will be addressed; however, the system of
monitoring and measurement of processes and monitoring and measurement of
product will considerably have adopted.
7.5.2.3 Al-XYZ will focus on the new requirements includes, product acceptance
criteria, use of appropriate infrastructure, process environment, monitoring and
measuring resources and competent persons.
7.5.2.5 Al-XYZ will adopt the “Post Delivery” to cover the activities after product
delivery such as shipment, associated consequences with the product delivery,
warranty claims, maintenance services etc.
45
Qc AlXYZ Contracting Company (KCC) EMB
b. Identify the status of outputs with respect to monitoring and
measurement requirements throughout production and service
provision.
c. Control the unique identification of the outputs when traceability
is a requirement, and shall retain the documented information
necessary
to enable traceability.
d.
Al-XYZ Traceability System shall operate from the specification of the
material through its manufacture to its inclusion as finished
product in a facility.
e.
Al-XYZ Traceability Requirements shall be kept to the minimum
consistent with the safe and efficient operation of the installation
concerned, and shall only be applied when failure of the
equipment or material could result in a hazard to person or the
environment, or significant loss of production output.
7.5.4.2 Al-XYZ procedures shall set out details of verification to be carried out on
receipt of any Company supplied items. It might require the QC inspector, in
consultation with leaders of any other discipline involved, determining the extent
of verification required in order to satisfy the Project requirements, so far as this
is
possible, as to the suitability/accuracy, and so on, of the Client supplied items.
7.5.5 Preservation of Materials and Equipment
7.5.5.1 A system shall, maintained for the handling, storage and shipping,
including cleaning, packing and preservation of all items through the entire
manufacturing and construction process. Precautions shall be taken to protect the
materials from abuse, misuse, damage, deterioration and unauthorized use.
7.5.5.6 Restricted storage area will be available for the isolation and protection
of accepted raw materials, semi-finished parts and finished parts pending use or
shipment.
7.5.5.7 Al-XYZ develops and maintains procedures for handling, storage and
preservation of all materials and equipment.
7.6.2 During the AI-XYZ QC Initial Survey for Third Party Independent Laboratory
all identified Equipment and Instrument to be used for this Project has been
inspected and verified its working condition and calibration certificates weather
it was in accordance to specifications and standards. Evidence documents,
calibration certificates where requested from the Agency to be submitted to
Client for verification and approval.
d.A program of corrective actions for previous accepted work, if defective equipment
and instruments are used to inspect or test the work;
7.6.4 All measuring and test equipment and devices having an effect on quality
shall bear a tag, sticker or other suitable marking, indicating status. The validity
of previous inspection and test results when measuring and test equipment are
found to be out of calibration shall be assessed and documented. Client may
verify the standards and master available.
7.6.5 Equipment and devices used for measuring, testing and inspection shall require
an initial inspection for accuracy, or shall be proven prior to release for use on
production.
7.6.6 The system shall provide for a pre-planned calibration frequency chart showing
all applicable test and inspection equipment, calibration frequency and status, in
no case shall equipment/Instrument calibration cycles exceed One (1) Year.
48
Oc AlXYZ Contracting Company (KCC) EMB
8.1 General
8.1.1 Al-XYZ has defined, planned and implemented the following measurement,
monitoring, analysis and improvement activities to ensure conformity and
achieve improvement.
8.1.2. Al-XYZ has defined for the characteristics of different outputs achieved at
the appropriate stages of product realization for meeting the customer
requirements. All these characteristics are planned, monitored and measured by
the designated personnel in respective departments in order to ensure that their
output requirements meet internal / external and legal requirements.
8.1.3. These characteristics have been defined in the Inspection Test Plan,
Method Statement and work instructions as applicable to the relevant stages of
processes. For all identified characteristics, the acceptance criteria had also been
defined. The in-process and final inspections are conducted to make evidence for
the same. All necessary records are maintained as given in the respective
documents.
8.1.4 The inspection and testing requirements shall be carried out in accordance
with Specifications. Notification requirements for “Request for Inspection” (RFI) shall
be a minimum of 24 hours and 48 hours for weekend inspections. Al-XYZ included
on this PQP Client Request for Inspection (RFI) Form. Request for Inspection (RFI)
shall be submitted to Client.
8.2.1.1.1 Al-XYZ has developed the following methods to obtain data and
b. Al-XYZ will conduct a quarterly survey from Client (Survey and Feedback) with
49
fiJ AlXYZ Contracting Company (KCC) EMB
the following criteria to verify Al-XYZ and its Subcontractors rating performance:
50
fiJ AlXYZ Contracting Company (KCC) EMB
• Handling of your Initial Inquiry
• Technical competence of our Team Member
• Attitude of our Team Member
• Update Information about new product
• Quality of product
• Timely delivered in specified locations
• Communication skills of our Team
• Disputes handling
c. Al-XYZ management team will establish regular communication with Client
representatives through telephone conversation, email, letter or any messages to
be updated of any latest information regarding the Project Status. Verify if any
complaint from Client for immediate action, and any other information to invite
customer satisfaction.
8.2.1.1.2 Al-XYZ shall monitor customer’s perceptions of the degree to which their
needs and expectations have been fulfilled. Al-XYZ determine the methods for
obtaining, monitoring and reviewing this information. Monitoring customer perceptions
can include customer surveys, customer feedback on delivered products and
services, meetings with customers, market-share analysis, compliments, warranty
claims and dealer reports.
8.2.2.2.3 Al-XYZ shall analyze and evaluate appropriate data and information arising
from monitoring and measurement. The result of analysis shall be used to
evaluate:
50
Oc AlXYZ Contracting Company (KCC) EMB
8.2.2 Internal Quality Audit
8.2.2.1 The Quality Assurance Manager will establish, document and implement
a plan for audits that objectively evaluate the effectiveness and adequacy of the
functions, systems and procedures as referenced in this Project Quality Plan. The
Quality audit Schedule shall include Design Phase, Construction, Procurement
and Management. Al-XYZ Senior Management, a person reporting directly to the
owner of board of directors having the proper authority as delegated by Al-XYZ
shall also review the Project-specific Quality Management System every six month to
measure the effectiveness of the System whether it is suitable, adequate or
useful.
8.2.2.2 The audit plan shall define: The funcfions, systems and procedures to be
audited Schedule of Audits Method of reporting findings and recommendations
and corrective and preventive actions. The means for having corrective actions
agreed upon and implemented.
8.2.2.3 Al-XYZ shall submit a quality audit schedule to Company for review and
approval within 21 calendar days from the effective date of the contract. Audits
shall be carried out at Twenty percent (20%) and seventy percent (70%) of
completion stage for design, procurement and construction Work phases. This
schedule is a part
of this Project Quality Plan.
8.2.2.4 Audits shall include an evaluation of:
8.2.2.6 Personnel performing audits shall not have direct responsibility for the
areas being audited. The minimum requirements of the auditor shall be as per
Specifications of this contract.
8.2.2.7 Management responsible for the area audited shall review, agree and correct
deficiencies revealed in the audit reports.
8.2.2.9 Al-XYZ shall submit to company a copy of each audit report within (2)
weeks of its completion.
51
AlXYZ Contracting Company (KCC) EMB
8.2.3Monitoring and Measurement of Processes
8.2.3.1Requirements:
52
AlXYZ Contracting Company (KCC) EMB
requirements. The Program will be controlled by written procedures, instructions or
checklist as appropriate. Results will be recorded, authenticated, and distribute
in accordance with written procedures. The measurement, monitoring and
acceptance of the design are addressed in the design development section.
8.4.2.2 The receiving discipline Quality Control Supervisor ensure that in coming
equipment and materials are inspected and accepted for Project use prior to
incorporation into construction. When material is received without inspection
release, the QA/QC Manager will perform inspection against the purchase order
requirements and verify that the equipment and material meets the specified
standards. The process will be documented through material receiving inspection
report. This includes the verification of delivery notes, purchase order, approved
comparison sheets, MSDS, and material storage instruction sheets.
8.4.2.5All test results will be documented on forms appropriate for the test, and
dates and signed by the test personnel. Results will be distributed simultaneously to
Al-XYZ and Client. It is the responsibility of discipline Client Site Inspector to
supervise and accept or report all Al-XYZ performed inspection and test.
8.2.1.4.1 The ITP shall be prepared and submitted to Client for review and
approval, as per Specifications. Al-XYZ will utilize Client Inspection Criteria and
Client Inspection and Test Plan.
N ote: ( Some of the Job Item may not be Included or applicable for KFUPM BUSINESS PARK Project)
53
Oc AlXYZ Contracting Company (KCC) EMB
TYPICAL INSPECTION PLAN (TIP) INDEX
Index
Form
TyDe
Sub
Typical Inspection Plan (TIP) Title Discipline
A 1 0 CiVIl
1 1
4 Earthwork- Site Preparation
B 00 01 Fireproofing Concrete Civil
6
H 00 Coating Application on Concrete Surfaces Civil
3
L 45 01 On-Land and Near-Shore Pipeline Civil
0
M 00 01 Security Fence and Gates Civil
6
M 10 01 CMU and Building Bricks CiVIl
0
M 10 02 Water Proofing of Roof Slab CiVil
0
M 10 03 Structural Steel for Buildings ClVil
0
M 10 04 Pre-Engineered Metal Building Civil
0
M 10 05 Gypsum Wall Board System Civil
0
M 10 06 Ceramic Wall and Floor Tiles CIVil
0
M 10 07 Metal Doors and Windows Civil
0
M 10 08 Acoustical False Ceiling CiViI
0
M 10 09 Glass and Glazing Civil
0
M 10 10 Resilient Vinyl Composition Floor Tiles CiVIl
0
D 00 01 Security Fence & Gates Type SSDI Standard Security Fence Civil
1
Q 00 02 Portland Cement — Batch Plant Management CiVil
1
0 00 03 Precast Concrete Fence Post - Fabrication Yard Civil
1
Q 00 04 Structural Precast Prestressed Concrete CIVil
1
o oo oi Asphalt Paving- Batch Plants Management Civil
6
54
Oc AlXYZ Contracting Company (KCCJ EMB
Q 00 02 Asphalt Paving CIVil
6
Q 00 03 Foam Asphalt Stabilization Rev. 1 CiVil
6
Q 01 01 Cement Based Non-shrink Grouting CIVil
0
Q 01 01 Epoxy Grout for Machinery Support Civil
1
Q 17 01 Earthwork Excavation and Backfill for underground utilities CiViI
0
P 10 01
3 AC UPS Systems Electrical
P 10 02 Electrical
3 Direct Current Power Systems
P 10 01 Electrical
4 Low Voltage (600V to 1kV) Cable
P 10 02 Electrical
4 Medium Voltage (1.001kV to 35 kV) Cable
P 10 03 Electrical
4 Cable Tray, Fittings, and Accessories
P 1 0 Electrical
0 4
4 Boxes (Junction, Terminal, & Pull), Wire Troughs & Wire ways
P 10 05 Electrical
4 Above-Grade Conduit, Fittings, and Accessories
P 10 07 Electrical
4 Below-Grade Conduit, Fittings, and Accessories
P 10 08 Electrical
4 HVAC Equipment
P 10 09 Electrical
4 High Voltage (35.001 kV to 69 kV) Cable
P 10 10 Electrical
4 High Voltage (35.001 kV to 69 kV) Cable
P 11 11 Electrical
4 Very High Voltage (above 69 kV) Cable
P 11 12 Electrical
4 Receptacles and Cord-Connected Equipment
P 10 01 Electrical
7 Over-head Transmission and Distribution Systems
P 11 01 Electrical
1 Grounding / Bonding
P 11 02 Electrical
1 Lightning Protection Systems
P 11 01 Electrical
3 LV Induction Motors
P 1 02 Electrical
1
3 M.V. Induction Motors Nameplate Voltage: 4 kV, 6.6 kV, & 13.2
kV
55
56
K 00 07 HVAC
1 Refrigerant piping
K 00 08 HVAC
1 Air Filtration Devices
K 00 09 HVAC
1 Through-The-Wall and Window-Mounted Air Conditioners
0 Air Ventilation / Cooling Systems (Exhaust Hoods and Passively HVAC
K 0 10 Cooled Shelters)
1
It 00 11 HVAC
1 A / C Split System
K 00 12 HVAC
1 Testing, Adjusting and Balancing of HVAC Systems
1 10 01 Instrumentati
0 Flow Instrumentation on
J 20 01 Instrumentati
0 Pressure Instrumentation on
J 30 01 Instrumentati
0 Liquid Level Instrumentation on
J 40 01 Instrumentati
0 Temperature Instrumentation on
J 70 01 Instrumentati
0 Motor Operated Valves (MOV) and Control Valves (CV) on
J 90 01 Instrumentati
0 Instrumentation Control Loop Checking on
J 90 01 Instrumentati
2 Metallic Instrumentation and Control Cable on
9 03 Instrumentati
0 on
2 Factory Assembled (Packaged) Auxiliary Instrumentation Systems
J 90 04 Instrumentati
2 Fiber Optic Cable on
J 90 05 Instrumentati
2 Electronic Control Systems - DCS ESD PLC SCADA on
9 Instrumentation Racks and Panels (open); Terminal Boxes and Instrumentati
J 0 06 Instrument Cabinets (enclosed) on
2
J 90 01 Instrumentati
3 Intrinsically Safe (IS) Systems on
J 90 01 Instrumentati
4 Foundation Field bus System-Cables and accessories on
57
G 00 01 Mechanical
6 Positive Displacement Pump
H 00 01 Mechanical
2 Cement Lining of Pipes and Fittings
H 00 02 Mechanical
External FBE Coating of Field Welded Joints
H 10 01 Mechanical
0 Paint Application of liquid Coating System for Industrial
facilities
H 00 06 Mechanical
Renovation and Repair Coating for Submerged Services-
APCS113
H 00 08 Mechanical
Pipe Internal Coating and Installation
58
&9
N 14 01 Mechanical
0 Refractory Ceramic Fiber Installation
N 00 02 Mechanical
1 Hot Insulation
N LP 01 Mechanical
DE T Liquid Penetrant Testing
N M 01 Mechanical
DE PI Magnetic Pamcle Testing
N U 01 Mechanical
DE T Ultrasonic Testing
N R 01 Mechanical
DT T Radiographic Testing
S 0 01 Mechanical
20 Process Plant Oily Water Sewer System
W 01 01 Mechanical
0 Welding of Pressure Vessel
W 01 01 Mechanical
1 Welding of On-Plot Piping
W 01 01 Mechanical
2 Welding of Pipelines
W 01 01 Mechanical
4 Welding of Overlays and Cladding Restoration
Welding of Special Corrosion Resistant Materials-including Mechanical
Duplex SS
W 01 01 Mechanical
7 Welding of API Tanks
B 06 01 Plumbing
9 Emergency Eyewash/Shower System
S 01 01 Plumbing
0 Gravity Sewer Piping and Sewer Manhole
S 01 02 Plumbing
0 Lift Station and Piping / Force Main
S 03 01 Plumbing
0 Storm Drain
60
Oc AlXYZ Contracting Company (KCC) EMB
S 04 01 Plumbing
0 Water Distribution Piping
S 05 01 Plumbing
0 Bldg. Sprinklers and Standpipe System
S 06 01 Plumbing
0 Electric Water Heaters
S 06 02 Plumbing
0 Drinking Fountain
S 06 03 Plumbing
0 Skid Mounted Reverse Osmosis System
S 06 04 Plumbing
0 Plumbing Fixtures and Fixture Fittings
S 06 05 Plumbing
0 Roof Drainage Piping System
S 06 06 Plumbing
0 Building Sanitary Drainage, Waste and Vent (DWV) Piping
S 06 07 Plumbing
0 Neutralization Tank, Indirect Waste & Special Waste
S 06 08 Plumbing
0 Copper Piping
S 07 02 Plumbing
0 Irrigation Piping
S 07 03 Plumbing
0 Thermoplastic & RTR Piping
T 15 01 Plumbing
1 Direct Current Power Systems (-48 and -24 VDC)
T 48 01 Plumbing
1 Powered In-Plant Communication Systems
T 49 01 Plumbing
2 Powered In-Plant Communication Systems
T 62 01 Plumbing
4 Fiber Optic Communications Cable
T 62 01 Plumbing
Copper Communication Cable (OSP/ISP/CO)
T 74 01 Plumbing
4 Communication Towers and Facilities (ISP/CO)
T 91 01 Outside Plant (OSP) Duct banks Plumbing
1
T 93 01 Outside Plant (OSP) System Plumbing
8
T 91 01 Building Premises Distribution System (PDS) Plumbing
6
61
AlXYZ Contracting Company (KCC) EMB
a. Process Description will be briefly describing the process of Quality
Control Requirements.
d. Identify the specific procedures used for this particular quality control
activity.
Percentage to be
done
Mandatory Hold Point
H
sw Sample
Witness Inspection
R Review of Documents
8.3.1 The Internal Non-conformance Report (NCR) Form has been revised and
updated to suit the Project requirements. Agreed Completion Date (ACD) must
be indicated in the form and sections provided for Client Representatives name,
signature and date for concurrence of the internal NCR closure. In addition, the
62
AlXYZ Contracting Company (KCC) EMB
closure of Internal NCR shall be reviewed and concurred by the Contractor QA/QC
Manager.
8.3.2 Any element of work not meeting the specified standards shall be
Reported. Quality Assurance and Quality Control Department shall issue Internal
Non-Conformance reports for all violations by AI-XYZ, its subcontractors,
manufacturers, suppliers to contract requirements and Company approved
procedures.
a. Rework
c. Report or Scrap
8.3.5 Al-XYZ shall submit a copy of each Internal NCR to Company within 48 hrs.
Quality personnel responsible for disposition non-conformities shall ascertain
that the deviation or discrepancy is clearly described relative to the
acceptance criteria.
8.4.1 Al-XYZ collects and analyzes appropriate data to determine the suitability and
effectiveness of its quality management system and to identify where improvement can
be made in the quality management system.
63
Qc AlXYZ Contracting Company (KCC) EMB
8.4.2 The following data are gathered and analyzed, The Project Manager for
the effort and to ensure closure where QMS improvements are warranted.
f. Other as applicable
8.4.3 Al-XYZ prepare and submit a Quality Management Report in a format acceptable
to Client.
8.5 Improvement
8.5.1.1 AI-XYZ continually improve the suitability, adequacy and effectiveness of the
quality management system. Al-XYZ will sum up the result of analysis and
evaluation, and the outputs from the management review, to determine if
there are needs or opportunities to be addressed as a part of continual
improvement.
8.5.2.1 Al-XYZ will develop a corrective action program to eliminate the causes of
non-conformity and prevent its recurrence. The corrective action will be
appropriate to the severity of the non-conformity identified. Al-XYZ Internal
Management Manual has developed the procedure for Corrective and Preventive
Plan.
64
AlXYZ Contracting Company (KCC) EMB
8.5.2.2 When non-conformity occurs, including any arising from complainants,
Al-XYZ shall:
65
AlXYZ Contracting Company (KCC) EMB
8.5.2.2.1 React to the conformity and, as applicable:
• Take action to control and correct;
• Provide a definite action plan;
8.5.2.2.2 Evaluate the needs for action to eliminate the cause(s) of the non-
conformity, in order that it does not recur of occur elsewhere, by:
• Reviewing and analyzing the conformity;
• Determining the causes of the nonconformity;
• Determining if similar nonconformities exist, or could potentially occur;
8.5.2.2.3Implement any action needed;
8.5.2.2.4Review the effectiveness of any corrective action taken;
8.5.2.2.5Update risk and opportunities determined during planning, if necessary;
8.5.2.2.6Make changes to the quality management system, if necessary;
8.5.2.2.7 Corrective actions shall be appropriate to the effects of the nonconformities
encountered.
8.5.2.2.11 The identification of the significant condition adverse to quality, the cause
of the condition and the corrective actions taken shall be documented and reported
to the appropriate Discipline Head.
Quality Assurance shall continue to monitor the processes and work operation and
analysis of records to detect and eliminate potential causes of non-
conforming product.
66
AlXYZ Contracting Company (KCC) EMB
RISK MANAGEMENT :
The purpose of this process is to provide guidelines for Risk Management process within
the Organizafion to have systematic application of management policies,
documented
information, process, services and practices to the tasks of establishing the context, identifying,
analyzing, assessing, treating, monitoring and communicating".
It is an iterative process that, with each cycle, can contribute progressively to
organizafional improvement by providing management with a greater insight into risks
and their impact.
Risk management can be applied to all levels of organizafion, in both the strategic and
operational contexts, to specific projects, decisions and recognized risk areas.
It also develop the Mifigafion or further controls for every identified risk to occur in the Project.
9.0 Procurement
66
9.5.2 KCC Purchasing discipline will prepare and issue a formal Purchase
Order to the Vendor based on a complete and revised Material Requisition
(MR) issued from engineering signed by Project Manager. Purchasing will
be
responsible for insuring that the Purchase Order is complete commercially,
incorporating all agreed terms and conditions, and that the technical
attachment is completed. The Purchase Order package will generally
comprise of, but not limited to, the document mentioned in Specifications.
67
AlXYZ Contracting Company (KCC) EMB
9.6.2 The appraisal of suppliers/vendors offer are done and evaluated in
the following parameters:
Technical Commercial
1. Complete understanding of Scope of work 1. Reasonable Price
2. Knowledge in specification comparison compliance 2. Terms and condition of payments
3. Quality Inspection requirements and acceptance 3. Validity period
4. Responsiveness of delivery schedule 4. Warranties
S. Availability of replacement spare parts 5. Insurance coverage , tax and other
6. All other technical and quality criteria that Client requires ascertaining full i" U e
' ‘
compliance to acceptable international, local codes and standards.
9.7.1 The Quality Control activities for inspection verification report on-site and off-site
9.7.2 The QA/QC Manager will lead the discipline QC Inspector in performing
inspection and testing with the direction of Procurement Manager. Every QC
personnel are to be directly related to the scope of work of this Project.
9.7.3 Responsibilities:
The QA/QC Manager at each location leads the QC team will coordinate with the
Project Manager. Every QC personnel are to be directly related to the
scope of work for this Project.
e. Review KCC scope of work and identify any specialist support that
may be needed (through the Project Manager)
68
AlXYZ Contracting Company (KCC) EMB
f. Monitor the performance of specialist subcontractors e.g. NDT,
concrete testing, equipment calibration, etc.
h. Ensure that all required inspection and testing reports are correctly
prepared in a timely manner.
69
@ AlXYZ Contracting Company (KCC) EMB
Other
70
@ AlXYZ Contracting Company (KCC) EMB
instructions may be acted upon directly by the QC team and
reported in the QC Monthly Report, as necessary.
9.8.1 A detailed report describing the type of fabrication work undertaken by the
vendor/manufacturer. The extent and finding of testing and inspection activities
70
AlXYZ Contracting Company (KCC) EMB
completed including all associate NDT reports and recommendations. Reports
which include the progress of work that has been completed and performed and
the status of ongoing activity. The inspection reports will have drafted by the
assigned inspector,
review by QC Supervisor and approved by the QA/QC Manager.
9.10.1 Upon completing all requirements, the Technical, Quality and Commercial
and has been compiled by the bidders, Al-XYZ Awarding Committee will give its final
disposition to award the contract to the successful bidder. The necessity of pre-
award meeting for the successful bidders will be conducted by Al-XYZ awarding
committee to finalize any outstanding commercial, technical or quality matters, and
that the vendor is fully aware of his obligations. Engineering, Quality Inspection and
expediting will attend as necessary. Sustaining minutes will be recorded by every
discipline signed by
attendees and retained by the Procurement Manager.
9.10.2 Award recommendations and no objection letter will be issued to successful
bidder. AlXYZ will send the recommended Vendor’s name to Client to sign the No
Objection
Letter.
71
AlXYZ Contracting Company (KCC) EMB
ASPE American Society of Plumbing Engineers
ASTM American Society for Testing and Materials
AWS American Welding Society
AWWA American Water Works Association, Inc.
BSI British Standards Institute
CSI Construction Specification Institute
CRS Concrete Reinforcing Steel Institute
10. Attachment
72
Oc AlXYZ Contracting Company (KCCJ EMB
10.1Standard Forms
AL-XYZ CONTRACTING
73
1.1.1 AI-XYZ evaluates and selects Sub-contractors based on their ability to supply
services in accordance to Al-XYZ requirements and conforming legal requirements related
to quality, environmental, health and safety. Criteria for selection, evaluation and
periodical reevaluation have been established.
1.1.2 All Sub-contractors, External Providers, Suppliers and Vendors are subject
for review and assessment of their QHSE System and / or supply and services
capability. An initial assessment involves sending a letter requesting theme to submit
appropriate quality services, product information and related document information. If
the results are acceptable, Al-XYZ Quality QHSE Manager, Material Management
Manager and HR Manager will make a request to externally audit. All successful Sub-
contractors, External Providers, Suppliers and Vendors will be included in Al-XYZ
approved list. All approved Subcontractors, External Providers, Suppliers and Vendor
will be controlled by Al-XYZ approving departments on their performance and ability
will be monitored.
74
0 AlXYZ Contracting Company (KCCJ EMB
1.1.3 If the situation arises where customer requires verifying the services, supply
of equipment being supplied by AI-XYZ, the main contractor along with the
subcontractors, external provider, suppliers and vendors will allow the
customer/client full access and assistance to do so. In addition, for off-shore operation
activity, customer/client representatives will witness and signs accepting all
equipment prior to the mobilization from Al-XYZ premises to customer location.
1.2.1 Contract - An agreement between two or more panes that creates an obligation
to perform a particular duty.
1.2.4 Statement of Work - A method that outline the procedure that the sub-
contractor will employ in accordance with the goals of the Project proposed by the
main contractor in the contract.
1.3.1 PURPOSE:
The purpose of this Procedure is to describe the means by which Al-XYZ to manage
and control the subcontractors based upon their ability to meet all contract
requirements including quality, environmental, health and safety.
1.3.2 SCOPE:
75
Oc AlXYZ Contracting Company (KCC) EMB
These scope covers on how Contractor’s control over the subcontractors on the
following activities:
1.3.2.1 Develop and maintain the schedule identifying all contract scope of work
to be sub contracted.
1.3.2.2 Identifying within the schedule any requirements for manufacturer’s
field services and also include details on these within the relevant Inspection
and Test
Plan. Maintain all records of all quality control activities related to manufacturer’s field
services requirements including inspection records signed off by an authorized
Technical Representatives on behalf of the Supplier/Manufacturer.
1.3.2.5 Attendance at all necessary hold points and offsite inspection and test.
1.3.2.6 Induction of subcontractors on Project quality, environmental,
safety and health requirements providing theme access to Al-XYZ Project
Quality Plan
at all times.
1.4 Responsibilities:
C. To maintain and assure the high quality and safety during every stage of
execution.
e. Manage and verify the sub-contractor’s activity two weeks look ahead,
progress schedule has been maintained.
b. List down all required drawings to be prepared by the subcontractors and plan
a schedule of submission for review and approval.
c. Review and validate all sub-contractor’s submitted drawings prior final submittal.
77
AlXYZ Contracting Company (KCC) EMB
e. Coordinate with subcontractors for material/equipment submittal approval,
materials samples to be handed to QC Department for verification and
validation prior to final inspection for Client’s acceptance.
g. Sub-contractor new personnel shall be inducted for quality information prior to start
their work.
h. Conduct weekly meetings with AI-XYZ QC and Sub-contractor QC to plan QC
activities and discuss Quality problem arising during construction.
1.5 Sub-contractor in Preparation of Work Procedure:
7.7.2.4.1 The QA/QC Manager will request from the Sub-Contractor’s Quality Team
to submit their Method Statement for review prior to submission to Client for final
approval. Upon getting the approval of such submittal, the QA/QC Manager will invite
Sub-contractor QC Team for preparatory meeting and this will be attended by
Construction Manager and Safety Manager to discuss the work procedure that is
mentioned in the method statement including safety information which is attached in
the document. Also coordination among Al-XYZ and Sub-contractor personnel for the
work interfacing each other to avoid conflict, risk to workers and equipment during
execution. In addition, in the meeting the sub-contractor will be requested to provide a
mock up set as a model on activity in connection with the method statement and this
mock-up will be approved by the Client prior to start the work. Al-XYZ QA/QC Manager, QC
discipline Inspector, and sub-contractor
78
Oc AlXYZ Contracting Company (KCC) EMB
QC jointly will conduct a surveillance inspection ensuring that the work procedure has
been applied correctly, likewise the approved mock-up was exactly followed by the sub-
contractor.
1.6 Al-XYZ Quality Control over the Sub-contractor in Preparation for Work
Inspection.
1.6.1 QCM will request the Sub-contractor to submit their two weeks look ahead
to be included in Al-XYZ two weeks look ahead schedule as part of agenda during
weekly progress meeting and this will be also the guide for inspection schedule to be
submitted to Client 24 hrs. during regular working days and 48 hours during the week
end, moreover Al-XYZ QC Inspector and sub-contractor’s QC jointly will do their
preliminary inspection of the work and in case there are comments, the sub-contractor
will promptly rectify such comment prior to submit inspection request to Client. In the
case of third party inspection or testing, the sub-contractor QC will coordinate to Al-
XYZ QC for sending request at Investigation, Inspection and Testing Agency (IITA) and
Client to witness the events. In terms of Inspection and Test Plan (ITP), Al-XYZ has
decided to ufllize Client Inspection and Test Plan Client Inspection Criteria, this will be
applied to the Sub-Contractor inspection processes; however, AI-XYZ will issue this
document to Sub-contractor in the form of controlled manner.
1.7 Al-XYZ Quality Control over Sub-contractor for Calibration of Testing Device.
1.8.1 PURPOSE:
The purpose of this Procedure is to describe the means by which AI-XYZ Discipline
Quality Control Personnel will report their observations and recommendations
during the course of construction.
79
Oc AlXYZ Contracting Company (KCC) EMB
1.8.2 SCOPE:
These scope covers to all in- site and off-site activities undertaken by Al-XYZ workers
and Sub-contractors in every discipline.
1.8.3 Procedure:
During In-site and Off-site operation all QC Discipline Inspectors are deployed at
site inspection, observation, witness, verification and surveillance on all ongoing
activities. Any activity being observed that does not follow the correct procedure or
does not comply the contract specification QC will immediately stop the work and
report with the site supervisor on irregularities that his workers being committed. Not
to delay the work, the Discipline QC will give his recommendation to the Site supervisor
to correct such comments and to be rectified immediately. Upon complying the
violation, the QC will allow the work to proceed. In other instances, the activity has
been done and completed but it was found to be defective and not acceptable, the QC
will issue proactive notification to the site supervisor with the instruction on how to
execute the rectification of such defects, in case the construction does not comply with
the comment, the QC Inspector will issue an internal NCR address to the Construction
Manager thru his site supervisor and that certain activity should not continue until the
internal NCR will be closed. These numbers of internal NCR being committed by the
discipline supervisor and Construction Manager will be counted and it will reflect
against their key performance indicator (KPI) which will be reported to the higher
management for an action. Pro-active notification will be made in the form of quality
action notices (QAN). In case a certain ongoing activity does not comply the
specification requirements or follow quality system, QC will issue a pro-active
notification address to the Construction manager thru his site supervisor in order not to
continue the wrong procedure or violation which will ultimately cause a rework and
time delay. QC shall clearly define his comment on specific activity being committed. QC
will also clarify his disposition, instruction, or recommendation on how to rectify the
comment. Upon complying the comment both QC and Site Supervisor will do the
inspection to close out the issued pro-active notification.
1.8.4 Responsibilities
a. Provide a safe working environment on all ongoing activities at the Project site.
b. Provide and assign the right person and the right equipment for the type of
work to be executed.
c. Overall responsible for the safety and quality of his workers and equipment at
site.
d. Provide the correct instructions to all his supervisors managing the workers under
their responsibility.
e. Responsible for the planning of all activities to be executed at the site.
80
c. Coordinate with Site QC Inspector and Safety Personnel during activity execution.
d. Responsible for the quality and safety on all activities done by his worker.
e. To correct all defective work being done by his worker that does not comply
with the requirements as per contract specifications and methodology.
g. Ensure workers are wearing safety protective equipment prior to work at site.
h. Ensure all equipment is in good condition with proper check-up and licenses.
e. Verify all operators, drivers and riggers have proper training and licenses.
f. Stop and report all unsafe and risky activity to be corrected immediately by
the site Supervisor and work shall not continue until unsafe condition being
rectified.
81
AlXYZ Contracting Company (KCC) EMB
2.1.1 The procedure to control all Quality Control documentation required by the
Contract, Technical Specifications, Design Drawings, or the Quality Control
Specification shall adhere to the following requirements;
a.
All Quality Control records will be kept in a centralized area and filed in
chronological order by pay items by possible. If reports related to a
system, including several pay items, they will be filled by Section of the
Technical
Specification to which they are referred.
b.
The filling of records shall be kept current and open to review by the Client.
c. All Quality Control records are easily identified and traceable to specific
requirement in the specification and drawings.
d. The Quality Control records, package for each pay item and index foresee
of reference will be turned over to the Client prior to initial acceptance.
2.1.2 Purpose
The purpose of this procedure is to establish and define the control needed for the
identification, storage, protection, retrieval, retention time and disposition
of records.
2.1.3 Scope
2.1.4 Responsibilities
a. The Quality Control Department makes provision for the storage and protection of the
records under his control.
a. QA/QC Manager through his document controller that all below listed
records for which directly responsible are index, file in logical manner,
such they are ready retrievable at all times.
PURPOSE
Risk Management is defined as "the systematic application of management policies, documented
information, process, services and practices to the tasks of establishing the context, identifying,
analyzing, assessing, treating, monitoring and communicating".
It is an iterative process that, with each cycle, can contribute progressively to organizational
improvement by providing management with a greater insight into risks and their
impact.
Risk management can be applied to all levels of organization, in both the strategic and operational
contexts, to specific projects, decisions and recognized risk areas.
Risk is defined as 'the chance of something happening that will have an impact on
objectives'. It is, therefore, important to understand what the objectives of the Organization,
department, projects, process and position of an employee, are, and prior to attempting to
analyze the risks.
The purpose of this process is to provide guidelines for Risk Management process
within the Organization.
SCOPE
This process applies to all Company Departments, Sections, process and Projects of AI XYZ
Contracting Company.
REFERENCE DOCUMENT
ISO 9001:2015
ISO 14001:2015
ISO 45001:2018
KCC Integrated Management System Manual
RESPONSIBILITY :
CEO
QHSE Manager
Department Managers
84
AlXYZ Contracting Company (KCC) EMB