Professional Documents
Culture Documents
Aim
• To familiarize with Primavera Software, a well
known project planning and scheduling and
monitoring tool.
Basic Concepts
What is a Project ???
Activity:
Activities represent work to be done in order to
complete a project.
Predecessor
Successor
Basic Terminologies
Successor:
The activity for which start or finish dates are dependent
on other activities (predecessor activities).
Predecessor
Successor
Basic Terminologies
Relationship:
Any sort of connection between two activities is
known as relationship.
Generally there are four types of relationships:
SS (Start to Start)
FS (Finish to Start)
FF (Finish to Finish)
SF (Start to Finish)
Basic Terminologies
Lag :
Lag staggers or delays the relationship of one activity
(predecessor) to another (successor).
Basic Terminologies
SS – Relationship between activities in which the start
of a successor activity depends on the start of its
predecessor.
A
Predecessor
Start-to-start
B
Successor
A
Start-to-start with lag Predecessor
Lag B
Successor
Basic Terminologies
FS – Relationship in which the start of successor
activity depends on the completion of its predecessor
activity.
Finish-to-start A
Predecessor
B
Successor
Finish-to-Finish A
Predecessor
B
Successor
Start-to-Finish A
Predecessor
B
Successor
A
Start-to-Finish with lag Predecessor
Lag
B
Successor
Basic Terminologies
FF (Free Float):
The amount of time, measured in planning units, the early start
of an activity can be delayed without delaying early start of a
successor activity. Such activities are called Non-critical
Activities.
Basic Terminologies
Constraints:
Constraints are ground realities that over-rule the logical
start and finish time of the activity.
Critical Path:
Chain of critical activities that has potential of delaying a
project is called Critical Path.
Successor
Forward Pass:
The process of calculating start and finish dates of each activity
starting from the project start date.
This process generates early start and early finish
dates for each activity.
Basic Terminologies
Backward Pass:
The process of calculating finish and start dates of each activity
starting from the project finish date.
This process generates Late Start and Late Finish
dates for each activity.
Data Date:
The point in time that separates actual (Historical) data
from future (Scheduled) data.
Basic Terminologies
Man-Hours:
It is yardstick for measurement of effort. For example, 4
Man-Hour will mean any of the following:
▫ 1 man working for 4 hours
▫ 2 men working for 2 hours
▫ 4 men working for 1 hour
Standard Man-Hours:
Estimated effort per unit required to perform a job in terms
of man-hours.
Basic Terminologies
Budgeted Cost:
Total estimated cost approved for execution of a project.
Cost at Completion:
The expected total cost at completion of an activity or a
project.
Cost at completion is estimated periodically during course
of project execution.
Basic Terminologies
Program Evaluation and Review Technique (PERT):
An event oriented network analysis technique used to estimate
project duration when there is a higher degree of uncertainty with
the individual activity duration estimates. PERT applies the Critical
Path Method (CPM) to a weighted average duration estimates.
Gantt Chart:
A graphic display of schedule-related information listing project
elements on left side of the chart, dates across the top and activity
durations are shown as date-placed horizontal bars. It is also known
as Bar Chart.
PERT
GANTT
Basic Terminologies
Resource:
• Manpower
• Tools & Plants
• Direct materials
• Consumables
• Special jigs & fixtures
Resource Allocation & Leveling
1. Project
1.1 Construction
1.1.1 Discipline
1.1.1.1 Zone/Area
PROJECT/SITE MANAGER