SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 30-Mar-13

SATR NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO TEST REPORT
Galvanic CP Testing SATR-X-3101 30-Apr-13 CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. PROCEDURE

Ensure that the proper voltmeters and ammeters and suitable reference SAES-X-400
A1
electrodes was used for CP testing.SAEP-332, Section 7 Sec. 3.1

Check the meter batteries periodically to ensure they still function


SAES-X-400
A2 properly. Generally, they should be replaced every year. SAEP-332,
Sec. 3.1
Section 7

SAES-X-400
A3 Ensure that all meters was calibrated.SAEP-332, Section 7
Sec. 3.1

Ensure that high input impedance meters for structure-to-electrolyte


potential measurements, especially in areas of high resistivity was used. SAES-X-400
A4
Input impedance should be 20 megohms or greater.SAEP-332, Section Sec. 3.1
7

Use a clamp-on-ammeter for the direct measurements of DC currents.


SAES-X-400
A5 Meters having current measuring capacity up to 200 amps and a variety
Sec. 3.1
of clamp sizes are preferred.SAEP-332, Section 7

Ensure that the copper-copper sulfate and silver-silver chloride SAES-X-400


A6
reference electrodes was properly maintained.SAEP-332, Section 7 Sec. 3.1

Check test leads of voltmeters used for structure-to-electrolyte


measurements periodically, for continuity and integrity. Repair or replace SAES-X-400
A7
faulty leads or connections before making measurements. SAEP-332, Sec. 3.1
Section 7

The minimum design life for galvanic or impressed current anode


SAES-X-500
A8 systems shall be either 7 years, or the testing and inspection (T&I)
Sec. 4.3.1
period, whichever is greater.

B. TEST EQUIPMENT AND MATERIALS CRITERIA

B1. Multimeter

C. TEST RESULTS

STRUCTURE TO POLARIZATION
GALVANIC ANODE
EQUIPMENT IDENTIFICATION TEST POINTS LOCATION ELECTROLYTE CURRENT REMARKS
TYPE (Amp)
POTENTIAL (mV)

Volt Meter
Brand: ______________

S/N: ______________
Page 1 of 3
Calib. Date:___________
Volt Meter
Brand: ______________

S/N: ______________

Calib. Date:___________

Ammeter
Brand: ______________

S/N: ______________

Calib. Date:___________

Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 30-Mar-13
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Galvanic CP Testing SATR-X-3101 30-Apr-13 CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

D. CONCLUSIONS

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Safety
Cathodic protection personnel are responsible for obtaining appropriate SAES-P-332
D1
work permits and associated gas test results from the operations Sec. 4
foreman in all classified areas before starting any job.

Test results are acceptable and in accordance with Saudi Aramco Schedule Q
D2
Engineering Standards and contractual requirements. Att. IV, Sec. 3

REMARKS:

REFERENCE DOCUMENTS:
1. SAEP-332 Cathodic Protection Commissioning, 25 December 2011
2. SAES-X-400 Cathodic Protection of Buried Pipelines, 13 December 2011
3. SAES-X-500 Cathodic Protection of Vessel and Tank Internals, 2 September 2009

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Name, Title, Department, Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Company, Initials and Name, Initials and Date:
Date:
QC Inspector PID Representative
Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Page 3 of 3