EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
A. PROCEDURE
Ensure that the proper voltmeters and ammeters and suitable reference SAES-X-400
A1
electrodes was used for CP testing.SAEP-332, Section 7 Sec. 3.1
SAES-X-400
A3 Ensure that all meters was calibrated.SAEP-332, Section 7
Sec. 3.1
B1. Multimeter
C. TEST RESULTS
STRUCTURE TO POLARIZATION
GALVANIC ANODE
EQUIPMENT IDENTIFICATION TEST POINTS LOCATION ELECTROLYTE CURRENT REMARKS
TYPE (Amp)
POTENTIAL (mV)
Volt Meter
Brand: ______________
S/N: ______________
Page 1 of 3
Calib. Date:___________
Volt Meter
Brand: ______________
S/N: ______________
Calib. Date:___________
Ammeter
Brand: ______________
S/N: ______________
Calib. Date:___________
Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 30-Mar-13
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Galvanic CP Testing SATR-X-3101 30-Apr-13 CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
D. CONCLUSIONS
ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Safety
Cathodic protection personnel are responsible for obtaining appropriate SAES-P-332
D1
work permits and associated gas test results from the operations Sec. 4
foreman in all classified areas before starting any job.
Test results are acceptable and in accordance with Saudi Aramco Schedule Q
D2
Engineering Standards and contractual requirements. Att. IV, Sec. 3
REMARKS:
REFERENCE DOCUMENTS:
1. SAEP-332 Cathodic Protection Commissioning, 25 December 2011
2. SAES-X-400 Cathodic Protection of Buried Pipelines, 13 December 2011
3. SAES-X-500 Cathodic Protection of Vessel and Tank Internals, 2 September 2009
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED
Page 3 of 3