Magnetic Marker Installation 3 21-May Pull through Test 1 7-Jul Mobilization of Tools up to MBCT 2 6-Jun Mobilization of MFL Tool 2 12-Jul Profile Pig Run 1 25-Jun MBCT Pig Run 1 26-Jun MFL Tool Run 1 14-Jul Submision of Preliminary Report 30 16-Jul Attend Dig Verification 15 17-Aug Submision of Final Report & FFP/RRR 10 3-Sep Acceptance of Final Report & FFP/RRR 7 14-Sep RBhPL IP Sch 21-May 10-Jun 30-Jun 20-Ju
Magnetic Marker Installation
Pull through Test
Mobilization of Tools up to MBCT
Mobilization of MFL Tool
Profile Pig Run
MBCT Pig Run
MFL Tool Run
Submision of Preliminary Report
Attend Dig Verification
Submision of Final Report & FFP/RRR
Acceptance of Final Report & FFP/RRR
RBhPL IP Schedule 30-Jun 20-Jul 9-Aug 29-Aug 18-Sep 8-Oct