Professional Documents
Culture Documents
Industrial Applications
Doug Durand, P.E.
▫ Introduction
▫ Using Log-Log Paper & TCCs ▫ Transformer Overcurrent Protection
▫ Motor Overcurrent Protection
▫ Types of Fault Current
▫ Conductor Overcurrent Protection
▫ Protective Devices & Characteristic ▫ Generator Overcurrent Protection
Curves
▫ Coordinating a System
▫ Coordination Time Intervals (CTIs) ▫ Coordination Quizzes
▫ Effect of Fault Current Variations ▫ Coordination Software
▫ Multiple Source Buses ▫ References
▫ Partial Differential Relaying
▫ Directional Overcurrent Coordination
Slide 2
Introduction
Protection Objectives
• Personnel Safety
Slide 4
Protection Objectives
• Equipment Protection
Slide 5
Protection Objectives
Slide 6
Types of Protection
•Distance
•High-Impedance Differential
•Current Differential
•Under/Overfrequency
•Under/Overvoltage
•Over Temperature
•Overload
•Overcurrent
Slide 7
Coordinating Overcurrent Devices
Slide 8
Coordinating Overcurrent Devices
Slide 9
Coordinating Overcurrent Devices
Slide 10
Coordinating Overcurrent Devices
Slide 11
Coordinating Overcurrent Devices
• Old-world craftsmanship…
Slide 12
Coordinating Overcurrent Devices
Slide 13
Coordinating Overcurrent Devices
• New-world craftsmanship…
Slide 14
Using Log-Log Paper & TCCs
Log-Log Plots
Time-Current Curve (TCC)
1000
effectively
steady state Why log-log paper?
100
1 minute I2t withstand
curves plot as
straight lines
• Log-Log scale compresses
values to a more manageable
Time In Seconds
10
typical motor range.
acceleration
0.1 5 cycles
(interrupting)
FLC = 1 pu Fs = 13.9 pu Fp = 577 pu
1 cycle
(momentary)
0.01
0.1 1 10 100` 1000 10000
Current in Amperes
Slide 16
Plotting A Curve
5000 hp Motor TCC
1000
13.8 kV
FLC = 598.9 A
100
13.8/4.16 kV
10 MVA
6.5%
Time In Seconds
10
Accel. Time = 2 s
4.16 kV
Slide 17
Plotting Fault Current & Scale Adjustment
5000 hp Motor TCC with Fault on Motor Terminal
1000
13.8 kV
FLC = 598.9 A
100
13.8/4.16 kV
10 MVA
6.5%
Time In Seconds
10
Accel. Time = 2 s
4.16 kV
1 15 kA
Slide 18
Voltage Scales
5000 hp Motor TCC with Fault on Transformer Primary
45 kA @ 13.8 kV 1000
13.8 kV
= ? @ 4.16 kV
= (45 x 13.8/4.16) 100
45 kA
= 149.3 kA @ 4.16 kV 13.8/4.16 kV
10 MVA
6.5%
Time In Seconds
10
4.16 kV
1 15 kA
Slide 19
Types of Fault Currents
Fault Current Options
Crest/Peak
Current
Interrupting/Breaking
Momentary
Initial Symmetrical
ANSI IEC
• Momentary Symmetrical • Initial Symmetrical (Ik’’)
• Momentary Asymmetrical • Peak (Ip)
• Momentary Crest • Breaking (Ib)
• Interrupting Symmetrical • Asymmetrical Breaking (Ib,asym)
• Adjusted Interrupting Symmetrical
Slide 21
Fault Current Options
Crest/Peak
Current
Interrupting/Breaking
Momentary
Initial Symmetrical
Slide 22
Protective Devices & Characteristic
Curves
Electromechanical Relays (EM)
100
IFC 53
RELAY
Very Inverse Time
Time-Current
10 Curves
TIME IN SECONDS
1
10
Time Dial
Settings
3
2
0.1 1
½
0.01
1 10 100
MULTIPLES OF PICK-UP SETTING
Slide 24
Electromechanical Relays – Pickup Calculation
IFC
For the IFC53 pictured, the available 800/5
53
Set AT = 4
ampere-tap (AT) settings are 0.5, 0.6,
0.7, 0.8, 1, 1.2, 1.5, 2, 2.5, 3, & 4.
M
4.16 kV
For this type of relay, the primary pickup 5000 hp
current was calculated as: FLC = 598.9 A
SF = 1.0
PU = CT Ratio x AT
Slide 25
Electromechanical Relays – Operating Time Calculation
100
4.16 kV
IFC 53
RELAY
TIME IN SECONDS
M
1.21 4.16 kV
1 5000 hp
1.05 10
Slide 26
Solid-State Relays (SS)
Slide 27
Solid-State Relays (SS)
Slide 28
Microprocessor-Based Relays
2000/5 52B
01-52B
41-SWGR-01B
13.8 kV
400/5 OCR F15B
01-F15B
52B
OC1
ANSI-Normal Inverse
Seconds
Pickup = 2.13 (0.05 – 20 xCT Sec)
Time Dial = 0.96
Inst = 20 (0.05 – 20 xCT Sec)
F15B Time Delay = 0.01 s
OC1
ANSI-Extremely Inverse
Pickup = 8 (0.05 – 20 xCT Sec)
Time Dial = 0.43
Inst = 20 (0.05 – 20 xCT Sec)
Time Delay = 0.02 s
52B – 3P
F15B – 3P
30 kA @ 13.8 kV
Slide 29
Microprocessor-Based Relays
Slide 30
Power CBs
Seconds
LT Pickup = 1 (3200 Amps)
LT Band = 4
ST Pickup = 2.5 (8000 Amps)
Power FCB ST Band = 0.3 (I^x)t = OUT
Cutler-Hammer RMS 520 Series
Sensor = 1200 ST Pickup
LT Pickup = 1 (1200 Amps)
LT Band = 2
ST Pickup = 4 (4500 Amps) ST Band
ST Band = 0.1 (I^x)t = OUT
Slide 31
Insulated & Molded Case CB
Seconds
LT Pickup = Fixed (1200 A)
LT Band = Fixed
ST Pickup = 4 x (4000 A)
ST Band = Fixed (I^2)t = IN
Override = 14000 A
Molded Case CB
HKD
Size = 250 A
Terminal Trip = Fixed
Magnetic Trip = 10
Fault current
< Inst. Override
Slide 32
Insulated & Molded Case CB
Seconds
LT Pickup = Fixed (1200 A)
LT Band = Fixed
ST Pickup = 4 x (4000 A)
ST Band = Fixed (I^2)t = IN
Override = 14000 A
Molded Case CB
HKD
Size = 250 A
Terminal Trip = Fixed
Magnetic Trip = 10
Fault current
> Inst. Override
Slide 33
Power Fuses
MCC 1
4.16 kV
Mtr Fuse
Mtr Fuse
JCL (2/03)
Standard 5.08 kV
5R
Seconds
Total
Clearing
Minimum
Melting
Mtr Fuse
15 kA @
4.16 kV
Slide 34
Coordination Time Intervals (CTIs)
Coordination Time Intervals (CTIs)
Slide 36
Coordination Time Intervals – EM
Seconds
Feeder
?s
30 kA
Slide 37
Coordination Time Intervals – EM
It is continuously adjustable
and not exact.
FIELD TESTING !
(not just hand set)
Slide 38
Coordination Time Intervals – EM
Plotting the field test points.
Feeder
Seconds
3x (9.6 kA), 3.3 s
“3x” means 3 times pickup
3 * 8 = 24 A (9.6 kA primary) 5x (16 kA), 1.24 s
8 * 8 = 64 A (25.6 kA primary)
30 kA
Slide 39
Coordination Time Intervals – EM
be?
Feeder
30 kA
Main w/ testing
Seconds
Main w/o testing
But, if test points are provided
what should the CTI be? Feeder
0.3 s 0.4 s
30 kA
Slide 40
Coordination Time Intervals – EM
Slide 41
Coordination Time Intervals – EM
Red Book (IEEE 141-1993, per Section 5.7.2.1)
Components
Buff Book (IEEE 242-2001, taken from Tables 15-1 & 15-2)
Slide 42
Coordination Time Intervals – EM & SS
So, lets move forward a few years….
For a modern (static) relay what part of the
margin can be dropped?
So if one of the two relays is static, we can
use 0.2 s, right?
Slide 43
Coordination Time Intervals – EM & SS
Seconds
Feeder (SS) Feeder EM
0.3 s
0.2 s
Amps X 100 (Plot Ref. kV=13.8) Amps X 100 (Plot Ref. kV=13.8)
Slide 44
Coordination Time Intervals – EM/SS with Banded Devices
OC Relay combinations with banded devices
disk overtravel x -
Static Relay
CT, relay errors √ 0.12 s
Power
Fuse Static Trip or
operating time x -
0.12 s
Molded Case
Breaker CTI
Slide 45
Coordination Time Intervals – EM/SS with Banded Devices
Seconds
0.22 s 0.12 s
25 kA 25 kA
Amps X 100 (Plot Ref. kV=0.48) Amps X 100 (Plot Ref. kV=0.48)
Slide 46
Coordination Time Intervals – Banded Devices
• Banded characteristics include
tolerances & operating times.
• There is no intentional/
additional time delay needed
between two banded devices.
• coordination of instantaneous
trips cannot be demonstrated
on TCCs.
Slide 47
Coordination Time Intervals – Summary
Slide 48
Effect of Fault Current Variations
CTI & Fault Current Magnitude
Relay Operating
Current Time Feeder
F1 = 10 kA
For a fault current of 10 kA the Main F2 = 20 kA
Seconds
CTI is 0.2 s.
Slide 50
Total Bus Fault versus Branch Currents
10 kA
15 kA
1.2 kA 0.8 kA 2 kA 1 kA
M M M
• For a typical distribution bus all feeder relays will see a slightly different
maximum fault current.
• Years back, the simple approach was to use the total bus fault current as
the basis of the CTI, including main incomer.
• Using the same current for the main led to a margin of conservatism.
Slide 51
Total Bus Fault versus Branch Currents
10 kA
Using Total Bus Using Actual
Fault Current of 15 kA Incomer Relay
15 kA Current of 10 kA
Feeder Feeder
M
Main
Main
Seconds
0.8 s
0.2 s
15 kA 10 kA 15 kA
Amps X 100 (Plot Ref. kV=13.8) Amps X 100 (Plot Ref. kV=13.8)
Slide 52
Curve Shaping
Seconds
current levels.
• This is a highly-recommended
0.2 s
change to old-school thinking.
20 kA
15 kA
10 kA
Slide 53
Curve Shaping – Danger of Independent OC Units
Seconds
• Under certain setting conditions, such
as with an extremely inverse
characteristic, the intended definite 0.2 s
time delay can be undercut at higher 0.1 s
fault levels.
40 kA
20 kA
15 kA
10 kA
Amps X 100 (Plot Ref. kV=13.8)
Slide 54
Multiple Source Buses
Multiple Source Buses
• Plotting the source curves to the total bus fault current will lead to
much larger than actual CTIs.
Slide 56
Multiple Source Buses
1 30 kA 1 1
Seconds
(don’t do this) 1.1 s
0.2 s
12 kA 30 kA 12 kA 30 kA
Amps X 100 (Plot Ref. kV=13.8) Amps X 100 (Plot Ref. kV=13.8)
Slide 57
Curve Shifting
• For example: 2 3
Slide 58
Curve Shifting
2.5 x
“7500 A pickup is
misleading/confusing
1 .
30 kA 1 1 2
2
Seconds
Doesn’t look
coordinated but is.
0.2 s 0.2 s
12 kA 30 kA 30 kA
Amps X 100 (Plot Ref. kV=13.8) Amps X 100 (Plot Ref. kV=13.8)
Slide 59
Multiple Source Buses with Closed Tie
10 kA 10 kA 5 kA
Bus A Bus B
15 kA (Fa)
10 kA (Fb)
Fa = 25 kA Fb = 25 kA
Slide 60
Partial Differential Relaying
Partial Differential (Summation) Relaying
Slide 62
Partial Differential Relaying
Slide 63
Partial Differential Relaying
Ip1 Is1
Is1+Is2+Is3
Is2
Ip2 0 • A dedicated relay is needed
Ip3
Is3
for each bus section.
Is2+ Is2+
Is3 Is3
• Partial differential schemes
Bus A Bus B
Ip2+Ip3 simplify the coordination of
Ip1+Ip2+Ip3
multiple source buses by
ensuring the main relay for
each bus always see the
Feeder A Feeder B
same current as the faulted
feeder.
Slide 64
Directional Overcurrent Relaying
Directional Current Relaying
67 67
Bus A Bus B
Slide 68
Transformer Overcurrent Protection
Slide 69
Transformer Overcurrent Protection
Relay pickup
Primary
FLC = 2.576 MVA/(√3 x 13.8) = 107.8 A PWR-MCB
Relay PU must be ≤ 600% FLC = 646.6 A
Using a relay setting of 2.0 x CT, the relay
PU = 2 x 200 = 400 A
2.576 MVA, 5.75% Z
400 / 107.8 = 371% so okay ∆-Y Resistor Ground
Secondary
Seconds
FLC = 2.576 MVA / (√3 x 0.48) = 3098 A
13.8 kV R-Primary
MCB Trip must be ≤ 250% FLC = 7746 A 200/5 optional time
Breaker Trip = 3200 A per bus rating R-Primary
delay settings
Slide 70
Transformer Overcurrent Protection
∆-Y Connections – Phase-To-Phase Faults
0.5 a
A
1.0 0
0.86
B b
0.5 c
C 0.86
Seconds
the primary.
Slide 71
Transformer Overcurrent Protection
∆-Y Connections – Phase-To-Ground Faults
1.0 2.576 MVA, 5.75% Z
0.577 a
A ∆-Y Resistor Ground
0.577
0 0 0 ∆-Y Solid Ground
B b
c
58%
0.577
C
R-Primary
Seconds
the secondary appears as a 58%
(1/√3) phase fault on the primary. 13.8 kV
200/5
• The transformer damage curve is R-Primary
PWR-MCB
3200 A Fs
480 V
Slide 72
Transformer Overcurrent Protection
Inrush Current
PWR-MCB
• Use of 8-12 times FLC @ 0.1 s is an
empirical approach based on EM
relays. (based on a 1944 AIEE paper)
2.576 MVA, 5.75% Z
∆-Y Resistor Ground
• The instantaneous peak value of the
Seconds
inrush current can actually be much
higher than 12 times FLC. 13.8 kV
200/5
R-Primary
• The inrush is not over at 0.1 s, the dot
just represents a typical rms 13.8/0.48 kV
2.576 MVA 8-12 x FLC
equivalent of the inrush from 5.75%
(typical)
energization to this point in time. PWR-MCB
3200 A
480 V Fs
Slide 73
Transformer Overcurrent Protection
Setting the primary inst. protection
PWR-MCB
• The primary relay instantaneous
(50) setting should not trip due to
the inrush or secondary fault
current. 2.4 MVA, 5.75% Z
∆-Y Resistor Ground
Seconds
asymmetrical rms value of 13.8 kV
secondary fault current (1.6 x sym) 200/5
to establish the instantaneous R-Primary
Slide 74
Transformer Overcurrent Protection
• A secondary L-G fault is not sensed by the ground (zero sequence) devices on
the primary (∆) side.
Slide 75
Transformer Overcurrent Protection
• The ground resistor size is selected to limit the fault current while still
providing sufficient current for coordination.
• The resistor ratings include a maximum continuous current that must be
considered. (as low as 10% of the rated current)
Slide 76
Motor Overcurrent Protection
Motor Overcurrent Protection
• Fuse provides short-circuit GE Multilin 469
Standard O/L Curve
protection. Pickup = 1.01 X FLC
Curve Multiplier = 3
Hot
Stall
1000 hp
• Overload pickup depends on 4.16 kV
Time
650% LRC
motor FLC and service factor. 6 s Accel
Seconds
• The time delay for the 49/51
protection is based on motor
stall time.
17 kA @
M 4.16 kV
Slide 78
Motor Overcurrent Protection
GE Multilin 469
• In the past, instantaneous OC Standard O/L Curve
protection was avoided on contactor- Pickup = 1.01 X FLC
Curve Multiplier = 3
fed motors since the contactors could
not clear high short-circuits. Bussmann
JCL Size 9R
Seconds
interrupting rating.
Contactor
6 kA Int.
17 kA @
M 4.16 kV
Slide 79
Motor Overcurrent Protection
Seconds
• Modern relays with filtering can ignore
the asymmetrical current, but it’s
advisable to include a generous
margin such as 2 x LRC.
Slide 80
Conductor Overcurrent Protection
Conductor Overcurrent Protection
LV Cables
NEC 240.4 Protection of Conductors – conductors shall be protected against
overcurrent in accordance with their ampacities
(B) Devices Rated 800 A or Less – the next higher standard device rating
shall be permitted
(C) Devices Rated over 800 A – the ampacity of the conductors shall be ≥ the
device rating
Slide 82
Conductor Overcurrent Protection
Slide 83
Conductor Overcurrent Protection
MV Motor Conductors
NEC 430.224 Size of Conductors
Conductors ampacity shall be greater than the overload setting.
Slide 84
Conductor Overcurrent Protection
• The insulation temperature rating
is typically used as the operating
temperature (To).
Seconds
To = 90 deg. C
Slide 85
Generator Overcurrent Protection
Generator Overcurrent Protection
Slide 87
Generator 51V Pickup Setting Example
19500 kVA
903 A
Xd = 280%
Fg
1200/5 51V
12.47 kV
Slide 88
Generator 51V Pickup Setting Example
Slide 89
Generator 51V Settings on TCC
Pickup = 1.15 x • At 100% voltage the overcurrent
20% x Pickup CT-Sec
function is fully restrained.
decreasing
voltage full
restraint
• As the bus voltage decreases the
no
restraint
restraint decreases and the
GTG-101A characteristic curve shifts to the left.
No Load
Constant Excitation
Total Fault Current • There was no guidance in the 1986
Seconds
Slide 90
Generator Overload Protection per 2001 Buff Book
Slide 91
Coordinating a System
Coordinating a System
Slide 93
Coordinating a System
• Showing a vertical
slice of the system
can reduce
crowding, but still
be hard to read.
• Upstream
equipment is
shown on multiple
and redundant
TCCs.
Slide 94
Coordinating a System
• A set of overlapping TCCs can be used to limit the amount of
information on each curve and demonstrate coordination of the
system from the bottom up.
Slide 95
Phase TCC Zone Map
TCC-6
TCC-3
TCC-2 TCC-Comp
TCC-5
TCC-1
TCC-4
TCC-307J
TCC-101J TCC-212J
Slide 96
Coordinating a System: TCC-1
Zone Map
Seconds
• Motor starting & protection is adequate.
• Cable ampacity & withstand protection is
adequate.
• The MCC main breaker may trip for faults
above 11 kA, but this cannot be helped.
• The switchgear feeder breaker is selective
with the MCC main breaker, although not
necessarily required Amps X 100 (Plot Ref. kV=0.48)
Slide 97
Coordinating a System: TCC-2
Zone Map
Seconds
• The switchgear feeder breaker settings
established on TCC-1 set the basis for this curve.
• The main breaker is set to be selective with the
feeder at all fault levels.
• A CTI marker is not required since the
characteristic curves include all margins and
breaker operating times.
• The main breaker curve is clipped at its through-
fault current instead of the total bus fault current
to allow tighter coordination of the upstream relay.
PWR MCB – 3P PWR FCB – 3P
(See TCC-3) 30 kA @ 0.48 kV 42 kA @ 0.48 kV
Slide 98
Coordinating a System: TCC-3
Zone Map
Primary relay pickup of 546 A
is high at 512% of transformer
FLC, but meets Code.
Seconds
• The LV switchgear main breaker settings
established on TCC-2 set the basis for this curve.
• The transformer damage curve is based on frequent
faults and is not shifted since the transformer is
resistance grounded.
• The primary side OC relay is selective with the
secondary main and provides adequate transformer
and feeder cable protection.
• The primary OC relay instantaneous high enough to
pass the secondary fault current and transformer
inrush current. Amps X 100 (Plot Ref. kV=0.48)
Slide 99
Coordinating a System: TCC-307J
Zone Map
Seconds
• This curve sets the basis for the upstream devices
since its motor is the largest on the MCC.
• Motor starting and overload protection is
acceptable.
• Motor feeder cable protection is acceptable
• The motor relay includes a definite time unit to
provide enhanced protection.
• The definite time function is delayed to ensure
fuse clears faults over the contactor rating.
Amps X 10 (Plot Ref. kV=4.16)
Slide 100
Coordinating a System: TCC-4
Zone Map
Seconds
TCC-307J set the basis for this curve.
• The tie breaker relay curve is plotted to the total
bus fault current to be conservative.
• The main breaker relay curve is plotted to its
let-through current.
• A coordination step is provided between the tie
and main relay although this decision is
discretionary.
• The definite time functions insulate the CTIs
from minor fault current variations.
• All devices appear selectively coordinated at all
fault current levels, but the independent OC
functions may be an issue. Amps X 10 (Plot Ref. kV=4.16)
Slide 101
Coordinating a System: TCC-5
Zone Map
Primary relay pickup of 1000 A
is 320 % of transformer FLC.
Seconds
• The MV MCC main breaker settings established on
TCC-4 set the basis for this curve.
• The transformer damage curve is based on frequent
faults and is not shifted since the transformer is
resistance grounded.
• The primary side OC relay is selective with the
secondary main and provides adequate transformer
and feeder cable protection.
• The OC relay instantaneous high enough to pass the
secondary fault current and transformer inrush current.
Amps X 10 (Plot Ref. kV=13.8)
Slide 102
Coordinating a System: TCC-Comp
Zone Map
Seconds
• Due to the compressor size, this curve may set
the basis for the MV switchgear main breaker.
• Motor starting and overload protection is
acceptable.
• Short-circuit protection is provided by the
relay/breaker instead of a fuse as with the
1000 hp motor.
• The short-circuit protection is delayed 50 ms to
avoid nuisance tripping.
Amps X 10 (Plot Ref. kV=13.8)
Slide 103
Coordinating a System: TCC-6
Zone Map
Seconds
• The feeder breaker settings established on
TCC-3, TCC-4, and TCC-Comp are shown as
the basis for this curve.
• The settings for feeder 52A1 (to the 2.4 MVA)
could be omitted since it does not define any
requirements.
• A coordination step is provided between the tie
and main relay although this decision is
discretionary.
• All devices are selectively coordinated at all fault
current levels.
• The definite time functions insulate the CTIs from
minor fault current variations.
Amps X 10 (Plot Ref. kV=13.8)
Slide 104
Ground TCC Zone Map
TCC-G1
TCC-G2
Slide 105
Coordination Quizzes
Coordination Quiz #1
2000/5 OCR
400/5 OCR
600/5 OCR • There is no need to maintain a
TR-FDR1 TR-FDR2
coordination interval between
feeder breakers.
Main-P
• The 0.3-s CTIs are sufficient
TR-FDR2-P unless all relays are electro-
Seconds
OC1
OC1
mechanical and hand set.
TR-FDR1-P
OC1
0.3 s • Fix – base the setting of the
0.3 s feeder 2 relay on its downstream
equipment and lower the time
delays if possible.
Main-3P
TR-FDR2-3P
TR-FDR1-3P
15 kA @ 13.8 kV
Slide 107
Coordination Quiz #2
Slide 108
Coordination Quiz #3
2000/5 OCR
400/5 OCR
600/5 OCR
• The marked CTIs are okay, but….
FDR--1 FDR--2
Main-3-P
OC1 the main relay (!!) and raise the
FDR--1-P
0.47 s
time delay to maintain a 0.2s CTI
OC1
at 50 kA (assuming static relays)
FDR--2-P 0.33 s
OC1
Main-3-3P
FDR--2-3P
FDR--1-3P
50 kA @ 13.8 kV
Slide 109
Coordination Quiz #4
Slide 110
Coordination Quiz #5
Slide 111
Coordination Quiz #6
space is sufficient.
LVFDR2
LVFDR1
• Fix – lower the main breaker
0.21 s
short-time delay band.
LVFDR2 – 3P
LVMain – 3P LVFDR1 – 3P
30 kA @ 0.48 kV 45 kA @ 0.48 kV
Slide 112
Coordination Quiz #7
10 kA 5 kA
Does this TCC look okay??
• The source relays should not be
plotted to the full bus fault level
unless their plots are shifted
Source1 - P
based on:
OC1 SF = Total fault current / relay
Source2 - P current.
Seconds
OC1
Slide 113
Coordination Quiz #8
Slide 114
Coordination Quiz #9
OC1
tightly with the feeder.
FDR-5 - P
OC1
0.30 s
• The 51V curve will shift left and
lose selectivity with the feeder if a
close-in fault occurs and the
voltage drops.
51V – 3P
• Fix – show both 51V curves and
FDR-5 – 3P raise time delay.
15 kA @ 13.8 kV
Slide 115
Coordination Software
Coordination Software
Slide 117
Coordination Software
Slide 118
References
Selected References
Slide 120