METODE KERJA TRIAL GROUTING DAN GROUTING

ALAT DAN BAHAN

No. Nama Alat Jumlah

1. Pompa Grouting (Koken MG10) 1 unit

2. Coloidol Mixer (RPM 1500) 1 Set

3. Agitator Mixer (RPM 200) 1 Unit

4. Kompresor Udara (Airman PDS1855) 1 Unit

5. Water Pump (Sunchin-sc-120) 2 Unit

6. Rotary Drilling Machine 2 Unit

Rubber Packer, Head Packer, Foot Packer, Outer


7. Packer, Liner Packer 8 Set

8. Mata Bor 1 Set

9. Pipe (Body Pipe, Barrel Pipe, dll) 1 Set

10. Pressure Stabilizer 1 Set

11. Water Flow Meter 1 Pcs

Bypass (Pressure Stabilizer Bypass, Grout Pump


12. Bypass, Packer Bypass 1 Unit

Selang (Selang Oil Hose 100Psi, 150Psi; Selang


13. Air) 1 Unit

Selang (Selang Oil Hose 100Psi, 150 Psi; Selang


14. Air) 1 Unit

15. Pressure Gauge 5 Pcs

16. Generator Set 1 Unit


 Kalibrasi alat di lapangan Untuk Pelaksanaan

a. Pressure Gauge

b. Flow Meter

 Check Fungsi Peralatan (Lapangan)

a. Pompa water & Pompa Grouting (Menggunakan Pressure Gauge & Flow M)

b. Coloidol Mixer ( RPM 1500 ) menggunakan Tacho Meter


c. Agitator Mixer ( RPM 200 ) menggunakan Tacho Meter

note : akan dilakukan pengecekan pada saat trial grouting

 Tes Material

a.Viscositas ( untuk mengetahui kekentalan bubur semen )

b.Gravity dan Density (untuk mengetahui berat jenis material)

c.Sedimentasi ( bleeding )
Mulai

Pilot Hole :  Lugeon < 3 No


Grouting
 Pengambilan  Lugeon > 3
Sample Grouting
 Water Test (multi
 Hole no ?  Lugeon < 3 No
 Water Test (single Grouting
 Lugeon > 3 Grouting
pressure)

Check Hole :
 Lugeon < 3 Ok
 Pengambilan  Lugeon > 3
Sample dan Grouting,
pengecekan penambahan
menggunakan quarternary hole
larutan penoftalin
 Water Test (multi
pressure)

Selesai
Tekanan Pada Pilot Hole Untuk WPT pada grouting
Multi Pressure Test
Stage P1 (10 menit) P2 (10 menit) P3 (10 menit) P4 (10 menit) P5 (10 menit)
1 0.4 0.6 1 0.6 0.4
1’ 0.8 1.2 2 1.2 0.8
2 0.8 1.2 2 1.2 0.8
2’ 1 1.5 2.5 1.5 1
3 1 1.5 2.5 1.5 1
3’ 1.5 2 3 2 1.5
4 1.5 2 3 2 1.5
4’ 2.5 3 4 3 2.5
5 2.5 3 4 3 2.5
5’ 3 3.5 4.5 3.5 3
6 3 3.5 4.5 3.5 3
6’ 2.5 4 5 4 3.5
7 3.5 4 5 4 3.5

Perbandingan antara nilai lugeon (Lu) dan campuran grouting

Hasil WPT Porsi campuran saat mulai grouting C:W

Lu < 3 Tanpa Grouting (backfill)

3 ≤ Lu ≤ 5 1:6

5 ≤ Lu ≤ 10 1:4

10 ≤ Lu ≤ 20 1:3

Lu > 20 1:2
Pergantian Campuran Semen Grouting

Campuran Semen Jumlah campuran semen yang masuk Berganti ke

(C:W) (Liter/Stage) (C:W)

1:6 300 1:4

1:4 300 1:3

1:3 300 1:2

1:2 600 1:1

1:1 600 Re-Grout