Method Statement
Method Statement
----------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------
( )
----------------------------------------
2. We undertake if our Tender is accepted to commence the Works within ______
( )weeks of the Date of Possession and to complete and deliver the whole
Works comprised in the Contract within weeks ( ) weeks calculated
from the said Liquidated and Ascertained Damages in respect of every week or
part of a week during which the Works remain incomplete after the above date,
at the rate of 0.25 per cent of the Contract Sum per week.
4. We agree to abide by this Tender for the period of 90 days from the date fixed
for receiving the same and it shall remain binding upon us and may be accepted
any time before the expiration of the period until withdrawn by us.
6. Unless and until a formal agreement is prepared and executed, this Tender,
together with your written acceptance thereof, shall constitute a binding Contract
between us.
7. We further agree that any errors in our priced Bills of Quantities supporting our
Tender will not affect the Tender Price and that such errors shall be adjusted in
accordance with the usual procedures.
8. We understand you are not bound to accept the lowest or any tender that you
may receive.
Signature ………………………………………………………………………………………
…………………………………………………………………………………………………
Name: …………………………………………………………………
Occupation: …………………………………………………………..
Address: ………………………………………………………………
…………………………………………………………