Professional Documents
Culture Documents
POWERGRID
P.N. Dixit, GM; S. Victor, AGM; V.K. Bhaskar, CM; Gunjan Agrawal, Manager
Operation Services Department
Power Grid Corporation of India Ltd.
victor@powergridindia.com
1.0 Introduction getting trouble free service. POWERGRID
starts their quality system from the
Power Grid Corporation of India procurement of raw material used in
(POWERGRID), the Central Transmission manufacturing of the transformers. Vendors
Utility (CTU) of India is engaged in are approved based on strict quality
construction and operation of EHV/UHV standards. Manufacturing of transformers is
power transmission system in India and carried out based on laid down strict
inter-connection with SAARC countries. Manufacturing Quality Plans (MQP) which
Presently 154 no of Substations having has a number of customer hold points and
transformation capacity of 1,31,000 MVA they need to be cleared before proceeding
are under operation in POWERGRID which further in the manufacturing process.
includes about 50 no. of 765kV, 300 no. of Sweep Frequency Response Analysis
400kV and 50 no. of 220kV/ 132kV grid (SFRA) is included as part of factory test
transformers. As the population of and the signatures are compared with pre-
transformers and reactors are going to be commissioning SFRA test. Short circuit test
doubled in another 5 years due to the rapid is introduced in transformers to improve the
growth of Indian power system and capability of the transformers in service.
specifically with the growth of 765kV POWERGRID has developed its own oil
system, a well defined transformer specification for all its transformers based
management system is required to on the past experience in transformer oil
effectively manage the huge population of and even impregnation of the transformer
the equipments. windings are done with the same
specification oil to avoid mixing.
The time required for repair/ refurbishment /
replacement of transformers and reactors 3.0 Transportation
are very high in comparison to any other
switchyard equipment. Further in the Transportation of transformers is one of the
regulatory regime, the penalty for non major concerns. Due to restriction on travel
availability of the element in service is huge. through bridges for bigger transformers, it
This throws the challenge for the need of takes longer time to reach the destination
systematic maintenance of transformers which involves several time manual loading
and reactors to make advance planning for and unloading during transit. POWERGRID
removing the ailing equipments from specify digital impact recorders to be fitted
service so as to reduce outage time. A on every consignment for better analysis.
scientific maintenance methodology is Mostly transformers are transported with
required to run the equipment trouble free. Nitrogen gas filled and continuous
monitoring is being done that the equipment
2.0 Quality of Manufacturing
is always kept under positive pressure.
Escorts are also provided for major
Better procurement specifications and
consignment to speed up the transportation.
better quality standards being followed
POWERGRID is also contemplating GPS
during procurement process is important in
1|Page Operational Management of Grid Transformer- POWERGRID Experience
based tracking system of the consignment tests are carried out and recorded in
movement. specified format. The test results are
reviewed by experts at central level before
4.0 Equipment Storage, Erection and clearing for charging. The review includes
Commissioning at site comparison of pre-commissioning results
with that of factory test results, Impact
Some of the equipments require long recorder data analysis and oil quality test
storage as they need to be kept as spares results and comparison of SFRA results
or awaiting site clearance for erection. If the with that of Factory signatures. As per our
storage period is more than 6 months, the internal standard, we get charging
equipments are kept in oil filled condition. clearance only when oil moisture content is
For equipments which are meant for long ≤ 5ppm and BDV of oil >70kV. Oil samples
storage as spares are designed with a small are collected for DGA before energizing,
conservator to be fitted during storage 24hrs, 7 days, 30 days, 3 months after
period as the other accessories are not energizing and further sampling is decided
erected during this period. Special packing based on the condition of gassing of the
procedure has been developed for storage equipment.
of accessories and is stored in covered
storage. For ease of loading the spare 5.0 Maintenance and Condition
transformers and reactors from one Assessment
Substation to other, spares are stored at
raised platform to match the height of the Transformer being static device, no
trailer. This helps in saving of time during frequent maintenance is required at site to
emergency. keep in good condition. The On-Load Tap
Changers, cooler fans and pumps, valves
Minimizing outage of transformers is very and taps, monitoring devices require
important to improve grid reliability. maintenance. We overhaul OLTC diverter
Procedures have been worked out and compartment after five years from
experimented for replacing 315MVA, 400kV commissioning and maintenance of other
transformer in 3 days which normally takes devices annually. Condition Assessment
about 10days. Procedures are in place for tests are carried out on yearly basis and
replacing bushings in shortest possible deterioration trends are monitored. Leakage
time. Replacement transformer is normally in Indian transformers is one of the major
fully erected and kept for charging before issues which take much of the time in
pulling to the plinth. Dry air is continuously arresting. New transformers are being
passed inside transformer during erection procured with on-line Hydrogen and
or during internal inspection using a dry air Moisture monitoring devices to give
generator and exposure time is kept to the advance information. POWERGRID has
minimum to avoid moisture entry. Before developed 6nos. state of the art Oil Testing
starting erection, internal inspection of the Laboratories to handle condition
equipment is carried out this includes assessment of oil filled equipments such as
photography of critical internal areas. transformers, reactors, CTs, bushings etc.
Internal photography helps in analysis of Inter-laboratory validation tests are carried
internal details in case of any problem after out frequently to keep all the laboratories in
commissioning. same standard. Tests are carried out for
new and used oil for oil quality, DGA, Furan
Once the transformer is erected and ready and DP of paper in the laboratory. Portable
for commissioning, all pre-commissioning DGA kits are also used for initial scanning
2|Page Operational Management of Grid Transformer- POWERGRID Experience
and in case of emergency. All transformer 7.0 Few Case Studies
test results are periodically reviewed by
Regional Transformer Committee once in 3 Few case studies have been presented
months and critical cases are reviewed by below indicating problems at different
Central Transformer Committee. stages, method of investigations carried out
and the action taken for rectification.
6.0 Failures and investigation
7.1 Case Study I: Transportation
Failures are inevitable when a large fleet of issue
transformers are handled. Normally new
transformers do not fail due to poor One 160MVA 220/132 kV auto-transformer
maintenance. The issues are mostly was received at Site. As per practice, the
because of the quality of the equipment, impact recorder file was downloaded and
manufacturing defects, transportation analysed. It was found that transformer has
related issues and frequent faults in the seen following impact during the
system. A vigilant monitoring can help in transportation:
identifying the defects in advance so that
catastrophic failures are avoided. It is very
much important to identify any latent defect
in transformer during warrantee period as
manufacturers are responsible for
rectification. POWERGRID has
standardized design of transformer for
interchangeability as in the event of failure,
the other make transformer can be installed
without losing time.
Date of charging:-24-04-2005
Date of Replacement of bushing: 30-01-
2010
In the above Reactor, fault gases were
rising (H2, CH4, CO & CO2) as shown in
the table below:
Sample
Date H2 CH4 C2H4 C2H6 C2H2 CO CO2
11/4/08 9 1 0 0 0 39 722
Copper globules were found and burning
marks also noticed on conductors of first 19/4/08 28 2 1 0 0 50 1821
disc from bottom and two bays towards the 4/5/08 90 2 1 0 0 74 3496
left of IV bottom lead. Flash over mark was 3/11/08 285 12 3 2 0 205 6770
also observed on bottom SER (Static End
12/2/09 350 21 3 3 0 223 7474
Ring).
22/6/09 427 37 3 4 0 255 9755
Tan δ values of B
DGA results of Reactor Ø Bushing Table-4 Rising Trend of fault gases
Date of Tan δ
Sample
Date H2 CH4 C2H4 C2H6 C2H2 CO CO2
meas.
8.0 Conclusion
17/10/08 144 30 3 8 0 123 1266 2006-07 0.0043
(Note: The authors are thankful to Power Grid Corporation of India Ltd. (POWERGRID) for preparation and
presentation of this paper at Trafotech 2012. The views presented in this paper are that of the authors and not
necessarily that of POWERGRID)