Professional Documents
Culture Documents
Concrete Repair Quality Control
Concrete Repair Quality Control
C O N C R E T E W O R K S
12
CONCRETE WORKS
ONCRETE
requirements add to its popularity.
Concrete does not rot, rust or decay and
is resistant to wind, water, rodents and
insects. It is a non-combustible material,
making it fire resistant and able to
CONCRETE WORKS
mixture of limestone and clay, which foundations needs less cement than
is ground into a very fine powder and structural concrete.
then burnt at a high temperature in a
rotating kiln, thereby fusing it into a The density and strength of the finished
material called clinker. The clinker is concrete also depends on the distribution
cooled down and ground into a fine of the particle sizes. By mixing the right
powder. Gypsum and various additives quantities of various sizes of gravel and
are then added to the cement. sand it is possible to achieve a dense and
strong concrete.
Concrete is similar in composition to
mortar, which is used as a bonding The gravel part of the aggregate forms
material in masonry works. Mortars the skeleton of the concrete, providing
are however normally made using sand its compression strength. The smaller-
as the sole aggregate, whereas concrete sized aggregate fills the empty spaces
contains a considerable amount of between the large particles, while the
larger size aggregate. cement paste fills the smallest spaces,
coats the aggregate particles and glues
Cement is the most costly of the ingredients them together. The very fine cement
required to produce concrete. This implies particles also fill the smallest empty
CONCRETE WORKS
bag is torn, moisture enters the cement sources. Natural aggregate for direct use
and triggers the chemical action causing without any mechanical treatment can
the cement to harden. Hardened pieces be extracted from riverbeds, gravel pits,
found when using the cement must be lakes and dunes. This aggregate normally
removed, because the strength of the consists of round and polished particles.
concrete will be reduced if they remain
inside the batch. Before using aggregates for concrete
manufacture it is important to make
The cement should sure that the particles are of sufficient
be stored in a dry strength and are not prone to erode or
place where the bags deteriorate. Aggregate should not be
do not get da mp porous, neither brittle nor soft.
or wet. The floor should have a good
clearance from the ground or walls, The composition of natural aggregate
to avoid moisture penetrating from may need to be adjusted before it can
below and secondly to allow for good be used for concrete manufacture. If it
ventilation. contains too high quantities of clay and
silt these fractions need to be removed.
Cement deteriorates with time and Sieving the materials will provide the
should therefore only be purchased correct grading. Large pieces can be
just before it is to be used. The oldest crushed manually or with the use of a
cement in the store should be used first. crusher.
BUILDING RURAL ROADS
rejected as far more cement and water is The good performance of the steel bars
required to obtain acceptable results. depends on a proper bond between the
steel and the concrete. This requires the
It is necessary to wash the aggregate if it steel to be clean and in good condition.
contains impurities, as these negatively
influence the strength of the finished Minor rust coatings have no effect
concrete. Clay impurities, especially, on its performance. Any loose rust
cause a high level of shrinkage, and should of course be removed, however,
prevent the concrete-steel adhesion there is no need to brush the bars free
in reinforced concrete. Dust and fine from all rust. Bars stored outside for
crushing residues reduce the mechanical a longer period may however have
strength and chemical resistance. To rusted so much that the diameter has
keep the aggregate clean, it should be been reduced. Any reinforcement steel
BUILDING RURAL ROADS
stored on clean hard ground (preferably with considerable amounts of pit rust
a concrete floor) away from trees. should not be used. It is not necessary
to remove mortar or cement droppings
Aggregates of different sizes should be that are firmly adhering to the bars.
stored separately. Too often, heaps of
different-sized gravels are dumped next Water
to each other with no separation in Good quality water is required for the
between. The heaps overflowing into mixing of concrete. Drinking water is
each other cause the different sizes to the best, however, water from rivers and
get mixed. As a result it will be difficult lakes is normally of adequate quality.
to obtain a mixture containing the right Salt water should not be used for
quantities of different size aggregate. mixing concrete.
3 9 2
Water is used for both the mixing of air space, with mortar and small
process as well as during curing. Before particles filling all voids.
the first of these activities commence, it
is important to make sure that the site Sand and gravel contain particles of
has adequate supply of water for both the different sizes with empty spaces in
mixing as well as the curing. This may between. Generally, it can be assumed 12
involve arrangements such as stockpiling that sand and gravel, in a dry condition,
water to ensure there is sufficient water consist of 60 percent solid matter and
CONCRETE WORKS
for the entire period from mixing until 40 percent empty spaces. To obtain a
the end of the curing process. dense concrete these empty spaces need
to be filled. The empty spaces between
Safety the sand grains are filled with cement,
When handling cement or fresh concrete, while the sand-cement-water paste
it should not come in contact with the (mortar) fills the empty spaces between
skin or eyes. Wearing gloves, a long- the gravel particles. An extra 10 percent
sleeved shirt, full-length trousers and of mortar is necessary to "coat" the
boots reduces the exposure. Wet concrete, particles completely.
mortar or cement should be washed from
the skin immediately. Eyes need to be This means that for a certain quantity of
flushed with lots of water for at least 15 gravel it is necessary to add 50 percent wet
minutes immediately after contact. mortar in order to fill the empty spaces and
The f inal strength of the f inished to coat the particles. In theory, therefore,
concrete depends on: a mixture of 1:2:4 (cement : sand : gravel)
will produce a dense concrete. In practice,
12.3 Proportion of when a dense but plastic concrete is
the Components required, a mixture of 1:2:3 is often
applied mainly because of the variation
(i) the proportions of the components, in the percentage of empty spaces.
i.e. the quantities of gravel, sand, However, different mixes are applied
cement and water; depending on the purpose for which the
BUILDING RURAL ROADS
(ii) the quality of the components; concrete is used. The table below shows
(iii) the distribution of the grain sizes various mix proportions used to produce
of the gravel and sand; various qualities of concrete.
(iv) how the components are mixed;
(v) how the mixture is transported, The volumes of cement and sand vary
placed, compacted and cured. considerably depending on the degree
W hen the mixture is prepared it to which they are compacted. The
is important to make sure that the volume of sand also varies with its
proportions of the aggregates used in moisture content. The volume of sand
the mixture are correct and that the can increase by up to 50 percent if the
right quantities of cement and water are water content is increased. For these
added. The ideal mixture is one that reasons, volumetric proportioning is not
solidifies with the minimum amount used when big quantities of high quality
3 9 3
12
concrete are produced. In such cases, the ratio produces a low strength concrete
CONCRETE WORKS
materials are weighed and the moisture but good workability. A careful balance
content is measured to determine the of cement to water is therefore required
exact quantities of gravel, sand, cement when preparing the mix. Water/cement
and water. For most concrete works ratios in the range between 0.4 and
carried out on rural roads, however, the 0.6 provide a good workability without
above rules of thumb can be applied. compromising t he qua lit y of t he
concrete. Hand-mixed and hand-placed
12.4 Water to Cement Ratio concrete requires more water to secure
sufficient workability (water/cement
When water and cement is mixed, it ratio between 0.5 and 0.65).
forms a paste that coats and binds the
aggregate particles together. Through a The characteristics of the aggregate
chemical process called hydration, the may also have an indirect impact on
paste hardens and gains strength. The the quality of the concrete. If the size
strength of the paste is determined by and shape of the aggregate makes the
the applied ratio of water to cement. concrete unworkable, the contractor is
likely to add more water, resulting in
The strength of concrete increases when a higher water to cement ratio and a
less water is used during the preparation weaker end product.
of the mix. Although the hydration
process consumes a certain amount of The aggregate may already contain a
water, wet concrete actually contains certain amount of water, which needs
BUILDING RURAL ROADS
more water than required for the to be taken into consideration when
hydration reactions. The excess water preparing the mix. Particularly when
is added to provide the wet mix with using moist sand, it may be necessary
sufficient workability. Concrete needs to to reduce the amount of water being
be workable so that it can be moulded added to the concrete.
into the desired shapes and consolidated
to the required density. Additional water should never be added
when a mix is drying up. If it is necessary
The quantity of water divided by the to improve the workabilit y of the
amount of cement gives the water to concrete, a mixture of cement and water
cement ratio. A low water to cement should be used instead.
ratio leads to high strength but low
workability while a high water to cement
3 9 4
12.5 Mixing Concrete The following steps describe a good
way to mix by hand:
Thorough mixing is essential in order
to obtain a homogeneous mixture of all • Limit the size of the batch to
the ingredients and achieving a suitable approximately a third of a cubic
work abilit y. The equipment a nd metre. 12
applied work methods need to be able • First place a layer of sand on
to effectively mix concrete containing the mixing platform on which
CONCRETE WORKS
the specified size aggregate, obtaining t he c ement i s spre ad. M i x
a uniform mixture with the required thoroughly by turning the heap
workability within an acceptable water over several times. This is best
cement ratio. done by two persons facing each
other, working the mix from
The term work abilit y is used to opposite sides. Mix until the
describe the ease at which the concrete cement is evenly distributed in
can be placed and consolidated without the sand, i.e. until the mix has a
segregation or separation. It takes a uniform colour.
greater effort to achieve a uniform and • Add coarse aggregate and turn
dense mass of concrete in structures the mix until the batch is once
containing a considerable amount of again properly mixed.
reinforcement bars as compared to mass • Sprink le the predetermined
concrete used in a foundation. The quantity of water gradually on
amount of large aggregate as well as the top of the mix while turning it
water content will greatly influence the over another three times, or until
workability of the concrete, however, the water is evenly distributed.
these are also factors determining the • Use the wet concrete immediately
final strength of the concrete. Another after it has been mixed. Make
alternative to improve the workability sure it is placed and compacted
of concrete is by using additives. straight away, avoiding that it
starts setting before it is used.
BUILDING RURAL ROADS
Hand Mixing
When mixing is carried out by hand it Mechanical Mixing
requires a suitable surface (metal sheets, There exist a large number of different
boards or lean concrete slab) to ensure types and sizes of concrete mixers.
that the mix is not contaminated with The most commonly found type on
soil. The surface should be level to construction sites is the tilting drum
prevent water or fluid material from mixer. Depending on their size, these
running off the mixing area. The mixers can be manually driven or
space needs to be sufficiently large to powered by electrical or diesel/petrol
allow for the required size of batches engines. The drum on the mixers can
to be mixed without spilling into be positioned at different angles for
surrounding areas. charging, mixing and discharging. The
drum rotates on an inclined axis when
3 9 5
(iv) add the cement;
(v) add the remainder of the coarse
gravel;
(vi) mix dry for one minute;
(vii) when the aggregate and the cement
12 have been thoroughly mixed, add
the remaining quantity of water
and mix wet for another two
CONCRETE WORKS
minutes.
(ii) charge half the volume of coarse following table shows the materials
gravel. The gravel will also assist necessary to produce one cubic metre of
in cleaning the inner surfaces of concrete.
the drum;
(iii) add the prescribed amount of It is always important to use a gauge box to
sand and finer gravel; measure and keep control of the volumes
3 9 6
12
CONCRETE WORKS
of the ingredients when mixing concrete.
A useful sized gauge box is one having
a volume corresponding to the volume
of 50kg bag of cement (with a density of
1.25kg/m³, a standard bag of cement will
have a volume of 0.04m³ or 40 litres). A
shovel should never be relied on as a
unit to measure the quantities of the
ingredients. A shovel full of sand does
not have the same volume as a shovel
BUILDING RURAL ROADS
concrete has set, in most cases when the essential task is to make sure that the
formwork is removed. reinforcement is properly covered and is
not exposed to air and humidity, thus
To avoid honeycombing, the following avoiding any future corrosion.
measures are recommended:
If the damage is extensive and appears to
• ensure that the mix contains compromise the integrity and strength
sufficient fine aggregate. Using of the structure, the section needs to be
concrete with a large proportion fully removed and replaced with new
of large aggregate increases the concrete. In such cases, it is necessary
risk of honeycombing; to obtain advice and directions from a
• make sure that the fresh mix has qualified engineer.
the correct workability;
4 0 0
12
CONCRETE WORKS
12.7 Transport of Concrete organise the supply from a local mixing
plant (if available), from which the
Concrete can either be produced on fresh concrete is transported by truck
site or at commercial mixing plants. to the work site. On site, concrete is
When large quantities of concrete are transported using wheelbarrows and
required, it is common practice to buckets to reach the final locations
where it is placed. The transport time
of any concrete should be as short as
BUILDING RURAL ROADS
cement trucks close access to the To avoid any delays during the supply
BUILDING RURAL ROADS
CONCRETE WORKS
of its ingredients. When placing the spots contain a considerable amount of
concrete, care need to be taken not to air, they compromise the strength and
damage the formwork or dislodge the impermeability of the concrete.
reinforcement.
The poured concrete therefore needs to
Placing the concrete starts from the be consolidated to secure the necessary
corners of the formwork with compaction density, imperviousness and strength as
of the concrete starting immediately well as to improve its adhesion to the
after it has been placed. In the case of reinforcement bars. This consolidation
a sloping site, pouring should start at can be done by hand with hand-
the lowest level. The concrete should be tampers or iron rods. A more effective
placed in layers not higher than 30 cm method is to use a poker vibrator.
when compacted by hand and in layers This is a steel tube, housing a rotating
not higher than 60 cm when compacted eccentric mass driven by compressed air
by vibration. or an engine.
Slabs and floors should be poured in The vibrator is immersed into the
one continuous operation to avoid any concrete at regular intervals of half
CONCRETE WORKS
reach if properly cured. By providing
starts setting roughly two hours after is proper water curing for three days
has been mixed. This implies that the will increase the strength to more
pouring and compaction need to be than 60 percent of its full potential.
This process continues over time
complete within this period of time. Any
reaching 95 percent after 28 days.
shaping or reworking of the concrete
once the concrete starts setting will cause
serious damage to the concrete.
the curing process, since hydration is a through evaporation. The most common
chemical process, taking place between method of keeping concrete moist is by
the water and the cement. Freshly frequently sprinkling or flooding the
mixed concrete contains suff icient surface, or by covering the surface with
water to secure that proper curing can wet jute, paper bags, sand or sawdust.
take place, however, any loss of water
caused by evaporation will compromise Equally, covering surfaces with plastic
the curing process. The curing process sheets, banana or palm leaves or other
is most critical during the initial days materials may reduce the evaporation
after pouring. The exposed surface of from bright sun and winds. Keeping
the concrete is therefore kept moist the casting forms on as long as possible
during a period of four to six days. reduces moisture loss from vertical
surfaces.
4 0 5
Exposed slab surfaces are especially into the concrete. The disadvantage of
sensitive to curing and need special these compounds is that they are costly
attention during the initial days of in comparison to the use of water.
curing. All the arrangements necessary Secondly, they will compromise the
for the curing process should be in bond between the concrete and any
12 place before commencing the pour. subsequent surface treatments.
Creating ponds is an effective and The curing process in concrete takes place
CONCRETE WORKS
inexpensive method to cure large during its entire life, however, the increase
horizontal surfaces, such as f loors in strength is more profound during the
and slabs. It also has the advantage first month after it has been poured.
of maintaining a uniform surface
temperature, thereby reducing the Concrete Works in Hot Weather
likelihood of thermal cracking. The The ideal climatic conditions for
pond can be created by building a dam setting and hardening are a constant
along the edges of the surface using temperature of 20°C and a relative
clayey soils or any other material that humidity of 80 - 90 percent. High
retains the water. temperatures, combined with strong
wind a nd low humidit y enha nce
the rate of evaporation of the water
required for the curing of the concrete.
Hot weather will also reduce the setting
time of the fresh mix, leaving less time
for transport, placing and compaction.
Finally, the lack of water as a result of
hot weather makes the concrete prone
to excessive contraction and may lead
to cracks developing soon after placing.
CONCRETE WORKS
is a relatively brittle material that shrinks itself is mainly related to (i) testing the
over time. Cracking occurs as a result workability of the delivered or produced
of the concrete being restrained from concrete, and (ii) taking samples for
contracting. The early loss of moisture later compressive strength testing.
from fresh concrete will accelerate the
shrinkage causing the cracks. Although Slump Test
these cracks appear small and shallow, The workability – or consistency - of
they may increase in size when loads concrete is an important feature when
are exerted on the structure and then pouring concrete. A more fluid mix is
cause more serious damage. Surfaces left easier to distribute in a dense manner
to dry out during the first few hours of into all corners and also into any tight
curing are more prone to cracking. spaces in between the formwork and the
reinforcement bars. The workability of
The most effective remedy against this the concrete essentially depends on its
phenomenon is therefore to keep the water content and any use of admixtures
concrete moist throughout the curing for this purpose. A high content of large
process and in particular during the aggregate will also result in a difficult
early stages while the concrete is still mix with a very low "slump". These
weak and more prone to damages. aspects need to be carefully weighed
Protecting the concrete surface during against the fact that the use of excessive
the first few hours significantly reduces amounts of water compromises the
the cha nces of crack ing. A good strength of the concrete.
BUILDING RURAL ROADS
The slump test cone is set up on a flat Commonly referred to as the Schmidt
clean surface and filled with the fresh hammer, this instrument is one of
concrete, in layers of equal thickness. the best-known methods of assessing
Each layer is hand tamped before the the quality of hardened concrete.
next is added. The cone is then lifted The hammer measures the rebound
straight off and placed back on the of a spring-loaded impact against the
ground next to the test material. When surface of a sample. What it actually
the cone is carefully lifted off, the measures is the surface hardness. The
material will slump a certain amount surface therefore needs to be clean
depending on its viscosity. A dry mix and smooth in order to obtain reliable
will settle very little, while wet concrete test results. Dirt or loose materials
will immediately loose its conical shape should be removed before carrying
and have very limited cohesion. A spirit out the test. As the instrument is easy
level and tape are used to measure how to use, it is possible to take numerous
much the concrete subsides. measurements.
Concrete Cubes
The most common
method of testing the
final strength of the
concrete is by taking
samples of the wet mix,
and moulding sample cubes (or cylinders),
which is subjected to compressive strength
tests once they have been cured.
4 0 8
CHAPTER 13
S E T T I N G U P A N D
A D M I N I S T E R I N G A S I T E
S 13
ETTING UP AND
ADMINISTERING A SITE
SETTING UP AND ADMINISTERING A SITE
The project needs to make adequate With clear procedures on how and by whom
provisions for the related costs of such these forms are filled out, the time spent on
work activities. These costs are normally administrative matters can be minimised
included in the budget items relating to and the supervisory staff can concentrate on
the work activities for which additional managing the actual construction work.
materials are required. The project also
needs to take into account any royalty Although these procedures may seem
costs related to the use of the quarries. tedious and repetitive, it is important
to ack nowledge their importa nce.
The client will often withhold the final The use of resources is directly linked
payment pending the reinstatement of the to incurring costs. All expenditures
borrow areas. need proper reporting for accounting
purposes. The reporting on the use of
4 1 4
materials, equipment and labour provides An important role of the site office is to
management with the basic information keep records of all expenditure and use
necessary in order to monitor progress of resources. It is the duty of the project
and efficiency on the work site. manager to organise this section and
to ensure that its work is carried out
Office Administration efficiently. Clearly defined procedures, 13
Every civil works project needs to establish duties and responsibilities must therefore
an office for administrative and logistical be established so that every staff member
The site office also plays an essential role in the supply chains. Workers and sub-
in relation to logistical support. As in any contractors need to be paid on time and
organisation, the site office needs a well equipment needs a steady supply of fuel
functioning registry. The registry deals and spare parts.
with receiving and recording incoming
mail and archiving all important reports Although the main office carries out
and documents in the correct files so that larger purchases, there will always be
they are readily available whenever they some financial transactions taking place
are needed. at the site. The local project office pays
local wages and there is always some
Communications is an essential responsibility procurement, taking place locally.
of the site office. It is useful to have a The project therefore needs access to
properly trained person who can manage accounting services, which takes care of
incoming calls and keep records of calls all payments of goods and services.
made and received. The phone operator
should be informed about the whereabouts Each project needs to adopt a system
of all staff members and thereby pass on in which the costs of all construction
incoming calls or take messages accurately. activities can be monitored. Expenditures
relating to labour, equipment and
Mail leaving the off ice should be materials need to be closely monitored.
recorded, noting to whom and when Each activity in the project budget will
the letter was sent and what the letter have a cost ceiling within which the
BUILDING RURAL ROADS
files kept on site cover financial issues, taken out, for use on site.
purchase orders, equipment hire, personnel
records, contracts and their amendments The camp would normally employ a
and variations, minutes of site meetings, person to take care of the maintenance
wage records and expenditure records. and service of equipment as well as repair
In add it ion, t he projec t keeps a l l of hand tools. On smaller sites, the role
reporting forms in dedicated files, thereby of the storekeeper is sometimes combined
maintaining a full histor y of work with the tasks of the site repairman or
progress, use of labour, equipment and mechanic.
materials on site, results of quality tests
and the invoicing for completed works. When necessary, a watchman is employed
to guard the stores when the storekeeper
is off duty.
4 1 7
Supply of Tools to ensure that sufficient materials are
The amount and type of hand tools available on site before commencing the
depends on the number of workers works. Materials comprise a significant
employed and the work methods used. value of any civil works project so proper
A standard list of tools for the work sites handling and storage are important in
13 is usually drawn up by the engineer in order to limit any losses due to spillage
charge of works preparations. Special and theft. When planning the initial
tools and equipment are supplied to sites materials purchase, the project manager
SETTING UP AND ADMINISTERING A SITE
ventilation under the bags. The roof and stores which are delivered to the work site
walls must be thoroughly checked for and must deal with any loss or improper
leaks. The oldest cement should be used use. As part of the works planning, the
first. project management needs to ensure that
the tools and materials are available when
Reinforcement Steel needed.
Reinforcement steel requires safe storage
close to where it is loaded and unloaded. Procurement
There needs to be sufficient space close by Procurement of goods is carried out
where cutting, bending and binding take using clear procedures laid down by
place. This work area should be near to the management. The authority for
the loading area, so the steel can easily be procuring goods and materials is vested
transferred to the work sites. with the project manager. This authority
4 1 9
will, however, be limited to certain goods
mainly related to consumables required • description of item,
on site on a timely and regular basis. • unit price and total value,
• suppliers name,
Larger purchases are often carried out by • amount delivered,
the head office. • date received,
• stock balance,
13 • amount issued, and
The project staff must be fully aware of • minimum and maximum stock levels.
the prevailing procedures, as they will be
SETTING UP AND ADMINISTERING A SITE
in which the staf f has the regular the project. They also need due notice
entitlements a s prescribed for t he so that they can plan and organise their
construction industry. regular commitments and work activities,
such as farming and household activities.
Casual labour is often treated separately, They can then set aside sufficient time
under the basic assumption that they to participate in the road works. The
are employed only for a day at the time. announcement should state:
The exact entitlements relating to this
employment arrangement are usually far • date, time and place of recruitment,
more limited, however, the regulations • conditions of employment,
vary signif icantly from one country • type and purpose of work, and
to another. Often, there are also large • who is eligible for work.
differences between the obligations of a
4 2 2
13
recorded in detail and on this basis wage paid to each worker and the total
payments are made. A muster roll is used amount needed;
for this purpose. At the end of the month • Authority needs to be obtained to
(or other period agreed with the workers), withdraw money from the bank,
the muster rolls are used to culculate collect the money in sufficiently
wages for each of the workers. small notes so that the exact
amount can be paid to each
The date and place of payment are worker;
announced to the workers well in advance • Transport and security need to
to make sure everybody attends on the be arranged to carry the money
payday. Wages can only be collected by the to the work site;
worker him/herself. All workers should • Payments need to be made to the
be properly identified by presenting right persons and the signature of
their identity card for inspection when each worker obtained, declaring
receiving their wages. that he /she has received the
wages due and that the amount
T h e o r g a n i s a t i on o f t h e p a y d a y was correct; and
requires special attention by the project • A report on the payments made
management. The project manager should be prepared and any
sets a date and place for this to happen, unpaid wages returned to the
and organises the logistical support bank.
required. It is the responsibility of an
BUILDING RURAL ROADS
the authority to call the meetings. and health on civil works sites. If such
regulations are violated, this not only
Written minutes are maintained on all increases the risk to the workers or any
decisions made during these meetings. third party, but it can also have an impact
T he m i nute s s hou ld i nc lude a ny on the insurers acceptance of insurance
instructions relating to changes in the claims. When the insurer finds evidence
contract, such as revised quantities of of gross negligence or violations of
works, improved work methods, quality standard safety regulations, the conditions
requirements, replacement of staff, of the insurance contract may relieve the
changes in work schedules, etc. During insurer of any obligations to the insurance
the next meeting, it is useful to revert contract purchased by the contractor.
back to the minutes and the decisions
made during the previous site meeting It is the responsibility of the contractor
4 2 5
and the supervising engineer to know all should be regularly replenished, so they
the relevant regulations in terms of safety are effective when an accident occurs.
and health on the work site. In addition For more serious accidents, the project
to installing appropriate measures to management needs to make contingency
protect its workers, the contractor is also plans for evacuating the injured from the
13 responsible for protecting the general sites and transporting them to the nearest
public against any hazards caused by the medical facility.
works both during and after working
SETTING UP AND ADMINISTERING A SITE
hours.
Prevention
Safety on site needs to be assessed on a
continuous basis. For every work activity,
there are a number of well-known safety
hazards which the workers should be
made aware of. During clearing works,
activities such as tree felling, blasting
and boulder removal pose the greatest
risks. During excavation works, unstable
slopes and cuts may pose a threat to the
workers. Activities involving the use of
large construction equipment such as
compaction and transport of materials are
always a risk on sites employing a large
workforce.
First Aid
Every site should be supplied with a
first aid kit. The medical kits should be
administered by someone who is properly
trained in using its contents. First aid kits
4 2 6
CHAPTER 14
W O R K O R G A N I S A T I O N
14
W O R K O R G A N I S AT I O N
14.1 Introduction
BUILDING RURAL ROADS
ORK
the specific work duties of each staff
member and (ii) identifying the person
to whom each individual reports. The
project management, as well as the
W O R K O R G A N I S AT I O N
below. a way that the best use is made of the
available labour, materials, tools and
Whether works are carried out using equipment.
equipment or by manual labour, the
essence of effective work organisation Depending on the size and complexity
is to make good use of the resources of the works, the site is managed by an
available on site. When carrying out engineer or a technician. On smaller
works using labour-based work methods work sites, it may be more feasible to
there are three basic elements that have a assign a manager to supervise several
major impact on the work performance. sites. The optimal size of the workforce
These are (i) good supervision, (ii) depends on the type of work being
the use of incentive schemes, and (iii) carried out, the expected level of
establishing an appropriate balance outputs and the availability of local
between labour and machines. Amongst labour. With sufficiently experienced
the three, the skills and experience of site supervisory staff, a single rural road
the supervisors have the greatest impact construction project applying labour-
on the productivity and quality levels based methods can employ up to 600
on site. workers during its peak performance.
An experienced supervisor should be
When the majority of the workforce able to manage 100 - 150 labourers.
consists of unskilled labour, the workers
rely on detailed instruction and guidance Ga ngs, formed for t he d if ferent
BUILDING RURAL ROADS
4 2 9
activities, normally range from 10 to 14.2 Work Programming
25 workers, depending on the nature
and amount of work to be carried out. The construction work is divided into a
Among the workers in each gang, one number of operations, each of which is
person is appointed as their leader - the sub-divided into activities.
14 Gangleader. This person receives the
work instructions from the supervisor With proper work programming it is
and hands them on to the workers in possible to arrange and distribute the work
W O R K O R G A N I S AT I O N
W O R K O R G A N I S AT I O N
Equally, grubbing and topsoil removal
Site clearing is an example of an operation. can only take place after bush clearing
This operation is sub-divided into has been completed.
activities such as bush clearing, grubbing
and topsoil removal, tree and stump An activity should follow the preceding
removal, and boulder removal. one as closely as possible without causing
interference or over-crowding. The
The separate operations on a construction distance between the first and last activity
site have to follow each other in a logical should preferably not exceed 2km.
sequence. Each activity is carried out by
a separate group of workers. If the work When starting a new project, it is important
areas for these activities are too close to to stagger the above operations, allowing
each other, the work may be disrupted at least three days before starting the next
(e.g. an excavation gang waiting for a operation. This also allows the supervisors
clearing gang to finish). On the other to organise the work properly and give
hand, when activities are spaced too far basic instructions and training to the newly
apart, the total length of the work site recruited labour. Starting the work with
too many new workers at the same time
can create disorder and problems for the
supervisors.
Gang Balancing
BUILDING RURAL ROADS
W O R K O R G A N I S AT I O N
supervisors and gangleaders work towards. any organisation, for any form of
On site, this includes establishing realistic work, using any type of construction
production rates for individual workers techniques.
and equipment.
The disadvantage of daily paid work is
The construction work cannot be that the amount of supervision efforts
planned, and realistic targets cannot be required to maintain reasonable outputs
set unless productivity rates are known. is relatively high. The productivity,
In order to achieve high and sustained and hence the rate of progress and
production levels, it is essential that the resulting unit costs are therefore
the work is planned against specific difficult to predict accurately.
productivity rates and outputs. With
a good knowledge of achievable work These disadvantages notwithstanding,
norms, it is possible to introduce both at the start of a new project and
effective incentives to motivate the whenever starting a new work task or
workers sufficiently and thereby reach activity, it is often necessary to pay
the set production targets. workers on a daily basis unless there
is data available on which to estimate
An effective approach is by introducing realistic rates for an incentive system.
a system which provides the workers Although this may be a valid issue in
with some kind of additional benefit or certain circumstances, it should not be
reward for increased work outputs. One used as an excuse for not installing a
BUILDING RURAL ROADS
way of doing this is through the use of more sophisticated system that includes
a performance based payment system. the use of incentives. It is important
to note that with effective incentives
Depending on the nature of the works, offered to the workers, production rates
there are several methods of organising can be increased two to three times.
the workforce and securing continued So, even if there are some uncertainties
high levels of production. regarding the appropriate work norms,
it is more effective to introduce a
Daily Paid Work production-based incentive as soon as
Daily paid work is the conventional possible.
approach of engaging casual labour to
carry out works required during a fixed Da i ly pa id work i s not d i rec t ly
period of time. In this arrangement, dependent on output and therefore
4 3 3
offers opportunities for fraud, which Ta sk work i s t he most c om mon
the project management needs to guard incentive scheme used for labour-based
against. Absent workers can be marked works. As compared to daily paid work,
as present on the muster roll or by it has several advantages:
adding invented names to the roll.
14 • Work planning is simplified because
The project management needs to the daily output of each worker is
control this by monitoring the output known;
W O R K O R G A N I S AT I O N
W O R K O R G A N I S AT I O N
that when applied on site, it also sets etc.) or to groups (especially suitable for
clear performance requirements for the large quantities of excavation). If task
site supervisory staff. When labour is work is given to a group of workers, care
employed without using a production should be taken that the workers are not
based remuneration system, there is in each other's way and have enough
really no need to define outputs on a room to work. The workers should not
daily basis. This certainly produces be released before they have finished
an easier life for the supervisory staff. their task unless unforeseen difficulties
On the other hand when applying task have arisen (encountering hard roots,
work, there are a number of advantages rock, bad weather, etc.). In these cases
resulting in increased work outputs. By the task should be adjusted if it is
allocating individual tasks the workers obvious that the applied task rate is no
are also distributed in an efficient longer appropriate. It is easier to adjust
manner, avoiding that certain areas are task rates by increasing or decreasing the
overcrowded. number of workers assigned to a certain
activity than by increasing or decreasing
The preparation of tasks needs to take quantities of work.
place before the workforce arrives
on site - usually the day before. This Team tasks have a number of advantages:
forces the supervisors to carry out
proper work planning and as part of • They are easier and quicker to set
this exercise, provides the supervisors a out and control than individual
BUILDING RURAL ROADS
to earn more than the standard daily Piecework payments can cause friction
pay by producing more. Similar to task among workers because of the differences
work, the main advantage of piecework in earning that may result. Sometimes
is thus higher productivity rates from this can be overcome by paying a large
the workforce. group as a whole, but the larger the
group, the smaller the incentive will be
to each individual. With larger gangs
there may be disputes among the gang
members about how to portion out work
among the individual workers.
W O R K O R G A N I S AT I O N
funds in government budgets there is no benefits from improved access, they do
other alternative but to encourage the not accept that the road improvement
local population to contribute their free is a benefit exclusively to them. After
labour to build and maintain the road all, most villagers do not own a vehicle.
assets. Furthermore it is often argued Many are subsistence farmers and have
that the assets created benefit the local limited need of roads.
population and therefore they should
contribute to the cost of the works. In the majority of cases, inputs in the
form of regular cash wages are necessary
Experience clearly show that relying in order to secure a continuous high level
on voluntary labour for road works is of work outputs from the workforce.
unsustainable in most circumstances Furthermore, it should be recognised
with the rare exceptions in which the that the labour inputs, even on roads
labour inputs required are limited to built using labour-based technology, only
smaller works over a short period of forms a part of the total construction
time. costs. In addition, there are substantial
costs related to materials, equipment and
Most roads are built to cater for other supervision.
W O R K O R G A N I S AT I O N
BUILDING RURAL ROADS
Not every activity is suited for task work, Task rates are expressed as the quantity
since it is necessary that the quantity of work that a person is able to finish
of work can be reliably measured and during a day's work, such as 2 cubic
the degree of difficulty of the work can metres of excavation per workday or
be determined. The table above shows 100m² bush clearing per workday.
common road works activities suitable
for task work. If a task is set correctly, the average
4 3 9
worker should be able to finish it in 14.5 Managing the Workforce
approximately 75% of the normal
working hours. Task work may not Good management of the workforce
be as effective if the workers cannot is important in order to achieve high
go home every day to work for their production targets. A well-organised and
14 own purposes or to spend leisure time content workforce is usually a productive
at home. Imported labour may not be workforce. The site management must
motivated by task rate system since look out for problems with the workers
W O R K O R G A N I S AT I O N
their leisure time can only be spent and take appropriate steps to deal with
in the labour camp or immediate such issues at an early stage.
surroundings.
Giving and receiving instructions is
In a more sophisticated system it may a major part of the responsibilities of
be possible to deduct wages if a task is the site supervisor. The manner in
not completed in one day. But such an which instructions are given influences
arrangement is difficult to administer how they will be carried out. Before
and normally not permitted by prevailing issuing instructions, it is important to
labour regulations. If the workforce understand:
frequently fails to complete their tasks,
the rates are probably set too high, • the exact nature and content of
supervision inadequate or the workers the work,
see no advantage in finishing work early. • how it should be carried out,
Normally, workers should be directed • who will do it, and
to remain on site until their task is • the possible difficulties involved
complete, even if it occasionally takes in completing the work.
more than eight hours.
Instructions can be given either directly
Adjusting Tasks to the person carrying out the work, or
It is important that the tasks are correctly indirectly through a gangleader. Direct
estimated. When task rates are changed for instructions to all concerned workers
BUILDING RURAL ROADS
reasons which are not clearly understood including their gangleader are more
and appreciated by the workers, discontent effective. Indirect instructions can be
and other difficulties can be expected. On given through a gangleader when he/
the other hand, if, for three consecutive she as well as the workers are familiar
days, a group of workers finishes their
daily tasks to soon (say, in 40 percent of
the normal working hours), the task rate
should be adjusted. Similarly, if a task is
not completed within the normal working
hours for three consecutive days, it is
necessary to review the task rate.
4 4 0
14
W O R K O R G A N I S AT I O N
with the task and the work methods. previous visit can be reviewed before
Questions should be asked to check commencing further discussions on work
that the instructions have been fully progress.
understood.
Control of Works
If the task is not familiar, careful All works need to be inspected and
attention should be given to explaining approved before the workers are released
the work in detail to the entire gang. for the day. The supervisors should
In many cases, it is useful for the be notified by the gangleaders when a
supervisor to actually demonstrate the particular task has been completed and
work and how it is properly done. is ready for inspection. BUILDING RURAL ROADS
return to the work site the following the rationale behind the decisions and
day to complete their task. The workers to verify that they are appropriate and
should only be recorded in the muster acceptable to all parties.
roll when they have fully completed
their daily tasks.
W O R K O R G A N I S AT I O N
14.6 Organising Subcontractors
Separate contracts may be let for specific the planning of the various inputs
activities such as delivery of gravel, of other contractors starts at an early
foundation works and construction of stage of the project to ensure that their
culverts and bridges. The subcontractors work is carried out at the appropriate
may be hired directly by the client or stage of the project. A good example
indirectly through the main contractor is when using separate contractors for
on site. The client would usually leave the construction of structures. The
the responsibility for coordinating ideal situation would be to start the
the inputs of other contractors to the culvert and bridge works first, thereby
main contractor. If the main contractor ensuring proper access when the road
hires the subcontractors, the full works activities commence. Equally, all
responsibility for the supervision and earthworks and structures need to be
timely delivery of the work of the completed before the involvement of
subcontractors is with main contractor. any pavement contractors. BUILDING RURAL ROADS
The involvement of subcontractors places The same concerns apply when hiring
additional challenges to work organisation equipment for specific activities. Once
on site. Before a subcontractor arrives on the equipment arrives on site, the
site it is essential that any preparatory supplier will normally charge hiring
works are complete and that the work site fees no matter whether the equipment
is clear and ready for the subcontractors is used or not. In order to fully utilize
to commence their work. Equally, it is the equipment, the works for which
important that the subcontractors mobilize it is intended must be ready for
their services on time and thereby carry commencement. If the equipment is to
out their part of the works as scheduled in be used in combination with certain
the overall project work plan. materials, other pieces of equipment or
labour, these inputs need to be supplied
In this respect, it is important that and readily available on site.
4 4 3
14.7 Traffic on Site
An important part of organising work on
site is to make appropriate arrangements
for the traffic to pass despite the fact
14 that extensive construction works are
taking place. Rural roads, although they Maintenance of Works
normally do not cater for high levels of Before completed works are officially
W O R K O R G A N I S AT I O N
traffic, still provide essential connections handed over to the client, the contractor
to the rural areas. Often these roads are is responsible for maintaining the
the only access to the villages, so in light completed road assets. This implies that
of this, the roads must remain open for the contractor must repair any wear and
traffic during the works. tear caused by regular traffic passing
through the work site. It is therefore
This requirement places extra challenges useful to establish a work unit with the
to the site planning and organisation. responsibility for preventive maintenance
Solutions involve carrying out works of the completed road sections.
on either side of the centre line while
allowing traffic to pass on the other Traffic will also be travelling on sections
side. When constructing cross drainage where works are still not complete.
structures, temporary bypasses need to Ongoing works therefore need to be
be organised away from the work site. organised in a manner in which damages
to recently completed works are rectified
During the dry season, bypasses are easy to before the next work activity commences.
construct as long as they do not encroach A good example is the construction of
upon cultivated land. In periods with rain, road fills. Before the next layer is spread,
bypasses need to be constructed with some the damage caused to the previous layer
basic drainage facilities. In some cases, it needs to be repaired, ensuring that the
may also be necessary to import quality original levels are reinstated. This may
materials for the surfacing of temporary seem fairly obvious, however, it does
BUILDING RURAL ROADS
R E P O R T I N G A N D C O N T R O L
R 15
EPORTING AND CONTROL
REPORTING AND CONTROL
and labour,
• identify weak components of the
production chain,
• enable the mana gement to
effectively re-plan and reschedule
remaining works,
• calculate payment of completed
works,
• provide reliable information to
others about the project activities,
and
• collect experience data to improve
planning of future new projects.
planned targets and actual results, the the client and to headquarters. The
management needs to find out why the responsibility for reconciling daily
targets have not been reached. Either the reports into week ly and monthly
targets have not been set correctly or the summaries is usually assigned to the
work has not proceeded as planned. With technicians. This exercise allows the site
the information coming from the work management to compare results with
site, it is possible to revise and improve current plans and assess whether any
the current plans as well as improve specific action is required in order to
planning and costing of future projects. improve progress.
BUILDING RURAL ROADS
The progress repor ts a lso give a n It is important that the aggregate figures
opportunity to analyse good performance, are provided to the supervisors, thus
i.e. when the targets have been exceeded. informing them about how their work
Accurate and timely reporting is also an is progressing according to plans and
indication of the skills and abilities of the giving them an indication whether the
supervisors. actual outputs are satisfactory.
The management needs to concentrate Whatever the reason are for incurring
15 on the failings in performance that have cost increases, it is important that it is
a significant impact on overall targets detected at an early stage. The reasons for
and objectives, and not waste time on the change in costs need to be examined
REPORTING AND CONTROL
activities which have a limited effect and on this basis new projections should
on overall work progress. For rural be made. With the new projections,
road construction, the most significant there may be a need for adjusting
operations are the earthwork, surfacing contract agreements and budgets. This
works and structures. These operations involves major decision-making by senior
have a major impact on both progress managers, and can only be done on the
and costs incurred on the project. basis of reliable cost monitoring and
projections.
Cost Monitoring
Monitoring costs is necessary to avoid cost A project may also have cost savings.
over-runs and to prevent unauthorised When this occur, the senior management
expenditure. Every civil works project should be informed at the earliest
needs to operate within the budgetary possible so that the unused funds can
limits set in contract agreements and be redirected to other activities. In some
annual work programmes. The three cases, savings on certain work activities
most common reasons for cost overruns can be used for covering cost increases
are poor work organisation, inefficient on other work operations. If it appears
utilisation of available resources and that the entire works project will cost less
inaccurate estimates of the quantities than originally estimated, unused funds
BUILDING RURAL ROADS
4 5 0
15
This implies that the cost monitoring from the vehicle cost reports alone. It
needs to look into the detailed costs of is necessary to cross check with the
each activity. All inputs such as labour, quarry operations, haulage distances
equipment and materials used for a and equipment availability for the same
particular activity need to be closely period in order to obtain a clear picture.
monitored and costed, and compared
to the original estimates. Equally, it is important to focus attention
on the large work operations, which
Special attention must be paid to overhead carry the largest quantities of works.
costs (supervision, administration, This work incurs the highest costs, so
transportation, etc.). The percentage any savings and productivity increases
of funds spent on overheads can easily here have a higher impact on the overall
become excessive if it is not controlled. project cost.
4 5 1
15.3 Drawings and Work Specifications
All civil works projects are described Specifications are either prepared by
t hrough a set of drawings, which prescribing the quality of all inputs
graphically describe the works to be and specifying the work methods or
15 carried out. The level of detail in the by describing the features of the end
drawings may vary, depending on the product. The most common method
complexity of the works and to what of describing the works is by issuing
REPORTING AND CONTROL
extent the works adheres to common design and method specifications. This
building practices and design standards. implies that the works are described in
Drawings for road works normally refer terms of quality of materials to be used
to a standard design used for the specific and by specifying the work methods.
type and class of road the authorities have Method specif ications of ten a lso
decided to build. Road works drawings include minimum requirements and
therefore concentrate on how these the type of equipment to be used.
designs are applied in the terrain through
which the alignment passes, describing The opposite of such specifications
the levels of the road and its curvature. are performance-based specifications,
where the results or intentions of the
finished product are described. In this
type of specification, the details of
materials and how to carry out the work
are left to the contractor to decide, only
ensuring that the end product meets
certain performance requirements. If
the selection of materials and work
methods prove to be inadequate, the
fault is then entirely with the contractor
who will need to redo the works using
higher quality materials and improved
BUILDING RURAL ROADS
work methods.
will install effective measures to ensure drawings and dimensions and are
that problems of such nature do not experienced in the work methods
occur – or at best are minimised. to be applied. Furthermore, the
skilled workers and equipment
(i) Before works commence, the operators need to k now the
project management needs to quality requirements for the
ensure that all tools, materials completed work s. Unsk illed
and equipment are available. workers need to be fully briefed
Materials should conform to on how their tasks are carried
prescribed quality standards and out and how it will be assessed
tools and equipment should be in as satisfactory. A good example
good condition, thus providing of where proper instruction is
the site with the necessary inputs required is during compaction
4 5 6
(iv) Proper supervision during the
works provides essential work
guida nce a nd ensures that
instructions are actually carried out
as intended. For some important
activities, it may be necessary to 15
keep technical personnel present
during the entire duration of the
indicates when and how often payment used in the same way by all staff, the
claims can be submitted to the client. report forms are issued with a set of
procedures and directions relating
When payments are due, the contractor to how and when they are used and
prepares an invoice detailing the how the information is passed on to
quantities of work completed since the superiors.
previous claim. These quantities are
based on information compiled from Depending on the size of the site, the
the site production reports. responsibility for maintaining these
report forms can be divided among
Before the client issues the payment, a the supervisors, storekeeper and site
final control of the works is necessary office staff. The supervisors remain
to verify that the quantities of work responsible for the end result and need
have actually been carried out, and to verify the accuracy of the reports.
that the works conform to prescribed
quality standards. Any errors in the Record keeping is a routine job which
claimed quantities are then rectified. takes time and despite the fact that
Equally, the client may deduct poor it may be perceived as tedious, it is
quality work from the claim. Based on extremely important, since the whole
the revised volumes of work, the client chain of planning, progress monitoring
can then finalise the payment. and control and payment processing is
based on the site reports.
BUILDING RURAL ROADS
15
The muster roll is updated in the Daily Site Record
morning with occasional checks in the The daily site record forms the basis for
Bill of Quantities;
The muster roll should be maintained • The input assigned to each
every day and be readily available for work activity such as labour and
inspection. Every week or at the end equipment;
of each month, depending on how • The overall productivity rate is
frequent the project carries out wage calculated from the inputs and
payments, the muster roll is reconciled completed outputs at the end of
to calculate the wages for the workers. the day.
This exercise determines the exact • It is also common practice to report
amount of payments required at each general site conditions including
site and for each worker. issues such as weather conditions,
any problems encountered, accidents
or unusual events on site.
4 5 9
The exact design and contents of the reports, are prepared by the site office. The
report form will vary from one programme main purpose of this exercise is to enable
to another. However, in one way or the management to monitor progress
another, it contains the information as against planned targets. Together with
shown in the table below. the daily and weekly progress reports, this
15 information also provides the basis for the
In some projects, the daily site record invoicing of completed works.
is combined with a daily work plan,
REPORTING AND CONTROL
outlining the planned activities, planned The summary reports contain output and
inputs and expected results by the end of productivity data for the current month
the day. and for the total period so far since
the project commenced. This enables
To simplify the monthly report writing, management to review performance
the daily records are summarised at the for the last month and the average
end of each week into a weekly report. performance during the year so far,
The project management needs to against planned outputs and productivity.
compare the daily, weekly and monthly
work outputs with project work plans. Summary reports are designed to meet
This comparison also needs a close the monitoring needs of each level of
review of the inputs used to ensure that management. Report forms are designed
these do not exceed the estimated inputs so that the information needed for
used when calculating the unit rates in performance monitoring is displayed
the BoQ. in a clear way that is easily understood
and recognised. The higher up in the
Monthly Progress Report management organisation, the more
Monthly summaries of performance, general picture will be required of the
based on the weekly totals of the daily performance statement.
���������������
��������� ����� ����� �� �������������������� �� ��� ��
������������������
����������������
����������� ����� ����� �� �� ����� ���
������������������
��������������������������
���������� ����� ����� �� �������������������������� �� ��� �
������������������������
����������������
������ ����� ����� �� ������������������������� �� ����� ���
�����������
4 6 0
���������������� �����
�������� ���� ������
������ ���� ��� ��� ��� ��� ���
��
BUILDING RURAL ROADS
���� ������
���� �
���
���
���
����
��
��������
���
���
���
�
���
��
��
���
��
���
�������
���
������
��� ��� ��� ��� ��� ��� ��� ��� ��� ��� ���
4 6 1
�������������������
����������� ������
��� ��������������� �� ���������
���� �����������
� ������������������ ��������
����������
� ������ ������������������� ��������
At the end of each month, the supervising materials stored on site and assesses
engineer and the site manager carries whether it is sufficient for the projected
out a final inspection to verify that the work activities. Before embarking on
reported works have been carried out new activities, the staff in charge of
according to prescribed quality standards. procurement needs to stock up on
During the field visit, the supervising necessary materials well in advance of the
engineer checks that actual progress start of the work. Any items that are no
compares to the monthly site report longer in demand should be transferred to
records. A monthly payment certificate other sites or returned to the main store.
is then issued and submitted to the client
for payment. Tools Inventory
Tools on site are monitored at two
Store Records levels, on a daily basis when they are
Accurate records need to be kept on all issued to the workers, and as a whole,
BUILDING RURAL ROADS
materials supplied to the project and also relating to the total amount of tools
where and when they are used. These on site. The daily recording of tools
records give details about date, movements issued to the workforce is carried out
(issued or received), quantity, origin and in order to make sure that all the tools
destination. Each entry is signed by the are returned when the workers have
responsible supervisor or storekeeper. At completed their work. Secondly, the
the end of each month, it is common project needs to establish an overview of
practice to count the contents in the stores all the tools available on site in order to
and check the current holdings against the assess whether they have the right type
records of consumption. and amount for the works taking place.
On a regular basis, the project management The tools inventory also records the
reviews the contents and quantities of condition of the tools and keeps track
4 6 2
of repairs and when tools are worn
out and need replacement. Similar
to the materials records, the tools
inventory also provides the details of
when tools were supplied to the project.
The regular control of tools is the 15
responsibility of the storekeeper.
track of the curing schedules of the
1. Rural Road Maintenance, Sustaining the Benefits of Improved Access, Chris Donnges,
Geoff Edmonds and Bjørn Johannessen, International Labour Organization, Bangkok, 2007
2. Implementing Employment Intensive Road Works, Construction Industry Development
Board, Pretoria, 2007
3. Increased Application of Labour-based Methods through Appropriate Engineering
Standards, Guideline for Quality Assurance Procedures and Specifications for Labour-
based Road Works, International Labour Organization, Harare, 2006
4. The Idiots' Guide to Highways Maintenance, www.highwaysmaintenance.com, C.J.
Summers, 2006
5. Macceferri brochures and drawings, www.maccaferri.com
6. BOMAG Soil and Asphalt Compaction, www.bomag.com
7. Surfacing Alternatives for Unsealed Rural Roads, MWH, World Bank, 2005
8. Hand tools for Trail Work, United States Department of Agriculture, Forest Service 2005
9. Design and Planning Manual for Farm to Market Roads, Infrastructure for Rural
Productivity Enhancement Sector Project, Department of Agriculture, Philippines 2004
10. Concrete Basics, A Guide to Concrete Practice, Cement Concrete & Aggregates
BUILDING RURAL ROADS
Australia, 2004
11. Basic Construction Training Manual for Trainers, Heini Müller, Skat Foundation, St.
Gallen, 2004
12. Management of Rural Road Networks, Overseas Road Note 20, Transport Research
Laboratory, Crowthorne, 2003
13. The Shell Bitumen Handbook, John Read and David Whiteoak, 2003
14. Improving Access in Rural Areas, Guidelines for Integrated Rural Accessibility Planning,
Chris Donnges, International Labour Organization, Bangkok, 2003
15. Building Local Government Capacity for Rural Infrastructure Works, Geoff Edmonds and
Bjørn Johannessen, International Labour Organization, Bangkok 2003
16. Manual for the Labour-based Construction of Bituminous Surfacings on Low-volume
Roads, Transport Research Laboratory, Crowthorne, 2003
17. Rural Roads Manual, Indian Road Congress, New Delhi, 2002
18. Technical Manual for Labour-based Road Rehabilitation Works, Ministry of Works and
Supply, Roads Department Training School, Lusaka and Norconsult A.S. Nairobi, 2000
19. A Guide to Surface Dressing in Tropical and Sub-tropical Countries, Overseas Road
Note 3, Transport Research Laboratory, Crowthorne, 2000
20. Standard Test Methods for Laboratory Compaction Characteristics of Soil Using
Standard Effort, ASTM D698 – 00a
21. Labour-Based Road Construction, Ministry of Rural Development, Rural Infrastructure
Improvement Project, Bjørn Johannessen, Cambodia, 2000
22. The Housing Concrete Handbook, Cement Concrete & Aggregates Australia, 2000
23. Technical Specifications for Labour-based Construction Work of Agricultural and
Rural Roads, International Labour Organization/Department of Local Infrastructure
Development and Agricultural Roads, Katmandu 2000
4 6 4
24. Standard Technical Specifications, Ministry of Communication, Transport, Post and
Construction, Lao PDR
25. Contracts Management, Labour-based Road Construction Works, Ministry of Rural
Development, Cambodia, Bjørn Johannessen, Phnom Penh 1999
26. Rural Road Maintenance Management, Ministry of Rural Development, Cambodia, Bjørn
Johannessen, Phnom Penh 1999
27. Capacity Building for Contracting in the Construction Sector, Peter Bentall, Andreas
Beusch and Jan de Veen, International Labour Organization, Geneva 1999
28. Contracting Entrepreneurial Training Programme, Start and Improve your Construction
Business, International Labour Organization, South Africa 1999
29. Technical Specifications for Labour-based Construction Work of Agricultural and
Rural Roads, Department of Local Infrastructure Development Agricultural Roads,
International Labour Organization, Nepal, 1999
30. Manuel pratique de formation pour cadres techniques de bureau d'etudes, Olivier and
Van Imschoot, Bureau International du Travail, Geneva 1999
31. Manuel pratique de formation pour cadre gerant d'entreprise, Gestion d'entreprise et
administration du contrat, Franco Olivier, Bureau International du Travail, Geneva 1999
32. A Guide to the Use of Otta Seals, Publication No. 93, Charles Øverby, Road Technology
Department, Norwegian Public Roads Administration, Oslo 1999
33. Culvert Manual, An Introduction to Hydraulics, Design and Construction, Ministry of Works
57. Labour-based Construction Programs – A Practical Guide for Planning and Management,
Basil Coukis, World Bank, 1983
58. Guide to the Training of Supervisors for Labour-based Road Construction and
Maintenance, Karlsson and de Veen, International Labour Office, Geneva, 1981
59. Guide to Tools and Equipment for Labour-based Road Construction, International
Labour Office, Geneva 1981
60. A Guide to the Structural Design of Pavements for New Roads, Road Note 29, Road
Research Laboratory, 1970
4 6 6