Professional Documents
Culture Documents
Sug Lecture Note
Sug Lecture Note
In highways, railways, or canals the curve are provided for smooth or gradual
change in direction due to the nature of terrain, cultural features, or other
unavoidable reasons. In highway practice, it is recommended to provide curves
deliberately on straight route to break the monoton in driving on long straight route
to avoid accidents. The horizontal curve may be a simple circular curve, compound
or reverse curve. For a smooth transition between straight and a curve, a transition
curve is provided.
Horizontal curves connect intersecting straight sections of roads. Point where the
straight sections intersect is called a Point of intersection (PI). The larger the radius,
the flatter the curve. The design of the curve is dependent on the intended design
speed for the roadway, as well as other factors including drainage and friction.
These curves are semicircles as to provide the driver with a constant turning rate
with radii determined by the laws of physics surrounding centripetal force. Types of
Horizontal Curves include:
The various elements of a Simple Circular Curve can be calculated the for use in
design and setting out, as follows;
→Tangent length (T) = R tan
→Length of the curve (L) = RΔ (rad) =
= (approximate)
b = √( ) -√( )
Tangential Angle =
EXAMPLE 1:
The chainage of the intersection point of two straight is 1060m, and the angle of
intersection is 120 . If radius of a circular curve to be set out is 570m, and peg
interval is 30 m, determine the tangent length, the length of the curve, the chainage
at the beginning and end of the curve, the length of the long chord, the lengths of the
sub-chords, and the total number of chords.
SOLUTION:
Deflection angle Δ = 180º - ɸ
= 180º - 120º = 60º
= = 596.90m
Thus N = 19 + 2 = 21
EXAMPLE 2:
The Centre-line of two straights is projected forward to meet at I, the deflection
angle being 30 . If the straight are to be connected by a circular curve of radius
200m, tabulate all the setting-out data, assuming 20m chords on a through chainage
basis, the chainage of I being 2259.59m.
Tangent length = R
= 200 = 200 = 53.59m
From which the number of chords may now be deduced. On the straight AI,
the chainage of T1 is (2 + 206). Therefore, a point P having chainage (2 + 200)
will be 6 m before T1 on AI. Since the peg interval is 20 m, the length of the
normal chord is 30 m. the first point on the curve will be at a distance of 20m
from P having chainage (2 + 220) and 20 – 6 = 14m from T1. Thus the length of
the first sub-chord = 14m
Thus N = 4 + 2 = 6
Deflection angles:
1st sub-chord = = 120.3’
=2 remaining 0.3’ 00’ remaining 0.3’x 60 =18’’
P C C Def Set R
o h h lect tin e
i a o ion g m
n i r An out a
t n d gle an r
a gle k
g l
e e
n
g
t
h
(
m
)
1 2 1 2 2 P
( 2 4 00 00 1
B 2 18 18
C 0
) .
0
0
2 2 2 2 4 P
2 0 51 52 2
4 53 12
0
.
0
0
3 2 2 2 7 P
2 0 51 44 3
6 53 05
0
.
0
0
4 2 2 2 10 P
2 0 51 35 4
8 53 58
0
.
0
0
5 2 2 2 13 P
3 0 51 27 5
0 53 51
0
.
0
0
6 2 1 1 14 P
( 3 0 32 59 6
E 1 . 08 59
C 0 7
) . 2
7
2
Check:
The sum of deflection angles = ⁄ = 14 59 59 ≈ 15
COMPOUND CURVES
Combination of two simple curves combined together to curve in the same direction.
The individual curves meet tangentially at their junction point. Smooth driving
characteristics require that the larger radius be more than 1 times larger than the
smaller radius. The elements of a compound curve shown below:
Fig 6.2: Compound Curve
= tan
=( ) +
=( ) +
Where Δ = +
ɭ = +
= ( )
iii. Chainages
Chainage of = Chainage of P.I. -
Chainage of = Chainage of +
Chainage of = Chainage of +
EXAMPLE 1:
The Centre-line of a new railway is to be set out along a valley. The first AI bear 75 0,
while the connecting straight IB bears 1200. Due to site conditions, it has been
decided to join the straights with compound curve. The first curve of 500m radius
commences at T1, situated 300m from I on straight AI, and deflect through an angle
of 250 before joining the second curve. Calculate the radius of the second curve and
the distance of the tangent point T2 from I on straight IB.
,
45 25 +
= 45 - 25 = 20
Tangent length T1t1 = R1 tan /2
= 500 tan 12 30’ = 110.8m
In triangle t1It2,
Angle t2It1 = 180 - = 135
Length It1 = T1I – T1t1
= 300 – 110.8 = 189.2m
By sine rule,
t1t2 = = = 391.2m
It2 = = = 233.8m
EXAMPLE 2:
A 200m length of straight connects two circular curve deflecting to the right. The
radius of the first circular curve is 250m and that of the second curve is 200m. The
central angle for the second curve is 15058’. The combine curve is to be replaced by
single circular curve between the same tangent points. Find the radius of the curve
and the central angle.
Since the combined curve is to be replaced by a single circular curve between the
same tangent points, the tangent length must be equal. Figure below shows the
original curve with a straight portion in between. The dotted line shows the
proposed circular curve.
Since the tangent length remain the same, the straight line AO1 and DO2 when
produced will intersect at O, the centre of the new curve.
At point O2,
= O1O2O + + 90 + = 180
O1O2O = 180 - ( + 90 + )
O1O2O = 180 - (14 2’ + 90 + )
= 60 00’00’’
16.2R = 61258.44
R= = 576.8m
= = 0.9985
33
REVERSE CURVES
Combination of two simple curves of same or different radii combined together to
curve in the different direction. Two straights to which a reverse curveconnectsmay
be parallel or non-parallel.
Fig. 6.3: transition Curve
R=
R=
Where = ( )
= ( )
= ( )
Case-3 Non parallel straights when R1 =R2, given , , Land R1 (or R2)
R2 =
* +
L = √[ ( )]
Fig 1.8
Example 1:
Two parallel railway tracks, Centre lines being 60m apart, are to be connected
by a reverse curve, each section having the same radius. If the maximum
distance between the tangent points is 220m calculate the maximum
allowable radius of the reverse curve that can be used.
we have
= √( )
= 228.035m
2R =
2Rsin =
sin =
2R x = 228.035
R= = 866.7m
Example 2: the first branch of a reverse curve has a radius of 200m. if the
distance between the tangent points is 110m, what is the radius of the second
branch so that the curve can connect two parallel straights, 18m apart? Also
calculate the length of the two branches of the curve.
Data given:
R1= 200m
D = 18m
L = 110m
From case-4 equation, we have
L = √[ ( )]
R2 = R1
= = 136.11m
From equation
= 2sin-1[√ (
]
)
= 18 50'10'' = 18,836 =
= = 65.75m
= = 44.75m
TRANSITION CURVES
A curve that has a varying radius. It permit gradual change of direction from
straight to curve and vice-versa, and at the same time gradual introduction of
superelevation. Transition curve is also required to be introduces between
two circular curve of different radii. The radius of transition curve at its
junction with the straight is infinity, i.e., that of the straight, and at the
junction with the circular that of the circular curve.
Consider a vehicle travelling at speed (V) along a straight. The forces acting
on the vehicle will be its weight W, acting vertically down, and an equal and
opposite force acting vertically through the wheel. But the moment it enters
the curve of radius R at tangent point T1, an additional centrifugal force (P)
acfson vehicle. If P is large the vehicle will be forced to the outside of the
curve and may skid or overturn.
Fig 1.10:
The resultant of the two forces is shown as N, and by lifting the outer edge
(superelevation) of the road or rail, the resultant can be made to act
perpendicular to the running surface and there will be no tendency for the
vehicle to skid.
Fig 1.11
V = Velocity ( Km/h)
When = L , then = =
4. =
C= constant =
(i) To introduce gradually the centrifugal force between tangent point and
the beginning of the circular curve, avoiding sudden jerk on the vehicle.
This increase the comfort of passenger.
(ii) To enable the driver turn the steering gradually for is own comfort and
security.
Types of Transition
Two straight are to be joined by a single curve with cubic spiral transition at
each end. The transition curves are to design such that:
c) Draw the setting out angles for the first three chords. Design speed =
100Km/h.
R= =400
(a) L= = 120m
S= = = 1.5
and = 50 = = 0.872778
Chainage at T2 =
= = = = 10313
As the chainage of T1 = 1907, then the first chord will be 3m long to give a
round chainage of 1910m
P C Ch Cu Deflectio
o h ord mm. n angle
i ai len Len ( )
n n gth gth
t g (m) (m)
e
(
m
)
0 1 0.0 0.0 0.0
9
( 0
T 7
1
)
1 1 3 3 0
9
1
0
2 1 10 13 0
9
2
0
3 1 10 23 0
9
3
0
Example 2:
Given that:
Chainage of I = 1530.685 m
(a) L= = 90m
S= = = 0.338m
and = 33 = = 0.5784
= 1188.105 + 90 = 1278.105m
As the chainage of T1 = 1188.105m, then the first chord for transition curve
will be 11.895m long to give a round chainage of 1200m
= = = = 1374.92
P Ch Ch Cu Deflection
o ain ord mm angle ( )
i age len .
n (m) gth Len
t (m) gth
(m)
0 118 0.0 0.0 0.0
8.1
( 05
T
1
)
1 120 11. 11.8 0° 00′ 54″
0 895 95
2 122 20 31.8 0° 06′ 29″
0 95
3 124 20 51.8 0° 17′ 09″
0 95
4 126 20 71.8 0° 32′ 54″
0 95
5 127 18. 90.0 0° 51′ 34″
8.1 105 0
( 05
A
)
=δ= minutes
= minutes
= 1.7189c minutes
P Ch C Defl Sett R
o ain h ectio ing e
i age o n out m
n r Ang ang a
t d le le r
k
l
e
n
g
t
h
(
m
)
5 127 0 0 0 A
8.1 0 0 0
( 05
A
)
6 130 2 0° 0° P
0 1 37′ 37′ 6
. 38.1 38.1
8 ″ ″
9
5
7 1 5 1° 2° P
3 0 25′ 03′ 7
5 56.7 35″
0 ″
8 1 5 1° 3° P
4 0 25′ 29′ 8
0 56.7 32″
0 ″
9 1 5 1° 4° P
4 0 25′ 55′ 9
5 56.7 28″
0 ″
1 1 5 1° 6° P
0 5 0 25′ 21′ 1
0 56.7 25″ 0
0 ″
1 1 5 1° 7° P
1 5 0 25′ 47′ 1
5 56.7 22″ 1
0 ″
1 1 5 1° 9° P
2 6 0 25′ 13′ 1
0 56.7 18″ 2
0 ″
1 1 5 1° 10° P
3 6 0 25′ 39′ 1
5 56.7 15″ 3
0 ″
1 1 5 1° 12° P
4 7 0 25′ 05′ 1
0 56.7 12″ 4
0 ″
5 1 5 1° 13° P
7 0 25′ 31′ 1
5 56.7 08″ 5
0 ″
( 176 1 0° 13° B
B 6.3 6 28′ 59′
) 90 . 10.4 19″
3 ″
9
0
The second transition curve is set out from tangent point T2 by measuring
distances in the direction from B to T2, and deflection angles for the
corresponding points from T2 measured in counterclockwise from T2I.
P Ch C Cu Deflectio
o ai h mm. n angle
i na o Len ( )
n ge r gth
t (m d (m)
)
l
e
n
g
t
h
(
m
)
1 17 1 90.0 0° 51′
6 66. 3 0 34″
39 .
( 0 6
B 1
) 0
1 17 2 76.3 0° 37′
7 80 0 90 09″
1 18 2 56.3 0° 20′
8 00 0 90 15″
1 18 2 36.3 0° 08′
9 20 0 90 26″
2 18 1 16.3 0° 01′
0 40 6 90 43″
.
3
9
0
2 18 0 00 00
1 56. 0
39
( 0
T
2
)
Example 3:
A compound curve AB, BC is to be replaced by a single arc with transition
curves 100m long at each end. The chord lengths AB and BC are respectively
661.54 and 725.76 and radii 1200m and 1500m. Calculate the single arc radius:
Fig 1.12
Chord AB = 2R1sin ⁄
Therefore sin ⁄ =
= 32
Similarly, sin ⁄ =
= 28
t2I = = 439 m
AI = (R + S) tan ⁄ + ⁄
Where S = ⁄ and = + = 32 + 28 = 60
L = 100m
R = 1182m
CI = (R + S) tan ⁄ + ⁄
813 = ( )tan 30 + 50
R = 1321m
VERTICAL CURVES
The vertical curves are used to provide a smooth change in direction taking
place in the vertical plane due to change of grade. Vertical curves are
introduced at the intersection of two gradients either as summit curves or sag
curves.
Summit Curves
Sag curves
The following are key Formulae used for vertical curves computations;
Equation for Parabola y=ax2
Chainage at BVC = chainage at VPI –
Mid-ordinate = e =
Where x =
Example 1:
Two straights AB and BC falling to the right at gradients 10% and 5%,
respectively, are to be connected by a parabolic curve 200 m long. Design the
vertical curve for chainage and reduce level of B as 2527.00 m and 56.46 m,
respectively. Take peg interval as 20 m.
The –ve sign just indicate the nature of the curve, Sag curve
Mid-ordinate = e =
= = 1.25
=2 n = L/20 = 200/20 = = 10
S Ch C G V R Re
/ ai h r e e m
N na o a r d ar
ge r d t u ks
d e i ce
( c d
l m a le
e ) l v
n o el
g f (
t f m
h s )
e
( t
m (
) m
)
1 24 0 6 0 66 B
27 6 .4 V
. 6 C
4
6
2 24 2 6 + 64 P1
47 0 4 0 .5
. . 1
4 0
6 5
3 24 4 6 + 62 P2
67 0 2 0 .6
. . 6
4 2
6
4 24 6 6 + 60 P3
87 0 0 0 .9
. . 1
4 4
6 5
5 25 8 5 + 59 P4
07 0 8 0 .2
. . 6
4 8
6
6 25 1 5 + 57 P5
27 0 6 1 .7
0 . . 1
4 2
6 5
7 25 1 5 + 56 P6
47 2 4 1 .2
0 . . 6
4 8
6
8 25 1 5 + 54 P7
67 4 2 2 .9
0 . . 1
4 4
6 5
9 25 1 5 + 53 P8
87 6 0 3 .6
0 . . 6
4 2
6 0
1 26 1 4 + 52 P9
0 07 8 8 4 .5
0 . . 1
4 0
6 5
1 26 2 4 + 51 E
1 27 0 6 5 .4 V
0 . . 6 C
4 0
6 0
Example 2:
Avertical curve of 120m long of the parabolic type is to join a rising gradient
of 1in 200 to a falling gradient of 1in 300. If the level and chainage of the
intersection of the two gradient are 105.96m, 2000.00 m. Give the level at 20m
interval along the curve.
Fig 1.15
For EVC,
Mid-ordinate = e =
= = 0.1245
=2 n = L/20 = 120/20 = 6
S Ch C G V R R
/ ain h ra e e e
N ag o d r d m
e r e ti uc a
d ( c e r
m a d k
l ) l le
e o ve
n f l
g f (
t s m
h e )
t
( (
m m
) )
1 19 0 10 0 10 B
40 5. 5. V
66 66 C
2 19 2 10 - 10 P
60 0 5. 0 5. 1
76 . 75
0
1
3
9
3 19 4 10 - 10 P
80 0 5. 0 5. 2
86 . 80
0 5
5
5
4 20 6 10 - 10 P
00 0 5. 0 5. 3
96 . 83
1 6
2
4
5
H 20 7 10 - 10 H
i 12. 2 6. 0 5. i
g 28 . 02 . 84 g
h 9 2 2 1 h
8 8 e
p 9 0 s
t 5 t
p
o
i
n
t
5 20 8 1 - 1 P
20 0 0 0 0 5
6. . 5.
0 2 8
6 2 3
1 8
6
7 20 1 10 - 1 P
40 0 6. 0 0 6
0 16 . 5.
3 8
4 1
6 4
8 20 1 1 - 1 E
60 2 0 0 0 V
0 6. . 5. C
2 4 7
6 9 6
8 2
Example 3:
A downward of 4% meets at a rising grade of 5% in a sag curve at the start of
the curve, the level is 123.06m at chainage 3420m, while at chinage 3620m
there is an overpass with an underside level of 127.06m. If the design curve is
to afford a clearance of 5m at this point, calculate the require length.
Fig 1.16
To find the offset distance CE
where A = g1-g2 = - 4 -5 = -9
note: the –ve shows the nature of the curve, sag
= CE = X =
L= = = 25
SETTING OUT
Setting out is the reverse of surveying. What is meant by this is that whereas
surveying is the process of producing a plan or map of a particular area,
setting out begins with the plan and ends with some particular engineering
project correctly positioned in the area. This definition can be misleading
since it implies that setting out and surveying are opposites. This is not true.
Most ofthe techniques and equipment used in surveying are also used in
setting out and it is important to realise that setting out is simply one
application ofsurveying. A better definition of setting out is provided by the
International Organisation for Standardization (ISO) in their publication
ISO/DP 7078 Building Construction which states that;
'Setting out is the establishment of the marks and lines to define the position
and level ofthe elements for the construction work so that works may proceed
with reference to them’. This process may be contrasted with the purpose of
surveying which is to determine by measurement the positions of existing
features.
- Most of the techniques and equipment used in surveying are also used in
setting out.
1. The control points should be located throughout the site in order that all
the design points can be fixed from at least two or three of them so that
the work can be independently checked.
2. The design points must be set out to the accuracy stated in the
specification.
The accuracy must be obtained throuhout the whole network and this can
be achieved by establishing different levels of control based on one of the
fundamental tenets of surveying: Working from the whole to the part. In
practice, this normally involves starting with a small number of very
accurately measured control points ( Primary control) which enclose the
area in question and then using these to establish secondary control points
near the site.
An example of working from the whole to the part using two different
levels of control are shown below. In this, the primary control points is
provided by a traverse which is run through the site in question to
provide a number of well positioned primary control points. These in turn
are used to establish a secondary control point. In this case secondary site
points at each of a series of baselines which define important elements of
the scheme.
On some schemes, the same control points that were used in production of
the site plan prior to design work are used for setting out. These must be
re-measured before setting out as position may have changed for a
number of reasons.
Baseline
A baseline is a line running between two points of a high position. Any
baselines required to set out a project should be specified on the setting out
plan by the designer and included in contract.
Baseline can take many forms: they can be simply two specified points joined,
they can run between two buildings, they can mark the centreline for a new
road. Baseline can be used in a number of different ways. Where a baseline is
specified to run between two points then once the ponts have been
established on site, the design points can be set out from the baseline by
offsetting using tapes ( as shown below).
Point Location
If two control points A and B are known, a third point C as shown in Fig. 9.1,
can be located in a number of ways.
θ
Steps:
(a) Set out distanees AC and BC.
A control grids enables points to be set over a large area. Many structures in
civil engineering consist of steel or reinforced concrete columns supporting
floor slabs as the disposition of these columns is inevitably that they are at
right angles to each other, the use of grid, where the grid intersections define
the position of the columns, greatly facilitates setting out. Several different
grids can be used in setting out.
Site grid: is used by the designer. Defines the position and direction of the
main building lines of the project.
Setting out is not limited to roads and rails. In any engineering projects, there
is need to set-out the corner points before construction commences. In doing
this, the base line which may be road centre lines, building lines or a line
joining the centre lines of series of pad foundationwill have to be first set out.
From this line, further lines e.g subsidiary lines may be set up. The process is
carried out by locating on the field survey control stations and obtaining their
cordinates from survey readings. A minimum of two survey controlpoints are
required to commence any setting-out procedure. If for example a building
line is required to be set up, the two end points of the building will have to be
separately set out. The coordinates of the points to be set out may also be
scale off from a topo plan.
To set out the corner points of that engineering structures the building lines
P1, P2 will have to be first set up. This will only be possible if there are
control poits A and B visible within the site. The coordinates of A and B as
explained earlier may be obtained from the survey ministry while those of P1
may be scaled off from survey plan.
There are two approach to this setting out in particular, the first approach is
the traditional method whereby analog equipment are used in the setting out
procedure. The procedure is longer and the volume of work involves is more
both in the office and in the field. However, this method is still relevant
where modern equipment is not readily available. The second approach is the
use of modern electronics facilities. Most of the calculation and procedure
that are in the tradition are done away with. It does not require the
computation of bearing and angles of setting out. The coordinate of the points
to be set out may be inputed into the equipment after the usual station
adjustment and distance and direction to locate the points will be displayed
on the screen, hence a reflector man may be directed straight to the position
of the points.
TRADITION SETTING OUT METHOD (THEODOLITE AND TAPE)
Example 1:
Consider example below:
It is required to set out a base point P from two visible controls A and B on a
construction site, by polar coordinates.
1. Obtain the coordinate of the control station A and B from survey ministry.
Also scale off the coordinate of P1 for instance from the survey plan.If the
coordinates of the control and those of P obtained from survey plan are;
A; 333444.05mE, 1167582.75mN
B; 333500.22mE, 1167559.01mN
P; 333470.75mE, 1167568.25Mn
2. Compute the bearing ⃗⃗⃗⃗⃗ and ⃗⃗⃗⃗⃗ and distance BA and BP from their
coordinate values.
Bearing ⃗⃗⃗⃗⃗
Obtain
tan = = =
= ( )= 16.543
= 16 32' 24''
Since both Easting and Northing are negative, then A is in third quadrant
Distance PA = √( ) ( ) =√
= 244.04m
Bearing ⃗⃗⃗⃗⃗
Obtain
= =
= ( )= 86.949
= 88 56' 55''
= = 88 56' 55''
Distance PA = √( ) ( ) =√
= 360.76m
Example 2:
The four comers A, B, C, and D of a rectangular building having the
coordinates given in Table below are to be set out from control station P by a
total station instrument. Calculate the WCB and distance to establish each
comer of the building.
C EAS NOR
OR TIN THIN
NE G G
R
A 117. 92.849
984
B 82.6 128.20
29 4
C 33.1 78.707
32
D 68.4 43.352
87
Since both Easting and Northing are positve, then A is in first quadrant
Distance PA = √( ) ( ) =√
= 13.797m
For comer B
Tan = = = 0.5921
Distance PA = √( ) ( ) =√
= 54.471m
For comer C
Tan = = = 29.407
Distance PC = √( ) ( ) =√
= 77.296m
For comer D
The point D is also in the third quadrant due to the same reasons as for C
above. Therefore
Distance PD = √( ) ( ) =√
= 56.55m
DEFORMATION SURVEYING
Over the last decade, an interest has grown among the civil engineering and
building professions in monitoring the movement of different types of
structure both during and after completion of construction. There are many
reasons why a structure may need to be monitored for movement. For
example, it is well known that dam walls change shape with varying water
pressure, that the foundations of large buildings are affected by changes in
ground conditions and that landslips sometimes occur on embankments and
cuttings. For all of these, deformation surveys can be used to measure the
amount by which a structure moves both vertically and horizontally over
regular time intervals. Although the principles of many of the techniques
used to do this are recognisable as those used for site surveying and setting
out, it is the taking of very precise periodic measurements that distinguishes a
deformation survey from other types of survey. In summary, the purposes of
a deformation survey are to ascertain if movement is taking place and to
assess whether a structure is stable and safe. In addition, movement may be
analysed to assess whether it is due to some daily, seasonal or other factor
and, most importantly, it may be used to predict the future behaviour of a
structure. The terms relative and absolute are often used for deformation
surveys. The measurement of relative movement is generally much easier
since movements are related to the structure itself or to some arbitrary
point(s) nearby. These may move during a survey but this does not affect the
results obtained. Absolute measurements, on the other hand, are related to
datum points that are assumed not to move during a survey. The accuracy
required for a deformation survey depends on many factors including the
type and size of building or structure, what is causing the movement
(environmental factors or loading) and whether an understanding of the
movement is needed. For many surveys, deformations of less than 1 mm are
measured and precisions of this order require the best survey techniques to
be used throughout a deformation survey. This is to ensure that the
systematic and random errors propagated in observations are less than the
smallest displacement that is being measured or is expected. Many different
types of measurement can be taken during a deformation survey using a
wide variety of equipment. This chapter will only consider methods for
monitoring that involve some of the surveying techniques already described
in this book and will not include details of monitoring using such methods as
photogrammetry and automated systems which involve the use of
transducers and sensors. Details of these can be found in the references given
at the end of this chapter.
VERTICAL MOVEMENT
For nearly all applications where levelling is to be used, an ordinary level and
staff are inadequate and special equipment is required so that sub-millimetre
readings can be taken. This consists of a precise optical level fitted with a
parallel plate micrometer and an invar staff (see figure below ). Alternatively,
a precise digital level such as the Wild NA3000 with its bar-coded invar staff
can be used (figure 15.2). Whatever equipment is used, the basic approach to
fieldwork is similar to that described in chapter 2 but much more care is taken
with the observations and with keeping sight lengths equal and much shorter
than for ordinary levelling.
Example:
In order to check for any subsudence of a multi storey block of flats, two
pillars A and B (see fig 3.1) were set up on solid foundations adjacent to the
building. A target T was fixed near the top of the building and a series of
angles and distances were measured at three month intervals using the same
equipment and methods.
Solution
Diagram below shows a plan view of the three points A, B, and T with
refrence to this, the horizontal distance DAT is obtained by solving triangle
ABT
DAT = ( )
= ( )
= 77.5729m
UNDERGROUND SURVEYING
Underground surveying embraces thhe survey operations performed beneath
the surface of the earth in connection with tunneling, exploration and
construction in subterranean passage ways. It is quite different from
surveying on the surface.
(iii) Instrument stations and benchmarks for levelling must often be set into
the roof of a passageway to minimize disturbance from the operations
being carried on in the workings.
(iv) Instrument stations are set with some difficulty since plugs must be
driven into drill holes in rock.
(v) In many instances the underground workings are wet, with considerable
water dripping from the roofs of passageways and running along the
floors.
v. Exact alignment
1. Surface survey
3. Levels in tunnels
Surface survey:
Surface survey connect points representing each portal of a tunnel. A traverse
connecting the portal points determines the azimuth, distance and differences in
elevation of each end of the proposed tunnels. Based on the local conditions and
proposed length of the tunnel the methods of working are adopted.
It is always advisable that the survey is based on the suitable local coordinate
system.thhe alignment is permanently referenced by a system of monuments within
an area outside each tunnel portal. And here is sketch regarding how the tunnelling
work proceeds.
Central line and grade stakes within the tunnelare usually set in the roof to avoid
displacement and destruction by the constant flow of people and machinery as
construction proceeds. If the stakes are set on the floor they should be offset into an
area along the tunnel’s edge.
Transfering the alignment underground:
For long tunnel excavation is carried inward from both parties. But vertical shafts
are also sunk up to the required depth along the alignment of the tunnel at
intermediate locations along the routes.the vertical alignment can be done by
i. Plumb bob
Optical plumbing becomes important with the increase in depth of internal shaft.
Various types of plummet are available for upwards and downward sighting to
alllow the establishment of a vertical line and these are normally manufactured so as
to be interchangeable with theodolites on their tripods.
As the line of sight of a theodolite in adjustment will transit in a vertical plane, it can
also be used to check perpendicularity.
ii. Can be used to set marks directly on the floor of a complete shaft
A laser equipment can be used to, provide a vertical line of sight. The laser generates
a light beam of high intensity and of low angular divergence and can be projected
over long distances since the spread of the beam is very small to provide a visible
line for constant reference.
Levels in tunnels:
In transferring levels underground, little difficulty is encoutered at the ends of the
tunnel, but at the shaft use is made of
i. Steel tap
ii. Chain
Nowadays EDMI is also used. But in all cases the main idea is to deduct the height
of the shaft measured from the top of a benchmark of known value.
Fig 9.2 How the depth is measured by steel tape
Sadanandam anupoju
REFERENCES
Uren J. and Price W.F (1994) survey For engineering, Palgrave, london, Pp
554-571