You are on page 1of 4

Coordinates: 50.785°N 3.

863°W

Den Brook Wind Farm


Den Brook Wind Farm is a windfarm in Devon, England. The
Den Brook Wind Farm
windfarm is located 2 kilometres (1.2 mi) south-east of North
Tawton and 2.5 kilometres (1.6 mi) south-west of Bow, and
comprises nine wind turbines, each 120 metres (390 ft) high.
Developer Renewable Energy Systems (RES) received planning
consent for the project in December 2009,[1] following a long
planning process which included two public inquiries and a
judicial review.

RES initially put forward proposals for a windfarm at Den Brook


in 2004, and in response the Den Brook Valley Action Group was
established to oppose the plan. A key concern was the potential
Location of Den Brook Wind Farm in Devon
impact of noise on local residents. In 2006, West Devon Borough
Council refused planning permission for the scheme, but RES Country England
appealed, and consent was granted in early 2007 following a public Location near North Tawton, Devon
inquiry. Still concerned about noise issues, local residents the
Coordinates 50.785°N 3.863°W
formed Den Brook Judicial Review Group which pursued a
Status Consented
judicial appeal. This resulted in the inquiry decision being
overturned, and a second public inquiry was held in October 2009, Owner(s) Renewable Energy
following which permission was once more granted, subject to a Systems
number of planning conditions. A second legal challenge was Hub height 80m
rejected in August 2010.[2] In 2011, the windfarm was the subject Rotor diameter 80m
of a television documentary series, Windfarm Wars, broadcast by
Power generation
BBC Two, which followed the history of the project.[3]
Units operational Nine
External links

Contents Website www.den-brook.co.uk (htt


p://www.den-brook.co.uk/)
Planning history
Planning application
Judicial review
Second public inquiry
Construction
Windfarm Wars
References
External links

Planning history
RES initially publicised two alternate proposals for Den Brook in 2004: a scheme of ten 100-metre (330 ft) turbines; and a
scheme of 19 80-metre (260 ft) turbines. Following consultation, a layout of nine 120-metre (390 ft) turbines was developed.[4]
Also in 2004, RES erected an anemometer mast to measure wind speed, and undertook background noise monitoring.[5]
Planning application
By April 2005, Den Brook Valley Action Group (DBVAG) had been formed, and was flying a balloon at the site to mark the
height of the proposed turbines.[6] The planning application was submitted to West Devon Borough Council (WDBC) in
November 2005.[7] Objections to the proposal came from the Campaign to Protect Rural England, Mid Devon District Council,
and from 2,915 objection letters, all citing grounds including visual impact, noise, and residential amenity.[8] Dartmoor National
Park and the Dartmoor Preservation Association also objected, as the site is located around 5.5 kilometres (3.4 mi) from the
national park boundary.[8] 71 letters of support were also received.[8] WDBC planning officers recommended refusal of planning
permission, on the grounds of visual impacts, and potential impacts on the historic environment.[8] On 31 January 2006 the
council voted to accept the recommendation, and refused planning permission.[9][10]

Four months later, RES announced their intention to appeal to the Planning Inspectorate against the decision, and to seek a public
inquiry.[11] The inquiry was held in November 2006, at which the appeal was opposed by representatives of WDBC and DBVAG.
In February 2007 the appeal was allowed by the planning inspector, and planning permission granted.[12]

Judicial review
In March 2007, the Den Brook Judicial Review Group (DBJRG) was formed by local residents. Headed by Mike Hulme, whose
property was one of the closest dwellings to the proposed site, the group came together over concerns regarding the potential for
noise pollution from the turbines.[13] A key concern was the potential for sleep disturbance due to a phenomenon known as
amplitude modulation. This form of noise, which has been reported at a small number of windfarm sites, is poorly understood.[14]

DBJRG launched an appeal, under Section 288 of the Town and Country Planning Act 1990, to the High Court, which was heard
in March 2008 by Justice Mitting. A key issue was the refusal of RES to release the background noise data to Mr Hulme, to allow
independent analysis. Although he criticised the approach taken by RES, Justice Mitting refused to overturn the result of the
inquiry, since the planning inspector had not made a legal error in coming to his decision.[15][16] In May, RES released the noise
data, and errors were subsequently discovered by DBJRG,[17] although RES denied that they were significant.[18] DBJRG then
took their case to the Court of Appeal, and permission to appeal was granted in June 2008.[5] To avoid the need for another court
hearing a consent order was agreed between DBJRG and the Secretary of State for Communities and Local Government (the
defendant in the case), which had the effect of overturning the planning inquiry, and returning the matter to the Planning
Inspectorate.[17]

Second public inquiry


The second public inquiry was initially scheduled for March 2009, but was postponed at the request of DBJRG, who had not then
had sufficient time to review new noise data supplied by RES.[19] The inquiry took place between July and October 2009, with
the appeal being opposed by WDBC, DBJRG, and the Campaign to Protect Rural England.[20] The appeal was once again
allowed in December 2009. A number of planning conditions were attached by the inspector[21], aimed at reducing the likelihood
of noise nuisance.[20]

Following the decision, a second judicial appeal was launched by Mike Hulme, which challenged the validity of the planning
conditions and claimed that the wording of the noise conditions rendered them ineffective.[2] The case was heard by Judge
Frances Patterson QC in July 2010. All ten grounds of the challenge were rejected by the judge in her decision.[22] Hulme went
on to lodge an appeal against this decision, which was dismissed by the Court of Appeal in May 2011.[23][24] Subsequently, RES
sought agreement with WDBC on how the planning conditions would be met.[25]

Construction
Construction commenced in 2015.
Windfarm Wars
The BBC commissioned a documentary on the development of Den Brook Wind Farm shortly after the inception of the
project.[26] Including face-to-face interviews with a number individuals concerned with the windfarm, it focused primarily on
Rachel Ruffle, project manager for RES, and Mike Hulme, local resident and member of DBJRG. Initially conceived as a single
film, it developed into a series as the planning process became more and more protracted. The timescale also consumed most of
the programme budget, with producer Jeremy Gibson eventually completing the films as a solo project.[26] The series was first
broadcast in May and June 2011.[3]

References
1. "RES welcomes approval of Den Brook Wind Farm" (https://web.archive.org/web/20111018104416/http://www.de
n-brook.co.uk/media/16981/RES%20WELCOMES%20APPROVAL%20OF%20DEN%20BROOK%20WIND%20F
ARM_111209final.pdf) (PDF). RES. 11 December 2009. Archived from the original (http://www.den-brook.co.uk/
media/16981/RES%20WELCOMES%20APPROVAL%20OF%20DEN%20BROOK%20WIND%20FARM_111209f
inal.pdf) (PDF) on 2011-10-18.
2. "Den Brook wind turbine challenge rejected by High Court" (https://www.bbc.co.uk/news/uk-england-devon-1102
9757). BBC News. 19 August 2010.
3. "Windfarm Wars" (http://www.bbc.co.uk/programmes/b00zzwv6). BBC Television. Retrieved 1 June 2011.
4. "Project Layout and infrastructure" (https://web.archive.org/web/20110615042235/http://www.den-brook.co.uk/ab
out-the-project/project-layout-infrastructure.aspx). Den Brook Wind Farm. RES. Archived from the original (http://
www.den-brook.co.uk/about-the-project/project-layout-infrastructure.aspx) on 15 June 2011. Retrieved 9 June
2011.
5. "The Story so Far..." (https://web.archive.org/web/20110612165357/http://www.denbrookvalley.co.uk/3.html) Den
Brook Judicial Review Group. Archived from the original (http://www.denbrookvalley.co.uk/3.html) on 12 June
2011. Retrieved 9 June 2011.
6. "Balloon shows wind turbine height" (http://news.bbc.co.uk/1/hi/england/devon/4496321.stm). BBC News. 29
April 2005.
7. "Planning Application 8250/2005/OKE" (http://apps.westdevon.gov.uk/planningsearch/default.aspx?shortid=825
0%2f2005%2fOKE). West Devon Borough Council. Retrieved 16 December 2016.
8. "Planning & Licensing Committee: Planning Applications and Enforcement Reports (Northern Area)" (https://web.
archive.org/web/20110928025749/http://www.westdevon.gov.uk/upload/public/attachments/500/oke%20apps%2
83%29.pdf) (PDF). West Devon Borough Council. 31 January 2006. Archived from the original (http://www.westd
evon.gov.uk/upload/public/attachments/500/oke%20apps%283%29.pdf) (PDF) on 28 September 2011.
9. "Windfarm plan refused by council" (http://news.bbc.co.uk/1/hi/england/devon/4666562.stm). BBC News. 31
January 2006.
10. "Den Brook decision: a missed opportunity to take positive action on climate change" (https://web.archive.org/we
b/20111003034835/http://www.res-group.com/media/230761/den%20brook%20decision.pdf) (PDF). RES. 31
January 2006. Archived from the original (http://www.res-group.com/media/230761/den%20brook%20decision.pd
f) (PDF) on 2011-10-03.
11. "RES to appeal Den Brook Wind Farm decision" (https://web.archive.org/web/20111003034844/http://www.res-gr
oup.com/media/230757/den%20brook%20appeal%20announcement%20300506.pdf) (PDF). RES. 30 May 2006.
Archived from the original (http://www.res-group.com/media/230757/den%20brook%20appeal%20announcemen
t%20300506.pdf) (PDF) on 2011-10-03.
12. "Green light for appeal wind farm" (http://news.bbc.co.uk/1/hi/england/devon/6353869.stm). BBC News. 12
February 2007.
13. "Den Brook Judicial Review Group: Who we are" (https://web.archive.org/web/20110612183241/http://www.denb
rookvalley.co.uk/2.html). Den Brook Judicial Review Group. Archived from the original (http://www.denbrookvalle
y.co.uk/2.html) on 12 June 2011. Retrieved 10 June 2011.
14. Bowdler, Dick (June 2008). "Amplitude modulation of wind turbine noise: a review of the evidence" (http://docs.wi
nd-watch.org/bowdler-amofwindturbines.pdf) (PDF). Industrial Wind Action Group.
15. "Fresh Legal Appeal Launched Against Den Brook Wind Farm" (https://web.archive.org/web/20111113075019/htt
p://www.denbrookvalley.co.uk/resources/High+Court+Action.pdf) (PDF). Den Brook Judicial Review Group.
March 2008. Archived from the original (http://www.denbrookvalley.co.uk/resources/High+Court+Action.pdf)
(PDF) on 2011-11-13.
16. "Hulme, R (on the application of) v Secretary of State for Communities & Local Government (2008) EWHC 637
(Admin)" (http://www.bailii.org/ew/cases/EWHC/Admin/2008/637.html). 19 March 2008.
17. "Den Brook Valley Wind Farm Judicial Review Information: Further Information" (https://web.archive.org/web/201
11113072249/http://www.denbrookvalley.co.uk/resources/PressRelease_03082008.pdf) (PDF). Den Brook
Judicial Review Group. 3 August 2008. Archived from the original (http://www.denbrookvalley.co.uk/resources/Pr
essRelease_03082008.pdf) (PDF) on 2011-11-13.
18. "Res reassures residents that Den Brook Wind Farm will not cause a noise nuisance" (https://web.archive.org/we
b/20111018104441/http://www.den-brook.co.uk/media/51577/den%20brook%20wind%20farm%20will%20not%2
0cause%20noise%20nuisance%20july%202008.pdf) (PDF). RES. 9 July 2008. Archived from the original (http://
www.den-brook.co.uk/media/51577/den%20brook%20wind%20farm%20will%20not%20cause%20noise%20nuis
ance%20july%202008.pdf) (PDF) on 2011-10-18.
19. "Den Brook Wind Farm: Second Public Inquiry Postponed" (https://web.archive.org/web/20111113075016/http://
www.denbrookvalley.co.uk/resources/Press+Release+Feb+2009.pdf) (PDF). Den Brook Judicial Review Group.
n.d. Archived from the original (http://www.denbrookvalley.co.uk/resources/Press+Release+Feb+2009.pdf) (PDF)
on 2011-11-13.
20. "Appeal Decision: Appeal Ref: APP/Q1153/A/06/2017162, Land to the south east of North Tawton and the south
west of Bow" (https://web.archive.org/web/20110321181805/http://www.denbrookvalley.co.uk/resources/Denbroo
k+APPEAL+DECISION-1.pdf) (PDF). The Planning inspectorate. 11 December 2009. Archived from the original
(http://www.denbrookvalley.co.uk/resources/Denbrook+APPEAL+DECISION-1.pdf) (PDF) on 2011-03-21.
21. "Den Brook Wind Farm | Acoustic Wind Turbine Testing" (http://hayesmckenzie.co.uk/about/case-studies/den-bro
ok-wind-farm). www.hayesmckenzie.co.uk. Retrieved 2018-04-10.
22. "Hulme, R (on the application of) v Secretary of State for Communities & Local Government (2010) EWHC 2386
(Admin)" (http://www.bailii.org/ew/cases/EWHC/Admin/2010/2386.html). 19 August 2010.
23. "Hulme v Secretary of State for Communities and Local Government & Anor (2011) EWCA Civ 638" (http://www.
bailii.org/ew/cases/EWCA/Civ/2011/638.html). 26 May 2011.
24. "Court of Appeal Judgement" (http://www.denbrookvalley.co.uk/index.html). Den Brook Judicial Review Group. 1
June 2011.
25. "Site Progress" (https://web.archive.org/web/20110613230916/http://www.den-brook.co.uk/about-the-project/site-
progress.aspx). RES. Archived from the original (http://www.den-brook.co.uk/about-the-project/site-progress.asp
x) on 13 June 2011. Retrieved 10 June 2011.
26. Gibson, Jeremy (24 May 2011). "Windfarm Wars: Filming the renewable energy debate in Devon" (http://www.bb
c.co.uk/blogs/tv/2011/05/windfarm-wars.shtml). BBC TV Blog. BBC Television.

External links
Den Brook Wind Farm (http://www.den-brook.co.uk/), RES website
Den Brook Valley Action Group (http://www.denbrook.co.uk/)
Den Brook Judicial Review Group (http://www.denbrookvalley.co.uk/)

Retrieved from "https://en.wikipedia.org/w/index.php?title=Den_Brook_Wind_Farm&oldid=846668729"

This page was last edited on 20 June 2018, at 05:43 (UTC).

Text is available under the Creative Commons Attribution-ShareAlike License; additional terms may apply. By using
this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a registered trademark of the Wikimedia
Foundation, Inc., a non-profit organization.

You might also like