Activity Number of Days Chronological Order Person Responsible Output


Pre-Procurement Day 1 BSPMC, PT, BAC Procurement Forms
1
Conference
Serving and Solicitation of Day 2 PT Acknowledgement
1
Canvass Receipt
Receipt of Canvass forms 1 Day 3 PT
Opening of Canvass Day 3 or 4 PT, BAC, BSPMC Abstract of Canvass
Forms
Evaluation 1 Day 3 or 4 PT, BAC, BSPMC
Filling up of Purchase Day 3 or 4 PT, BAC, BSPMC Purchase Order
Order
Serving of Purchase Order 1 Day 4 or 5 PT
Delivery of Goods Depends on the number of days stated on the Supplier
P.O.
Inspection of Delivered Warehouseman, MIT
Upon delivery
Goods
Processing of Payment Treasurer, BSPMC and
Upon completion of Delivery
Bookkeeper
Local Shopping for Works

Activity Number of Days Chronological Order Person Responsible Output


Pre-Procurement Day 1 BSPMC, PT, BAC Procurement Forms
1
Conference
Serving of Invitation to Day 2 PT Acknowledgement
1
Quote Receipt
Contractors Conference 1 Day 4 PT, BAC TWG, BSPMC Minutes w/ Agreements
Opening of Quotations Day 9 PT, BAC, BAC TWG, Pass Fail Matrix
1
BSPMC
Evaluation of Quotations 1 Day 10 BAC, BAC TWG, BSPMC Abstract of Quotations
Post Qualification 1 Day 11 PT, BAC, BAC TWG Post Qualification Report
Recommends Winning Day 12 BAC, BSPMC Resolution to Award
1
Bidder
If contract is above P Day 13 RPMO Request for NOL
500,000.00 Request for 1
NOL
Issuance of NOL 1 Day 14 RPMO No Objection Letter
Issuance of notice to Day 15 BSPMC Notice to Award
1
Award
Posting of Performance Day 16 Contractor Performance Security
1
Security
Issuance of Notice to Day 17 BSPMC, Contractor Notice to Proceed
1
Proceed/ Start of Work
Payment Every Substantial Accomplishment of 20% or Treasurer, Bookkeeper,
More BSPMC
Direct Contracting for Goods

Activity Number of Days Chronological Order Person Responsible Output


Procurement Forms,
Certification that there is
only 1 local supplier and
Pre-Procurement it is cheaper to purchase
1 Day 1 BSPMC, PT, BAC
Conference from lone supplier than
look for other suppliers
outside the
barangay/municipality
Serving and Solicitation of Day 2 Acknowledgement
1 PT
Canvass to single supplier Receipt
Receipt of Canvass forms 1 Day 3 PT
Opening of Canvass
Day 3 or 4 PT, BAC, BSPMC
Forms
Evaluation 1 Day 3 or 4 PT, BAC, BSPMC Abstract of Canvass
Filling up of Purchase
Day 3 or 4 PT, BAC, BSPMC Purchase Order
Order
Serving of Purchase Order 1 Day 4 or 5 PT
Depends on the number of days stated on the
Delivery of Goods Supplier
P.O.
Inspection of Delivered
Upon delivery Warehouseman, MIT
Goods
Processing of Payment Treasurer, BSPMC and
Upon completion of Delivery
Bookkeeper
Direct Contracting for Works

Activity Number of Days Chronological Order Person Responsible Output


Pre-Procurement Day 1 BSPMC, PT, BAC Procurement Forms
Conference Certification that there is
only 1 local supplier and
it is cheaper to purchase
1 from lone supplier than
look for other suppliers
outside the barangay
/municipality.

Serving of Invitation to Day 2 PT Acknowledgement


1
Quote to lone supplier Receipt
Opening of Quotations Day 4 PT, BAC, BAC TWG,
1
BSPMC
Evaluation of Quotations Day 5 BAC, BAC TWG, BSPMC Pass Fail Matrix, Abstract
1
of Quotations
Post Qualification 1 Day 6 PT, BAC, BAC TWG Post Qualification Report
Recommends Winning Day 7 BAC, BSPMC Resolution to Award
1
Bidder
Request for NOL 1 Day 8 RPMO Request for NOL
Issuance of NOL 1 Day 9 RPMO No Objection Letter
Issuance of notice to Day 10 BSPMC Notice to Award
1
Award
Posting of Performance Day 11 Contractor Performance Security
1
Security
Signing of Contract Day 12 Contractor, BSPMC Notarized Contract
1
Issuance of Notice to Day 13 BSPMC, Contractor Notice to Proceed
1
Proceed/ Start of Work
Payment Every Substantial Accomplishment of 20% or Treasurer, Bookkeeper,
More BSPMC
Local Bidding for Goods
Activity Number of Days Chronological Order Person Responsible Output
Pre-Procurement Procurement Forms
1 Day 1 BSPMC, PT, BAC
Conference
Serving and Issuance of Day 2-16 Acknowledgement
1 PT
Bid Documents Receipt
Posting of Invitation to Acknowledgement
1 Day 2-16
Bid Receipt
Pre-Bid Conference 1 Day 13 PT, BAC, BAC TWG Minutes w/ Agreements
Site Visit 1 Day 13 BSPMC, Supplier Site Visit Certificate
Receipt of Bids 1 Up to Day 19 PT
Opening of Bids 1 Day 20 PT, BAC, BSPMC Pass Fail Matrix
Evaluation 1 Day 21 PT, BAC, BSPMC Abstract of Bids
Filling up of Purchase Draft Purchase Order
1 Day 22 PT, BAC, BSPMC
Order
Request for NOL 1 Day 23 BSPMC
Review and Issuance of No Objection Letter
NOL ( for PO P 500,000.00 1 Day 24 RPMT
to P 1,000,000.00)
Review and Issuance of No Objection Letter
NOL ( for PO P
5 Day 29 NPMT
1,000,000.00 to P
2,500,000.00)
Review and Issuance of No Objection Letter
NOL ( for PO P 10 Day 34 WB
2,500,000.00 and above )
Serving of Purchase Order Upon Issuance of Purchase Order
1 PT
NOL
Delivery of Goods Depends on the number of days stated on the
Supplier
P.O.
Inspection of Delivered
Upon delivery Warehouseman, MIT
Goods
Processing of Payment Treasurer, BSPMC and
Upon completion of Delivery
Bookkeeper
Local Bidding for Works

Activity Number of Days Chronological Order Person Responsible Output


Pre-Procurement Procurement Forms
1 Day 1 BSPMC, PT, BAC
Conference
Serving and Issuance of Bid Day 2-16 Acknowledgement Receipt
1 PT
Documents
Posting and Publication of Acknowledgement Receipt
1 Day 2-16 PT
Invitation to Bid
Pre-Bid Conference 1 Day 9 PT, BAC, BAC TWG Minutes w/ Agreements
Site Visit 1 Day 9 BSPMC, Contractor Site Visit Certificate
Receipt of Bids 1 Up to Day 19 PT
Opening of Bids 1 Day 20 PT, BAC, BSPMC Pass/ Fail Criteria
Evaluation 1 Day 21 PT, BAC, BSPMC Abstract of Bids
Post Qualification 1 Day 22 PT, BAC TWG Post Qualification Report
Recommendation of Resolution to Award
1 Day 23 BAC, BSPMC
Winning Bidder
Drafting of Contract 1 Day 24 PT, BAC, BSPMC Draft Contract
Request for NOL Request for No Objection
1 Day 25 BSPMC
Letter
Review and Issuance of NOL No Objection Letter
( for Contract P
5 Day 30 NPMT
1,250,000.00 to P
2,500,000.00)
Review and Issuance of NOL No Objection Letter
( for Contract P 10 Day 35 WB
2,500,000.00 and above )
Serving of Notice of Award 1 Upon Issuance of NOL PT Notice of Award
Posting of Performance Upon Receipt of Notice Performance Security
1 Contractor
Security to Award
Signing of Contract Upon Posting of Notarized Contract
1 BSPMC, Contractor
Performance Security
Issuance of Notice to Upon Signing of Notice to Proceed
1 BSPMC
Proceed Contract
Start of Works Must be completed according to the approved work
Contractor
schedule
Payment Every Substantial Physical Accomplishment of 20%
or More