Professional Documents
Culture Documents
fs = 0.58 x Fy x Ast
Ast
= 0.58 x 500 x 696.4
942.5
fs = 214.3 N/mm2
Pt prov = 0.63 %
Read MF = 1.8
Required d = 3500 = 97.2 mm < dprov SAFE
1.8 x 20
DATA -
Size of Hall/Floor = 9 x 12 m
d = 1500
30
= 50 mm
D = 50 + 25 = 90 mm
Fck = 20 N/mm2
Fy = 415 N/mm2
Clear cover = 25 mm
Density of conc. = 25 kN/m3
Load Calculations
αx = 0.062
αy = 0.062
Mux = αx x q x lx^2
= 0.062 x 13.125 x 2.25
= 1.83094 kN-m
Muy = αy x q x lx^2
= 0.062 x 13.125 x 2.25
= 1.83094 kN-m
Check for depth selected
1.Bending consideration
Mulim. = 0.138 x fck x bd^2
= 6.9 kN-m > Mux
= 1 x 13.125 x 0.75
2
= 4.92188 kN
Vu
Ʈv = bxd
Reinforcement :
A) In Short direction
Mux = 1.83094 kN-m
S = 473.782 mm
S = 300 mm
Provide T8 @ 300 mm c/c in Short direction
B) In Long direction
Muy = 1.83094 kN-m
S = 473.782 mm
S = 300 mm
Provide T8 @ 300 mm c/c in Long direction
Design of Ribs
D = 360 to 450
= 450 mm
Therefore,
deff. = 360 mm
= 48 Nos.
= 243.00 kN/m2
self wt per unit area
= 2.25 kN/m2
Live load = 5 kN/m^2
Floor finish = 1 kN/m^2
= 8.25 kN/m^2
Ly = 1.33
Lx
= ( r^4/(1+r^4))*Q
q1 = 9.401 kN/m2
Load per unit length in Longer direction,
= ( 1/(1+r^2))*Q
q2 = 4.455 kN/m2
width of flange B = lo + bw + 6 x Df
6
where, lo = 0.7 l = 1050 bw
bw = 100 mm Df
Df = 90 mm
B= 815 mm
Overall depth of Rib
= 170160264 N-mm
= 170.16 kN-m >
Vu
Ʈv = bxd
p = 2.15609
Ʈc = 0.79 N/mm2
Sv = 300 mm
Provide 2 Legged 8 mm dia. Stirrups @ 300 mm c/c throughout for all beams.
SUMMARY -
Provide T8 @ 300 mm
c/c in Short direction
Provide T8 @ 300 mm
c/c in Long direction
Slab Thk. Df = 90 mm .
RIB Beams
Provide bottom T 16 mm 4 Nos. bars in shorter direction
Provide bottom T 16 mm 4 Nos. bars in longer direction
Provide top R/f T 12 mm 2 Nos. Hanger bar / Anchor bar
Provide 2 Legged 8 mm dia. Stirrups @ 300 mm c/c throughout for all beams.
Overall Depth of beam D= 450 mm
Width of RIB Beam B= 150 mm
Slab Reinforcement
Df
Bottom Reinforcement
B
BBS Grid Slab Length of Bar
Cutting
Bar No. Direction Bar Shape "a" "b" "c" "d" "e" Dia. Of bar Spacing No. TOR 8 TOR 10 TOR 12 TOR 16 TOR 20 TOR 25 TOR 32
length
a
1 Slab X dir. b 9000.00 128.00 0.000 0.000 0.000 8 300 9128.00 40 365.12 - - - - - -
2 Slab Y dir. a 12000.00 128.00 0.000 0.000 0.000 8 300 12128.00 30 363.84 - - - - - -
b
Beam X a
3 9000.00 720.00 0.000 0.000 0.000 12 50 9720.00 16 - - 155.52 - - - -
dir. Top b
Beam X
4 a 12000.00 720.00 0.00 0.00 0.00 16 50 12720.00 24 - - - 305.28 - - -
dir. Bott. b
a
Shear c
5 Links X 100.00 380.00 192.00 0.00 0.00 8 300 1152.00 252 290.304 - - - - - -
dir. b
Beam Y a
6 b 9000.00 720.00 0.00 0.00 0.00 12 50 9720.00 16 - - 155.52 - - - -
dir. Top
Beam Y a
7 12000.00 720.00 0.00 0.00 0.00 16 50 12720.00 32 - - - 407.04 - - -
dir. Bott. b
a
Shear
8 Links Y c 100.00 380.00 192.00 0.00 0.00 8 300 1152.00 243 279.936 - - - - - -
dir. b
Total Steel Required for 2 Pile Group Footing TOR 8 TOR 10 TOR 12 TOR 16 TOR 20 Unit weight kg/m 0.395 0.617 0.889 1.580 2.469 3.858 6.321
= 513.264 0.000 276.480 1125.641 0.000 Weight in Kg. 513.264 0.000 276.480 1125.641 0.000 0.000 0.000