You are on page 1of 7

Figure 1

shallower berthage at the West Quay, ground swell, has been an important
1.0 INTRODUCTION
which could handle vessels up to 6,000 harbour for many years.
DWT at suitable tides. The earliest harbour works of
1.1 Foynes Port
importance were begun in 1846 with the
1.2 New Deepwater Facility construction of a masonry wharf 83
Foynes Port has traditionally been a
metres long and 12 metres wide in the
commercial port to all sea-going vessels
Foynes Harbour Trustees, location now known as the West Quay.
wishing to service the west coast of
recognising the need to progress the The cost of these works was
Ireland. Over the past twenty-five years
development of the port, made essentially funded by Lord Monteagle
the port has grown such that in the early
application in 1993 under the National whose family has long been associated
nineties, Foynes Harbour Trustees
Development Plan to the Department of with Foynes.
recognised the need to develop a modern
the Marine and Natural Resources to The Foynes Harbour Trustees were
deepwater facility capable of handling
carry out works to extend the handling formed in 1890 and they immediately
vessels up to Panamax size.
capability of the port by construction of constructed a short timber jetty on
Over that time the port was used
new jetty facility, dredging, and provision greenheart piles running from the end of
both for export of goods such as frozen
of port related infrastructure. These the masonry pier. This timber structure
meat, bagged sugar, milk powder, and
proposals were subsequently was later removed in 1934 to make way
ore materials – barytes, lead and zinc
incorporated in the commercial seaports for the new West Jetty.
concentrate – and for import of bulk
measure of the EU Operational A spur from the foreshore at the
goods such as coal, animal feed,
Programme for Transport 1994-1999. eastern end was constructed in 1915. It
fertilisers, general cargo, molasses and
The steady growth in port traffic was 46 metres long and 5.5 metres wide
oil products.
from typical 660,000 tonnes handled in and consisted of cast in-situ concrete
The berthage available consisted
1983 to 1,275,000 tonnes handled in beam and slab placed over precast piles
primarily of the East and West Jetties.
1993 indicated the need for the and precast concrete walls. This
The existing West Jetty, 106 metres long,
development. A pre-feasibility study was structure remains in place today in good
handled vessels up to 22,000 DWT, but
commissioned in 1995 by Foynes working order.
was limited in its load carrying capacity,
Harbour Trustees to determine the The West Jetty structure was
as it was maintained dredged to a level of
optimisation of the proposed constructed in 1936 to service vessels up
–10.15m OD (Poolbeg). The East Jetty,
development. This study formed the to 8,000 tonnes displacement and 7.6
296 metres long, was capable of handling
basis of the new work incorporating the metres draught. This was a concrete
vessels up to 35,000 DWT, which was
deepwater facility. structure founded on precast concrete
maintained dredged to a level of –11.3m
piles driven to firm stratum in groups, with
OD, i.e. below Mean Low Water Springs.
1.3 History cylindrical heads filled with in-situ
The bulk liquids berth consists of
concrete at the top of the pile extending
two dolphins linked to the shore, and was
Foynes Harbour, having a good through a splayed concrete pile cap to in-
constructed in 1992. This available
sheltered location from heavy seas and situ flat slab concrete deck.
berthage also included 140 metres of

1
This structure was upgraded as part of square metre was initially considered. • Complete the works with a separate
the new works. However, port experience on the East dredging contract.
Further berthing facilities were Jetty with the flexibility for crane loading
provided in 1968 when the first element given by a higher design capacity of 75 2.3 Navigation Studies
of the existing East Jetty, 144 metres kN per square metre meant that this
long, together with concrete access eventually prevailed. Following receipt of tender submissions
viaduct was provided, followed by an from a number of hydraulic specialists,
extension of 155 metres in 1984 to (ii) The berth occupancy studies in 1996, H R Wallingford Limited were
complete this jetty. The dolphin system showed that the East Jetty was the most commissioned by Foynes Harbour
to enable import of oil and chemicals was heavily used facility and that, if trade Trustees to carry out Navigation Studies
completed in 1992. forecasts were correct, additional of the port approaches and within the
Under the Harbours Act 1996, berthage in addition to the proposed inner port area so as to fine tune the
Foynes Harbour Trustees was replaced extension of the West jetty would be proposals for the new West Jetty and the
by Foynes Port Company in March 1997. required within the time frame 2001 to associated capital dredging works. As
The extent of the jurisdiction of the port 2005. These predictions of pressure for well as setting up a port model, a number
was determined and this enabled an additional berthage are already being of real-time simulations were carried out
overview to be taken on the capital works confirmed in practice. at H R Wallingfords premises in UK
programme relating to future marine using the H R Mardyn simulator. Foynes
infrastructure. (iii) The navigation study concluded Harbour Trustees pilots participated in
that the size of the navigation channel simulation exercises to ensure that they
2.0 DESIGN APPROACH and turning circle were below PIANC were satisfied with the results.
recommended standards. In particular, The results of these studies were
2.1 Pre-Feasibility Study the constraint at Barneen Point would used to:
require attention by dredging and land
The pre-feasibility study removal. The study also concluded that (a) Assess the projected rates of
commissioned by Foynes Harbour navigation aids should be improved in the siltation arising within the Harbour.
Trustees in 1995 was carried out by H R port and in the East Channel so that
Wallingford Limited. It addressed four vessels leaving the port could use them. (b) Determine the optimum dimensions
main aspects: for vessel manoeuvrability in
(iv) Siltation in the port was shown respect of both daylight and night
• Alternative jetty layouts, forms of predominantly to be caused by the ebb time navigation.
construction and costs tide through the harbour and it was
• Analysis of trade and berth concluded that the new berth at the West (c) Establish the new approach
occupancy to assess future demand Jetty would have some increase on the channel to the port and thereby
for berthage maintenance dredging commitment. determine the extent of dredging
• Desk studies on navigation and Flow and siltation modelling studies were necessary to achieve these defined
requirements for navigation channels recommended for the port and its areas.
and turning areas approaches.
• Examination of siltation risks based (d) Confirm the appropriateness of
on desk studies and field 2.2 Project Planning navigational aids, particularly at
measurements night.
Based on the pre-feasibility study,
(i) It was confirmed that the Michael Punch & Partners initiated a Conscious of the need to set up the port
proposed layout suggested by the port preliminary design review of the proposal model correctly and to determine the
was feasible from an engineering point of for the new development in consultation optimum manoeuvres, significant time
view. Ideally filling should be right up to with Foynes Harbour Trustee was allowed to carry out the fieldwork
the back of the quay to maximise access Management in 1995. Studies of the and subsequent analysis prior to issue of
but ground conditions subsequently scope of the works required to bring the report. The results obtained were then
precluded full implementation of this. project to completion were undertaken used to determine the extent of the
Alternative structural forms were and decision made as to the sequence Capital Dredging Works to conclusion.
examined. and the extent of the works.
Sheet pile quays were impractical Decisions were taken as follows: 2.4 Jetty Design Concept
because of the presence of unsuitable
ground (soft silts overlying boulder clay • Set up a flow model of the port and An integrated Design Team
and rock). carry out siltation monitoring prior to approach was adopted from an early
Serious consideration was given to completing navigation to determine stage of the project design. Together
gravity structures – block-work walls and the best option for new approach to with Michael Punch & Partners as Team
caissons – but it was concluded that the the upgraded berths. Leaders, H R Wallingford Limited
unevenness of the underlying strata, plus specialist marine consultants advised on
the need to remove soft silty material to • Carry out the jetty construction the fundamental design elements, and
provide adequate foundations made them works as a single contract including Healy Kelly & Partners Chartered
impractical. Sites for construction and any ancillary works such as Quantity Surveyors were retained as
launching caissons were also not installation of new navigation lights, quantity surveyors.
available conveniently. landing stages for small craft using Conceptual design on the new jetty
An open piled deck was therefore the port, and provision of support commenced in 1995. Initially a view had
selected supported on tubular steel piles. buildings. to be taken on the existing West Jetty
A standard design loading of 25 kN per and in particular its further design life.

2
A desktop study of old drawings and site The jetty is designed to take a • The maximum size of vessel which
data in the possession of Foynes 35,000 DWT bulk carrier vessel fully can be handled following the
Harbour Trustees was carried out. laden or a partly laden vessel of 45,000 completion of the development is:
Preliminary calculations were made on DWT. The jetty length of 270 metres is
the adequacy of the structure and a view such that it can accommodate both a Length 204 m
taken on its load carrying capacity. In 35,000 DWT vessel and a 22,000 DWT Beam 29 m
this instance the Paper on the “New vessel simultaneously. Working draught 10.5 m
Deep-Water Jetty at Foynes, Co
Limerick” by H A Delap and T A 2.5 Dredging The live load capacity of the new
Simington published in 1938 by the jetty is 75 kN per sq metre. This provides
Institution of Engineers of Ireland was The design approach to the scope of for operation of large mobile cranes at
most helpful. the dredging works was determined by any position on the new jetty.
the requirements of Foynes Port
The clients brief called for extension Company to provide deepwater berthing
of the existing West Jetty eastwards for a for larger vessels at all stages of the tide. 3.0 PRELIMINARY DESIGN
distance of 164 metres and an upgrading In particular, the design dredge levels to
of the existing jetty. With respect to the – 12.0 m OD in the berths and to – 8.1 m 3.1 Overall Design Considerations
existing structure, it was considered that OD elsewhere in the inner port area were
a load test on single pile unit be carried requested at an early stage. The new West Jetty structure is
out to verify load carrying capacity. After Studies were carried out on the designed as two independent structures.
some investigation, it was agreed that approaches to the berths and on turning One structure forms the extension to the
such check would be too onerous and circles within the inner port area, and the east while the other occupies the area of
would require significant opening up and limit of the dredge was determined. This the old West Jetty. This is primarily due
destruction of existing structure. dredge limit was then verified or modified to the difference in site conditions
A design decision was taken to as appropriate when the real time between the two elements, as work over
ignore the structural support provided by simulation studies were carried out. water and work from a solid platform
the existing West Jetty in any new require different design approaches.
scheme. It was therefore decided to pile Another important reason for the
through the existing deck and to cast a 2.6 Operational Issues incorporation of independent structures
new in-situ flat slab supported as a with separate construction phases, is the
temporary works measure off the existing Arising from the signing off of the design client’s requirement to have use of as
deck but designed to span onto the new criteria, the following operational issues much of the available quayside facilities
piles. were determined: as possible during construction. The
works were therefore set out on a phased
It was also decided to include • The port is capable of handling basis to enable partial hand-over to take
ancillary works such as provision of two vessels up to Panamax size partly place midway through the contract.
new landing stages for small craft on the laden subject to dimensional checks The phase 3 element of the new
mainland in lieu of the existing landing on vessel. West Jetty is a marginal quay structure
stage being made obsolete by the new and occupies the western 106 metres of
construction. This work also included • The limit of size of vessel is so the new jetty, while the remaining 164
provision of new landing stage at Foynes determined by the ability to swing the metres is offshore and accessed from the
Island. vessel within the inner port area. west by the marginal quay and from the
east by a new concrete viaduct.

Figure 2

3
The phase 2 jetty extension is given and 850 mm high and span from pile to The scope of the EIS included
lateral support at the west end by a pile. Insitu pile caps connect the beams detailed examination of the
group of raking piles. The extension is and transfer the loads to the pile. The environmental effects arising during the
given lateral support at the east end from full slab depth of 550mm over the beams construction period. Sediment analysis
raking piles on the land-ward end of the is incorporated in the composite design that had heretofore been carried out for
concrete viaduct. The jetty deck spans of the beams. The piles are 1067mm previous dredging works, were reviewed
horizontally between these two strong outside diameter, with a wall thickness of and used as a baseline for input into EIS.
points to resist any applied horizontal 25mm. Observations were made by third parties
lateral loads. The phase 3 jetty The access viaduct to the eastern during the planning period.
upgrading is given lateral support along end of the extension, and the old west Planning permission for the works
the central 70 percent of its length also basin infill slab are also of composite was issued in January 1997 with 7 no.
by raking piles. Applied horizontal concrete construction. conditions attaching.
longitudinal loads are resisted through
portal action of all 102 no. piles in phase 4.0 PROJECT PLANNING 4.2 Foreshore Lease
2 and 69 no. piles in phase 3.
4.1 Planning Permission and EIS Prior to the submission of
3.2 Load Conditions application for Foreshore Lease for the
Planning permission was sought Jetty Works, detailed discussions were
As discussed in item 2.1 above, from Limerick County Council in mid held with the Department of the Marine
the design loading for the deck was 1996 for the development works and Natural Resources. The lease was
established as a characteristic imposed proposed. The application was duly issued in December 1997 prior to
blanket loading of 75 kN per Sq metre. accompanied by an EIS. the main works proceeding.
This loading relates to the deck area
nearest the berth for a distance of
approximately 18 metres from the berth.
The open tidal basin at the rear of
the existing West Jetty was designed to
be filled with a structural deck, which has
a characteristic imposed load capacity of
35 kN per Sq metre. The access viaduct
at the eastern end of the new extension
also has a characteristic imposed load
capacity of 35 kN per Sq metre. The
horizontal characteristic berthing load on
the structure is 2000 kN when transferred
through the fender system, and
characteristic bollard loads are 1000 kN.

3.3 Preliminary Design – Layout and


Sizes

The structure is designed to maximise


the use of precast concrete elements to
provide a permanent shutter and working
platform for insitu works while minimising
the amount of temporary works over
water.
The structure of the extension at the
West Jetty is designed as a composite
concrete three-span deck spanning
continuously between support beams
running longitudinally along the length of
the extension. The beams are at
6.39 metre centres. The concrete deck
is 550mm thick consisting of 200mm
solid precast pre-stressed concrete slabs
topped with 350mm of insitu reinforced
concrete. The entire deck is at a
gradient of 1:100 for drainage.
The support beams are also
designed as a composition of precast
and insitu concrete and span between
piles driven at 7.62 metre centres along
the line of the beams. This dimensional
grid was determined by the spacing of
existing piles at the old West Jetty. Figure 3
The precast beams are 1500mm wide

4
Figure 4

4.3 Site Investigation 4.4 Tendering for Jetty to the contractual programme and
substantially completed the contract with
Simultaneous with the detail design The tendering process was to this 7 week over-run. Some extra works
work, a site investigation contract was comply fully with Council Regulations were incorporated in the contract at the
put in place over the period June to (EEC) 2082 / 93 and 2083 / 93. It was conclusion of the works, which extended
September 1996. decided that the method of procurement the contractors duration on site. The
The investigation consisted of shell- of the project was to invite applications contractor demobilised from site for the
and-auger and rotary core test holes from contractors for inclusion in a main works in September 1999.
using NQ (Samples of 57mm diameter) tendering short list. A contractor pre-
and HQ (Samples of 64mm diameter) qualification notice was published in the 5 DETAIL DESIGN &
rigs from floating pontoons, and a PQ rig OJEC in May 1997. CONSTRUCTION
(giving 87mm samples) working from the A total of twelve applications were
existing jetty deck. Core samples were received from which seven contractors 5.1 Jetty Pile Design
difficult to obtain, as recovery was poor were selected and issued with full tender
nd
arising from poor quality rock. documents on 2 July 1997. Tenders The agreed design approach for the
It was confirmed at an early stage were received from each of the founding of the tubular piles was to
st
that the site covers a geological fault contractors on 1 September 1997. After provide open ended tubular piles driven
zone, so extra trial borings were made to reporting to Foynes Port Company to the firm fluvio-glacial till (boulder clay)
determine the extent of the anomaly. following the opening of tenders, a or sedimentary mudstone rock. Such
This fault was in the form of a buried reduced scope of works was determined piles perform and are designed to reach
valley in the area midway along the and a decision was taken in December their working capacity by forming a plug
phase 2 jetty extension. A sand deposit 1997 to award the jetty works contract to within the shell core when driven through
was found at depth in this valley. The Ascon Limited. boulder clays. The appropriate schedule
general pattern of the stratum recorded of pile lengths was drawn up on the
was silt, overlaying clays with boulders 4.5 Jetty Contract basis of penetration into the boulder clay
on to a very poor mudstone rock. (6 x pile diameter) in accordance with the
The investigation also revealed that The contract commenced on 2nd API code.
the piles to the existing West Jetty were February 1998. Whilst the contract
founded on boulder clay at the east end, duration called up in the tender 5.2 Pre-Compression Load
and not on rock as thought at the time of documents specified a contract duration Testing of Piles
driving these piles. of 82 weeks, the contractor’s programme
The interpretative report and corings stated a 52 week completion. The A number of pre-compression pile
taken were reviewed in detail by the construction programme over-ran by 7 load tests were carried out prior to driving
design team prior to issue of tender weeks from a time very early in the the permanent phase 2 and phase 3
documents. Also the tendering contract, due to difficulties encountered in tubular piles. The design load
contractors were invited to examine the piling in April and May 1998. The requirement for the new
samples on site. contractor, however, continued working

5
construction is 75 kN per Sq metre which design length which necessitated an
generates a working pile load of 550 extension and re-driving of the pile to
tonnes. It was found during the tests that obtain the required design pile set.
the boulder clay could not sustain this
load and the full test load was not 5.3 Pile Types
attained. Further investigation of the
boulder clay revealed the presence of the The tubular piles for the support of
geological fault such that the deposits the jetty deck are 1067mm outside
were of a much coarser nature than diameter 25mm thick. There is a
originally determined during the initial site corrosion allowance on the wall
investigation. thickness - without cathodic protection or
After review of the information from protective coatings - for a design period
the test piles and the further of 50 years. This corrosion allowance is
investigation, a decision was taken to based on British Steel recommended
provide concrete plugs in the toe of the corrosion allowances for a marine
pile so as to enhance the load carrying environment. The grades of steel used
capacity of each pile. The piling was are API grade X60 / X65, which satisfy
then carried out in a satisfactory manner the requirements of BS10025 grade
and no undue difficulties were found in S355 GP (Grade 50).
obtaining the necessary pile set. The At the toe of many of these piles a Figure 6
weak sedimentary nature of the closed-ended shoe was fitted. A method
mudstone bedrock (UCS below 5000 kN of transferring the large driving forces 5.4 Piling
per Sq metre) meant that the piles were, from the shoe to the steel wall of the pile
in some cases, driven beyond their in a suitable manner needed to be The large tubular piles were driven
devised. The method used was to insert by Delmag D55 and Delmag D62 diesel
a plug of concrete within the bottom piling hammers. These were operated on
2500mm of the pile prior to pitching. a flying leader from a 150 tonne tracked
In order to transfer the loads from mobile crane located on the shore or
the concrete plug to the wall of the pile, from a large floating barge, the ‘Marlin’,
mild steel shear connectors in the form of equipped with fixed leader. This barge is
50mm square bars were welded to the 60 metres in length and 23 metres in
inside wall of the pile prior to installation width and was also used to position the
of permanent shutters. The cavity was first precast concrete beams. The
then filled with the concrete mix ‘Ascon 5’ barge was also used in the
incorporating admixture to reduce latter stages of the project.
shrinkage of the concrete. This helped to Based on the test driving monitored
give an intimate bond between the face during the pile tests, the tubular piles
of the concrete and the wall of the pile, were driven to a set of 35 blows for
improving the shear capacity of the shoe 50mm. This set was generally achieved
within the pile. in a single set-up. However, some piles
Non Destructive Testing of pile had to be re-driven after a period, in
material was carried out using order to verify the set.
radiographic and ultrasonic methods
before sign-off of pile fabrication welds 5.5 Pile Caps
carried out both on-site and in the
fabrication works in Middlesbrough. At each pile head, a method of
transferring the large forces from the
Precast concrete piles 350mm concrete to the steel wall of the pile in a
square in section were driven at a rake suitable manner needed to be devised.
of 1:3 at the bank-seat on phase 3 of the The method used was to create a plug of
work to support the bank-seat and concrete within the pile for the top
stabilise the phase 3 deck under lateral 1250mm. A permanent shutter was
loads. No tension is developed in these slung from the rim of the pile.
piles under lateral loading due to the In order to transfer the loads from
weight of the deck overhead. the concrete plug to the wall of the pile,
mild steel shear connectors in the form of
356 x 406 634 kg/m steel H piles 25mm square bars were welded to the
were driven for the fenders in the main inside wall of the pile above the
berths and in the return berths on the permanent shutter. This gave the edges
western side of the jetty. These piles of the concrete plug sufficient bearing
were designed as cantilevers from the area to transmit the loads safely and
underlying stratum. Independent uniformly to the wall of the pile and down
specialist verification of the agreed pile to the bearing stratum. This element of
size was provided by the contractor for the pile cap was usually cast only when
the fender piles. the upper element between the precast
beams was also ready for casting.
Figure 5

6
Further beams were installed parallel
to the span of the deck slabs at 22.86
metre centres for the purpose of
stiffening the deck as a whole when the
deck slab is under lateral loading and
spanning horizontally as a deep beam
between the strong points at either end.

5.7 Insitu Beams

Some beams located on the grid-


line nearest the berth could not be
constructed in precast concrete due to
their larger size. This size is due to the
presence of large fenders at 22.86 metre
centres along the berth, offset ship-ward
of the cope-line by approximately
Figure 7 1300mm. The soffit level of these
beams is 1100mm below that of the
In some cases, where the pile heads and give the beam a good bond with the precast beams on either side. As a
were out of position, increasing the pile insitu concrete, which would later be cast result these beams were constructed in
cap dimensions to encompass the pile over it. insitu concrete. This work necessitated
head accommodated the piles. The steel beams extending from the a substantial amount of temporary
ends of the concrete beams were works, much of which was below high
5.6 Precast Beams – Phase 2 required to carry only the weight of the water, and thus accessible only for
beams alone in the temporary condition. several hours each day.
The deck spans between reinforced Before the precast deck slabs could be
concrete beams. The beams were placed on the beams, the upper portion 5.8 Deck Slabs – Phase 2
precast on site in a precast yard set up of the pile cap was poured between the
by the contractor within 200 metres of ends of two opposing beams over a With the beams cast in position over
their final position. The beam single pile. The reinforcement projecting the piles, the precast deck slabs were
dimensions were 1500mm wide and from each beam would lap with the lowered into position on the beams. The
850mm deep, so chosen to facilitate corresponding reinforcement from the precast deck slabs were fabricated off-
tolerances in the pile locations after other and, when cast, the pile cap would site by Banagher Concrete at their works
driving. form a continuous beam running the in Co. Offaly. The grade of concrete
The grade of concrete used was length of the jetty extension. used was 60N20 with minimum cover to
42.5N20 with minimum cover to Vertical reinforcement projected from reinforcement of 50mm.
reinforcement of 65mm. This design the top of the beams to tie into The precast slabs were solid slabs
complies with Table 3.4 of IS 326, Part 1. corresponding reinforcement that would 5250mm in length, were 200mm in
The two critical design criteria were later be placed within the insitu slab. In thickness and were pre-stressed using 12
ultimate limit strength and crack widths. this way the down-stand beam acted no. cables of 12.9mm diameter
The maximum crack width under full compositely with the slab and utilised the superstrand giving a total pre-stressing
imposed loading is 0.29mm. full depth of the beam/slab combination force of 1674kN per slab. Reinforcement
The beams were cast to fit between to minimise the effect of bending moment extended from the top of the slabs in the
the pile heads and had two steel beams on crack widths and ultimate limit state form of T10 open links. These links were
extending from each end to allow the design. used to tie to the reinforcement at the top
beam to be rested on the top of the pile
when cut-off to the required level. The
concrete beams had the ends and top
surface treated to expose the aggregate

Figure 8 Figure 9

You might also like