Professional Documents
Culture Documents
April 2014
Richard Chamberlain
Timetable
Time Topic
5 mins Timetable
8 mins FIDIC Range of Contracts
3 mins Contractual Roles
8 mins The Contractor and Clause 8
4 mins The Contractor and Sub Clause 20.1
2 mins Clause 8 and relevant Sub Clauses
5 mins The Engineer
10 mins Engineer’s calculation and determination
5 mins Employer’s Claims & Delay Damages
Demonstration and illustration of unliquidated and liquidated
10 mins
damages
5 mins Conclusion
Questions & Answers
2
FIDIC Range of Contracts
Recommended for
building or engineering
works of a relatively small
capital value, for relatively
simple work, or work of a
short duration.
4
RED BOOK
Conditions of Contract
for Construction
for Building and Engineering
Works Designed by the
Employer
5
PINK BOOK
Construction
Contract MDB
Harmonised Ed
(Version 3: June
2010)
6
YELLOW BOOK
7
SILVER BOOK
Conditions of Contract
for EPC/Turnkey
Projects
8
GOLD BOOK
9
WHITE BOOK
Client/Consultant Model
Services Agreement
(4th Ed 2006)
10
10
Contractual Roles
• Provide possession of
the Site
• Provide information
• Consultancy Agreement
• permits and consents
• Responsible for Design
• Appoint the Engineer
• Supervision of
Contractor • Payment
Engineer Employer
Obligations Obligations
Engineer
Contractor
Administers
Obligations
• Instructions Contract
• Variations • Complete design
• Certifier of extensions • Progress the works in a
to Time for Completion regular and diligent
• Certifier of Payments manner
• Determinations • Safe manner of work
• Workmanship
13
The Contractor & Clause 8
15
15
Clause 8
16
16
Sub Clause 8.3 Programme
■ Summary:
■ The Contractor shall submit a programme to the
Engineer as required in the Contract.
■ The Employer's Personnel shall be entitled to rely upon
the programme when planning their activities.
■ The Contractor shall promptly give notice to the
Engineer of specific probable future events or
circumstances which may delay the execution of the
Works.
■ If the Engineer gives notice to the Contractor that a
programme fails the Contractor shall submit a revised
programme to the Engineer in accordance with this Sub-
Clause.
17
17
Clause 8.4: Extension of Time for Completion
■ Summary
■ The Contractor shall be entitled to an extension to Time for
Completion, if delayed by any of the following causes:
■ (a) a Variation
■ (b) a cause of delay under a Sub-Clause of these Conditions
■ (c) exceptionally adverse climatic conditions
■ (d) any Unforeseeable delay, impediment or prevention caused
by Employer
■ ….”the Contractor shall give notice to the Engineer in
accordance with Sub-Clause 20.1 [Contractor's Claims]”
■ ….”the Engineer shall review previous determinations and may
increase, with the Employer's written approval, but shall not
decrease, the total extension of time”
18
18
The Contractor and Sub Clause 20.1
20
Avoiding “probable and aware”
Cl 20.1
Cl 8.3 & 20.1 Cl 20.1
Fully Detailed Claim
"Probable "and "Aware" are Fully Detailed Claim
(Interim)
merged (Interim)
Update or final after end of effects
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
21
Clause 8 Matrix
23
The Engineer
25
25
The Engineer - Certification
■ The Engineer
■ acts as the Employer’s agent
■ must consult with the Contractor and Employer when
differences arise
■ must carry out fair determinations
■ must calculate all certificates in a logical and methodical
manner
26
Engineer’s calculation and determination
28
Step 1 - Investigation
Investigation
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Investigation Summary Verification Analysis Causation Liability
29
Step 1 - Typical record types
•Is o / s p o o l d w g t r a c ki ng s c he d ul e s
•Ba s e l i ne P r o g r a m m e •Is o / s p o o l fa b / d e l i ve r y r e c o r d s
•R e vi s e d B a s e l i ne p r o g r a m m e s •D r a w i ng r e g i s t e r s
•P r o g r e s s P r o g r a m m e U p d a t e s •Ins p e c t i o n a nd t e s t r e c o r d s
• R e a c t o r ve s s e l / p l a nt i t e m d e s i g n, m a nufa c t ur e a nd
d e l i ve r y r e c o r d s
•F EED d e s i g n d e t a i l s
Progress Records
Payment records
•P r o g r e s s R e p o r t s
•M a r ke d up p r o g r e s s d r a w i ng s •EP C c o nt r a c t o r a p p l i c a t i o ns
•P r o g r e s s P ho t o s •S up p l i e r / s ub - c o nt r a c t o r a p p l i c a t i o ns
•S i t e d i a r i e s
•M i nut e s o f S i t e M e e t i ng s
Project Admin Records
Contract Documents
•Client instructions
•Site Instructions
•D r a w i ng s •Change notices
•S p e c i fi c a t i o n •Delay Notices
•Co nd i t i o ns o f Co nt r a c t •Correspondence
•Any claims submissions to date by Tecnicas Reunidas
30
Step 2 - Summary
Summary
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Investigation Summary Verification Analysis Causation Liability
31
Step 3 - Verification
Verification
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Investigation Summary Verification Analysis Causation Liability
32
Step 4 - Analysis
Analysis
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Investigation Summary Verification Analysis Causation Liability
33
Step 5 - Causation
Causation
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Investigation Summary Verification Analysis Causation Liability
34
Step 6 - Liability
Liability
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6
Investigation Summary Verification Analysis Causation Liability
35
FIDIC & Delay Damages
Employer breaches:
• interference and prevention
• late supply of information
• failure to give possession
37
Liquidated damages
Qatar
39
Middle East (FIDIC delay damages –v- Liquidated damages)
40
Middle East (FIDIC delay damages –v- Liquidated damages)
Sultanate of Oman
Royal Decree No. 29/2013 enacting the Civil Code issues such as liquidated
damages relating to building contracts (Muqawala) is codified as follows:
• In all cases, the court may, upon application of either of the parties amend
such agreement to make the compensation equal to the damage , and any
agreement to the contrary shall be null and void
Result :
• courts may award liquidated damages
41
Summary (FIDIC delay damages –v- Liquidated damages)
42
Presenting extensions to Time for
Completion
7+
40
km
0
3+
km
40
Km 115+000
11
0
5+
00
0
km
10
9
km
+0
Km 7+400
10
0
0
6
+4
00
A2
A1
km
10
A3
0
+5
00
B 1- km 3+365
A4
km
B 2 - km 1+440
94
+5
00
B 3 - km 109+137
km
A5
B 4 - km 109+067
90
+0
00
B 5 - km 107+170
km
83
km
+2
81
0
0
+0
0 0
A6
km
20
75
+5
00
t
km
A7 B 6 - km 96+300
c
72
km
ra
+6
B 7 - km 96+088
69
00
t
+5
n
00
A8 B 8 - km 94+700
Negreni Lane
Co
B 9 - km 92+500
A7
km
B 3 - km 86+476
60
A6
+5
km
00
58
B 2 - km 82+191
+0
00
km
A5
54
+0
A4 B 1- km 75+634
00
km
49
B 4 - km 71+863
km
+0
7
0
47
A3
0
20
B 5 - km 70+650
+3
06
B 6 - km 70+265
c t
km
ra
A2
42
km
+1
t
80
41
n
+6
Co
A1
50
km
B 7 - km 59+050
37
+2
00
km
32
A8
km
+6
0
29
Saru Forest
+6
9
B 6 - km 48+570
km
A7
0
24
B 5 - km 48+250
+6
A6
50
km
A5 B 4 - km 44+850
21
Key
+2
0
B 3 - km 43+550
0
A4
Km 21+200
A1 A2 A3
6
20 = Bridge:- Number &
B 2 - km 33+180
B1 - km 75+634
t
B 1- km 28+179
Chainage
rac
nt A7 = Programme Window \
Co Timeslice
= Tree Felling
46
Construction Methods
Stage 1 : Original Road Profile and Structure Exhibit C-2 : Typical Cross Section
Nr. 1
Exhibit C-2 : Typical Cross Section
Nr. 1 shows the proposed
rehabilitated road profile in black
lines. Original road profile shown in
broken green line
47
Construction Methods
Stage 2 : Topsoil Removed
Working Drawings Non-Critical
A 1km stretch of carriageway is
closed and the topsoil removed
from the banks and stored for
future use
48
Construction Methods
Stage 3 : Excavation
Working Drawings Non-Critical
The existing bank is excavated to
enable the new profile of the
rehabilitated road to be formed and
the foundation layers placed
49
Construction Methods
Stage 4 : Fill to Form Bank Profile
Working Drawings Non-Critical
A portion of the excavated area is
filled with earth to form the new
road bank profile and enable work
to begin on the foundation layers of
the road
50
Construction Methods
Stage 5 : 4% Lime Sub-Base
Working Drawings Non-Critical
51
Construction Methods
Stage 6 : Granular Sub-Base
Working Drawings Non-Critical
52
Construction Methods
Stage 7 : Stabilised Ballast 6%
Cement
Working Drawings Non-Critical
A 25cm layer of natural aggregates
stabilised with 6% cement is laid
using shuttering to the outer edge
53
Construction Methods
Stage 8 : Regulating/Base Course
Working Drawings Critical
A 4cm base course is laid across the
carriageway together with a
regulating course where necessary
to achieve the proposed road profile
54
Construction Methods
Stage 9 : Binder Course
Working Drawings Critical
55
Construction Methods
Stage 10 : Fill up to Base Course
Level
Working Drawings Non-Critical
The new bank is filled to underside
of the stabilised ballast layer
56
Construction Methods
Stage 11 : Identical Works to Opposite
Carriageway
The same 1km stretch of the
opposite carriageway is closed and
stages 1 to 10 inclusive are carried
out to that side (construction up to
binder course)
57
Construction Methods
Stage 12 : Wearing Course to First
Carriageway
Working Drawings Critical
A 4cm wearing course (MASF16) is
laid to the first carriageway
58
Construction Methods
Stage 13 : Wearing Course to Opposite
Carriageway
Working Drawings Critical
A 4cm wearing course (MASF16) is
laid to the opposite carriageway
59
Construction Methods
Stage 14 : Fill to Shoulders
Working Drawings Non-Critical
The remaining section of the new
bank is filled. During this process a
small length of one side of the
carriageway is closed to carry out
the work
60
Construction Methods
Stage 15 : Topsoil to Banks Exhibit C-2 : Typical Cross Section
Working Drawings Non-Critical Nr. 1
Constructed
The new banks are covered with
topsoil using the material removed
in stage 2
Completed Road
61
Photographs to illustrate
the critical path
(Entrance to the site and car park and work which has encountered
a critical path delay of 34 days)
63
South Central Depot Improvement Contract
Littlehampton Depot Volume 1:
(An area of work located between the cleaning shed and train
washer and adjacent the car park and that has encountered a critical
path delay of 42 days)
64
South Central Depot Improvement Contract
Littlehampton Depot Volume 1:
65
South Central Depot Improvement Contract
Littlehampton Depot Volume 1:
7.0 EXTENSION OF TIMEPARTICULARS
Delay Event 4: PSU DELAY EVENT 4
(The upgrade of the power supply that is located adjacent the car park
and which has caused a critical path delay of 81 days)
66
South Central Depot Improvement Contract
Littlehampton Depot Volume 1:
7.0 EXTENSION OF TIMEPARTICULARS
67
South Central Depot Improvement Contract
Littlehampton Depot Volume 1:
7.0 EXTENSION OF TIMEPARTICULARS
68
Modelling the critical path
70
70
71
71
Construction Sequence
72
72
Piles
Piles
73
73
Pile Caps
Pile Caps
Piles
74
74
Walls & Columns
Columns
Walls
Pile Caps
Piles
75
75
Podium Steel
Podium Steel
Columns
Walls
Pile Caps
Piles
76
76
Trackslab and Platforms
Podium Steel
Columns
Walls Platforms
Trackslab Trackslab Trackslab
Pile Caps
Piles
77
77
Temporary Supports
Podium Steel
Piles
78
78
Podium Slab
Columns
Walls Platforms
Trackslab Trackslab Trackslab
Pile Caps
Piles
79
79
Platform Finishes
Platform
Columns
Walls Platforms
Finishes
Piles
80
80
Flow charting the critical
path
Remove
Perforated
Plate and Perforated Plates
blank 1
No Bell
Mouth
Acoustically
line 4No Bell
Mouths
Revised
Minimum Disable CV Box
Air
OffVolumes
Site design Modify
of software /
graphics &
Volumes to
development of perimeter
DOP’s zones
82
Analysis of commissioning plansNote: Off Site
Operations should be
complete.
• Engineer located at
the Head End.
• Engineer located at
the Controller.
• Engineers
communicate via radio.
• Certain conditions
require simulation by
the Engineer at the
Controller i.e. Boilers
and Chillers need not be
available.
• All points would be
checked in this way.
• The Specification set
out that Systems 33 &
35 should be
commissioned
separately.
• In our opinion, 1 - 2
Off Site design days would have been
of software / allowed to commission
graphics & System 33.
development • After all points are
DOP’s checked and both
Engineers satisfied, the
System is ready for
83
witnessing.
SPECIFIED WITNESSING PROCEDURE
Stage 1 - Point to
Point Checks.
84
SPECIFIED WITNESSING PROCEDURE
Stage 2
• Engineer located at
Controller.
• Engineer at Head End
along with the
Witnessing Authority.
• Communication via
radio.
• Proving the
functionality of the plant
in automatic mode using
graphics.
• This witness would take
place on a System by
System basis again with
simulation being
generated to prove
Global Interfaces.
88
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
Contractor theoretical
critical path
89
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
2 Month Delay
90
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
91
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
92
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
12 Month Delay
93
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
12 Month Delay
94
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
15
Month
Delay
95
Factual Analysis
Dealing with Scenario 3 – Impact on Level 3
2 Month Delay
12 Month Delay
12 Month Delay
15
Month
Delay
96
Charts in general
98
98
Factual Analysis PROCUREMENT DELAY EVENT 1: ROOF FANS
■
by red delay bars that represent late detail design
PROCUREMENT DELAY EVENT 6: IN PLANT CONVEYORS
■ Each red delay bar in each facility has a different effect and
length of delay, this is called causative potency PROCUREMENT DELAY EVENT 7: BELT FEEDER
■ The longest red bar in a facility = the primary critical path and
the others that follow behind are the secondary critical paths
PROCUREMENT DELAY EVENT 9: BRIDGE CRANE
99
99
Factual Analysis
Dealing with Scenario 3 – Resource Analysis
100
100
Thank You
Questions & Answers