Professional Documents
Culture Documents
06 GT 01 Protection
06 GT 01 Protection
Palmiet Pumped Storage Power Station is due for an upgrade that includes the control and instrumentation system, electrical protection system,
excitation system and accelerating system.
The acceleration system is a variable A paralleling device (synchroniser) monitors Absence of a generator LV circuit
frequency converter (SFC) that is shared voltages on either side of the load breaker
between two units. Three acceleration switch. Near synchronous speed (pump Motor synchronising functionality
configurations are possible as shown or generate mode) it starts to control the
in Fig. 1. They are: conventional, cross- machine speed and voltage and closes Instrument transformer locations and
feed and back to back configuration. the load switch at synchronous conditions. protection functions
The latter two configurations are seldom The machine is now connected to the grid.
If the machine is in pump mode the turbine With the upgrade the existing instrument
used. Fig. 1 shows machine 2 as it is being
is flooded to commence pumping water t r a n s f o r m e r s a r e r e - u s e d. T h e s t a t i c
accelerated. The SFC arrangement is
to the upper dam. If it is in generate mode protection that requires the use of
symmetrical, therefore the configurations
it uses the upper dam water to generate interposing is replaced with modern
of machine 1 is a mirror image of Fig. 1.
electricity as it flows into the lower dam. numerical protection. Modern numerical
With conventional and cross-feed protection allows the flexibility to remove
configuration the SFC accelerates The protection and synchronising the interposing current transformers.
machine 2. Back to back acceleration application at a pumped storage plant Fig. 2 shows the important current and
is used when the SFC is not available. has more considerations compared to voltage transformer (CT and VT) locations.
Machine 1 and 2 are configured as a conventional generation plant. In must Although single CTs is shown they are fully
a synchronous generator and motor also accommodate the following; redundant. An important design criterion is
respectively. Machine 1 is accelerated that secondary CT wiring are not switched
SFC transformer protection
with excitation using the hydro turbine. but accommodated in the intelligent
It provides electrical power with an Frequency variation during electronic device (IED) software. Control
increasing frequency to accelerate acceleration, and secondary VT signals are allowed to
machine 2 as a synchronous motor. Effect of reversing isolators be switched.
Fig. 2 indicates the instrument transformers
l o c a t i o n. T h e i m p o r t a n t p r o t e c t i o n
functions and associated instrument
transformers are listed in Table 1.
differential zone, current path and terminal switch open and the SFC in operation, The SFC transformers CT arrangement
CTs during conventional SFC operation the current through the transformer-side results in four-terminal differential schemes
(braking and accelerating). load switch CT is zero and does not affect to be implemented at both transformers.
the protection stability. The difference
It is a four terminal differential scheme. Fig. 5 shows the machine- and line side
(compared to the transformer differential)
The CTs on the transformer-side of the load transformer differential protection zones.
is that the generator differential protection
switch operates at 50 Hz but the generator- The line-side differential protection current
must be reliable and follow the frequency
side CT frequency follows the SFC output. terminals always operate at a fundamental
ramping to 50 Hz. It is practically not
However the generator-side CT current of 50 Hz, any harmonics are rejected.
possible to have the generator differential
is zero during SFC operation because
function active and reliable as soon as All four machine-side differential protection
the load switch is open and bypassed.
SFC operation commences (0 Hz). This current terminals follow the SFC output
Therefore the generator transformer
is because of the low frequency limit of frequency. This differential function must
differential protection remains stable and
the protection IED is around 6 – 10 Hz. track the fundamental frequency of the
operates at 50 Hz. When the load switch
Furthermore the CTs at the differential voltage applied to the machine stator and
closes, current starts to flow through the
terminals are different (ratio, make, reject any harmonics.
load switch and the generator side CT.
class). Their per formance at reduced
The two systems are now tied via the
frequencies and current is unknown and During SFC operation (acceleration
load switch and all the currents are at
the resulting differential error could be the and braking) only two circuit breakers
the same frequency at 50 Hz. The SFC
limiting factor. The limit of operation will be are closed at any time for any of the
is stopped and machine and line side
determined during commissioning and the acceleration modes shown in Fig. 1.
SFC breakers are opened which does
function is inhibited below the limit. Usually the conventional configuration
not affect the generator transformer
is used. SFC fault isolation is simplified
differential protection reliability. At frequencies lower than the limit one has
if all four SFC breakers are tripped for
to rely on other means of protection, such
The generator differential protection is machine-, or line side faults. The SFC and
as the SFC protection and perhaps peak
a three-terminal scheme. During SFC AVR controllers must be stopped or tripped.
sensing overcurrent.
operation the transformer-side load switch Stop refers to the preferable case where
CT operates at 50 Hz but the neutral- and The SFC uses two 27 MVA three-winding the SFC or AVR shuts down subsequent to
machine side SFC CTs follows the SFC transformers installed at the line- (rectifier) dissipating any stored energy – providing
output frequency (Fig. 4). With the load and machine-sides (inverter) respectively. the delay is not excessive. Trip implies the
Fig. 6: SFC zone fault isolation. Fig. 7: SFC breaker fail implication.
By tripping the four SFC breakers, the SFC and both AVR’s the fault
is cleared and a breaker fail scenario does not result in slower
fault clearance.
Cross-feed and back-to-back configurations are rarely used and
it is anticipated that the outage duration subsequent to a fault
occurrence will be longer than normal to determine the fault
location and perform analysis.