JOB INFORMATION

PROJECT CR TANZA YARD ENGR ABMoral JOB # 1


SUBJECT DESIGN OF FOOTING DATE 7/17/2019 SHT # 1
P
DESIGN PARAMETER
Ps = M
216.97 KN V Rebar along L
Pu = 273.30 KN
Ms = 124.67 KNm

embedment
Mu = 466.67 KNm d
c1
Embedment = 1.50 meter
B c2
Density, g = 18.00 KN/m3
qall = 95 KPa

"t"
Minimum "t" = 150 mm
Minimum "L" = 0.5 meter
L L
Increment of L = 100 mm
Increment of t = 50 mm Rebar along B
bar f = 20 mm
c1 = 900 mm L/B Ratio = 1.00
c2 = 600 mm as = 40.00
f'c = 28 Mpa qu = 319.43 Kpa (max)
fy = 414 Mpa qu = -206.50 Kpa (mmin)
b= 0.667
DIMENSION REQUIRED
Areqd = 2.284
B= 2.150 meter say B = 2.20 meter
L= 2.150 meter say L = 2.20 meter

SINGLE SHEAR
Vud = qu[0.5(L - c1) - d]B
fVc = f(f'c)1/2Bd/6
Effective, d = 194.22 mm
t = 279.22 trial t = 250.00 mm

CHECK PUNCHING
Trial 1 Trial 2 Trial 3
d= 165 mm trial t ok mm trial t ok mm
bo = 3660 mm ---- mm ---- mm
Pup = 13 KN ---- KN ---- KN
f(f'c)1/2bod/3 = 905 safe ---- ---- ---- ----
f[1/6+1/3b](f'c)1/2bod = 1811 safe ---- ---- ---- ----
f[1/6+asd/12bo](f'c)1/2bod = 861 safe ---- ---- ---- ----

BENDING d = 165
Mu = 224.88 steel ratio, r = 0.0112
rrqrd = 0.0112 required As = 4052.46
rmin = 0.0034 number of bars = 12.90
say = 13.00 pcs - 20 mmf Both Ways
USE t = 250 mm
JOB INFORMATION
PROJECT CR TANZA YARD ENGR ABMoral JOB # 1
SUBJECT DESIGN OF FOOTING DATE 7/17/2019 SHT # 2

CHECK FOR OVER TURNING

Ps
Vs
Ps = 216.97 KN
Vs = 54.205 KN
1

embedment
Righting Moment 2
Overturning Moment

"t"
RM = 238.66 KN-m
OM = 124.67 KN-m

TOTAL FORCE DOWNWARD

F.S. = 1.91 SAFE > 1.5

CHECK FOR SLIDING

P
V= 83.45 KN
P= 423.86 KN V
F= 211.93 KN
embedment

F.S. = 2.54 SAFE > 2.5


"t"

L
F
Horizontal Vertical
Node L/C Force-X k Force-Y kN
1 17 54.205 216.965
2 17 -180.886 206.89
2 8 -86.68 182.922
2 11 -144.597 179.761
2 13 -144.597 179.761
1 13 49.586 179.056
1 11 49.586 179.056
1 8 86.68 149.877
1 9 3.253 132.418
2 9 -129.935 122.343
2 18 22.024 113.435
2 14 7.586 109.67
1 14 82.011 65.188
1 18 97.439 65.14
1 18 97.439 65.14
2 10 72.976 28.888
1 10 46.487 -19.406

1
2

1
2

2
1
2
3
4
Horizontal Vertical Horizontal
Node L/C Force-X k Force-Y kN
2 23 -202.902 273.298
1 23 97.334 269.578
2 22 -117.251 233.65
1 25 14.224 232.483
1 22 117.251 200.605
2 25 -225.361 200.27
2 24 -33.81 195.419
1 29 -21.97 170.611
1 24 133.362 143.057
2 21 -50.02 137.725
2 29 -189.166 128.484
1 21 50.02 91.462
1 30 50.086 -82.43
2 26 112.823 44.511
2 30 149.018 -27.275
1 26 86.281 -20.558

17 54.205 216.965
17 -180.886 206.89

18 97.439 65.14
17 -180.886 206.89

V -83.447
P 423.855

17 -180.886 206.89 0 0 0 0