You are on page 1of 2

ATTACHMENT A

SCHEDULE OF MEMBERS

FOUNDATION
Bored Pile Location Diameter Length Vertical Bars Transverse Reinforcement
BP-1 Loading Bay 2000 mm 20 m 32 - 36 mm ϕ 20 mm ϕ ties with 75 mm pitch spacing

COLUMN
Column Mark Location Dimension Vertical Bars Transverse Reinforcement
FTNG-2ND
GC-1 1000x1500 36- 36 mm ϕ 6 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
GC-1A 1000x1500 48 - 36 mm ϕ 6 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
GC-1B 1200x1700 54 - 36 mm ϕ 6 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
GC-2 1000x1500 46 - 36 mm ϕ 6 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
GC-2A 1200x1700 60 - 36 mm ϕ 6 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
GC-2B 1300x1800 70 - 36 mm ϕ 6 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
2ND – 3RD
SC-1 800x1000 36 - 32 mm ϕ 4 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm
SC-2 800x1000 32 - 32 mm ϕ 4 sets 16 mm ϕ @ 100 mm, Joint/Conf. Hoops, rest @ 150 mm

PROJECT TITLE:

THE MRT 7 PROJECT


STATION 8
REINFORCED CONCRETE
LOCATION:
QUEZON CITY- SAN JOSE DEL MONTE BULACAN
ATTACHMENT A

STEEL SCHEME

C1

C1

C2
C1

C1
REINFORCED / PRESTRESSED CONCRETE
(AASHTO I-BEAM)

PROJECT TITLE:

THE MRT 7 PROJECT


STATION 6
REINFORCED / PRESTRESSED CONCRETE (AASHTO I-BEAM)
LOCATION:
QUEZON CITY- SAN JOSE DEL MONTE BULACAN

You might also like