Activities Start Date Duration (days)


Educational tour 1-Aug 7
Acquisition of materials and equipments needed 8-Aug 30
Securing of Permits (Occupancy, building, clearance, business etc.) 10-Aug 30
Farm Preparation 25-Aug 10
Soil Conditioning 5-Sep 5
Development of Nursery 10-Sep 2
Well drilling 1-Sep 5
Planting of Suckers 15-Oct 5
Construction of Admin Office and Stock room 10-Sep 80

43678.00

43804.00
WORK PLAN

WORK PLAN

1-Aug 21-Aug 10-Sep 30-Sep 20-Oct 9-Nov 29-Nov

Educational tour
Acquisition of materials and equipments needed
Securing of Permits (Occupancy, building, clearance, business etc.)
Farm Preparation
Soil Conditioning
Development of Nursery
Well drilling
Planting of Suckers
Construction of Admin Office and Stock room