You are on page 1of 40

Western Sydney

Infrastructure Plan
1 July 2017 – 30 June 2018
Report Card
Contents

Western Sydney The Northern Road upgrade 15


Infrastructure Plan overview3 The Northern Road upgrade,
The Old Northern Road to
Progress  4 Peter Brock Drive16

Employment  4 The Northern Road upgrade,


Peter Brock Drive to Mersey Road 18
Supporting Local Business  4
The Northern Road upgrade,
Providing Employment Opportunities 5 Glenmore Parkway to Jamison Road 20
Expenditure6 The Northern Road upgrade,
Milestones7 Mersey Road to Glenmore Parkway  22
Environment  8
Bringelly Road upgrade 24
Work, Health and Safety  10
Bringelly Road upgrade – Stage 1 25
Consultation  11
Bringelly Road upgrade – Stage 2 27
Werrington Arterial Road  13
M12 Motorway  29

Glenbrook Intersection upgrade 31

Local Roads Package 33

Front cover: Looking east from The Northern Road over the Western Sydney Airport Growth Area

Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Message from the Ministers

The Western Sydney Infrastructure In February 2018, we were pleased to announce And the best is yet to come! The peak annual
the release of the preliminary design for the expenditure of over $550 million for the WSIP
Plan (WSIP) has continued to make M12 Motorway. The M12 will provide first rate program is forecast to take place in the 2019–20
a significant difference in western connectivity to Western Sydney Airport and financial year, which means the residents and
Sydney over the last 12 months. a direct connection to Sydney’s motorway businesses of western Sydney will continue to
network, helping to unlock access to future benefit from the WSIP projects in years to come.
Since the 2016–17 report card, we have opened housing developments and economic precincts.
The Northern Road upgrade, The Old Northern The M12 will be built in time for the opening of
Road to Peter Brock Drive to traffic and substantial Western Sydney Airport in 2026.
progress has been made on others. In April, we Work is also continuing on the $200 million Local
had the pleasure of officially opening the first stage Roads Package. Roads and Maritime is working
of The Northern Road upgrade between The Old with local councils to help progress projects
Northern Road, Narellan and Peter Brock Drive, Oran worth $62 million. Many of the projects will go
Park. As residential and commercial development into construction later this year, providing local
occurs in western Sydney, traffic is expected to communities with safer and more efficient roads.
increase on The Northern Road. The $1.6 billion
upgrade will increase capacity, improve safety and Road users aren’t the only group benefiting from
reduce congestion and travel times in the future. WSIP road upgrades. Western Sydney businesses
and job seekers are also reaping positive rewards.
Two other sections of The Northern Road upgrade As of 30 June 2018, there were around 1798 full
are under construction; between Peter Brock time equivalent jobs created as part of WSIP
Drive, Oran Park and Mersey Road, Bringelly, and projects – an amount which has doubled in the last
between Glenmore Parkway, Glenmore Park and twelve months as projects move into construction.
Jamison Road, South Penrith. Good progress A total of $163 million worth of contracts have
has also been made on the upgrade of Bringelly been awarded to western Sydney businesses. The Hon. The Hon.
Road, with the first stage due to be open to traffic Of the 636 businesses working on WSIP projects, Alan Tudge MP Melinda Pavey MP
later this year and the second stage between 373 are based in western Sydney. Minister for Cities, NSW Minister for Roads,
King Street, Rossmore and The Northern Road, Urban Infrastructure Maritime and Freight
Bringelly under construction. and Population

1
The Northern Road and Erskine Park Road
• Intersection upgrade studies – complete Castle Hill
• Erskine Park Road intersection upgrades
– design complete Bungarribee Road and NorthConnex
Penrith • The Northern Road intersection upgrades Flushcombe Road traffic lights Motorway
– construction started scoping study – complete Dee Why
St Marys
Mt Druitt M2 Sydney Metro Northwest Brookvale
M7 Epping
Glenbrook Blacktown Macquarie Manly
Park
Glenmore
Park Werrington Arterial
Road – complete Eastern M4
ad

Glenbrook Creek Parramatta Chatswood


Ro

intersection Smithfield Road upgrade St Leonards


or thern

WESTERN SYDNEY – construction started


upgrade EMPLOYMENT
– in construction AREA
M12 Motorway Prairiewood North
Sydney
eN

In planning
Wetherill Street
Th

upgrade – complete Homebush WestConnex


Luddenham Motorway
Fairfield Strathfield
Cumberland Chullora
Highway Sydney
Elizabe intersection upgrades CBD
The

th D rive Cabramatta
The Northern Road upgrade – complete Burwood Bondi Junction
The Northern Road is being Western Sydney Airport Sydney Metro
Nor

upgraded in six stages:


• The Old Northern Road to M7 City and
th e

Peter Brock Drive –


Southwest
complete Liverpool
rn

• Peter Brock Drive to Mersey R WESTERN SYDNEY


Road – construction started AIRPORT GROWTH Bankstown
oa

• Mersey Road to Eaton Road – AREA


d

in planning
• Eaton Road to Littlefields Road B ringell
– in planning y Ro a d M5 Maroubra
• Littlefields Road to Glenmore
Parkway – in planning Leppington East Hills Kogarah
• Glenmore Parkway to Jamison Bringelly
Road – construction started SOUTH WEST LEGEND
GROWTH AREA Bringelly Road upgrade Hurstville
Stage 1 – in construction Local Roads Package
ay

Argyle Street/Camden Valley Way


W

Stage 2 – in construction Port Botany ($200 million Australian


Oran
y

• Corridor upgrade and studies –


lle

Park Government funded)


Va

complete
M31
n

• Stage 2 – Macarthur Road Raby Road from Eschol Park Major WSIP road projects
de

Intersection – construction started Drive to Stranraer Drive study


m
Ca

• Grahams Hill Road and Minto and designs – complete Existing The Northern Road
Richardson Road Intersection –
in design Other major transport
Eagle Vale Drive Miranda
Na projects underway
upgrade – complete
re Sutherland Cronulla
la l Rail
Porrende Street upgrade Narellan n Ro
scoping study – complete ad Campbelltown
Heathcote

Above: Western Sydney Infrastructure Plan overview map

2 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Western Sydney Infrastructure Plan overview

The Australian and NSW • Stage 2 is a 4.3 kilometre section between • Littlefields Road, Luddenham and Glenmore
King Street, Rossmore and The Northern Road, Parkway, Glenmore Park (six kilometres) –
governments are jointly funding Bringelly. A sod-turning event was held in June announcement of the construction contractor is
this $3.6 billion road investment 2017 to mark award of this contract. expected shortly
program for western Sydney. The upgrade will provide a generally four lane • Glenmore Parkway, Glenmore Park and Jamison
divided road with six lanes between Eastwood Road, South Penrith (four kilometres) – a sod
The Western Sydney Infrastructure Plan (WSIP) Road and Upper Canal Bridge, through the future turning event was held in June 2017 to mark
is delivering major road infrastructure upgrades Leppington Town Centre. award of this contract. Due to be open to traffic
to support an integrated transport solution for the in 2020.
region and capitalise on the economic benefits The Northern Road upgrade will see around
from developing the Western Sydney Airport. 35 kilometres of road upgraded between The The Northern Road upgrade will cater for future
Old Northern Road at Narellan and Jamison Road traffic from planned residential and commercial
WSIP will provide significantly safer and more at South Penrith. The overall upgrade is being developments.
efficient roads for customers. delivered in six sections between: The new M12 Motorway will provide direct access
The Werrington Arterial Road, which opened to • The Old Northern Road, Narellan and Peter to the Western Sydney Airport at Badgerys Creek
traffic in May 2017, was the first major project to be Brock Drive, Oran Park (3.3 kilometres) – and connect to Sydney’s motorway network.
completed as part of WSIP. The upgrade provided opened to traffic April 2018
road users with better, safer access between the The Glenbrook Intersection upgrade, due
• Peter Brock Drive, Oran Park and Mersey Road, to be completed in October 2018, weather
M4 Motorway and the Great Western Highway.
Bringelly (11.3 kilometres) – a sod-turning event permitting, will improve safety and access at the
The 10 kilometre Bringelly Road upgrade was held in June 2017 to mark award of this intersection of Ross Street and the Great Western
is being delivered in two stages between contract. Due to open to traffic in 2020 Highway, Glenbrook.
Camden Valley Way, Leppington and
• Mersey Road, Bringelly and Eaton Road, The Australian Government is also investing
The Northern Road, Bringelly.
Luddenham (5.5 kilometres) – construction $200 million in a Local Roads Package as part of
• Stage 1 is a 5.7 kilometre section between expected to commence in October 2018 WSIP, allowing western Sydney councils to deliver
Camden Valley Way, Leppington and King improved road connections that support the WSIP.
• Eaton Road, Luddenham and Littlefields
Street, Rossmore which should be opened to
Road, Luddenham (4.5 kilometres) – the call
traffic in late 2018, weather permitting
for tenders for a construction contractor is
expected to take place in late 2018

3
Progress

The Australian and NSW governments have • Continuing work on 25.3 kilometres of Employment
made significant progress in the delivery of the road including the Bringelly Road upgrade
WSIP including: between Camden Valley Way, Leppington and The Australian and NSW governments expect
• Completion of 5.3 kilometres of major road The Northern Road, Bringelly, and sections the WSIP projects to create about 4,000 direct
upgrades as part of the Werrington Arterial of The Northern Road upgrade between and indirect jobs over the 10 year lifetime of
Road and The Northern Road upgrade, Narellan and Mersey Road, Bringelly and the program.
The Old Northern Road to Peter Brock Drive. between Glenmore Parkway, Glenmore Park
As of 30 June 2018 there were around 1798 full
and Jamison Road, South Penrith.
time equivalent jobs created as part of WSIP
projects. This is almost double the number at
this time last year as more projects move towards
construction with the associated increase in jobs
and contracts.

Supporting Local Business

9km
A total of $163 million worth of contracts have
been awarded to businesses based in western
Sydney for WSIP projects.
Roads being
A total built
of 636 businesses are working on
WSIP projects, 373 of which are based in
0 10 20 30 40 50 60 63 western Sydney.

COMPLETED BEING BUILT IN PLANNING OR DESIGN

5.3km 25.3km
completed being built
32km
in planning or design

4 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Progress

Providing Employment Opportunities


The Northern Road Training and “I had been trying to get into the industry for
Employment Hub, Glenmore Parkway some years and completed formal vocational
to Jamison Road training in carpentry and other building skills,
but I found that what I was promised and
Through their historic infrastructure spend, the
the support I had when working, were two
Australian and NSW governments are creating
different things. Things are a lot better now
training and careers for western Sydney people
and I am learning so much.”
who face barriers to employment.
Ten women have so far completed a six-week
The Northern Road Training and Employment
pre-employment training course through the
Hub was set up in July 2017 linking Aboriginal
Hub and now work full-time on The Northern
and Torres Strait Islanders, refugees, long-term
Road upgrade.
unemployed, women and young people under
25 with on the job training and employment. Shelley, 22, from Penrith said the Hub training
So far, the Hub has trained around 30 people program gave her the employment stability
from these target groups, placing them she needed to discover what she was really
into potentially lifelong careers, while also passionate about.
contributing to the future of western Sydney.
“I was craving stability and wasn’t really sure
For skilled migrant and civil construction what I wanted to do with my time,” Shelley
apprentice Casidhe Lee, from Lalor Park, said. “I love being able to take something and
the Hub has provided a vital foot-in-the-door make something of it, and see what I have
to the construction industry, and the chance accomplished. I am learning about safety,
to earn formal civil construction qualifications hazards, the way roads are made and all the
through an apprenticeship with The Northern little bits and pieces that are put into it to
Road upgrade contractor, Lendlease. make the whole project.”

Civil Construction Apprentice, Casidhe Lee and


the Lendlease Project Director, Barry Murphy

5
Expenditure 800
Actual expenditure – to FY 2017/18
Of the $3.6 billion for the WSIP, the Australian Forecast expenditure

Annual spend/budget
Government will fund $2.9 billion, while the NSW
600
Government will invest $700 million.

$ millions
Peak expenditure for the program is forecast to be
over $550 million during the 2019/20 financial year 400
when simultaneous construction will be underway
on the majority of the projects.
Expenditure on the WSIP for the full 2017/18 200
financial year was $328 million.

0
Up to FY 16 FY 17 FY 18 FY 19 FY 20 FY 21 FY 22 FY 23 FY 24 FY 25
FY 2015
Financial year

6 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Progress

Milestones The following six milestones are targeted for


Six key milestones targeted for the 2017/18 financial year were completed: the 2018/19 financial year:

Project Milestone Target achieved Project Milestone

The Northern Road upgrade, Site work commenced Bringelly Road Stage 1 Open to traffic
Peter Brock Drive to Mersey Road
Bringelly Road upgrade Stage 2 Site work commenced
The Northern Road Start major
The Northern Road upgrade, Site work commenced upgrade, Mersey Road to construction
Glenmore Parkway to Jamison Road Eaton Road
Local Roads Package – Round 2 Start work on all Round 2 projects
The Northern Road Start major
The Northern Road upgrade, Open to traffic
upgrade, Littlefields Road construction
Oran Park to Peter Brock Drive
to Glenmore Parkway

Local Roads Package – Start work on


M12 Motorway Submit preliminary business case
Round 2 all Round 2
projects

Glenbrook Open to traffic


intersection upgrade

M12 Motorway Market


sounding to
commence

7
Progress

Environment
Roads and Maritime is committed to the delivery A number of environmental impact assessments The presence of bonded Asbestos Containing
of efficient and effective environmental outcomes have taken place on projects in both development Material (ACM) identified on WSIP projects
throughout the planning and construction of and construction. In May 2018, Roads and Maritime poses a continuing challenge to construction
projects within the WSIP. This includes providing achieved a significant milestone in obtaining both timeframes and budgets. We have developed
advice on the planning process, monitoring NSW and Australian Governments approval for a process in consultation with the Environment
construction activities to mitigate the impact on The Northern Road upgrade between Mersey Protection Authority (EPA) on several WSIP
the environment, and liaising with government and Road and Glenmore Parkway. As the upgrade projects to encapsulate bonded ACM to minimise
community stakeholders to address concerns. had significant impacts on Commonwealth safety and environmental impacts. Roads and
land, separate NSW and Australian Government Maritime will continue to work collaboratively
Performance of construction contractors
approvals were required. with regulatory stakeholders, industry specialists,
is monitored via fortnightly site inspections
our contractors and the community to effectively
and scheduled management system audits. We invited comments from the community and
manage this issue.
Contractors are assessed against environmental stakeholders on the preliminary design and access
management practices and encouraged to strategy for the M12 Motorway in February and
look for innovation to achieve outcomes. Between March 2018. An environmental impact statement
July 2017 and June 2018, 72 scheduled inspections for the project is currently being prepared.
of projects within the WSIP were carried out.

8 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Progress

The purchase of biodiversity offset credits for


the WSIP under the NSW BioBanking scheme
is ongoing. In December 2017, we launched
a public Expression of Interest (EOI) process
whereby advertisements were placed in relevant
newspapers asking interested landholders to
contact the Roads and Maritime Office about
creating biodiversity credits on their land for
exclusive purchase by Roads and Maritime.
In May 2017, approval was granted to purchase
$13 million of biodiversity offset credits listed on
the OEH Public Register. This tranche comprised
about 12 per cent of the total biodiversity offset
credit requirements for The Northern Road
upgrade and M12.
These credits compensate for the lost vegetation
by protecting and managing biodiversity in
one area in exchange for the impact created
by a project.
BioBanking allows ‘biodiversity credits’ to be
generated by landowners and developers who
agree to enhance and protect biodiversity values
on their land through a BioBanking agreement.
These credits can then be sold, generating funds
for the management of the site.

Cumberland Plain Woodland

9
Progress

Work, Health and Safety


People Plant Proximity Technology Trial
We continue to work closely with our industry
partners to manage risk and promote a safe We have committed to carry out a trial of we are still exposed. The pilot is moving and
work culture during construction of WSIP projects. ‘wearable technology’ aimed at improving the maturing as technology improves and there are
safety of people in the vicinity of mobile plant further aspirations to be realised to make this
Working collaboratively and gaining
(People-Plant-Proximity) on our projects. technology even more interactive.
industry partner participation has proven
invaluable, allowing us to share lessons across Roads and Maritime is partnering with our
our program and project offices. Roads and contractor for the initial trial over a 12 month
Maritime sponsored a safety forum that brought period on The Northern Road upgrade,
together 80 Roads and Maritime and industry Mersey Road to Glenmore Parkway to benefit
leaders to discuss innovation and consistency the wider construction community.
across projects. This leads directly to specific
We have used the system EgoPro that offers
improvements across WSIP projects.
proximity warning and alerts to workers and
We collaborate on all safety matters with our operators in real time. The system provides
industry partners to challenge the status quo sound and visual display alarms based on
and promote continuous improvements and presence of workers around plant or vehicles.
innovating in safety.
The pilot consists of EGOPro devices fitted to
17 items of plant and 200 individual sensors for
project staff and contractors.
Not only do the devices offer a layer of controls
to prevent people and plant incidents, the data
from these devices allowed this information
to assist in better planning and improved the Executive Director Technical Project Services,
management of work environments. Jeff McCarthy and Director of Engineering,
Chris Harrison getting hands-on experience with
The pilot has been invaluable to help quantify the People-Plant-Proximity wearable technology
the number of people/plant interactions on site, trial at the Northern Road upgrade, Mersey Road
as well as providing insights into areas where to Glenmore Parkway

10 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Progress

Consultation
Taking a leap ahead with technology, we plan to implement the proposed Roads and Maritime
Roads and Maritime is committed to transparent 360 Virtual Reality App to enable users to explore the new M12 Motorway design and intersections
and inclusive consultation throughout the with their own phone for a completely immersive experience. The VR app includes proposed
development of projects. We work collaboratively 360° images, 360° videos and an interactive map of the motorway. Google Cardboard devices will
with residents, stakeholders, interest groups, be given away at the community consultation and pop-up events so stakeholders can download
community representatives and councils to gain the app and experience VR on their own device (iPhone or Android) anytime.
feedback and suggestions which helps to inform
our planning and decision making.
These opportunities occur at specific project
milestones such as selecting new road
corridor alignments or during the display of
environmental assessments.
We encourage the community to have a
say at important milestones during project
development through:
• one-on-one meetings
• community information sessions
• information displays
• postal submissions
• Roads and Maritime and other NSW
Government websites.

A user experiencing the Virtual Reality App at a community information session

11
Progress

141,083
Information on WSIP projects is provided through: The WSIP web pages received 141,083 page views
• project update newsletters during the 2017/18 financial year.

• regular website updates Roads and Maritime is continually updating


the interactive digital portal on the WSIP
page views for project web pages • social media web page which features project information,
from July 2017 to June 2018
• letters to land owners and residents animated videos, maps and photo galleries.
• staff visiting affected land owners and residents To explore the interactive digital portal, visit

193,600
www.rms.nsw.gov.au/wsip.
• electronic message signs targeting road users.
Approximately 193,600 project update newsletters,
letters and notifications were distributed for WSIP
project update newsletters, Project
update projects from 1 July 2017 to 30 June 2018. Our
letters and notifications sent
from 1 July 2017 to 30 June 2018
project teams met with education institutions,
businesses, councils, other government agencies,
residents and property owners throughout project

58,185
areas to consult on various project matters.

More than 62,156 people visited the


portal, playing the videos around
58,185 times since its launch in July 2015.

12 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Open to traffic

Werrington Arterial Road Penrith

Grea St Marys
t We Mt Druitt
stern
High
way

M4

o ad
Werrington

nR
Arterial Road

er
The North
M4 Motorway to the Great Western Benefits
Highway, Claremont Meadows M7
• Better access and network connections for
The Werrington Arterial Road upgrade opened to motorists and road freight by providing new
traffic in May 2017. This upgrade is providing road east facing ramps on and off the M4 Motorway.
users with faster and safer access between the • Reduced congestion and more reliable travel
M4 Motorway and the Great Western Highway. times, especially on The Northern Road and Project snapshot
Mamre Road.
The completed project included widening a Project value: $55 millionElizabeth Driv
• Enhanced safety at intersections with traffic e
two‑kilometre section of the Kent Road and
Construction contractor:

Th e N
Gipps Street corridor to four lanes as well as lights, pedestrian crossings, separate turning
two new east facing ramps to the M4 Motorway. lanes, and a separate shared path. Burton Contractors Pty Ltd
This has increased capacity on the road and t

or
he March 2015
Construction started:
improved travel times.
M

rn
Open to traffic: May 2017

R
oa
d
ringelly B
Australian Government contribution: Road
50 per cent

Budget Saving: $15 million Leppington

NSW Government contribution: 50 per cent

ay
W
y
lle
Va
Oran M31

n
de
Park

m
Ca
Na
re 13
ll an
R
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

5
Features
• Traffic lights on Kent Road for the new Intersections
eastbound entry ramp to the M4 Motorway improved
and at the westbound M4 Motorway exit ramp
• A shared pedestrian and cycle bridge over
the M4 Motorway
• New line marking on the Kent Road Bridge 183 38
DAYS
DAYS
to create two northbound lanes and
one southbound lane
• Improvements to five intersections,
including three new intersections
• A noise wall on the western side of
Gipps Street between Caddens Road and
the Great Western Highway.

Newly built Werrington Arterial Road

14 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
The Northern Road upgrade
The upgrade of The Northern Road extends around
35 kilometres between The Old Northern Road at Narellan
and Jamison Road at South Penrith.
The upgrade is being delivered in six stages:

 Completed
• The Old Northern Road, Narellan Key benefits
and Peter Brock Drive, Oran Park • Enhanced travel times and access to future • Improved safety for cyclists and pedestrians
(3.3 kilometres) precincts along The Northern Road by by building a new shared path
increasing the number of lanes • Better access to the Western Sydney
 Being built
• Increased capacity to accommodate future Employment Area, the South West Growth
• Peter Brock Drive, Oran Park and growth and development needs Area, and the Western Sydney Airport
Mersey Road, Bringelly (11.3 kilometres)
• Better public transport by providing • Enhanced access for the construction of the
• Glenmore Parkway, Glenmore Park dedicated bus lanes Western Sydney Airport at Badgerys Creek
and Jamison Road, South Penrith and surrounding developments
(four kilometres). • Improved safety for motorists by:
–– building new intersections with traffic • Improved access and travel times for road
freight in Sydney’s south west.
 In planning lights to access precincts
• Mersey Road, Bringelly and Eaton Road, –– building a central median to separate
Luddenham (5.5 kilometres) opposing traffic flows
• Eaton Road, Luddenham and Littlefields –– building turning lanes at 20 intersections
Road, Luddenham (4.5 kilometres) –– installing traffic lights at 27 intersections
• Littlefields Road, Luddenham and
Glenmore Parkway, Glenmore Park
(six kilometres).

15
Th e N
th

or
Open to traffic e
M7 L

rn
R oa
Bringelly
Road

d
Preston

The Northern Road upgrade, Leppington

The Old Northern Road to

ay
W
y
lle
orthern Road

Va
Peter Brock Drive
rive
ter Broc k D
Pe
M31

n
de
Oran

m
Park

Ca
The Old Northern Road

eN
Na to Peter Brock Drive
re

h
lla

T
The first stage of The Northern Road Features n Ro
ad
upgrade opened to traffic in April 2018,
with 3.3 kilometres of new dual carriageway • Three lanes in each direction – two for general Narellan
completed between The Old Northern Road, traffic plus a kerbside bus lane
Narellan, and Peter Brock Drive, Oran Park. Campbelltown
• Upgraded intersections at Fairwater Drive,
Camden
Hillside Drive and Cobbity Road, with traffic
Benefits lights and dedicated turning lanes Project snapshot
• An increased 80 km/h speed limit Project value (of all six sections): $1.6 billion
• Increased capacity to cater for future population
growth in the area • A new off-road shared pedestrian and cycle path.
Construction contractor for this section:
• Improved safety for road users through: Georgiou Group Pty Ltd
–– New intersections with traffic lights to Contract awarded: November 2015
access precincts
–– A central median to separate opposing Open to traffic: Early 2018
traffic flows
Australian Government contribution:
–– Turning lanes at intersections 80 per cent
• Enhanced safety for cyclists and pedestrians
NSW Government contribution: 20 per cent
through an off-road shared path
• More reliable travel times and access to future
precincts along The Northern Road
• Improved access and travel times for road
freight in Sydney’s south west.

16 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

3 Intersections
improved

213 11
DAYS
DAYS

Local State Member Camden, Chris Patterson; Minister Melinda Pavey (front centre); Federal Minister, Paul Fletcher

17
Being built
Elizabe
th Driv
e

The Northern Road upgrade, The Bringelly Road


and The Northern M7
Peter Brock Drive to Mersey Road Road Interchange
Bringelly
Road

n Ro a d
Peter Brock Drive
to Mersey Road Leppington

h er

ay
W
Nort

y
lle
Construction on The Northern Road upgrade Features

Va
The
rive
ter Broc k D
between Peter Brock Drive, Oran Park and Mersey Pe

n
de
Road, Bringelly started in July 2017. • 11.3 kilometres of main line road and associated Oran M31

m
Park

Ca
local road improvements
This project is being built together with the
Bringelly Road upgrade between King Street, • About 11 kilometres of shared pedestrian
and cyclist path N
Rossmore and The Northern Road, Bringelly.
• Nine new intersections with traffic lights and
Project snapshot
ar
ell
an
Ro
a further six intersections to be upgraded Project value (of all six sections):a$1.6
d billion
Narellan
• Wide shoulders in both directions
Construction contractor for this section:
• Existing bridge at Thompsons Creek replaced Lendlease Engineering Campbelltown
with new twin bridges Camden
Start of construction: Mid-2017
• An interchange to separate vehicles on The
Northern Road and Bringelly Road for better Expected to be open to traffic: 2020
traffic flow, with The Northern Road passing
under Bringelly Road Australian Government contribution:
• A new connection from Robinson Road to 80 per cent
The Northern Road and an off-road shared path NSW Government contribution: 20 per cent
for pedestrians and cyclists
• Changes to access for some properties along
The Northern Road, Bringelly Road and
Robinson Road.

18 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

Progress – July 2017 to June 2018 Next Steps


• During the 2017/18 financial year $41 million • Commencement of pavement layers
was spent • Commencement of superstructure for
• Total expenditure as of 30 June 2018 is $147 million Bringelly Interchange Bridge.
• Forecast expenditure for the 2018/19 financial
year is $107 million Next major milestone
• Earthwork and drainage being progressed
• Open to traffic in 2020.
site wide
• New roundabout to improve traffic flow
• Thompsons Creek northbound bridge
60 per cent complete
• Foundations for Bringelly interchange
bridge complete
• Utility adjustments approaching
40 per cent completion
• Ongoing property adjustment work.

241 9
DAYS
DAYS

Recently completed traffic switch to facilitate


the Stage 1 construction of the southern end of
The Northern Road, Oran Park

19
Being built

The Northern Road upgrade, Penrith

Glenmore Parkway to Grea


t We
stern St Marys
High
way

Jamison Road
Jamiso Mt Druitt
Road n

M4

ad
Glenmore Parkway

n Ro
to Jamison Road

r
Construction commenced on site in August 2017 Features

he
The Nort
for the upgrade of The Northern Road between
Jamison Road and Glenmore Parkway. To date • Four kilometres of road and four kilometres M
a significant amount of earthwork has been of shared pedestrian and cyclist path
completed to build up the embankments on the • Ten intersections M12 Motorway study area
northern and southern sides of the M4 Motorway
for the new bridge. Critical work including • Bus priority lanes in each direction
Project snapshot
stormwater drainage and utility relocations are • New and upgraded traffic lights and turning
well underway, with the substructure for the new Elizabe $1.6 billion
Project value (of all six sections):
lanes at six intersections. th D rive
bridge completed in May 2018.
Construction contractor for this section:

Th e N
Lendlease

Start of construction:
t h Mid 2017

o
e

r
7

rn
Expected to be open to traffic: 2020
238

R oa
Bring
Australian Government contribution:elly Road
DAYS

d
DAYS

80 per cent
Leppington
NSW Government contribution: 20 per cent

ay
W
y
le
orthern Road

l
Va
rive
ter Broc k D
Pe
M31

n
de
Oran

m
Park

Ca
eN
Na

h
re

T
20 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card llan
Ro
a d
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

Progress – July 2017 to June 2018 Next Steps


• $60million was spent during the 2017/18 • Complete all design packages for the project
financial year • Finish construction of the new bridge over the
• Total expenditure as of 30 June 2018 was M4 and switch traffic to the future southbound
$105.4 million carriageway in late 2018
• Forecast expenditure for the 2018/19 financial • Demolish the existing bridge and partially open
year is $83 million the new bridge to traffic in January 2019
• Penrith Christian School oval relocation • Complete all underbores for utilities under
completed in April 2018 the M4 Motorway.
• New bridge columns were completed in May 2018
• Utility relocations for Telstra, Endeavour Energy Next major milestone
and Sydney Water began in May 2018 • Complete the construction of the new bridge
• Significant volume of bonded Asbestos over the M4 Motorway in early 2019.
containing material discovered on site with more
than 5,000 cubic metres removed to date.

Construction of the columns for the southern abutment


of the new bridge

21
Detailed design

The Northern Road upgrade,


Mersey Road to Glenmore Parkway

In mid-2017, Roads and Maritime invited comments • About eight kilometres of new road between • A new shared path on the western side of
from the community and stakeholders on the Mersey Road, Bringelly and just south of the The Northern Road and pedestrian paths
Environmental Impact Statement (EIS) and existing Elizabeth Drive, Luddenham to realign on the eastern side of The Northern Road
concept design for The Northern Road upgrade the section of The Northern Road that currently where required.
between Mersey Road and Glenmore Parkway. runs through the Western Sydney Airport site
and to bypass the Luddenham town centre
In response to submissions received, the design Progress – 1 July 2017 to
was refined and approved by the Australian • About eight kilometres of upgraded and
widened road between the existing Elizabeth
30 June 2018
Minister of the Environment and Energy and the
NSW Minister for Planning in May/June 2018. Drive, Luddenham and just south of Glenmore • During the 2017/18 financial year $72 million
Parkway, Glenmore Park was spent
Features • Separate bus lanes at all intersections and • Total expenditure as of 30 June 2018 is
dedicated bus lanes to serve existing communities $96 million
• A minimum of two general traffic lanes in each north of Bradley Street, Glenmore Park
• Forecast expenditure for the 2018/19 financial
direction between Mersey Road, Bringelly and • Provision to extend bus lanes as growth and year is $125 million
just south of Glenmore Parkway, Glenmore Park service demand requires
• Consulted the community about the concept
• Three lanes and a bus lane in each direction • Access to the Luddenham town centre from the design and exhibited and obtained approval
between Bradley Street and Glenmore Parkway realigned The Northern Road with traffic lights for the EIS – both Federal and State
• A central median to allow for an extra travel lane • Eight new traffic light intersections and new • Substantially progressed property acquisition
in each direction in the future, if required traffic lights at existing intersections
• Called and received tenders for the sections
• Local road changes and upgrades to current between Mersey Road and Eaton Road, and
access arrangements for businesses and Littlefields Road and Glenmore Parkway.
private properties

22 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract
Penrith traffic
option assessment
Grea
t We
St Marys
Jamiso
n Road stern H M
ighw
ay

Project snapshot
G lenm
or
Project value (of all six sections): $1.6 billion Parkwaye Wentwo
rt h Road

o ad
Design consultant: Jacobs Pty Ltd for the
section between Mersey Road and Eaton Road Littlefields Road to

nR
Glenmore Parkway

e N orther
Design consultant: Mott MacDonald Pty Ltd E
Littlefi e lds

ad
for the section between Eaton Road and
oa Ro

Ma
R
Littlefields Road d m
ha

mr
Th

en

eR
Design consultant: GHD Pty Ltd for the

dd

oa
Lu
section between Littlefields Road and
Glenmore Parkway Eaton Road to
The Northern Road next to the Western Sydney Littlefields Road Elizab
Expected start of construction: eth Dr
Airport site ive
Late 2018 (in stages)
Luddenham
Next steps Expected to be open to traffic:

Th
Eaton Road
Western
From 2020 (in stages)

e No
• Complete property acquisition Sydney airport
(operational by 2026)
• Award contracts and start construction of the Australian Government contribution:

rt h e
80 per cent Mersey
sections between Mersey Road and Eaton Road, Road

rn
and Littlefields Road and Glenmore Parkway R
NSW Government contribution: 20 per cent oa
• Call tenders for and award contract for the section

d
between Eaton Road and Littlefields Road. Mersey Road Bringelly
to Eaton Road Road
Next major milestone
Map showing theBringelly
three sections of The Northern
• Start of construction in late 2018. Road upgrade between Mersey Road, Bringelly and
Glenmore Parkway, Glenmore Park
Lepping
Peter Brock Drive South Wes
Priority Lan
to Mersey Road
Release Ar
23

d
Roa
Bringelly Road upgrade
The $509 million Bringelly Road upgrade is being delivered
in two stages to support the development of growth centres,
employment and Western Sydney Airport.
This 10 kilometre project includes upgrading Bringelly
Road from two lanes to a six lane divided road between
the Upper Canal bridge and Eastwood Road, through
the future Leppington Town Centre.
The rest of Bringelly Road will be upgraded from two lanes
to a four lane divided road with a central median, allowing
for widening to six lanes when required.

Key benefits:
• Improved access to the Western Sydney Airport site, Leppington Railway Station,
the new Leppington Town Centre and the M5 and M7 motorways
• Increased road capacity
• Improved safety for motorists
• Better bus priority and facilities
• More reliable travel times
• Improved access and safety for pedestrians and cyclists.

Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Being built
Elizabe
th Driv Cabramat
e

Bringelly Road upgrade – Stage 1

No Ro
M7

Thther
r ad
Leppington

e n
North
Bringelly
Road

The Nort
Presto
Leppington
Stage 1

ay
W
ern Road h

y
lel
Va
Camden Valley Way, Leppington Progress – July 2017 to June 2018

n
de
to King Street, Rossmore M31

m
• During the 2017/18 financial year $42 million

Ca
In October 2017, traffic moved onto the newly built was spent
eastbound carriageway between Camden Valley • Total expenditure as of 30 June 2018 is
Way and Edmondson Avenue, allowing work to $216 million
start on the westbound carriageway. • Forecast expenditure for 2018/19 financial year
Project snapshot
Na
re
lla
n
Work is also progressing on upgrading is $31 million Project value StagesR1oand
ad 2: $509 million
key intersections along Bringelly Road and • Girder erection of westbound bridge over Narellan
installing new traffic lights. Construction contractor:
the Upper Canal completed
BMD Constructions Pty Ltd (Stage 1 only)
Campbelltown
• Westbound carriageway foundation and
Features upper zone formation completed including Camden
Construction started: January 2015
major cut areas
• Improvements to nine intersections Expected to be open to traffic: End 2018
• Utility relocation work progressed significantly
• New traffic lights at seven existing intersections Australian Government contribution:
with designated right and left turning lanes • Eastbound and westbound carriageways opened
to traffic at the intersection of Bringelly Road, 80 per cent
• Realignment of the Bringelly Road/Camden Camden Valley Way and Cowpasture Road.
Valley Way/ Cowpasture Road intersection NSW Government contribution: 20 per cent
and upgrade of the traffic lights
• An extension to the existing noise wall
on the corner of Cowpasture Road and
Camden Valley Way
• 80 kilometres per hour speed limit.

25
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

9
Next Steps
• Complete relocation work for electrical Intersections
and telecommunication utilities to be improved
• Complete property adjustments
• Landscaping and finishing work
• Complete heavy duty base on the remaining
sections of westbound carriageway and lay 246 28DAYS
DAYS
asphalt on both carriageways
• Open Eastwood Road to traffic
• Pour deck slab of the bridge over the
upper canal to complete bridge work.

Next major milestone


• Open to traffic end 2018.

Water quality testing

26 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Being built
Elizabe
th Driv Cabramat
e

Bringelly Road upgrade – Stage 2

No Ro
M7

Thther
r ad
Leppington

e n
North
Bringelly
Road

The Nort
Stage 2
Presto
Leppington

ay
W
h

y
ern Road

lle
Va
King Street, Rossmore to Progress – July 2017 to June 2018

n
de
m
The Northern Road, Bringelly M31

Ca
• During the 2017/18 financial year $48 million
Construction of the Bringelly Road upgrade was spent
between King Street, Rossmore and The Northern • Total expenditure as of 30 June 2018 is
Road, Bringelly started in July 2017. $80 million
This project is being built together with The • Forecast expenditure for the 2018/19
Project snapshot
Na
re
lla
n
Northern Road upgrade between Peter Brock financial year is $60 million Project value StagesR1oand
ad 2: $509 million
Drive, Oran Park and Mersey Road, Bringelly. • Earthworks and drainage underway across Narellan
Construction contractor: Lendlease
the site
Engineering (Stage 2 only)Campbelltow
Features • Rossmore Public School rear carpark
Camden
Construction start: Mid 2017
construction complete
• 4.3 kilometres of road
• Utility adjustments approaching Expected to be open to traffic: 2020
• 4.2 kilometres of shared pedestrian and 50 per cent completion
cyclist path Australian Government contribution:
• Ongoing property adjustments work.
• Four upgraded intersections with traffic lights 80 per cent
and upgrades to three existing intersections
• New twin bridges over South Creek.
Next Steps NSW Government contribution: 20 per cent

• Installation of pavement layers


• Construction of superstructure for eastbound
bridge over South Creek.

27
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

Next major milestone


• Open to traffic in 2020.

7 Intersections
to be improved

241 9
DAYS
DAYS

Bringelly interchange looking south

28 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Grea St Marys
t We Mt Druitt
stern
H
Announce preferred option ighw
ay
Black
M4

M12 Motorway

ern Road
M7
M12 Motorway Prairie

orth
Preferred Corridor

heN
T
Elizabe
th Driv Cabram
e

Between the M7 Motorway, Cecil Hills Features


and The Northern Road, Luddenham • An east-west 16 kilometre motorway
The M12 Motorway will provide direct access to between the M7 Motorway, Cecil Hills
Western Sydney Airport and connect to Sydney’s and The Northern Road, Luddenham
Project snapshot
Bringelly
Road
motorway network. • A four lane motorway (with provision for

rn R o a d
six lanes) with a central median to separate Project value: $1.25 billion Pre
In February 2018, Roads and Maritime invited
opposing traffic flows
community feedback on the preliminary design Design consultant: Leppington
Aurecon Pty Ltd

rth e
and access strategy for the M12 Motorway. The • New ‘at grade’ connection to The Northern Road (strategic corridor route options)

ay
consultation report, responding to comments

e No

W
• Motorway-to-motorway interchange at
Design consultant and environmental

y
raised, will be released in late 2018.

le
the M7 Motorway

l
Th

Va
assessment: Jacobs Pty Ltd / Arcadis Pty Ltd
The M12 Motorway will be built as four lanes with • A new grade-separated interchange with the Joint VentureOran
(concept design and EIS) M31

n
de
capacity for six lanes in the future. A central access road to the Western Sydney Airport site. Park

m
Ca
median will separate opposing traffic flows. Expected start of construction: Early 2020s
Further community consultation on the planned
Once complete, the M12 Motorway will increase M12 Motorway will be done as part of the Expected to be open
Na to traffic: prior to
capacity and provide improved access to future Environmental Impact Statement (EIS) and re Sydney Airport
opening of the Western
ll an
development areas, including the Western Sydney concept design.
oa R
Airport Growth Area and the Western Sydney Australian Government contribution:
d
Employment Area. It will improve the movement The scope will be updated as the design progresses. Narellan
80 per cent
of freight in and through western Sydney.
Campbelltow
NSW Government contribution: 20 per cent
Camden

29
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

Progress – 1 July 2017 to Next Steps


30 June 2018 • Prepare environmental assessment
• During the 2017/18 financial year $12.4 million • Complete field investigations for concept design
was spent and environment assessment
• Total expenditure as of 30 June 2017 is • Complete concept design.
$20.6 million
• Forecast expenditure for the 2018/19 Next major milestone
financial year is $21.5 million
Display the environmental assessment
• Announced the preliminary design and
and concept design for community feedback in
access strategy in February 2018 and sought
second half of 2019.
community feedback
• Field investigations for concept design
and environmental assessment continued
during 2018.

Elizabeth Drive looking east toward Kemps Creek

30 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Being built

Glenbrook intersection upgrade Penrith

Grea St Marys
t We Mt Dru
stern
H ighw
ay
Glenbrook
M4

ad
n Ro
er
The North
The Australian and NSW governments are Features
upgrading the Great Western Highway and
Ross Street intersection at Glenbrook as part • New traffic lights at the Great Western
of the WSIP. Construction on the Glenbrook Highway and Ross Street intersection with
intersection upgrade started in June 2018. pedestrian crossings
The Glenbrook intersection upgrade will improve • Right turns permitted from Ross Street onto Project snapshot
safety and access along the Great Western the Great Western Highway
Project value: $5 million Elizabe
Highway, while enhancing the primary gateway • Closing general traffic access to the Great th Driv
e
to Glenbrook Village. Western Highway from Hare Street (south), Construction contractor: RD Miller Pty. Ltd
while maintaining access for emergency vehicles

Th e N
Start of construction: June 2018
• Extending the existing right turn lanes on
the Great Western Highway, allowing for th

or
Expected to be open to traffic:
e End 2018
more vehicles turning right into Ross Street

rn
and Hare Street (north) Australian Government contribution:

R
oa
50 per cent Bringelly
• New signage, line marking and R oad

d
footpath connections. NSW Government contribution: 50 per cent

ay
W
Leppington

y
lle
Va
n
de
m
Ca
Oran
Park

Na
re 31
llan
Ro
Scoping and Announce Display Project Detailed Award Building started Open to
investigation preferred environmental approval design contract traffic
option assessment

Progress
• Contract for work awarded to RD Miller Pty. Ltd
on 7 April 2018
• Work commenced on 12 June 2018
• During the 2017/18 financial year $1.2 million
was spent
• Forecast expenditure for 2018/19 financial year
is $3.9 million
• Utility work adjustments began 20 June 2018.

Next steps
Open to traffic October 2018.

Wascoe Street, Ross Street and Great Western Highway intersection at Glenbrook.

32 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Local Roads Package

The Australian Government is Round One Projects The last of the upgraded intersections opened to
traffic in September 2016, significantly improving
funding the $200 million Local Roads traffic flow for motorists travelling in and around
Package to support local councils to The Northern Road and
Cabramatta, Canley Heights and Fairfield West.
Erskine Park Road Study
deliver road improvement projects.
Penrith City Council was granted $1.1 million to Wetherill Street upgrade
This gives councils an opportunity to enhance carry out a traffic, safety and scoping study Fairfield City Council was granted $8.2 million over
local transport connections in western Sydney. to identify issues and options to upgrade two years to upgrade Wetherill Street, Wetherill
The Northern Road, Orchard Hills/South Penrith Park between Polding Street and Victoria Street.
Eligible councils are Liverpool, Camden, and Erskine Park Road, Erskine Park. This project
Wollondilly, Campbelltown, Penrith, Fairfield is now complete and has resulted in Penrith The upgrade duplicated Wetherill Street to a
and Blacktown. Council being successful in obtaining Round 2 four lane divided road, realigned the intersection
funding for construction. of Wetherill Street and The Horsley Drive, provided
Funding is being announced progressively over
new traffic lights at the intersection of Wetherill
four rounds.
Cumberland Highway Intersection upgrades and Shakespeare streets and improved side street
• The seven projects funded as part of Round access to Wetherill Street. The upgrade opened
One were completed for $29.45 million. Funding Fairfield City Council was granted $5.8 million
over two years to upgrade the Cumberland to traffic in July 2016, and has made it easier
was provided to Fairfield, Penrith, Camden and for motorists to access key destinations in the
Campbelltown Councils. Highway intersections at Hamilton Road, St Johns
Road and John Street. The project included road Fairfield Local Government Area.
• In January 2016, $62 million was provided as widening, increasing the capacity of turning bays,
part of Round Two allocation to Fairfield, Penrith, adjustments and rephasing of traffic lights and
Camden, Campbelltown and Blacktown Councils. utility services work.

33
Local Roads Package

Eagle Vale Drive upgrade Argyle Street/Camden Valley Way Round Two Projects
Campbelltown City Council was granted upgrade study – Stage 2
$12.01 million over two years to upgrade Eagle Vale Camden Council was granted $150,000 for a Smithfield Road upgrade
Drive, between Badgally Road, Blairmount and study to identify future road improvements along Fairfield City Council was granted $16.4 million to
Raby Road, Eagle Vale. Camden Valley Way between the Camden Town upgrade Smithfield Road to a continuous two lane
A 1.7 kilometre upgrade of Eagle Vale Drive Centre and The Northern Road. two way road. The project includes a number of
between Badgally Road at Blairmount and This project is complete and has resulted in intersection upgrades and realignment of Richards
Raby Road at Eagle Vale was completed in Camden Council being successful in obtaining Road at Smithfield Road.
December 2016. Round Two funding for the upgrade of The detailed design is currently progressing.
The upgrade has increased road capacity and Grahams Hill Road and Camden Valley Way. Construction is scheduled to start in early 2019
provided safer and improved access from with completion expected in mid 2020.
residential areas to the major road network Argyle Street/Camden Valley Way/
including to the Raby Road on ramp at Macarthur Road Intersection Study Erskine Park Road and Peppertree Drive
the Hume Motorway. Camden Council was granted $50,000 to Intersection upgrade
complete option testing and prepare a concept Penrith City Council was granted $11.3 million to
Argyle Street/Camden Valley Way design to improve safety and efficiency at upgrade the existing intersection at Erskine Park
Corridor upgrade – Stage 1 this intersection. Road and Peppertree Drive to a seagull intersection.
Camden Council was granted $2.14 million This work was completed in July 2015 and has The upgrade will significantly improve road safety
over two years to construct new traffic lights resulted in Camden Council being successful and traffic efficiency. The detailed design has been
at the intersection of Argyle Street and in obtaining Round Two funding for construction. finalised and the contract has been awarded with
Oxley Street, Camden.
construction scheduled to start in September 2018
The upgrade also included replacing a marked and finish in late 2019.
pedestrian crossing with pedestrian activated
traffic lights on Argyle Street west of Hill Street,
Camden. The project was completed in August
2016 and has improved safety and access through
the Camden town centre.

34 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
Local Roads Package

Erskine Park Road and Bennett Road upgrade At the completion of the Erskine Park Road Camden Valley Way/Argyle Street – Stage 2
Penrith City Council was granted $7.5 million to intersection upgrades, Erskine Park Road will have – Macarthur Road Intersection
upgrade the intersection at Bennett Road and been widened to four lanes between Bennett Road Camden Council was granted $4.3 million to
Erskine Park Road and install traffic lights. and Explorers Way to join the existing four lane realign Macarthur Road on the approach to
section north of this location. The detailed design Camden Valley Way and install new traffic lights
The upgrade will improve road safety and has been finalised and the contract has been
traffic efficiency. The detailed design has been at the Camden Valley Way and Macarthur Road
awarded with construction scheduled to start intersection at Elderslie. Work commenced in early
finalised and the contract has been awarded with in September 2018 and finish in late 2019.
construction scheduled to start in September 2018 2018 and will be completed by late 2018.
and finish in late 2019. The Northern Road Intersections upgrade Camden Valley Way/Argyle Street – Grahams
Penrith City Council was granted $6.7 million to Hill Road and Richardson Road Intersection
Erskine Park Road and Coonawarra Drive
upgrade intersections on The Northern Road at
Intersection upgrade Camden Council was granted $4 million to
the Great Western Highway and at Derby Street.
Penrith City Council was granted $6.9 million to upgrade the intersection to include right turn bays
A roundabout will also be built at the Bringelly
upgrade the intersection at Coonawarra Drive on Camden Valley Way into Grahams Hill Road.
Road/Caddens Road intersection.
and Erskine Park Road to a seagull intersection. The project also includes traffic light adjustments
The intersections form a part of the A9 corridor
The upgrade will improve road safety and and a new shared path on the southern side of
connecting Windsor to Campbelltown via Penrith.
traffic efficiency. The detailed design has been Camden Valley Way. The work on the intersection
The upgrade of these intersections will significantly
finalised and the contract has been awarded with of Camden Valley Way and Richardson Road will
improve road safety and traffic efficiency.
construction scheduled to start in late 2018 and be completed in late 2018.
finish in late 2019. The Bringelly Road/Caddens Road intersection
was completed at the end of June 2017. Work on
Erskine Park Road and Explorers Way the Northern Road intersection upgrade at Derby
Street and Great Western Highway commenced in
Intersection upgrade
July 2018 and will be completed in mid 2019.
Penrith City Council was granted $3.4 million
to upgrade the intersection at Explorers Way
and Erskine Park Road and install traffic lights.
The upgrade will improve road safety and
traffic efficiency.

35
Local Roads Package

Raby Road from Eschol Park Drive


to Stranraer Drive scoping study
Campbelltown City Council was granted $655,000
to carry out traffic, safety and scoping studies to
identify issues and options to upgrade Raby Road
from Eschol Park Drive to Stranraer Drive.
The study was completed in March 2017 and
Council is now progressing concept designs at
two intersections; Raby Road/Eagle Vale Drive
and Raby Road/Spitfire Drive. Council is proposing
to seek construction funding as part of its
Round Three project proposals.

Bungarribee Road and Flushcombe Road


signalisation scoping
Blacktown City Council was granted $526,000
to develop options and complete preliminary
investigations for safety and efficiency
improvement at this intersection.
The detailed design of the selected option was
completed in late 2017.

Porrende Street upgrade scoping


Camden Council was granted $120,000 to
develop options and complete a detailed design
for Porrende Street between The Northern Road
intersection and Grahams Hill Road. The detailed
design was completed in August 2017 and Council
will be seeking construction funding as part of its Camden Valley Way/Macarthur Rd Intersection upgrade – Preparation work for utility adjustments on
Camden Valley Way eastbound.
Round Three project proposals.

36 Western Sydney Infrastructure Plan | 1 July 2017 – 30 June 2018 Report Card
37
The Northern Road southbound, south of Hillside Drive

For further information about the Western Sydney Infrastructure Plan visit the interactive digital portal

www.rms.nsw.gov.au/WSIP wsip@rms.nsw.gov.au Roads and Maritime Services


PO Box 973
Parramatta NSW 2124

Western Sydney Infrastructure Plan 1 July 2017 – 30 June 2018 Report Card
RMS 18.1053
ISBN: 978-1-925797-95-4

You might also like