ROP calculation

Supply Chain View


A closer look at the supply chain www.supplychainview.com

Reorder point example calculations V1.0


Enter values for the parameters in the yellow cells below.
For more information see http://www.supplychainview.com/blog/?p=88

Forecast demand 5 units per week


Supplier lead time 4 weeks
Review time 1 weeks
Process lead time 0 weeks
Planned order size 5 units
Safety stock 10 units

Effective lead time 5 weeks


Lead time demand 23 units
Reorder point 33 units
Order up to 38 units

Stock on hand 8 units


Stock on order 16 units
Back-orders 0 units

Effective stock 24 units

Place an order? Yes


Order size 14 units