Summary
This proposal documents an initial program design with associated costs and schedule. The
outputs include manuals, procedures and policies to allow GIZ to roll out the entire program
not only in ARMM but anywhere in the Philippines with ASDSW or other partners.
Also included in this process is working with Fit for Schools so as to validate at a ground level
the roll out of their EHCP program along with efforts to raise WaSH awareness within DepEd,
local government and most importantly schools and communities.
1. Objective
2. Outputs
3. Preliminary Designs of Planning and Stakeholder Workshop
3.1 Stakeholder Workshop
3.2 School Planning Process
4. Implementation Methodology
4.1 Construction and Supervision
4.2 Sustainability Mechanisms
5. Work and Financial Plan
1. Objective:
Pilot Sanitation facility upgrade program in ARMM schools. To design a program that is effective,
economic and replicable by any organization in any area.
2. Outputs:
Pilot in 20 schools
Planning session in school to:
o Validate EHCP (Essential Health Care Program)
o Identify needs per school
o Plan implementation
o Mobilize local counterpart
Implementation of Repairs/New Facilities
o Material purchase and supply
o Setting up organization to produce rings for septic system
o Delivery and accountability mechanisms for material delivery
o Skilled and bayanihan labor organization
o Supervision and check list sign off
Consolidation
o Supply of cleaning supplies for start up
o School orientation policy and procedure start up (2 day sustainability Program)
o Referral system
o Manuals
o Desludging and sludge processing back up
o Region wide WaSH day to solidify institutionalization
Program Development
Detailed design
o Planning session
o New Facility design and BOM
o Supervision documentation
o 2 days sustainability program
o Program overview documentation
Stakeholder Inclusion Mechanisms
o Project start up and feed back workshop
Overview of project steps with feedback from pax
Detailed review of planning steps
Facility Design feedback
Role review for Pax
Pax
GIZ
FIT
ASDSW
DepEd ARMM
PWTF
BDA
o Progress Reporting
o Inclusion in Pilot Evaluation workshop
Manualization
o Process Manual for roll out by any organization
Planning workshop and documentation
Purchasing and delivery documentation
Construction and supervision/Quality control documentation
Consolidation and Monitoring
o Operation and Maintenance Manual for schools
o Sanitation addition to EHCP manual
Pilot Monitoring Evaluation Accountability and Learning process
o Base line and key indicator design
Meeting the needs
Appropriateness of intervention
Use and behavior change
Program implementation
Cost of Implementation (ROI)
Logistical evaluation
Counterparting value
Evaluation of Manuals
o Workshop for stakeholder feedback based on MEAL.
o Updating of manuals
3. Preliminary Designs of Planning and Stakeholder workshop
Output
Identified work needed
Work Plan and role definition
Preliminary work
DepEd and School coordination
o Schedule
o Preparation of children and teachers
Community and Local stakeholder coordination
o Orientation and invitations
FIT coordination
Planning
The planning process will determine the scope of work as well as the responsibility that will be taken by
the community and school for construction. ASDSW will then facilitate the purchase and delivery of
materials, supervision of construction and quality control checks.
Design Issue
Note that the main issue that needs to be resolved is the design of the new toilet block. This needs
official approval by DepEd ARMM so that the schools will accept the design and there may be a need for
it to be adaptable for local conditions.
The engineers would be tasked to ensure that the quality of construction meets standards, ensure
material delivery is on time, trouble shooting and overall supervision. Check lists for construction and
repair would be maintained for the project.
The Planning Mechanism is the initial key to raise demand for implementation and planning
construction. However with completion of the facility there is a need to ensure that responsibility for
the upkeep of the facility is taken over by the appropriate mechanisms. Note that schools are difficult as
children, parents and teachers are transitory as children move through the education system. There is a
need to institutionalize WaSH within the system.
Manuals
Table of Contents would include:
1. Introduction to the facilities involved
2. Daily, weekly and monthly maintenance routines
a. Checklists
b. Who is responsible
c. Materials and tools
3. Maintenance and troubleshooting
4. Desludging and Sludge processing
5. Referral system for outside assistance
Engagement of all Local Stakeholders in the Process
This process is to transfer responsibility to the local community. This is a two day workshop that would
include:
Teachers
Children
School Maintenance Staff
School Admin staff
BLGU/MLGU (WaSH Task Force or WaSH related officials)
Parent Teacher Association
Local informal leaders
The Manual would be the basis of this where site specific items can be added based on the workshop.
DepEd Institutionalizing
For each region once the construction is completed a one day centralized activity ie. WaSH in Schools
day would be held. This is where teacher/children representatives would gather with key DepEd ARMM
and other key LGU officials. The work done would be presented along with the sustainability plans. This
allows DepEd to acknowledge the work done and commit to support the installed infrastructure.
This is also another venue for awareness raising for WaSH in schools and support to the EHCP work that
is ongoing.
5. Work and Financial Plan
ID Task Outputs Expenses Costs Staff Vehicle per Mngt workshop materials local
fees diem travel labor
TOTAL 3380150 1192000 632000 58750 106400 246000 1010000 135000
2 FA and Project design agreed Flights for ASDSW 19200 19200
Agreement management 2
Negotiation round trips manila
with
accommodation
Proposal completed
FA signed
First Tranche invoiced
6 Detailed Stakeholder 2 staff 10 days 70000 70000
design of Workshop sessions
Planning and materials
and Planning workshop
Stakeholder Sessions and materials
workshops
All Program Staff
Oriented and included
in project
Project Site visits and 2 staff 10 days 70000 70000
initial organization
with teachers
Base line data Vehicle 10 days 40000 40000
gathered
Perdiem 5000 5000
7 Stakeholder Invitations, Venue 4 staff 5 days 70000 70000
workshop materials
preparation Vehicle 2 days 8000 8000
Materials 10500 10500
ID Task Outputs Expenses Costs Staff Vehicle per Mngt workshop materials local
fees diem travel labor
8 Stakeholder Workshop for 30 Participant costs, 60000 60000
Workshop participants plus Venue, meals,
ASDSW Staff. accommodation
Assuming Cotabato
City
ASDSW mngt travel 34000 34000
9 Completion Update design based 6 staff 4 days 72000 72000
of Planning on workshop
design,
Complete 1 vehicle 4 days 16000 16000
material
arrangements with
purchase,
schools
coordination
Material preparation 20 schools * 2000 40000 40000
Logistical preparation
10 Planning Planning and 6 staff 10 days (3 210000 210000
Workshops implementation plans teams)
20 schools complete for all 20
schools
Includes consolidation 3 vehicles 10 days 120000 120000
of results
Per diem staff 15000 15000
12 Constructio Implementation of the Construction 800000 800000
n and Repair repairs and new Materials estimated
toilets at 40,000/school