MANPOWER SCHEDULE (CANTILEVER RETAINING WALL)

MANPOWER

Heavy
Safety Unskilled SUB-
MONTH WEEKS Project Manager Site Engineer Foreman Skilled Laborer Steel Man Equipment
Officer Laborer TOTAL
Operator

1 1 1 10 12
2 1 1 1 1 10 14
MONTH 1
3 1 1 1 1 10 14
4 1 1 1 1 10 14
5 1 1 1 5 10 18
6 1 1 1 5 10 18
MONTH 2
7 1 1 1 8 12 1 24
8 1 1 1 8 12 1 24
9 1 1 1 8 12 5 1 29
10 1 1 1 10 12 5 1 31
MONTH 3
11 1 1 1 10 12 5 1 31
12 1 1 1 10 12 5 1 31
13 1 1 1 10 12 5 1 31
14 1 1 1 10 12 5 1 31
MONTH 4
15 1 1 1 1 10 12 5 1 32
16 1 1 1 1 10 12 5 1 32
17 1 1 1 1 10 12 5 1 32
18 1 1 1 1 10 12 5 1 32
MONTH 5
19 1 1 1 1 10 12 5 1 32
20 1 1 1 1 10 12 5 1 32
21 1 1 1 1 10 12 5 1 32
22 1 1 1 1 10 12 5 31
MONTH 6
23 1 1 1 1 10 12 5 31
24 1 1 1 1 10 12 5 31
25 1 1 1 1 10 12 3 29
26 1 1 1 1 10 15 29
MONTH 7
27 1 1 1 1 10 15 29
28 1 1 1 1 10 15 29
29 1 1 1 1 10 15 29
30 1 1 1 1 10 15 5 34
MONTH 8
31 1 1 1 1 10 15 5 34
32 1 1 1 1 10 15 5 34
33 1 1 1 1 10 15 5 34
34 1 1 1 1 10 15 5 34
MONTH 9
35 1 1 1 1 10 15 5 34
36 1 1 1 1 10 15 3 1 33
37 1 1 1 1 10 15 1 30
38 1 1 1 1 10 15 1 30
MONTH 10
39 1 1 1 1 10 15 1 30
40 1 1 1 1 10 15 1 30
41 1 1 1 1 10 15 5 1 35
42 1 1 1 1 10 15 5 1 35
MONTH 11
43 1 1 1 1 10 15 5 1 35
44 1 1 1 1 10 15 5 34
45 1 1 1 1 10 15 5 34
46 1 1 1 1 10 15 5 34
MONTH 12
47 1 1 1 1 10 15 29
48 1 1 1 1 10 15 29
49 1 1 1 1 10 15 1 30
50 1 1 1 1 10 15 1 30
MONTH 13
51 1 1 1 1 10 15 5 1 35
52 1 1 1 1 10 15 5 1 35