Professional Documents
Culture Documents
Fig. 2 : The Simple for Dead Load and Continuous for Live
Load System (Source: Ref. 7)
Acrow Panel Bridging System, also known as the for wider bridges. An example of bridge using this
700XS® System, is a light bridge composed of system is shown in Fig. 6.
large orthotropic deck units and tall truss systems.
The trusses of this type of bridge are 50% taller than
alternate panel bridges and provide 50% greater
bending strength and 20% greater shear strength.
An example of an Acrow Panel Bridge is shown in
Fig. 5.
Fabrication of the folded steel plate girder at the 12.5 mm thick plates (A709 Grade 50 steel) using break
factory involves the following five simple steps: press (Fig. 8). This operation takes approximately
Cold bending the steel plates: Cold bending of 10 to 2-3 hours.
Fig. 8 : Cold Bending of Plates to the Required Shape Using a Break Press (Source: Macey, 2015)
Installation of necessary hardware: Welding of Installation of shear studs: welding shear studs may
bearing stiffeners, sole plates and bolting of flange take about a day (Fig. 10).
separators, which takes approximately 1-2 days
(Fig. 9).
Corrosion protection of the girders: Corrosion to add removable, galvanized bird screens to the open
protection may be provided either by hot-dip bottom of the FSPG girders, which will allow easy
galvanizing, metalizing, or painting (Fig. 11). inspection of the girders while still keeping birds and
The galvanizing has a guarantee of 25 years and other critters from nesting inside the bottom flanges.
reduces maintenance over that time frame-to a level Instead of such measures, weathering steel could also
equivalent to or better than that of concrete. It is better be used to prevent corrosion.
Typically, a 12 m long folded plate girder with The FSPG bridge system has the following advantages
precast deck will weigh about 10,900 kg. Hence, in its design and construction (Azizinamini, 2009 and
a relatively lightweight crane can be used at the Stockhausen, 2017):
construction site to lift and place them in position, 1. The inverted tub shape is a stable bridge girder
on elastomeric bearing pads, placed over existing configuration during fabrication, shipping, and
abutments, as shown in Figs. 7(b), 7(c), and 14. Each erection. It also does not require internal or
composite girder could be erected at site within an external cross frames for either local or global
hour. stability. Flange separators provided at regular
intervals, brace the bottom flanges and transmit
lateral loads. Elimination of cross frames
reduces the cost considerably. As welding is
minimized, fatigue and fracture observed in
older steel bridges, is not a concern. In addition,
only conventional equipment and practices are
used for the casting of concrete.
2. The weight of the girders are approximately 1/3
the weight of concrete beams. The system uses
less steel by weight compared with typical ABC
steel stringer construction. Shipping weight and
length reduce hauling permits.
Fig. 14 : Erection of Composite Units Over Existing Abutments
(Source: Macey, 2015) 3. The top flange of this system is wide enough
(about 625 to 890 mm) to serve as a work
A typical two-lane county type bridge will require
platform, and help to reduce construction
three such folded girder sections placed side-by-
hazards associated with workers walking on
side and connected longitudinally, as shown in
girders during construction.
Figs. 14 and 15. These side-by-side placed FSPG
sections are connected using cast in place closure 4. The system requires only smaller work force and
pours between the concrete slabs as shown in Fig. 15. uses smaller capacity cranes. Hence the overall
Completion of closure pours take approximately 2 cost is competitive with other ABC construction
hours per joint (Macey, 2015). types.
The folds in the plates are kept uniform while the 5. Box girder bridges are very efficient systems and
thickness (10 mm or 12.5 mm) and their cross- used already in spans longer than 90 m. The box
sectional dimensions are varied depending on the span sections used in such long span bridges are deep
of the bridge. Different top and bottom flange widths and hence facilitate internal inspection. However,
or web depth are obtained just by changing the bend in short-span bridges, the required depth of the
locations. Hence it is possible for the fabricators to box is so small that it prohibits crawling inside
fabricate the girders for any span from just two plate the box for inspection. This is one of the reasons
thicknesses. for not using box girder bridges for short-span
2. A 17.68 m span Primrose East Bridge, in Boone Bridge Systems was also able to reduce the total
County, Nebraska was constructed in 2014. production time for the Pennsylvania bridges to
Four pre-topped folded steel plate girders were as little as 14 weeks, including steel procurement
erected in just two hours. Closure pours of ultra- (Stockhausen, 2017).
high performance concrete (UHPC) were used,
University of Massachusetts Amherst (UMass)
3. A two-lane, 15.2 m bridge near Bradford, instrumented and monitored the performance of the
Pennsylvania was erected in October 2016 in bridge at Uxbridge since construction for twenty
less than three hours. Closure pours of this bridge months, with load testing and also did analysis
took only a few days, which enabled the bridge to present an independent evaluation. Field data
to be reopened in 30 calendar days, five days obtained were compared with 2D hand calculations
ahead of the accelerated, five-week schedule as well as the results obtained from SAP- 2000 and
for the project detour. This is a full month faster ANSYS finite element models with 3D effects and
than it would have taken for a conventional cast- nonlinear soil-structure interaction (Civjan, et al.,
in-situ construction (Stockhausen, 2017), and 2014). Stresses in concrete and steel components were
4. The bridge in Lewiston, Pennsylvania was found to be within expected ranges of values during
opened to traffic just two weeks later in 2016, the service-level loads. Long term data collection and
and it took only 2½ hours for the erection. CDR truck load testing indicated a conservative design of
100 Volume 47 │ Number 1 │ March 2017 The Bridge and Structural Engineer
this innovative structure. Through the first two years to the FSPG system, either hot-dipped galvanized
of service, no signs of distress were noted and readings or weathering steel could be used. Once the shape
were within the expected range of bridge behavior. has been formed using press brakes, shear studs are
Based on this study, the FSPG system was found to welded to the top flanges. A reinforced concrete deck
be an effective system for accelerated construction of is then cast on the girder in the fabrication shop and
short span bridges (Civjan, et al., 2014). allowed to cure, and the composite modular unit is
3. The Press-Brake-Formed Tub Girders transported to the site. These standard modules are
System longitudinally joined at the site using ultra-high
The Press-brake-formed tub girder system is similar performance concrete (Michaelson and Barth, 2017).
to the FSPG system, except that the steel trapezoidal Unlike FSPG system, it is a closed system, since the
section is placed in the reverse direction as compared girder is closed at the bottom and hence has increased
to the FSPG system, as shown in Fig. 17. Similar torsional stiffness.
The system offers several advantages and they are EVRAZ North America) as well as computer analysis
also similar to the FSPG system: (1) The girder itself using FEM modeling were carried out.
is simple to fabricate, requiring minimal welding, (2) Unlike the FSPG system, the press-brake-formed tub
Because of the system’s modular composite design, girder system is an open source. The Short Span Steel
there is a reduced need for additional details such Bridge Alliance has developed standardized plans
as stiffeners or cross-frames, and (3) The composite using standard plate sizes (widths of 1.50, 1.82, 2.13,
unit can be easily shipped to the bridge site, allowing 2.44, 2.74, and 3.00 m). The designs were developed
for accelerated construction and reduced traffic to achieve maximum structural capacity. Press-brake-
interruptions. formed tub girders are versatile for multiple-deck
While modular precast concrete decks are options. They can be used for both tangent and skewed
recommended, multiple deck options are available. configurations, as well as simple and continuous
Examples include the use of full-depth/partial-depth spans. They are recommended for single spans up to
precast concrete deck panels, cast-in-place concrete 18 m. Spans may be spliced together to form a multi-
decks, or more advanced composite decks such as span bridge greater than 18 m.
the Sandwich Plate System (a structural composite The Amish Sawmill Bridge located in Fairbank, Iowa
material comprising two metal plates bonded with is the first Press-brake-formed tub girder steel bridge
a polyurethane elastomer core). Extensive research in the USA and was opened to traffic on 8th January
and development work on this system was carried out 2016 (see Fig. 18). Researchers from West Virginia
at West Virginia University. Based on this study, for University, Marshall University, and the University of
each standard plate width and thickness, an optimum Wyoming monitored and studied the field performance
depth of girder was obtained (Michaelson and Barth, of this bridge. Two more press-brake-formed tub
2017). To verify the performance and capacity of the girder bridges are scheduled for construction in West
system, three years of testing (on eight press-brake Virginia (Michaelson and Barth, 2017). This system
tub girder specimens donated by Nucor Corporation, offers significant cost savings, ease in shipment and
SSAB Americas, United States Steel Corporation, and fabrication, accelerated construction and design
The Bridge and Structural Engineer Volume 47 │ Number 1 │ March 2017 101
versatility, and has the potential to replace numerous References
short span bridges in future.
1. Azizinamini, A. (2009). “A New Era for Short-
Span Bridges.” Modern Steel Construction,
American Institute of Steel Construction (AISC),
Sept., 2 pp. www.aisc.org/globalassets/modern-
steel/archives/2009/09/2009v09_new_era.pdf
2. Azizinamini, A. (2014). “Simple for Dead
Load--Continuous for Live Load Steel Bridge
Systems,” Engineering Journal, AISC, Vol. 51,
2nd Quarter, pp. 59-82.
Fig. 18 : The Amish Sawmill Bridge, Buchanan County, Iowa 3. Civjan, S.A., Sit, M.H., and Breña, S.F. (2014)
(Source: Ref. 7) “Field and Analytical Studies of the First Folded
Plate Girder Bridge”, Transportation Research
4. Conclusions Board 2014 Annual Meeting on Celebrating Our
The Modular Steel Bridge Task Group formed by Legacy, Anticipating Our Future, Washington,
the Short Span Steel Bridge Alliance has developed D.C., Jan.12-16, 19 pp.
several alternative bridge systems to meet the
4. Macey, M.J. (2015), “Folded Steel Plate Girder
needs of the industry, including Accelerated Bridge
System-Applications in Accelerated Bridge
Construction (ABC). Out of these solutions, the
Construction”, AASHTO SCOBS Technical
technology of folded steel plate girders is appealing
because it offers significant cost savings, ease of Committee for Construction (T-4) Presentation,
shipment and fabrication, accelerated construction, Annual Meeting, Apr. 21. http://bridges.
design versatility, and sustainability. In addition to transportation.org/Documents/2015%20
their reduction in weight, their life-cycle costs are SCOBS%20presentations/Technical%20
also competitive. As steel is the world’s most recycled C o m m i t t e e / T- 4 % 2 0 P r e s e n t a t i o n % 2 0 7 _
material, at the end of useful life of these bridges, they Matthew%20Macey_FSPG%20-%20CDR%20
may be transformed into other steel products. With so Bridge%20Systems.pdf
many benefits, this technology provides the potential
5. Michaelson, G.K., and Barth, K.E. ( 2017),
for accelerated bridge construction, not only in USA
but also throughout the world, and may solve the “A New Shape for Short Span steel Bridges”,
challenge of replacing aging critical infrastructure. Structure Magazine, NCSEA/CASE/SEI of
Naturally, several state Departments of Transportation ASCE, Mar. 2017, pp.26-29.
in USA have already expressed interest in building 6. Stockhausen, T., “A New Take on Plate Girders”,
such steel tub girder bridges in their jurisdictions. Modern Steel Construction, AISC, Vol. 57, No.1,
5. Acknowledgements Jan. 2017, pp. 56-59.
The photos used in this paper were adopted from the 7. http://www.shortspansteelbridges.org/steel-
references given below. solutions/systems.aspx
102 Volume 47 │ Number 1 │ March 2017 The Bridge and Structural Engineer