You are on page 1of 3

Mapping the Future State

A Future State Value Stream Map helps with the larger process of developing your Lean Manufacturing
Strategy. It requires significant knowledge of Core Disciplines and other specific topics. Designing a Fu-
ture State requires more art, engineering and strategy than Present State mapping. On this page, we
show mapping, but the background knowledge is in these other parts of our site.
Cellular Manufacturing
Takt Time
Kanban
Setup Reduction
Implementing
Kaizen
Group Technology
Lot Sizing
Here, we use the example from our page on Present State Mapping. After constructing the Present State
Map, follow steps 1-7. The map below shows the final results. Note the large improvements in Lead Time,
productivity and inventory reduction. You can expect much discussion about details of implementation
and feasibility of various options. This is normal. Our goal, here, is not to decide every detail of the de-
sign. Rather, it is to establish general feasibility.

1.Calculate Takt Time


Takt time is the average time between production units necessary to meet cus-
tomer demand. We use the available time divided by the required number of
units. From the example

2. Identify Bottleneck Process


The bottleneck process is the operation with the longest
cycle time. In the example, this is machining at 44 seconds.
The bottleneck is important because it:
Determines total system output.
Becomes the primary scheduling point
A work balance chart (figure) is helpful for steps 2 and 3.
Cycle time is plotted on the vertical axis for each opera-
tion.

3. Identify Lot Sizing/Setup Opportunities


Present lot size is 1000 pieces, about two day's production. This requires at least 3-6 days finished goods
and prevents daily adjustments to mix or demand. If the lot size were simply cut, it would allow faster
response but additional setup time in machining would use available time. Machining could not meet the
average customer requirements. However, if a focused setup reduction is made on machining and setup
becomes 20-30 minutes, a batch size of 500, or even 250 is feasible. The mapping team established this
as a goal, noted by a Kaizen Burst.
Future State Value Stream Map
4. Identify Potential Workcells
The balance chart shows cycle time for each of the five process steps. Machining and honing operations
are closely balanced. cycle times for clean/deburr, inspection and packaging are quite short in compari-
son.
The very short cycle times for clean/deburr and packaging
might normally preclude them from a workcell since utiliza-
tion would be low. However, inspection and packaging are
manual operations that require little more than a workbench
and hand tools. High equipment utilization is not critical.
The clean/deburr process is run on specialized, high-speed
equipment in a central area. If clean/deburr can be scaled
down as a manual or semi-manual operation, it can go in
the cell. This seems feasible and the team accepts that,
somehow, it will be done. It appears that three operators
can run the cell. This is not a precise calculation. It only
considers present cycle times and ignores setup.
However, for a variety of reasons, 2-3 operators is probably feasible. Workcells are lot more involved than
suggested here. However, our purpose is not to finalize details but make reasonable guesses about the
general configuration. A Kaizen Burst identifies a need for more work.

5. Determine Kanban Locations


With a workcell for five processes, scheduling between them becomes a trivial case. They will be
directly linked with continuous or small-batch flow. Kanban, internal to the cell, is unnecessary or be-
comes part of the detailed cell design.
Kanban does apply at two other locations:
Between cell and supplier
Between cell and customer
The detailed design of the kanban system is shown as a Kaizen burst. Inventory levels are current best
estimates.

6. Establish Scheduling Methods


Kanban and direct links now schedule all operations short term. Both the workcell and the supplier, how-
ever, need forecasts to plan staffing and possible changes in inventory levels. The map shows this
monthly information flow.
Purchasing must arrange for payment. They intend to do so with monthly blanket orders, also shown.

7. Calculate Lead and Cycle Time.


The final step in the Future State Map is to complete the timeline at bottom, and calculate Lead Time,
Cycle Time and Work Time.

Results
In this example, the mapping team estimates a Lead Time reduction of 85% and a productivity increase of
25%. Inventory will decrease about 85%. Many additional, but unpredictable benefits are also likely.

You might also like