Billing plan

In SAP SD a billing plan is a schedule of individual billing dates for a single item in a sales document.
You can define a billing plan at header level, which is then valid for all items assigned to it.Depending
on the kind of business process you are carrying out, the system can automatically propose the billing
plan.
Types of billing plan SAP
SD has two billing plans a.
Periodic billing Plan
b. Milestone billing Plan
When to Use Periodic billing plan: -
Periodic billing plans are used for service products such as rentals or maintenance mostly. You should
have a service product with a time-dependent price (i.e. calculation type M, N, O or P) which need to
be billed regularly, e.g. monthly, quarterly, etc. Client can raise the rental or maintenance/service
invoices based on monthly, quarterly, yearly etc. basis to their customers.
NOTE: - The sum of every line item added to the Net the value of the contract.
Example– One service contract being billed on monthly basis. Start
date -27.08.2015
End Date – 26.10.2015
Settlement from Settlement to Billing date Billing Value
27.08.2015 26.09.2015 27.08.2015 100 MYR
27.09.2015 26.10.2015 27.09.2015 100 MYR
From the above example value of the contract will be 200 MYR.
When to Use Milestone billing plan: -
Milestone billing is used for sales products in big projects when the product is paid in various
installments. Milestone billing plans are used in sales quotations and sales orders or Items in service
orders. You have a sales product with a known net value.
NOTE: - You distribute the net value over several milestones.
Example- One sales order created having value 200 MYR.
Value of 200 MYR will be distributed among various dates (% or amount) as per the configuration.

Billing Date Description Billing Value


27.08.2015 Phase -I Completion 50 MYR
27.09.2015 Phase -II Completion 100 MYR
27.11.2015 Phase- III Completion 50 MYR
From the above example value of the sales order will be 200 MYR.
Configuration steps for Periodic billing plan 1. Define Billing Plan Types
Spro > S&D >Billing >Billing Plan
Maintain billing plan types for periodic billing
A. Start date: - Date from which billing plan will start. Start date is compared with next billing date(5)
and gives first date of “Settlement To” and “Billing date” in periodic plan. ie. If your start date is the
24rd of a month and you are billing monthly, all billing date will start on the 23rd” (if there are no
further conditions discussed in the later part of the document). B. End Date: - Date on which billing
plan ends. Screen shot from rental contract header.
C-horizons :- This is optional field .If there is no End date entered or Contract end date is far in the
future . Not all billing dates can be accommodated in the billing date screen. The horizon calculates
the last billing date in the billing plan, based on the current date plus a specified time period.
Example-
If the rental /service contract which is valid from 24.08.2015 until 23.12.2098 .
Before: Rental contract with no Horizon
Screen 1 – End date far in future
Screen 2 – No Horizon period
Screen 3 – Billing dates created up to 2098 .
After : Rental contract with Horizon
Screen 1 – End date far in future
Screen 2 – Horizon period

Screen 3 – Billing dates created only up to Horizon period.(Only for current quarter ).
Note : – Schedule a back ground job for RVFPLAN01(T-code V.07) to create the future billing date
for the given horizon period.
D. Dates From To : – These date has meaning when item level has certain validity . Billing plan
will be deactivated after validly expired on item level.
Example- Rental contract has two line Items.
Item 10- Header plan- validity from 27.08.2015 Until 26.08.2016 . (Billing dates created up to
26.08.2016)
Item 20 Item level Dates from – 27.08.2015 to Dates Until 26.09.2015 .So Item second has validly
only until 26.09.2015.(Billing dates created up to 26.09.2015)
E. Rule for Origin of Next Billing/Invoice Date :- This is copied from customization , The rule
assigned here is compared with start date and billing dates are proposed in the contract.Please refer
to point number A.
F. Rules for determining deviation in Billing/Invoice date :-
This field determines if there is exception or deviation in billing dates proposed by billing rule .The
customer is to be billed retrospectively for the rental of a photocopier at the end of every month. The
customer, however,wants to be billed two days before the end of each month. You enter a date
determination rule, which subtracts two days from the billing date determined by the system.
Example :- Your client is billing the customer at the end of every month. Client wants to bill the
customer 2 days before end of the month. With deviation rule you can force system to calculate
billing date before or after deviation days .
Before : No data maintained for deviation rule

After : Maintained billing deviation rule ( 2 days before month end ) Billing
date is 2 days before compared to other screen above .
G. Days in year/Days in Month :- Give number of days in year or months if rental contract has
to be billed for given number of days in month or days in year.
H. Autom. Date Creation in Billing/Invoicing Plan Maintenance:-Mark this (X) if you want
system to propose billing /invoice dates automatically . Leave it blank if you want to enter the billing
date manually .
Before : If you do not check (X)
After : If you do check (X)

I. Billing/Invoice Creation in Advance :- Check (X) this field if you want to system to
propose advance billing date (rental on 1st date of the months ). Example – Client has
retroactive rental contract with customer Before Check- Rental contract 1 yr.
01-01-2015 to 31-01-2015 .System proposing billing date on 31-01-2015 .

After check (X)- Rental contract 1 yr.


01-01-2015 to 31-01-2015 .System will propose billing date on 01-01-2015.
J. Automatic creation of correction dates in Billing Plan :- If this field is checked (X) ,
system can determines if correction date has to be proposed .
Logic – if End date of or To date changed and it falls before the last billed date , System propose a
correction date and correction amount automatically

Example – In the below screen customer was billed for the period of billing Plan dated 01.07.2015
until
31.07.2015 for 100 Euro . But later contract was foreclosed dated 25.07.2015.Credit issued to the
customer for the period of 26.07.2015 to 31.07.2015
2. Define Date Description:-
Date descriptions are defined to describe the various purposes for which billing Plans can be
used.This is only for description only. It has no effect in transaction.
Path – Spro> S&D >Billing >Define Date Description
3. Define and assign Date Category:-
Path – Spro> S&D >Billing >Define and assign Date Category Date category
has following information. i. Billing Plan type- Periodic billing ii. Date category –
Its free text iii. Date description – Date description proposed as maintained in

previous step. iv. Billing Rule – assign the billing rule to period billing .
v. Pricing – If you want to carry out new pricing at the time of billing.
vi. Billing Type- This is the default billing type proposed at the time of contract creation in billing Plan.
4. Allocate date category :- Assign the date category to billing plan
5. Assigning Billing Plan Types to Sales Document Type:- This assignment will tie sales
document type with header periodic billing plan.

This is the last section of the documentation for periodic billing plan.Please proceed with T-code
va41 and test on different scenarios .

Related Sap Notes :-


1112798 – FAQ note billing plans
499688 – FAQ: Ending an invoicing plan / restricting date period
537779 – Date generation for Periodic Invoicing Plans Related user exits for billing plan
Related Exits :-
BILLING_SCHEDULE_DELTA
USEREXIT_MOVE_FIELD_TO_FPLT