EXM CEUTICALS PROJECT DAILY WORKPLAN

WORK EXECUTED TODAY TUESDAY 10TH July 2019

Demolition and creating provision for plumbing works at 98%


Skimming of Kitchen/Dressing Rooms at 30%.
fixing gypsum boards on walls at 95%.
Fixing pipes at 65%
Fixing gypsum board on ceiling at 100%

CHALLENGES FACED TODAY WEDNESDAY 11th July 2019


No Mjor problems encountered

WORK PLANNED FOR WEDNESDAY 11th July 2019


Item Activity Tools and materials PPE Manpower Duration Comment

Excavating trench for


1 pipeworks and Sledge hammer, grinder, Helmet, Gloves, Obwona, Walter 8:15am -5:30pm
creating provision for chisel, hammer Boots
shower tray

Fixing Toilet Wall Helmet, Gloves, Ronald,Gilbert,


2 Drill, screws, scaffold Steven, 8:15AM -9:00AM,
frames Boots Masks, Onesmus

Fixing gypsum on the Drill, Drill bits, screws, Helmet, Gloves, Ronald,Gilbert,
3 Steven, 9:00am -1:00pm
Toilet wall concrete nails Boots Onesmus

Daniel, Lukaka to
be joined by
4 Scheminig Tape, Plaster, scrapper, Helmet, Gloves, Ronald,Gilbert, 8:15am -5:30pm
steel float Boots Steven, and
Onesmus at
2:00PM

5 Electrical works Electrical equipment Helmet, Gloves, Bonnie, 8:15am -5:30pm


Boots Electrician

6 Plumbing works Drill, Drill bits, screws Helmet, Boots, Micheal, Ascari 8:15am -5:30pm
Gloves
WORKLOAD TABLE
Job 1 2 3 4 5 6 Total
Daniel 8.25 8.25
Michael 8.25 8.25
Onesmus 0.75 4 3.5 8.25
Electrician 8.25 8.25
Bonnie 8.25 8.25
Ronald 0.75 4 3.5 8.25
Obwona 8.25 8.25
Steven 0.75 4 3.5 8.25
Walter 8.25 8.25
Gilbert 0.75 4 3.5 8.25
Askari 8.25 8.25
Lukaka 8.25 8.25

ACTIVITY PHOTOS
Figure 1 Scheeming ongoing Figure 2 Close look at the scheemed joint

Figure 3 Fixed Ply wood boards to receive the shower mixer Figure 3 Fixing Gypsum board to wall at the mens dressing room
Figure 3 Cteating provision for the shower tray at the mens toilet side Figure 3 Connected Wash hand basin in the mens toilet