JADWAL WAKTU PELAKSANAAN ( TIME SCHEDULUE

BULAN KE 1 BULAN KE
No. Uraian Pekerjaan Jumlah Harga (Rp) Bobot (%)
1 2 3 4 5

1 Pekerjaan Tanah 2,606,000.00 1.44 0.719 0.719


2 Pekerjaan Beton 70,081,000.00 38.67 5.524 5.524 5.524
3 Pekerjaan Pasangan 44,488,000.00 24.55 2.455 2.455 2.455 2.455
4 Pekerjaan Atap Dan plafond 30,872,500.00 17.03
5 Pekerjaan Kusen Alumunium 14,230,000.00 7.85
6 Pekerjaan Instalasi Listrik 2,500,000.00 1.38
7 Pekerjaan Instalasi Air 1,805,000.00 1.00
8 Pekerjaan Pengecetan 14,652,500.00 8.08

TOTAL 181,235,000.00 100.00 0.719 3.174 7.979 7.979 7.979


BOBOT RENCANA KUMULATIF (%) 0 0.719 3.893 11.87 19.85 27.83
BOBOT REALISASI KOMULATIF (%)
SELISIH (%)
IME SCHEDULUE )

BULAN KE 2 BULAN KE 3
%
6 7 8 9 10 11 12
100%

5.524 5.52 5.52 5.52


2.455 2.45 2.45 2.45 2.45 2.455
4.26 4.26 4.26 4.26
3.93 3.926 50%
0.69 0.69
1.00
4.042 4.04
0%
7.979 12.24 12.24 13.23 11.33 11.11 4.04
35.81 48.05 60.28 73.52 84.84 95.96 100