A. Zero
B. One
C. Two
D. Three
(Ans.: C)
Explanation: Activity D depends on activities A and C, whereas activity E depends only on activity A.
First Dummy is placed here.
Activity J depends on activities G and I, whereas activity H depends only on activity G. This shows
that the second dummy is placed here.
Answer questions 10 – 13 of the engineering project modelled by the activity network as shown
below. The activities are represented by the arcs. The number in brackets on each arc gives the time,
in days, to complete the activity. Each activity requires one worker. The project is to be completed in
the shortest time.
10. What is the early time and the late time for event 9?
A. 54, 54
B. 45, 45
C. 39, 42
D. 33, 33
(Ans.: A)
Explanation:
Answer questions 14 – 17 based on a project that is modelled by the activity network shown below.
The activities are represented by the arcs. The number in the brackets on each arc gives the time, in
hours, to complete the activity. The number in circles is the event numbers. Each activity requires one
worker.
14. Calculate the early time and the late time for the event 9?
A. 31 and 31
B. 22 and 32
C. 38 and 38
D. 22 and 22
(Ans.: A)
Explanation:
Answer questions 18 – 21 based on the network as shown below. The network shows the activities
that need to be undertaken to complete a project. Each activity is represented by an arc. The number
in brackets is the duration of the activity in days. The early and late event times are to be shown at
each vertex and some have been calculated for you.