SOUTHERN GENERAL LIMITED

ID Task Name Duration Start Finish 18 Aug '19 25 Aug '19 01 Sep '19
S S M T W T F S S M T W T F S S M T W T F S
1 Construction of Canopy Bases 15 days Mon 19 Aug '19 Fri 06 Sep '19
2 Mobilization of Materials, Tools and Equipment 1 day Mon 19 Aug '19 Mon 19 Aug '19
3 Excavation of Trenches for Foundation 2 days Tue 20 Aug '19 Wed 21 Aug '19
4 Storing of Excavated Materials for Re-Use 2 days Tue 20 Aug '19 Wed 21 Aug '19
5 Return Fill and Ram Excavated Material around 2 days Wed 21 Aug '19 Thu 22 Aug '19
Foundation

6 Leveling and Compacting - Bottom of Excavation 1 day Thu 22 Aug '19 Thu 22 Aug '19
7 Placing and Compacting of Imported Sandfill 2 days Fri 23 Aug '19 Mon 26 Aug '19
8 Leveling and Compacting - Surfaces of Filling 1 day Mon 26 Aug '19 Mon 26 Aug '19
9 Installation of Formwork 3 days Tue 27 Aug '19 Thu 29 Aug '19
10 Installation of Polythene 1 day Thu 29 Aug '19 Thu 29 Aug '19
11 Installation of BRC and Reinforcement Bars 2 days Thu 29 Aug '19 Fri 30 Aug '19
12 Concrete Works 2 days Fri 30 Aug '19 Mon 02 Sep '19
13 Filling to cores of hollow Blocks 1 day Fri 30 Aug '19 Fri 30 Aug '19
14 Block Works 3 days Tue 03 Sep '19 Thu 05 Sep '19
15 Rendering Works 2 days Thu 05 Sep '19 Fri 06 Sep '19
16 Demobilization of Materials, Tools and Equipment 1 day Fri 06 Sep '19 Fri 06 Sep '19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline

Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress


Construction of Cabopy Bases Inactive Task Start-only

Inactive Milestone Finish-only

Page 1